Skala (%) : Jadwal Pelaksanaan Supervisi
Skala (%) : Jadwal Pelaksanaan Supervisi
PEKERJAAN : Supervisi Lanjutan Pembangunan Jarngan Irigasi D.I Pitap di Kabupaten Balangan
KONSULTAN : CV.JATI UTAMA
NO. KONTRAK : HK.0203/SNVT.PJPA-WS.BRT/IRWA-II/203
WAKTU PELAKSANAAN : 243 HARI
NILAI KONTRAK : Rp. 391.831.000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
BOBOT BULAN KE-1 (April - Mei) BULAN KE-2 (Mei - Juni) BULAN KE-3 (Juni - Juli) BULAN KE-4 (Juli - Agust) BULAN KE-5 (Agust - Sept) BULAN KE-6 (Sept - Okt) BULAN KE-7 (Okt - Nov) BULAN KE-8 (Nov - Des)
NO. URAIAN PEKERJAAN Skala (%)
(%) 15 - 21 22 - 28 29 - 5 6 - 12 13 - 19 20 - 26 27 - 2 3-9 10 - 16 17 - 23 24 - 30 1-7 8 - 14 15 - 21 22 - 28 29 - 4 5 - 11 12 - 18 19 - 25 26 - 1 2-8 9 -15 16 - 22 23 - 29 30 - 6 7 - 13 14 - 20 21 - 27 28 - 3 4 - 10 11 - 17 18 - 24 25 - 1 2-8 9 - 13
I. TAHAP PERSIAPAN
1 Pengurusan ijin, inventarisasi data, dan Identifikasi Eksisting 2.64 0.66 0.66 0.66 0.66 100
-
2 Persiapan Pelaksanaan Pekerjaan 2.08 0.52 0.52 0.52 0.52
-
3 Mobilisasi Personil 2.12 0.71 0.71 0.71
90
-
II. TAHAP PEKERJAAN SUPERVISI -
-
1 Membuat Format Standar Bermacam-macam Laporan 3.00 0.75 0.75 0.75 0.75
80
-
2 Pengecekan Hasil Pengukuran 4.12 1.03 1.03 1.03 1.03
-
3 Meneliti Gambar Kerja Dan ABD Kontraktor 5.12 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64
- 70
4 Melakukan Check Kualitas Pekerjaan (Kontrol Kualitas) 13.89 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63 0.63
-
5 Uji Material 4.28 1.07 1.07 1.07 1.07
- 60
6 Pengawasan Lapangan 23.15 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89 0.89
-
7 Melakukan Kontrol Progress Pelaksanaan Pekerjaan 9.79 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70
- 50
8 Pengecekan Pekerjaan Fisik Mingguan 6.81 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31 0.31
-
9 Pertemuan Bulanan Antara PPK, Konsultan dan Kontraktor 3.98 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
- 40
10 Perhitungan Dan Pengecekan MC Kontraktor 4.28 0.71 0.71 0.71 0.71 0.71 0.71
-
11 Pengawasan Akhir 5.37 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
-
30
III. TAHAP PELAPORAN -
-
1 Pembuatan Laporan Pendahuluan 1.84 0.92 0.92
-
2 Pembuatan Laporan Bulanan 1.84 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 20
-
3 Pembuatan Laporan Akhir 1.84 0.92 0.92
-
4 Diskusi Laporan 1.84 0.92 0.92 10
-
5 Softcopy semua Data Dokumen ( Hardisk ) 1.99 0.99 0.99
0
JUMLAH BOBOT 100.00
BOBOT RENCANA 0.71 1.36 2.12 3.58 2.85 2.16 2.12 2.33 1.20 2.91 3.54 4.24 4.97 4.20 4.20 4.91 5.64 2.53 2.53 2.53 3.26 2.53 2.53 2.53 3.24 3.27 2.50 2.50 2.50 3.23 2.19 1.30 1.59 3.51 2.64
BOBOT RENCANA KUMULATIF - 0.71 2.07 4.19 7.76 10.62 12.78 14.90 17.23 18.43 21.34 24.89 29.13 34.10 38.30 42.50 47.41 53.05 55.59 58.12 60.65 63.91 66.44 68.97 71.50 74.74 78.02 80.52 83.02 85.53 88.76 90.95 92.26 93.85 97.36 100.00
BOBOT REALISASI - 0.00 0.00 0.00 0.00 0.00
BOBOT REALISASI KUMULATIF 0.00 0.00 0.00 0.00
DEVIASI
Keterangan :
Kurva Rencana Gusti Abdul Azis, ST Mispandi Ir. Achmad Afif Alwi,MT
NIP. 19711117 200701 1 004 NIP. 19660319 200604 1 012 Team Leader
Kurva Realisasi
Pekerjaan : Supervisi Lanjutan Pembangunan Jarngan Irigasi D.I Pitap di Kabupaten Balangan
Lokasi : Kabupaten Balangan
Waktu : 8 (Delapan) Bulan
II TENAGA PENDUKUNG
1 Ass Construction Engineer 1.825 0.456 0.456 0.456 0.456
2 Ass Health Safety Envorinment (HSE) 1.825 0.456 0.456 0.456 0.456
3 Inspector 9.826 0.328 0.328 0.328 0.328 0.328
4 Juru Ukur (Surveyor) 2.807 0.351 0.351 0.351 0.351
Sub Total II 16.283
Total Biaya A (I+II) 83.209
V BIAYA PELAPORAN
1 Laporan Pendahuluan 0.211 0.211
2 Laporan Bulanan 1.123 0.140
3 Laporan Akhir 0.421
4 Diskusi Laporan 0.983
5 Soft Copy Laporan Dalam Hard Disk Eksternal 0.270
Sub Total V 3.007
Total Biaya B (I+II+III+IV+V) 16.791
Jumlah Total 100.00 Rencana 2.997 2.997 4.869 3.910 3.535 3.676 2.623 2.623 2.623
Rencana Kumulatif 2.997 5.994 10.863 14.773 18.308 21.984 24.607 27.230 29.853
Realisasi
Realisasi Kumulatif
Deviasi
Juni Juli Agustus September Oktober
M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24
1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968
0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328
0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099
0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066
0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033
0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129
0.187
2.763 2.623 2.623 2.623 2.623 2.763 2.623 2.623 2.623 2.950 2.623 2.623 2.623 2.763 2.623
32.616 35.239 37.862 40.485 43.108 45.871 48.494 51.117 53.740 56.690 59.313 61.936 64.559 67.322 69.945
30
1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968 1.968
0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328 0.328
0.351 0.351 0.351 0.351
0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099 0.099
0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066 0.066
0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033 0.033
0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129 0.129
0.187
0.140
2.623 2.623 2.623 2.763 2.623 2.623 2.974 3.114 2.974 5.115
72.568 75.191 77.814 80.577 83.200 85.823 88.797 91.911 94.885 100.000