Professional Documents
Culture Documents
COMMISSION ON AUDIT CIRCULAR NO. 82-101-H January 22, l982
COMMISSION ON AUDIT CIRCULAR NO. 82-101-H January 22, l982
Enumerate hereunder are the documents required to be submitted to the COA Technical
Service Office in connection with its review and inspection of infrastructure contracts and
contract changes:
b. Plans;
c. Specifications;
e. Approve Agency Estimate (AEE) or Program of Work broken down into work
items and cost computations showing in sufficient detail the derivation of all
prime/direct cost (equipment, fuel, labor, materials and overhead/indirect costs;
f. Average Government Estimates (AGE) and the proposed contract price broken
down by work items and cost components;
2. Abstract of Bids
b. Breakdown of the total additive/deductive amount involved into work items and
cost components including detailed quantity estimates of any additional work;
e. Inspection Report of a COA Technical Property Inspector verifying the need for
the change or variation and indicating the specific items of work affected with
their value, to be duly noted by the COA official authorizing the inspection;
These requirements are enumerated on the assumption that all the required documents
listed under No. 1 Contract Review have been submitted. Otherwise the documents required
under No.1 Contract Review shall be submitted upon request including all previous
Supplemental Agreements/Change Orders/Extra Work Orders/Variation Orders issued if so
required.
a. Statement of time elapsed for the project as of the date of request, to be verified
by the Auditors;
c. Latest PERT/CPM Network Diagram duly approved by the Head of the agency, if
any revisions were made on the original due to variation orders or time
extensions/suspension orders previously issued;
d. Computations showing how the number of days of contract time extension being
granted was determined;
f. Certification or reports establishing the existence of the grounds for contract time
extension to be issued by authorized government agencies, for example:
c. Date of bidding;
d. Contract (as to its scope of work) and copies of duly approved Supplemental
Agreements/Change Orders/Extra Work Orders/Variation Orders is any;
e. For 100% complete projects, Certificate of Final Inspection and Acceptance and
As Built Plans.