DAILY PROGRESS REPORT


Project Name MDPE Pipe Laying and Domestic Connection, Banaskantha
Client M/s IRM Energy Pvt. Ltd.
TPIA M/s TUV SUD South Asia Pvt. Ltd. Date : 08-10-2020
Work Order No:- IRMEPL/PROJ/WO/18-19/TPIA/BK/TUV-SUD/197
Contractor MME Infracon Pvt. Ltd.
Item Description Size Today Cummulative Remarks
Ø 125 mm 0.00 12222.40
Ø 90 mm 0.00 1094.00
MDPE Pipeline Laying (in Mtr.)
Ø 63 mm 0.00 5852.00
Ø 32 mm 137.00 35157.50 Radhe Villa Bun., Abu Highway
Ø 125 mm 0.00 7901.40
Commissioning of MDPE Ø 90 mm 0.00 1094.00
Pipeline (in Mtr.) Ø 63 mm 0.00 5852.00
Ø 32 mm 0.00 33020.80
B - 25 0 10
B - 50 0 11
Installation of SRM (Service
Regulator Module) (in Nos.) B - 100 0 8
B - 200 0 0
Ø 125 mm 0 5
Installation of Valve Chamber Ø 90 mm 0 0
(in Nos.)
Ø 63 mm 0 6
Ø 32 mm 0 24
PPT 0 4331

Domestic Connection (in Nos.)


Conversion (MMT) 0 4269
RFC (Ready For
Conversion)(MMT) 0 62
Commercial Connection (in
Nos.)
Commission 0 24
Industrial Connection (in Nos.) Commission 0 1
Remarks 1) MMT Conversion WIP.

M/s ________
(TPIA)
Sign :

Name :