TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES

Ayala Blvd., Ermita, Manila, Philippines


COLLEGE OF ENGINEERING
Civil Engineering Department

Standard Three-Storey
School Building
(6 Classrooms)

Construction Methods and Project Management

CE 414D

Submitted by:

Catibog, Charles Tovi C.


Juan, Regina May C.

Romuar, Allyza Cielo O.

Submitted to:
Engr. Edgardo S. Legaspi
TABLE OF CONTENTS

Drawing Plan I
Architectural Plan
Structural Plan

Plumbing Layout

Electrical Plan

Material Estimates II
Concrete Works

Steel Works

Masonry Works

Carpentry Works

Form Works

Scaffolding and Staging

Roof Works

Tie Wires

Paint Works

Tile Works

Earthworks

Doors and Windows

Plumbing

Electrical

Material Cost III


Concrete Works

Steel Works

Masonry Works

Carpentry Works

Form Works

Scaffolding and Staging

Roof Works
Tie Wires

Paint Works

Tile Works

Earthworks

Doors and Windows

Plumbing

Electrical
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila, Philippines
COLLEGE OF ENGINEERING
Civil Engineering Department

DRAWING
PLAN
TABLE OF CONTENTS
GENERAL ARCHITECTURAL STRUCTURAL PLUMBING ELECTRICAL
G-1 BILL OF QUANTITIES A-1 PERSPECTIVE, TABLE OF CONTENTS S-1 GENERAL NOTES P-1 GROUND FLOOR, TYPICAL SECOND & THIRD EE - 1 GENERAL NOTES, LEGEND,
G-2 BILL OF QUANTITIES FLOOR PLUMBING LAYOUT, FLUORESCENT LIGHT FIXTURE MOUNTING
G-3 BILL OF QUANTITIES A-2 KEY PLAN S-2 GENERAL NOTES GROUND FLOOR, TYPICAL SECOND & THIRD DETAIL, LOAD SCHEDULE, PANEL BOARD
FLOOR WATER LINE LAYOUT DIAGRAM AND ELECTRICAL RISER DIAGRAM ( 3-CL )
G-4 BILL OF QUANTITIES A-3 GROUND FLOOR PLAN, SECOND FLOOR & THIRD FLOOR PLAN, S-3 FOUNDATION PLAN, 2nd & 3rd FLOOR FRAMING PLAN
FRONT ELEVATION, SCHEDULE OF FINISH P-2 ISOMETRIC DRAINAGE LINE LAYOUT, EE - 2 POWER LAYOUT AND LIGHTING LAYOUT ( 3-CL )
S-4 COLUMN SCHEDULE, SCHEDULE OF FOOTING, ROOF DRAINAGE LAYOUT,
A-4 REAR ELEVATION, LEFT & RIGHT ELEVATION, SCHEDULE FOOTING BEAMS, TYPICAL FOOTING DETAIL SECTION OF DRAIN PIPE EE - 1 GENERAL NOTES, LEGEND FLUORESCENT LIGHT
LONGITUDINAL SECTION & CROSS SECTION DETAIL, ELEVATION OF COLUMN & DETAIL OF WALL AND SPOT DETAIL FIXTURE MOUNTING DETAIL, LOAD SCHEDULE,
FOOTINGS PANEL BOARD DIAGRAM AND ELECTRICAL
A-5 GROUND FLOOR, SECOND FLOOR & THIRD FLOOR REFLECTED P-3 ISOMETRIC WATER LINE LAYOUT RISER DIAGRAM ( 6-CL )
CEILING PLAN, ROOF PLAN S-5 PLAN FOOTING F-3, ELEVATION FOOTING F-3, AND SEWER LINE LAYOUT
PLAN FOOTING CF-1 & TYPICAL ELEVATION OF EE - 2 POWER LAYOUT AND LIGHTING LAYOUT ( 6-CL )
A-6 SCHEDULE OF DOORS & WINDOWS, DETAIL PLAN, MICRO-PILE P-4 PLAN OF SEPTIC TANK, LONGITUDINAL
ELEVATIONS & SECTION OF RAMP, SPOT DETAILS SECTION, CROSS SECTION DETAIL,
S-6 SCHEDULE MAIN BEAMS, SCHEDULE OF SECONDARY MANHOLE COVER DETAIL, CATCH BASIN
A-7 SECTION DETAIL OF EAVES, SPOT DETAIL CORNER CEILING, BEAMS, SCHEDULE OF SLABS, TYPICAL SLAB DETAIL, LEGEND AND PLUMBING NOTES
CONCRETE SUN BREAKER DETAIL, PERSPECTIVE, SECTION & ELEVATION, TYPICAL BEAM ELEVATION &
SPOT DETAIL OF CEILING, PLAN & SECTION OF VENTILATION TYPE OF STIRRUPS

A-8 STAIR DETAILS S-7 DETAIL OF STAIR, RAMP DETAIL,


DETAIL OF DC-1, DETAIL OF STAIR ON GRADE &
A-9 BAY SECTIONS, DOOR FRAME TYPICAL PLAN & DETAIL OF WALL ON FTB
SECTION, JALOUSIE DETAILS & FIRE ESCAPE DETAILS
S-8 ROOF FRAMING PLAN
A - 10 DETAIL PLAN OF TOILET & SECTION,
DETAIL OF COUNTER SINK, URINAL SECTION & DETAIL S-9 ELEVATION OF END WALL FRAME,
DETAIL SECTION OF PC-1,
A - 11 DETAILS OF BLACKBOARD CONNECTION OF PURLINS TO RG-4,
CONCRETE SUN BREAKER DETAIL

S - 10 TRUSS DETAILS & CONNECTION DETAILS

S - 11 BASE PLATE DETAILS, ANCHOR BOLT DETAIL, ROOF


PANEL SIDE LAP DETAIL, J-BOLT TO PURLIN CONN.
DETAIL, J-BOLT SPACING, PURLIN CONN. DETAIL,
SECTION, TRUSS DETAIL AT GUTTER END

S - 12 FIRE ESCAPE ELEVATION

S - 13 FIRE ESCAPE DETAILS

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD 5
NOTE : STANDARD THREE-STOREY TABLE OF CONTENTS A-1
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
( 3-CLASSROOMS )
THIRD FLOOR PLAN

( 3-CLASSROOMS ) ( 3-CLASSROOMS )

GROUND FLOOR PLAN SECOND FLOOR PLAN


K E Y P L A N

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD 6
NOTE : STANDARD THREE-STOREY KEY PLAN A-2
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 3-CLASSROOMS )
SECOND FLOOR PLAN FRONT ELEVATION SCHEDULE OF FINISH

GROUND FLOOR PLAN THIRD FLOOR PLAN

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS GROUND FLOOR PLAN, BOD
SECOND FLOOR & THIRD FLOOR PLAN, 7
NOTE : STANDARD THREE-STOREY FRONT ELEVATION, A-3
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING SCHEDULE OF FINISH
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
RIGHT SIDE ELEVATION LEFT SIDE ELEVATION CROSS SECTION

REAR ELEVATION LONGITUDINAL SECTION

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
REAR ELEVATION, LEFT & RIGHT 8
NOTE : STANDARD THREE-STOREY ELEVATION, LONGITUDINAL SECTION A-4
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON & CROSS SECTION 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
SECOND FLOOR REFLECTED CEILING PLAN ROOF PLAN

GROUND FLOOR REFLECTED CEILING PLAN THIRD FLOOR REFLECTED CEILING PLAN

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
GROUND FLOOR, SECOND FLOOR & 9
NOTE : STANDARD THREE-STOREY THIRD FLOOR REFLECTED CEILING A-5
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON PLAN, ROOF PLAN 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
SPOT DETAIL
DETAIL ELEVATION OF RAMP
DETAIL SECTION OF RAMP
SPOT DETAIL

DETAIL SECTION

SCHEDULE OF DOORS AND WINDOWS DETAIL PLAN OF RAMP

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS SCHEDULE OF DOORS & WINDOWS, BOD 10
NOTE : STANDARD THREE-STOREY DETAIL PLAN, DETAIL PLAN, ELEVATION A-6
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON & SECTION OF RAMP, SPOT DETAILS 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
SECTION ( CEILING )

SECTION DETAIL (VENT.)

SPOT DETAIL

PERSPECTIVE ( CEILING )
CONCRETE
SUNBREAKER DETAIL DETAIL PLAN (VENT.)

SECTION DETAIL (EAVES) SPOT DETAIL (EAVES)


SPOT DETAIL (CORNER CLG.)

VARIOUS DPWH SECTION DETAIL OF EAVES,


(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS SPOT DETAIL CORNER CEILING, BOD
CONCRETE SUNBREAKER DETAIL, 11
NOTE : STANDARD THREE-STOREY PERSPECTIVE, SECTION & A-7
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING SPOT DETAIL OF CEILING,
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS ) PLAN & SECTION OF VENTILATION
CRASH RAILING
ELEVATION DETAIL

BALCONY RAILING DETAIL

NOSING DETAIL

SPOT DETAIL SPOT DETAIL


DETAIL SECTION OF STAIR HANDRAIL DETAIL

(AT GROUND FLOOR ) (AT SECOND FLOOR) (AT THIRD FLOOR)


DETAIL PLAN OF STAIR DETAIL PLAN OF STAIR DETAIL PLAN OF STAIR SECTION DETAIL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD 12
NOTE : STANDARD THREE-STOREY STAIR DETAIL A-8
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
CLASSROOM
CORRIDOR

CORRIDOR
CLASSROOM

DOOR FRAME TYPICAL


PLAN & SECTION DETAIL

CORRIDOR

BAY SECTION (ALONG TOILETS)

CLASSROOM
FIRE ESCAPE ELEVATION
GLASS JALOUSIE TYPICAL
DETAIL PLANS

CLASSROOM

CORRIDOR GROUND 2nd 3rd


FLOOR PLAN FLOOR PLAN FLOOR PLAN

GLASS JALOUSIE TYPICAL


BAY SECTION (ALONG CORRIDORS) DETAIL SECTIONS FIRE ESCAPE PLAN

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BAY SECTIONS, DOOR FRAME BOD
TYPICAL PLAN & SECTION, 13
NOTE : STANDARD THREE-STOREY JALOUSIE DETAILS & FIRE A-9
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING ESCAPE DETAILS
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
URINAL TROUGH
SECTION & DETAIL

DETAIL SECTION DETAIL SECTION

DETAIL OF COUNTER SINK

DETAIL SECTION OF TOILET


( GROUND FLOOR ) ( TYPICAL SECOND FLOOR & THIRD FLOOR )
DETAIL PLAN OF TOILET DETAIL PLAN OF TOILET

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
DETAIL PLAN OF TOILET & SECTION, 14
NOTE : STANDARD THREE-STOREY DETAIL OF COUNTER SINK, A-10
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON URINAL SECTION & DETAIL 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
SECTION
CHALK DUST BOX DETAIL

SPOT DETAIL SECTION


EDGE FRAMING

BLACKBOARD DETAIL CONNECTION SECTION DETAIL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BLACKBOARD DETAIL, BOD
CONNECTION SECTION DETAIL,SECTION, 15
NOTE : STANDARD THREE-STOREY SPOT DETAIL SECTION EDGE FRAMING, A-11
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING CHALK DUST BOX DETAIL
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA 16
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY GENERAL NOTES S-1
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS )
VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA 17
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY GENERAL NOTES S-2
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS )
2nd FLOOR FRAMING PLAN 3rd FLOOR FRAMING PLAN

FOUNDATION PLAN

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA FOUNDATION PLAN, 2nd & 3rd FLOOR 18
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY FRAMING PLAN S-3
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS )
TYPICAL FOOTING DETAIL

ELEVATION OF
COLUMN

DETAIL OF WALL FOOTINGS

VARIOUS DPWH COLUMN SCHEDULE,


(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS SCHEDULE OF FOOTING, BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA SCHEDULE FOOTING BEAMS, 19
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY TYPICAL FOOTING DETAIL, S-4
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING ELEVATION OF COLUMN, &
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS ) DETAIL OF WALL FOOTINGS
TYP. SECTION OF MICRO-PILE

PLAN FOOTING F-3

PLAN FOOTING CF-1

TYPICAL ELEV. OF MICRO-PILE

ELEV. FOOTING F-3

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS PLAN FOOTING F-3, BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA ELEV. FOOTING F-3, 20
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY PLAN FOOTING CF-1 & S-5
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING TYPICAL ELEV. OF MICRO-PILE
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS )
TYPICAL SLAB ELEVATION

TYPICAL BEAM ELEVATION

TYPE OF STIRRUPS

VARIOUS DPWH SCHEDULE MAIN BEAMS,


(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS SCHEDULE OF SECONDARY BEAMS, BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA SCHEDULE OF SLABS, 21
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY TYPICAL SLAB ELEVATION, S-6
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING TYPICAL BEAM ELEVATION &
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS ) TYPE OF STIRRUPS
SPOT DETAIL SECTION OF STAIR SLAB

SPOT DETAIL
SPOT DETAIL

RAMP DETAIL

DETAIL OF DC-1

DET. OF STAIR
ON GRADE

STAIR FRAMING PLAN STAIR SECTION DETAIL

DET. OF WALL ON FTB

VARIOUS DPWH
DETAIL OF STAIR,
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA RAMP DETAIL, 22
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY DETAIL OF DC-1, S-7
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON DETAIL OF STAIR ON GRADE & 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY DETAIL OF WALL ON FTB
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOMS )
ROOF FRAMING PLAN AT BOTTOM CHORD LEVEL ROOF FRAMING PLAN AT TOP CHORD LEVEL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA 23
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY ROOF FRAMING PLAN S-8
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM )
DET. SECTION OF PC-1

DETAIL

ROOF DETAIL AT END BAY

DETAIL DETAIL

CONCRETE
SUNBREAKER DETAIL

ELEV. OF END WALL FRAME

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS ELEV. OF END WALL FRAME, BOD
NELSON S. ANTONIO DOMICIANO B. LUSICA DET. SECTION OF PC-1, 24
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY CONNECTION OF PURLINS TO RG-4, S-9
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING CONCRETE SUNBREAKER DETAIL
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM )
SCHEDULE OF TRUSS MEMBERS
MARK POSITION SECTION CONFIGURATION

L L L

DETAIL DETAIL DETAIL

WELD DETAIL
DETAIL DETAIL SECTION A DETAIL CONN. OF CROSS-BRACING

TRUSS - COLUMN
CONNECTION DETAIL

A TRUSS -1 DETAIL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NAPOLEON B. TORIBIO NELSON S. ANTONIO DOMICIANO B. LUSICA TRUSS DETAILS 25
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY CONNECTION DETAILS S-10
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM )
ROOF PANEL SIDE LAP DETAIL

ANCHOR BOLT DETAIL


BASE PLATE DETAILS

PURLIN CONNECTION DETAIL


J-BOLT TO PURLIN CONNECTION DETAIL
J-BOLT SPACING

CEILING LN

SECTION B SECTION C TRUSS DETAIL AT GUTTER END

VARIOUS DPWH BASE PLATE DETAILS


PROPOSED PROJECTS ANCHOR BOLT DETAIL
NAPOLEON B. TORIBIO NELSON S. ANTONIO DOMICIANO B. LUSICA (SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) ROOF PANEL SIDE LAP DETAIL BOD 26
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY J-BOLT TO PURLIN CONNECTION DETAIL S-11
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON J-BOLT SPACING 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING PURLIN CONNECTION DETAIL SECTION
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM ) TRUSS DETAIL AT GUTTER END
FIRE ESCAPE ELEVATION

DETAIL
DETAIL DETAIL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NAPOLEON B. TORIBIO NELSON S. ANTONIO DOMICIANO B. LUSICA 27
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY FIRE ESCAPE ELEVATION S-12
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM )
SECTION B-B

SECTION A-A

FIRE ESCAPE FRAMING PLAN

DETAIL DETAIL

PLAN IN-BETWEEN LANDING


SECTION C-C DETAIL

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
NAPOLEON B. TORIBIO NELSON S. ANTONIO DOMICIANO B. LUSICA 28
STRUCTURAL DESIGN STRUCTURAL DESIGN PROJECT MANAGER STANDARD THREE-STOREY FIRE ESCAPE DETAIL S-13
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
POSITION: STRUCTURAL ENGINEER POSITION: STRUCTURAL ENGINEER SCHOOL BUILDING
PRC No.: 32516 TIN No.: 107-915-002 PRC No.: 14234 TIN No.: 178-384-258 OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
PTR No.: 7653512 PTR No.: 8108050
( 6-CLASSROOM )
1 2 3 4 5 6 1 2 3 4 5 6
22700 22700
9000 9000 4700 9000 9000 4700
4500 4500 4500 4500 1900 1200 1600 4500 4500 4500 4500 1900 1200 1600

A A

1000

1000
2000

2000
SHE SHE

2000 2000

2000

2000
HE HE
1000 1000 1000 1000

CLASSROOM 3 CLASSROOM 4 CLASSROOM 3 CLASSROOM 4


7000

7000

7000

7000
5000

5000
9500

9500
4000

4000
3780

3780
B DN UP
B DN UP

1800 1440 1460 1800 1440 1460


2500

2500

2500

2500
C C

2 TYP. 2ND & 3RD FLOOR PLUMBING LAYOUT 4 TYP. 2ND & 3RD FLOOR WATER LINE LAYOUT
P-1 SCALE 1:100M. P-1 SCALE 1:100M.

1 2 3 4 5 6 1 2 3 4 5 6
22700 22700
9000 9000 4700 9000 9000 4700
4500 4500 4500 4500 1850 1450 1400 4500 4500 4500 4500 1850 1450 1400

CB CB CB CB CB CB 2300

A A

1000

1000
2000

2000
PWD PWD
SHE SHE

3200
2000

2000
HE HE
2000 2000
1000 1000 1000 1000

CLASSROOM 1 CLASSROOM 2 CLASSROOM 1 CLASSROOM 2

7000
7000

7000

7000

7000
1400

1400
1600
5000

5000
9500

9500
4000

4000
2380

2380
1600
STO. STO.

B UP
B UP

1800 1440 1460 1800 1440 1460


2500

2500

2500

2500
C C
400

400
UP UP UP UP
1200

1200
4300 4300 4300 4300

CB CB CB CB
8600 3600 1700 8600 3600 1700

1 GROUND FLOOR PLUMBING LAYOUT 3 GROUND FLOOR WATER LINE LAYOUT


P-1 SCALE 1:100M. P-1 SCALE 1:100M.

VARIOUS DPWH
PROPOSED PROJECTS GROUND, TYP. SECOND & THIRD BOD
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) 29
FLOOR PLUMBING LAYOUT,
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY GROUND, TYP. SECOND & THIRD P-1
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING FLOOR WATER LINE LAYOUT,
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
1 2 3 4 5 6
600 22700 600
9000 9000 4700
4500 4500 4500 4500

1500
A

6450
7000
9500

6425
2500

C
1500

2 ROOF DRAINAGE LAYOUT


P-1 SCALE 1:100M.
4 SPOT DETAIL
P-4 SCALE 1:15M.

3 DETAIL SECTION OF DRAIN PIPE


1 ISOMETRIC DRAINAGE LINE LAYOUT P-4 SCALE 1:15M.

P-2 SCALE 1:100M.

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS ISOMETRIC DRAINAGE LINE LAYOUT BOD
ROOF DRAINAGE LAYOUT, 30
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY P-2
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON DETAIL SECTION OF DRAIN PIPE
36
SCHOOL BUILDING AND SPOT DETAIL
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
1 ISOMETRIC WATER LINE LAYOUT 2 ISOMETRIC SEWER LINE LAYOUT
P-3 SCALE 1:100M. P-3 SCALE 1:100M.

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
ISOMETRIC WATER LINE LAYOUT 31
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY AND SEWER LINE LAYOUT P-3
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
4 MANHOLE COVER DETAIL
P-4 SCALE 1:10M.

3 CROSS SECTION DETAIL


P-4 SCALE 1:30M.

LEACHING LEACHING
DIGESTIVE CHAMBER CHAMBER CHAMBER

2 LONGITUDINAL SECTION DETAIL


P-4 SCALE 1:30M.

PLAN

SECTION

5 CATCH BASIN DETAIL


1 PLAN DET. OF SEPTIC TANK P-4 SCALE 1:30M.
P-4 SCALE 1:30M.

VARIOUS DPWH PLAN OF SEPTIC TANK,


PROPOSED PROJECTS LONGITUDINAL SECTION, BOD
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) 32
CROSS SECTION DETAIL,
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY MANHOLE COVER DETAIL, P-4
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING CATCH BASIN DETAIL,
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS ) LEGEND AND PLUMBING NOTES
GENERAL NOTES :
1. ALL ELECTRICAL WORKS SHALL COMPLY WITH THESE PLANS AND SPECIFICATIONS. THE APPLICABLE
PROVISIONS OF THE LATEST EDITION OF THE PHILIPPINE ELECTRICAL CODE (PEC), THE RULES AND
REGULATIONS OF THE LOCAL ENFORCING AUTHORITY AND THE REQUIREMENTS OF THE LOCAL
POWER COMPANY.

2. THE ELECTRICAL SERVICE POWER SHALL BE 1-PHASE,2-WIRE,230V AC, 60Hz.

3. WIRING METHOD SHALL BE AS FOLLOWS:


RIGID STEEL CONDUIT OR POLYVINYL CHLORIDE CONDUIT SCHEDULE 40 SHALL BE USED AS
SPECIFIED IN THE PLAN.

4. ALL WIRES SHALL BE COPPER AND THERMOPLASTIC INSULATED TYPE "THHN" UNLESS OTHERWISE
INDICATED IN THE PLAN. THE MINIMUM SIZE WIRE FOR POWER AND LIGHTING CIRCUIT
TOTAL CONNECTED LOADS: 11696 VA

11696
I = (.80) = 40.68 AMPERES

450
L 230 (70A/40.68A) 1 2
5. ALL OUTLET BOXES SHALL BE GALVANIZED GAGE NO. 16 DEEP TYPE.

GROUND TERMINAL BLOCK 6. ALL MATERIALS TO BE USED SHALL BE BRAND NEW AND APPROVED FOR THE PARTICULAR
LOCATION AND USAGE.

7. EQUIPMENT GROUNDING SYSTEM SHALL BE PROVIDED TO THE ELECTRICAL SYSTEM AS PER


PHILIPPINE ELECTRICAL CODE REQUIREMENT.

8. MOUNTING HEIGHT OF WIRING DEVICES SHALL BE AS FOLLOWS:


a. LIGHT SWITCH - 1.20M ABOVE FINISH FLOOR
b. CONVENIENCE OUTLET - 0.3M ABOVE FINISH FLOOR

9. ALL ELECTRICAL WORKS SHALL BE DONE UNDER THE DIRECT AND IMMEDIATE SUPERVISION OF A
DULY REGISTERED ELECTRICAL ENGINEER.
FLUORESCENT LIGHT
3 PANELBOARD DIAGRAM 4 FIXTURE MOUNTING DETAIL
EE-1 NOT TO SCALE EE-1 NOT TO SCALE

LEGEND

- 1-18 WATTS COMPACT FLUORESCENT LAMP WITH MEDIUM BASE,


KEYLESS TYPE PORCELAIN RECEPTACLE

1 - 1 x 36 WATTS FLUORESCENT LIGHTING FIXTURE, BOX TYPE


TOTAL CONNECTED LOADS: 7955 VA
2 - 2 x 36 WATTS FLUORESCENT LIGHTING FIXTURE, BOX TYPE WITH
I @ 85% DF
L CANOPY BASE AND STEM 1.5 FT (450mm) LENGTH SIMILAR TO AMCO
7955 AP-1113-1.5 OR APPROVED EQUAL
I = 0.85 = 29.40 AMPERES
L 230 (55A/29.40A)
2
- 2 x 36 WATTS FLUORESCENT LIGHTING FIXTURE, BOX TYPE

WF - WALL FAN OUTLET

- SINGLE POLE WALL SWITCH

- DUPLEX SWITCH, 2 SINGLE POLE SWITCHES ON ONE-GANG SWITCH


PLATE

- THREE WAY WALL SWITCH

- FAN CONTROL SWITCH


- RACEWAY CONDUIT CONCEALED IN CEILING

- RACEWAY CONDUIT CONCEALED UNDER FLOOR

- PANELBOARD, MARKED AS "LP"

- CKT. BREAKER, RATING AS INDICATED

- DUPLEX CONVENIENCE OUTLET, GROUNDING TYPE 15 AMPS,


240 VOLT
TOTAL CONNECTED LOADS: 3741 VA
I @ 80% DF
L WP - WEATHERPROOF DUPLEX CONVENIENCE OUTLET,
5000mm

3741 GROUNDING TYPE,15 AMPS, 240 VOLT


I L= 0.80 = 13.01 AMPERES
230 (55A/13.01A)
1800mm

- CIRCUIT HOMERUN

- ENCLOSED AIR CIRCUIT BREAKER

FA - FIRE ALARM CONTROL PANEL

1 LOAD SCHEDULE F

B
-

-
FIRE ALARM STATION OUTLET

FIRE ALARM BELL


EE-1 NOT TO SCALE
2 ELECTRICAL RISER DIAGRAM M - SERVICE METER

- SERVICE ENTRANCE
EE-1 NOT TO SCALE
MDP
- MAIN DISTRIBUTION PANELBOARD

VARIOUS DPWH GENERAL NOTES, LEGEND,


(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS FLUORESCENT LIGHT FIXTURE BOD
MOUNTING DETAIL, 35
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY LOAD SCHEDULE, EE-1
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING PANEL BOARD DIAGRAM AND
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY ELECTRICAL RISER DIAGRAM
( 6-CLASSROOMS )
1 2 3 4 5 6 1 2 3 4 5 6
22700 22700
9000 9000 4700 9000 9000 4700
4500 4500 4500 4500 1900 1200 1600 4500 4500 4500 4500 1900 1200 1600

SFC SFC
A SHE
A SHE

1000

1000
WF WF

2000 2000 2 2 2 2 2 2

2000

2000
HE HE
1000 1000 1000 1000 a b c a b c

CLASSROOM 5 CLASSROOM 6 CLASSROOM 5 CLASSROOM 6


7000

7000

7000

7000
4 1
LPB 1
1
9500

9500
LPB

4000

4000
3780

3780
2 2 2 2 2 2
a b c a b 3 c
LPB

WF WF
B F DN UP
B 2 DN UP
LPB
B
2500

2500

2500

2500
1 1 1 1 1

C C

3 THIRD FLOOR POWER LAYOUT 6 THIRD FLOOR LIGHTING LAYOUT


SCALE 1:100M. SCALE 1:100M.
EE-2 EE-2

1 2 3 4 5 6 1 2 3 4 5 6
22700 22700
9000 9000 4700 9000 9000 4700
4500 4500 4500 4500 1900 1200 1600 4500 4500 4500 4500 1900 1200 1600

SFC SFC
A A

1000

1000
SHE WF WF SHE

2000 2000 2 2 2 2 2 2

2000

2000
HE HE
1000 1000 1000 1000 a b c a b c S S

CLASSROOM 3 CLASSROOM 4 CLASSROOM 3 CLASSROOM 4


7000

7000

7000

7000
7 1
d DOWN TO S 3 Wd
LPA 1
1 @ GROUND FLOOR
9500

9500
LPA

4000

4000
3780

3780
2 2 2 2 2 2
a b c a b 5 c
LPA
UP TO S 3 Wd
WF WF @ 3RD FLOOR
B F DN UP
B 2 DN UP
LPA
B
2500

2500

2500

2500
1 1 1 1 1

C C

2 SECOND FLOOR POWER LAYOUT 5 SECOND FLOOR LIGHTING LAYOUT


SCALE 1:100M. SCALE 1:100M.
EE-2 EE-2

1 2 3 4 5 6 1 2 3 4 5 6
22700 22700
9000 9000 4700 9000 9000 4700
4500 4500 4500 4500 1850 1450 1400 4500 4500 4500 4500 1850 1450 1400

SFC SFC
A A
1000

1000
WF WF
PWD PWD
SHE SHE
2 2 2 2 2 2
2000

2000
HE HE
2000 2000 a b c a b c
1000 1000 1000 1000

CLASSROOM 1 CLASSROOM 2 CLASSROOM 1 CLASSROOM 2


7000

7000

7000

7000
1400

1400
8
LPA 1
3
9500

9500 LPA
4000

4000
2 2 2 2 2 2
a b c a b 6 c
2380

2380 LPA UP TO S 3 Wd
STO. WF WF STO. @ 2ND FLOOR
S3Wd
B F UP
B 4 S UP
B LPA
2500

2500

2500

2500
1 1 1 1 1

C C
UP UP UP UP
1200

1200
1 GROUND FLOOR POWER LAYOUT 4 GROUND FLOOR LIGHTING LAYOUT
SCALE 1:100M. SCALE 1:100M.
EE-2 EE-2

VARIOUS DPWH
(SEE COVER SHEET) (SEE COVER SHEET) (SEE COVER SHEET) PROPOSED PROJECTS BOD
POWER LAYOUT AND 36
NOTE : ADOPTED FROM DEPED STANDARD PLANS STANDARD THREE-STOREY LIGHTING LAYOUT EE-2
GILBERTO S. REYES RAUL C. ASIS ROGELIO L. SINGSON 36
SCHOOL BUILDING
OIC, BUILDINGS DIVISION DIRECTOR IV, BOD UNDERSECRETARY SECRETARY
( 6-CLASSROOMS )
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila, Philippines
COLLEGE OF ENGINEERING
Civil Engineering Department

MATERIAL
ESTIMATES
BILL OF ESTIMATES
CONCRETE WORKS

Materials Estimated Quantity Required


MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
FOUNDATION
Volume of footing (m3): 10.5
Quantity: 6
Plus: 10% allowance for wastage: 1.05
Total Volume (m3): 64.05
CF-1
Class: A (1:2:4) 40kg / bag
Cement: 64.05 x 9 = 576.45 ; say. . . 577
Sand: 64.05 x 0.5 = 32.025 ; say. . . ............ 33
Gravel: 64.05 x 1 = 64.05 ; say. . . ........................ 65
3
Volume of footing (m ): 5.78
Quantity: 6
Plus: 10% allowance for wastage: 0.578
Total Volume (m3): 35.258
CF - 2
Class: A (1:2:4) 40kg / bag
Cement: 35.258 x 9 = 317.322 ; say. . . 318
Sand: 35.258 x 0.5 = 17.629 ; say. . . ............ 18
Gravel: 35.258 x 1 = 35.258 ; say. . . ........................ 36
3
Volume of footing (m ): 1.296
Quantity: 13
Plus: 10% allowance for wastage: 0.1296
Total Volume (m3): 16.9776
WF -1
Class: A (1:2:4) 40kg / bag
Cement: 16.9776 x 9 = 152.7984 ; say. . . 153
Sand: 16.9776 x 0.5 = 8.4888 ; say. . . ............ 9
Gravel: 16.9776 x 1 = 16.9776 ; say. . . ........................ 17
3
Volume of footing (m ) 0.048
Quantity 2
Plus: 10% allowance for wastage 0.0048
Total Volume (m3) 0.1008
WF - 2
Class: A (1:2:4) 40kg / bag
Cement: 0.1008 x 9 = 0.9072 ; say. . . 1
Sand: 0.1008 x 0.5 = 0.0504 ; say. . . ............ 1
Gravel: 0.1008 x 1 = 0.1008 ; say. . . ........................ 1
3
Volume of footing tie beam (m ) 0.375
Quantity 6
Plus: 10% allowance for wastage 0.0048
Total Volume (m3) 2.2548
FTB - 1
Class: A (1:2:4) 40kg / bag
Cement: 2.2548 x 9 = 20.2932 ; say. . . 21
Sand: 2.2548 x 0.5 = 1.1274 ; say. . . ............ 2
Gravel: 2.2548 x 1 = 2.2548 ; say. . . ........................ 3
Volume of footing tie beam (m3) 1.05
Quantity 6
Plus: 10% allowance for wastage 0.0048
Total Volume (m3) 6.3048
FTB - 2
Class: A (1:2:4) 40kg / bag
Cement: 6.3048 x 9 = 56.7432 ; say. . . 57
Sand: 6.3048 x 0.5 = 3.1524 ; say. . . ............ 4
Gravel: 6.3048 x 1 = 6.3048 ; say. . . ........................ 7
3
Volume of footing tie beam (m ) 0.675
Quantity 6
Plus: 10% allowance for wastage 0.0048
Total Volume (m3) 4.0548
FTB - 3
Class: A (1:2:4) 40kg / bag
Cement: 4.0548 x 9 = 36.4932 ; say. . . 37
Sand: 4.0548 x 0.5 = 2.0274 ; say. . . ............ 3
Gravel: 4.0548 x 1 = 4.0548 ; say. . . ........................ 5
Materials Estimated Quantity Required
MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
COLUMNS
GROUND FLOOR - SECOND FLOOR
Volume of column (m3) 0.512
Quantity 3
Plus: 10% allowance for wastage 0.0512
Total Volume (m3) 1.5872
C-1
Class: A (1:2:4) 40kg / bag
Cement: 1.5872 x 9 = 14.2848 ; say. . . 15
Sand: 1.5872 x 0.5 = 0.7936 ; say. . . ............ 1
Gravel: 1.5872 x 1 = 1.5872 ; say. . . ........................ 2
Volume of column (m3) 1.058
Quantity 3
Plus: 10% allowance for wastage 0.1058
Total Volume (m3) 3.2798
C-2
Class: A (1:2:4) 40kg / bag
Cement: 3.2798 x 9 = 29.5182 ; say. . . 30
Sand: 3.2798 x 0.5 = 1.6399 ; say. . . ............ 2
Gravel: 3.2798 x 1 = 3.2798 ; say. . . ........................ 4
3
Volume of column (m ) 0.968
Quantity 3
Plus: 10% allowance for wastage 0.0968
Total Volume (m3) 3.0008
C-3
Class: A (1:2:4) 40kg / bag
Cement: 3.0008 x 9 = 27.0072 ; say. . . 28
Sand: 3.0008 x 0.5 = 1.5004 ; say. . . ............ 2
Gravel: 3.0008 x 1 = 3.0008 ; say. . . ........................ 4
SECOND FLOOR - THIRD FLOOR
Volume of column (m3) 0.512
Quantity 3
Plus: 10% allowance for wastage 0.0512
Total Volume (m3) 1.5872
C-1
Class: A (1:2:4) 40kg / bag
Cement: 1.5872 x 9 = 14.2848 ; say. . . 15
Sand: 1.5872 x 0.5 = 0.7936 ; say. . . ............ 1
Gravel: 1.5872 x 1 = 1.5872 ; say. . . ........................ 2
3
Volume of column (m ) 0.968
Quantity 3
Plus: 10% allowance for wastage 0.0968
Total Volume (m3) 3.0008
C-2
Class: A (1:2:4) 40kg / bag
Cement: 3.0008 x 9 = 27.0072 ; say. . . 28
Sand: 3.0008 x 0.5 = 1.5004 ; say. . . ............ 2
Gravel: 3.0008 x 1 = 3.0008 ; say. . . ........................ 4
Volume of column (m3) 0.968
Quantity 3
Plus: 10% allowance for wastage 0.0968
Total Volume (m3) 3.0008
C-3
Class: A (1:2:4) 40kg / bag
Cement: 3.0008 x 9 = 27.0072 ; say. . . 28
Sand: 3.0008 x 0.5 = 1.5004 ; say. . . ............ 2
Gravel: 3.0008 x 1 = 3.0008 ; say. . . ........................ 4
THIRD FLOOR - ROOF
Volume of column (m3) 0.4
Quantity 3
Plus: 10% allowance for wastage 0.04
Total Volume (m3) 1.24
C-1
Class: A (1:2:4) 40kg / bag
Cement: 1.24 x 9 = 11.16 ; say. . . 12
Sand: 1.24 x 0.5 = 0.62 ; say. . . ............ 1
Gravel: 1.24 x 1 = 1.24 ; say. . . ........................ 2
Materials Estimated Quantity Required
MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
COLUMNS
THIRD FLOOR - ROOF
Volume of column (m3) 0.506
Quantity 3
Plus: 10% allowance for wastage 0.0506
Total Volume (m3) 1.5686
C-2
Class: A (1:2:4) 40kg / bag
Cement: 1.5686 x 9 = 14.1174 ; say. . . 15
Sand: 1.5686 x 0.5 = 0.7843 ; say. . . ............ 1
Gravel: 1.5686 x 1 = 1.5686 ; say. . . ........................ 2
3
Volume of column (m ) 0.506
Quantity 3
Plus: 10% allowance for wastage 0.0506
Total Volume (m3) 1.5686
C-3
Class: A (1:2:4) 40kg / bag
Cement: 1.5686 x 9 = 14.1174 ; say. . . 15
Sand: 1.5686 x 0.5 = 0.7843 ; say. . . ............ 1
Gravel: 1.5686 x 1 = 1.5686 ; say. . . ........................ 2

Materials Estimated Quantity Required


MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
BEAMS
MAIN BEAMS
Volume of girder (m3) 0.49
Quantity 12
Plus: 10% allowance for wastage 0.049
Total Volume (m3) 5.929
G-1
Class: A (1:2:4) 40kg / bag
Cement: 5.929 x 9 = 53.361 ; say. . . 54
Sand: 5.929 x 0.5 = 2.9645 ; say. . . ............ 3
Gravel: 5.929 x 1 = 5.929 ; say. . . ........................ 6
3
Volume of girder (m ) 0.556
Quantity 12
Plus: 10% allowance for wastage 0.0556
Total Volume (m3) 6.7276
G-2
Class: A (1:2:4) 40kg / bag
Cement: 6.7276 x 9 = 60.5484 ; say. . . 61
Sand: 6.7276 x 0.5 = 3.3638 ; say. . . ............ 4
Gravel: 6.7276 x 1 = 6.7276 ; say. . . ........................ 7
3
Volume of girder (m ) 0.613
Quantity 10
Plus: 10% allowance for wastage 0.0613
Total Volume (m3) 6.1913
G-3
Class: A (1:2:4) 40kg / bag
Cement: 6.1913 x 9 = 55.7217 ; say. . . 56
Sand: 6.1913 x 0.5 = 3.09565 ; say. . . ............ 4
Gravel: 6.1913 x 1 = 6.1913 ; say. . . ........................ 7
3
Volume of girder (m ) 0.4
Quantity 4
Plus: 10% allowance for wastage 0.04
Total Volume (m3) 1.64
G-4
Class: A (1:2:4) 40kg / bag
Cement: 1.64 x 9 = 14.76 ; say. . . 15
Sand: 1.64 x 0.5 = 0.82 ; say. . . ............ 1
Gravel: 1.64 x 1 = 1.64 ; say. . . ........................ 2
3
Volume of girder (m ) 1.4
Quantity 4
Plus: 10% allowance for wastage 0.14
Total Volume (m3) 5.74
G-5
Class: A (1:2:4) 40kg / bag
Cement: 5.74 x 9 = 51.66 ; say. . . 52
Sand: 5.74 x 0.5 = 2.87 ; say. . . ............ 3
Gravel: 5.74 x 1 = 5.74 ; say. . . ........................ 6
Materials Estimated Quantity Required
MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
BEAMS
MAIN BEAMS
Volume of girder (m3) 0.4
Quantity 8
Plus: 10% allowance for wastage 0.04
Total Volume (m3) 3.24
G-6
Class: A (1:2:4) 40kg / bag
Cement: 3.24 x 9 = 29.16 ; say. . . 30
Sand: 3.24 x 0.5 = 1.62 ; say. . . ............ 2
Gravel: 3.24 x 1 = 3.24 ; say. . . ........................ 4
Volume of girder (m3) 1.4
Quantity 2
Plus: 10% allowance for wastage 0.14
Total Volume (m3) 2.94
G-7
Class: A (1:2:4) 40kg / bag
Cement: 2.94 x 9 = 26.46 ; say. . . 27
Sand: 2.94 x 0.5 = 1.47 ; say. . . ............ 2
Gravel: 2.94 x 1 = 2.94 ; say. . . ........................ 3
3
Volume of girder (m ) 1.4
Quantity 6
Plus: 10% allowance for wastage 0.14
Total Volume (m3) 8.54
G-8
Class: A (1:2:4) 40kg / bag
Cement: 8.54 x 9 = 76.86 ; say. . . 77
Sand: 8.54 x 0.5 = 4.27 ; say. . . ............ 5
Gravel: 8.54 x 1 = 8.54 ; say. . . ........................ 9
SECONDARY BEAMS
Volume of beam (m3) 0.36
Quantity 16
Plus: 10% allowance for wastage 0.036
Total Volume (m3) 5.796
B-1
Class: A (1:2:4) 40kg / bag
Cement: 5.796 x 9 = 52.164 ; say. . . 53
Sand: 5.796 x 0.5 = 2.898 ; say. . . ............ 3
Gravel: 5.796 x 1 = 5.796 ; say. . . ........................ 6
3
Volume of beam (m ) 0.564
Quantity 2
Plus: 10% allowance for wastage 0.0564
Total Volume (m3) 1.1844
B-2
Class: A (1:2:4) 40kg / bag
Cement: 1.1844 x 9 = 10.6596 ; say. . . 11
Sand: 1.1844 x 0.5 = 0.5922 ; say. . . ............ 1
Gravel: 1.1844 x 1 = 1.1844 ; say. . . ........................ 2
Volume of beam (m3) 0.32
Quantity 2
Plus: 10% allowance for wastage 0.032
Total Volume (m3) 0.672
B-3
Class: A (1:2:4) 40kg / bag
Cement: 0.672 x 9 = 6.048 ; say. . . 7
Sand: 0.672 x 0.5 = 0.336 ; say. . . ............ 1
Gravel: 0.672 x 1 = 0.672 ; say. . . ........................ 1
ROOF BEAMS
Volume of roof beam (m3) 0.545
Quantity 15
Plus: 10% allowance for wastage 0.0545
Total Volume (m3) 8.2295
RB - 1
Class: A (1:2:4) 40kg / bag
Cement: 8.2295 x 9 = 74.0655 ; say. . . 75
Sand: 8.2295 x 0.5 = 4.11475 ; say. . . ............ 5
Gravel: 8.2295 x 1 = 8.2295 ; say. . . ........................ 9
3
Volume of roof beam (m ) 0.56
RB - 2 Quantity 4
Plus: 10% allowance for wastage 0.056
Materials Estimated Quantity Required
MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
BEAMS
ROOF BEAMS
Total Volume (m3) 2.296
Class: A (1:2:4) 40kg / bag
RB - 2 Cement: 2.296 x 9 = 20.664 ; say. . . 21
Sand: 2.296 x 0.5 = 1.148 ; say. . . ............ 2
Gravel: 2.296 x 1 = 2.296 ; say. . . ........................ 3
3
Volume of roof beam (m ) 0.38
Quantity 4
Plus: 10% allowance for wastage 0.038
Total Volume (m3) 1.558
RB - 3
Class: A (1:2:4) 40kg / bag
Cement: 1.558 x 9 = 14.022 ; say. . . 15
Sand: 1.558 x 0.5 = 0.779 ; say. . . ............ 1
Gravel: 1.558 x 1 = 1.558 ; say. . . ........................ 2
3
Volume of roof beam (m ) 0.2
Quantity 2
Plus: 10% allowance for wastage 0.02
Total Volume (m3) 0.42
RB - 4A
Class: A (1:2:4) 40kg / bag
Cement: 0.42 x 9 = 3.78 ; say. . . 4
Sand: 0.42 x 0.5 = 0.21 ; say. . . ............ 1
Gravel: 0.42 x 1 = 0.42 ; say. . . ........................ 1
3
Volume of roof beam (m ) 0.56
Quantity 2
Plus: 10% allowance for wastage 0.056
Total Volume (m3) 1.176
RB - 4B
Class: A (1:2:4) 40kg / bag
Cement: 1.176 x 9 = 10.584 ; say. . . 11
Sand: 1.176 x 0.5 = 0.588 ; say. . . ............ 1
Gravel: 1.176 x 1 = 1.176 ; say. . . ........................ 2

Materials Estimated Quantity Required


MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
SLABS
2ND FLOOR & THIRD FLOOR
Volume of slab (m3) 1.575
Quantity 8
Plus: 10% allowance for wastage 0.1575
Total Volume (m3) 12.7575
S-1
Class: A (1:2:4) 40kg / bag
Cement: 12.7575 x 9 = 114.8175 ; say. . . 115
Sand: 12.7575 x 0.5 = 6.37875 ; say. . . ............ 7
Gravel: 12.7575 x 1 = 12.7575 ; say. . . ........................ 13
Volume of slab (m3) 1.575
Quantity 4
Plus: 10% allowance for wastage 0.1575
Total Volume (m3) 6.4575
S-2
Class: A (1:2:4) 40kg / bag
Cement: 6.4575 x 9 = 58.1175 ; say. . . 59
Sand: 6.4575 x 0.5 = 3.22875 ; say. . . ............ 4
Gravel: 6.4575 x 1 = 6.4575 ; say. . . ........................ 7
3
Volume of slab (m ) 1.125
Quantity 10
Plus: 10% allowance for wastage 0.1125
Total Volume (m3) 11.3625
S-3
Class: A (1:2:4) 40kg / bag
Cement: 11.3625 x 9 = 102.2625 ; say. . . 103
Sand: 11.3625 x 0.5 = 5.68125 ; say. . . ............ 6
Gravel: 11.3625 x 1 = 11.3625 ; say. . . ........................ 12
Materials Estimated Quantity Required
MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
SLABS
2ND FLOOR & THIRD FLOOR
Volume of slab (m3) 1.175
Quantity 2
Plus: 10% allowance for wastage 0.1175
Total Volume (m3) 2.4675
S-4
Class: A (1:2:4) 40kg / bag
Cement: 2.4675 x 9 = 22.2075 ; say. . . 23
Sand: 2.4675 x 0.5 = 1.23375 ; say. . . ............ 2
Gravel: 2.4675 x 1 = 2.4675 ; say. . . ........................ 3
Volume of slab (m3) 1.41
Quantity 2
Plus: 10% allowance for wastage 0.141
Total Volume (m3) 2.961
S-5
Class: A (1:2:4) 40kg / bag
Cement: 2.961 x 9 = 26.649 ; say. . . 27
Sand: 2.961 x 0.5 = 1.4805 ; say. . . ............ 2
Gravel: 2.961 x 1 = 2.961 ; say. . . ........................ 3
3
Volume of slab (m ) 0.74
Quantity 2
Plus: 10% allowance for wastage 0.074
Total Volume (m3) 1.554
S-6
Class: A (1:2:4) 40kg / bag
Cement: 1.554 x 9 = 13.986 ; say. . . 14
Sand: 1.554 x 0.5 = 0.777 ; say. . . ............ 1
Gravel: 1.554 x 1 = 1.554 ; say. . . ........................ 2

Materials Estimated Quantity Required


MARK CALCULATION Cement Sand Gravel Gravel Fill
(bags) (cu.m) (cu.m) (cu.m)
STAIRS
GROUND FLOOR - THIRD FLOOR
Volume of steps (m3): 0.071
Quantity: 38
Volume of landing (m3): 0.413
Quantity: 2
Volume of string (m3): 0.945
Quantity: 4
STAIRS Plus: 10% allowance for wastage: 0.0071
Total Volume (m3): 7.3111
Class: A (1:2:4) 40kg / bag
Cement: 7.3111 x 9 = 65.7999 ; say. . . 66
Sand: 7.3111 x 0.5 = 3.65555 ; say. . . ............ 4
Gravel: 7.3111 x 1 = 7.3111 ; say. . . ........................ 8
BILL OF MATERIALS
STEEL WORKS

Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
FOUNDATION

5.69 0.24 -- 5.93 20 120 0.02


CF-1 6
3.35 -- -- 3.35 20 120 0.02

3.09 0.24 -- 3.33 20 120 0.02


CF-2 6
3.25 -- -- 3.25 20 120 0.02

0.09 0.144 -- 0.234 50 650 0.01


WF-1 13
16.05 -- -- 16.05 3 39 0.01

0.09 0.048 -- 0.138 2 4 0.01


WF-2 2
0.45 -- -- 0.45 3 3 0.01

0.24 0.10996 1.149 1.499 2 12 0.02

FTB-1 0.480 0.10996 1.31833 1.908 6 2 12 0.02

1.96746 0.24 -- 2.207 2 12 0.02

0.24 0.10996 2.799 3.149 2 12 0.02

FTB-2 0.480 0.10996 4.26833 4.858 6 2 12 0.02

6.39246 0.24 -- 6.632 2 12 0.02

0.24 0.10996 1.945 2.295 2 12 0.02

FTB-3
0.480 0.10996 2.61 3.200 6 2 12 0.02
(A)

3.90496 0.24 -- 4.145 2 12 0.02

0.24 0.10996 2.012 2.362 2 12 0.02

FTB-3
0.480 0.10996 2.74333 3.333 6 2 12 0.02
(B)

4.10496 0.24 -- 4.345 2 12 0.02


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
COLUMN (VERTICAL BARS)
FOUNDATION - GROUND FLOOR

C-1 0.144 0.066 1.413 1.623 6 12 72 0.012

C-2 0.144 0.066 1.413 1.623 6 12 72 0.012

C-3 0.144 0.066 1.413 1.623 6 12 72 0.012

GROUND FLOOR - SECOND FLOOR

C-1 3.3 -- -- 3.300 6 12 72 0.012

C-2 3.3 -- -- 3.300 6 12 72 0.012

C-3 3.3 -- -- 3.300 6 12 72 0.012

SECOND FLOOR - THIRD FLOOR

C-1 3.3 -- -- 3.300 6 12 72 0.012

C-2 3.3 -- -- 3.300 6 12 72 0.012

C-3 3.3 -- -- 3.300 6 12 72 0.012

THIRD FLOOR - ROOF LEVEL

C-1 2.6 -- -- 2.600 6 12 72 0.012

C-2 2.6 -- -- 2.600 6 12 72 0.012

C-3 2.6 -- -- 2.600 6 12 72 0.012

Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
COLUMN (LATERAL TIES)
FOUNDATION - GROUND FLOOR

C-1 0.947 2.367 0.126 3.439 6 15 90 0.012

C-2 1.413 3.533 0.126 5.073 6 15 90 0.012

C-3 1.347 3.367 0.126 4.839 6 15 90 0.012


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
COLUMN (LATERAL TIES)
GROUND FLOOR - SECOND FLOOR

C-1 0.853 2.133 0.126 3.113 6 27 162 0.012

C-2 1.32 3.3 0.126 4.746 6 27 162 0.012

C-3 1.253 3.133 0.126 4.513 6 27 162 0.012

SECOND FLOOR - THIRD FLOOR

C-1 0.853 2.133 0.126 3.113 6 27 162 0.012

C-2 1.253 3.133 0.126 4.513 6 27 162 0.012

C-3 1.253 3.133 0.126 4.513 6 27 162 0.012

THIRD FLOOR - ROOF LEVEL

C-1 0.853 2.133 0.126 3.113 6 27 162 0.012

C-2 0.987 2.467 0.126 3.579 6 27 162 0.012

C-3 0.987 2.467 0.126 3.579 6 27 162 0.012


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
MAIN BEAMS

0.240 0.110 1.822 2.172 2 8 0.02

G-1 (A) 0.480 0.110 1.400 1.990 4 -- -- 0.02

4.090 0.240 -- 4.330 4 16 0.02

0.240 0.110 0.988 1.338 2 2 0.02

G-1 (B) 0.480 0.110 1.067 1.657 1 -- -- 0.02

1.590 0.240 -- 1.830 4 4 0.02

0.240 0.110 1.888 2.238 2 2 0.02

G-1 (C) 0.480 0.110 2.867 3.457 1 -- -- 0.02

4.290 0.240 -- 4.530 4 4 0.02

0.240 0.110 1.938 2.288 4 16 0.02

G-2 (A) 0.480 0.110 2.617 3.207 4 -- -- 0.02

3.915 0.240 -- 4.155 4 16 0.02

S 0.240 0.110 1.105 1.455 4 4 0.02


E
G-2 (B) 0.480 0.110 0.950 1.540 1 -- -- 0.02
C
O 1.415 0.240 -- 1.655 4 4 0.02

N 0.240 0.110 2.005 2.355 4 4 0.02

D G-2 (C) 0.480 0.110 2.750 3.340 1 -- -- 0.02

4.115 0.240 -- 4.355 4 4 0.02


F
L 0.240 0.110 1.922 2.272 4 16 0.02

O G-3 (A) 0.480 0.110 2.633 3.223 4 -- -- 0.02

O 3.940 0.240 -- 4.180 4 16 0.02


R
0.240 0.110 2.013 2.363 4 4 0.02

G-3 (B) 0.480 0.110 2.767 3.357 1 -- -- 0.02

4.140 0.240 -- 4.380 4 4 0.02

0.240 0.110 1.701 2.051 5 5 0.02

G-4 0.480 0.110 1.342 1.932 1 2 2 0.02

2.002 0.240 -- 2.242 4 4 0.02

0.240 0.110 3.326 3.676 10 20 0.02

G-5 0.480 0.110 4.292 4.882 2 2 4 0.02

6.427 0.240 -- 6.667 4 8 0.02

0.240 0.110 1.701 2.051 6 30 0.02

G-6 0.480 0.110 1.342 1.932 5 2 10 0.02

2.002 0.240 -- 2.242 4 20 0.02


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
MAIN BEAMS

S 0.300 0.114 3.353 3.767 9 9 0.025


E
C G-7 0.600 0.114 4.292 5.006 1 2 2 0.025
O
N
6.421 0.300 -- 6.721 4 4 0.025
D

0.300 0.114 3.353 3.767 8 24 0.025


F
L
G-8 0.600 0.114 4.292 5.006 3 2 6 0.025
O
O
R 6.421 0.300 -- 6.721 4 12 0.025

Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
MAIN BEAMS

0.240 0.110 1.822 2.172 -- -- 0.02

G-1 (A) 0.480 0.110 1.400 1.990 4 -- -- 0.02

4.090 0.240 -- 4.330 2 8 0.02

0.240 0.110 0.988 1.338 -- -- 0.02

G-1 (B) 0.480 0.110 1.067 1.657 1 -- -- 0.02

1.590 0.240 -- 1.830 2 2 0.02

0.240 0.110 1.888 2.238 -- -- 0.02

G-1 (C) 0.480 0.110 2.867 3.457 1 -- -- 0.02

4.290 0.240 -- 4.530 2 2 0.02

T 0.240 0.110 1.922 2.272 2 8 0.02

H G-2 (A) 0.480 0.110 2.633 3.223 4 -- -- 0.02

I 3.940 0.240 -- 4.180 4 16 0.02


R
0.240 0.110 1.180 1.530 2 2 0.02
D
G-2 (B) 0.480 0.110 1.150 1.740 1 -- -- 0.02

F 1.715 0.240 -- 1.955 4 4 0.02

L 0.240 0.110 1.988 2.338 2 2 0.02


O
G-2 (C) 0.480 0.110 2.767 3.357 1 -- -- 0.02
O
R 4.140 0.240 -- 4.380 4 4 0.02

0.240 0.110 1.922 2.272 2 8 0.02

G-3 (A) 0.480 0.110 2.633 3.223 4 -- -- 0.02

3.940 0.240 -- 4.180 4 16 0.02

0.240 0.110 2.013 2.363 2 2 0.02

G-3 (B) 0.480 0.110 2.767 3.357 1 -- -- 0.02

4.140 0.240 -- 4.380 4 4 0.02

0.240 0.110 1.680 2.030 5 5 0.02

G-4 0.480 0.110 1.350 1.940 1 2 2 0.02

2.015 0.240 -- 2.255 4 4 0.02


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
MAIN BEAMS

0.240 0.110 2.755 3.105 8 16 0.02

G-5 0.480 0.110 4.300 4.890 2 3 6 0.02

T
6.440 0.240 -- 6.680 4 8 0.02
H
I 0.240 0.110 1.680 2.030 4 20 0.02

R G-6 0.480 0.110 1.350 1.940 5 2 10 0.02

D 2.015 0.240 -- 2.255 4 20 0.02

0.300 0.114 2.799 3.212 6 6 0.025


F
L G-7 0.600 0.114 4.333 5.047 1 2 2 0.025

O 6.484 0.300 -- 6.784 4 4 0.025

O 0.300 0.114 2.799 3.212 4 12 0.025

R
G-8 0.600 0.114 4.333 5.047 3 2 6 0.025

6.484 0.300 -- 6.784 4 12 0.025

Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
SECONDARY BEAMS

0.300 0.114 1.849 2.262 -- -- 0.025

B-1 0.600 0.114 2.733 3.447 4 -- -- 0.025


S
E 4.084 0.300 -- 4.384 4 16 0.025
C
O 0.240 0.110 1.888 2.238 2 2 0.02
N
D
B-2 0.480 0.110 2.867 3.457 1 2 2 0.02

F
4.290 0.240 -- 4.530 4 4 0.02
L
O
O 0.300 0.114 1.615 2.029 -- -- 0.025
R
B-3 0.600 0.114 2.467 3.181 1 -- -- 0.025

3.684 0.300 -- 3.984 4 4 0.025

0.300 0.114 1.849 2.262 -- -- 0.025

B-1 0.600 0.114 2.733 3.447 4 -- -- 0.025

T
4.084 0.300 -- 4.384 4 16 0.025
H
I
R 0.240 0.110 1.888 2.238 2 2 0.02
D
B-2 0.480 0.110 2.867 3.457 1 2 2 0.02
F
L 4.290 0.240 -- 4.530 4 4 0.02
O
O 0.300 0.114 1.615 2.029 -- -- 0.025
R
B-3 0.600 0.114 2.467 3.181 1 -- -- 0.025

3.684 0.300 -- 3.984 4 4 0.025


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (HORIZONTAL BARS)
ROOF BEAMS

0.192 0.107 1.800 2.099 4 16 0.016

RG-1 (A) 0.384 0.107 2.733 3.224 4 2 8 0.016

4.095 0.192 -- 4.287 4 16 0.016

0.192 0.107 1.867 2.166 4 4 0.016

RG-1 (B) 0.384 0.107 2.867 3.357 1 2 2 0.016

4.295 0.192 -- 4.487 4 4 0.016

0.192 0.107 1.833 2.132 4 32 0.016

RG-1 (C) 0.384 0.107 2.700 3.191 8 2 16 0.016

4.045 0.192 -- 4.237 4 32 0.016

0.192 0.107 1.900 2.199 4 8 0.016

RG-1 (D) 0.384 0.107 2.833 3.324 2 2 4 0.016

4.245 0.192 -- 4.437 4 8 0.016

R
0.192 0.107 1.575 1.874 2 4 0.016
O
O RG-2 (A) 0.384 0.107 1.383 1.874 2 1 2 0.016

F
2.070 0.192 -- 2.262 4 8 0.016

L 0.192 0.107 2.667 2.966 2 4 0.016


E
V RG-2 (B) 0.384 0.107 4.367 4.857 2 1 2 0.016

E
6.545 0.192 -- 6.737 4 8 0.016
L
0.192 0.107 1.575 1.874 1 2 0.016

RG-3 (A) 0.384 0.107 1.383 1.874 2 -- -- 0.016

2.070 0.192 -- 2.262 4 8 0.016

0.192 0.107 2.667 2.966 1 2 0.016

RG-3 (B) 0.384 0.107 4.367 4.857 2 -- -- 0.016

6.545 0.192 -- 6.737 4 8 0.016

0.192 0.107 2.825 3.124 -- -- 0.016

RG-4 (A) 0.384 0.107 3.883 4.374 2 -- -- 0.016

5.820 0.192 -- 6.012 4 8 0.016

0.192 0.107 2.417 2.716 1 2 0.016

RG-4 (B) 0.384 0.107 3.867 4.357 2 -- -- 0.016

5.795 0.192 -- 5.987 4 8 0.016


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (STIRRUPS)
FOUNDATION

FTB-1 0.220 0.420 0.063 0.703 6 36 216 0.01

FTB-2 0.220 0.420 0.063 0.703 6 36 216 0.012

FTB-3 0.220 0.420 0.063 0.703 15 72 1080 0.012

MAIN BEAMS

G-1 0.220 0.420 0.063 0.703 12 92 1104 0.01

G-2 0.220 0.370 0.063 0.653 12 80 960 0.012

G-3 0.220 0.370 0.063 0.653 10 45 450 0.012

G-4 0.320 0.320 0.063 0.703 2 19 38 0.012

G-5 0.320 0.420 0.063 0.803 4 58 232 0.012

G-6 0.320 0.320 0.063 0.703 10 19 190 0.012

G-7 0.320 0.420 0.063 0.803 2 58 116 0.012

G-8 0.320 0.420 0.063 0.803 6 58 348 0.012

SECONDARY BEAMS

B-1 0.120 0.320 0.063 0.503 8 37 296 0.01

B-2 0.220 0.320 0.063 0.603 2 38 76 0.01

B-3 0.120 0.320 0.063 0.503 2 34 68 0.01


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
BEAMS (STIRRUPS)
ROOF BEAMS

RG-1 0.220 0.320 0.063 0.603 15 74 1110 0.01

RG-2 0.120 0.320 0.063 0.503 4 69 276 0.01

RG-3 0.120 0.320 0.063 0.503 2 69 138 0.01

RG-4 (A) 0.120 0.320 0.063 0.503 2 46 92 0.01

RG-4 (B) 0.120 0.320 0.063 0.503 2 46 92 0.01


Length per bar Total length per No. of Structural No. of pieces per Total number of Bar Diameter
MARK Figure
a b c Bar member member bars (m)
STAIRS
STAIRS FOUNDATION

0.4 0.04 0.04 0.480 5 5 0.01


STAIRS
FOUNDATION 1
BARS
1.37 -- -- 1.37 3 3 0.01

FIRST FLOOR - SECOND FLOOR

LATERAL TIES 0.12 0.02356 0.27 0.414 19 19 0.01

CLOSED TIES 0.288 0.13195 2.74 3.160 19 19 0.012

NOSING BARS 1.37 -- -- 1.37 19 19 0.01


1
TOP BARS 0.7 -- -- 0.7 190 190 0.01

BOTTOM BARS 0.7 -- -- 0.7 190 190 0.01

LONGITUDINAL
0.2 2 1.56 3.76 20 20 0.016
BARS

SECOND FLOOR - THIRD FLOOR

LATERAL TIES 0.12 0.02356 0.27 0.414 19 19 0.01

CLOSED TIES 0.288 0.13195 2.74 3.160 19 19 0.012

NOSING BARS 1.37 -- -- 1.37 19 19 0.01


1
TOP BARS 0.7 -- -- 0.7 190 190 0.01

BOTTOM BARS 0.7 -- -- 0.7 190 190 0.01

LONGITUDINAL
0.2 2 1.56 3.76 20 20 0.016
BARS
Materials Estimated Quantity Required
MARK CALCULATION
6m 7.50 m 9m 10.6 m 12 m
SLABS
SECOND FLOOR
Area (m2): 15.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 4
Total Area (m2): 63
TWO-WAY SLAB
S-1 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
202.923 144.648 58.023 87.066
Therefore use; 58.023
No. of commercial length: 58.023 ;say. . . ........ ........ 58
3
Area (m ): 15.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 4
Total Area (m2): 63
TWO-WAY SLAB
S-2 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
202.923 144.648 58.023 87.066
Therefore use; 58.023
No. of commercial length: 58.023 ;say. . . ........ ........ 58
Area (m3): 11.25
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 5
Total Area (m2): 56.25
TWO-WAY SLAB
S-3 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
181.181 129.15 51.806 77.738
Therefore use; 51.806
No. of commercial length: 51.806 ;say. . . ........ ........ 52
Area (m3): 11.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 11.75
TWO-WAY SLAB
S-4 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
37.847 26.978 10.822 16.239
Therefore use; 10.822
No. of commercial length: 10.822 ;say. . . ........ ........ 11
Area (m3): 14.1
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 14.1
TWO-WAY SLAB
S-5 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
45.416 32.3736 12.986 19.486
Therefore use; 12.986
No. of commercial length: 12.986 ;say. . . ........ ........ 13
3
Area (m ): 7.4
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 7.4
ONE-WAY SLAB
S-6 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
23.835 16.9904 6.815 10.227
Therefore use; 6.815
No. of commercial length: 6.815 ;say. . . ........ ........ 7
Materials Estimated Quantity Required
MARK CALCULATION
6m 7.50 m 9m 10.6 m 12 m
SLABS
THIRD FLOOR
Area (m2): 15.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 4
Total Area (m2): 63
TWO-WAY SLAB
S-1 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
202.923 144.648 58.023 87.066
Therefore use; 58.023
No. of commercial length: 58.023 ;say. . . ........ ........ 58
Area (m3): 15.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 4
Total Area (m2): 63
TWO-WAY SLAB
S-2 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
202.923 144.648 58.023 87.066
Therefore use; 58.023
No. of commercial length: 58.023 ;say. . . ........ ........ 58
Area (m3): 11.25
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 5
Total Area (m2): 56.25
TWO-WAY SLAB
S-3 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
181.181 129.15 51.806 77.738
Therefore use; 51.806
No. of commercial length: 51.806 ;say. . . ........ ........ 52
3
Area (m ): 11.75
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 11.75
TWO-WAY SLAB
S-4 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
37.847 26.978 10.822 16.239
Therefore use; 10.822
No. of commercial length: 10.822 ;say. . . ........ ........ 11
3
Area (m ): 14.1
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 14.1
TWO-WAY SLAB
S-5 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
45.416 32.3736 12.986 19.486
Therefore use; 12.986
No. of commercial length: 12.986 ;say. . . ........ ........ 13
Area (m3): 7.4
Diameter (m): 0.01
Bar spacing (mm): 200
Quantity: 1
Total Area (m2): 7.4
ONE-WAY SLAB
S-6 No. of pcs per C/L of bars
Area x Multiplier
6m 7.50 m 9m 12 m
Factor 3.221 2.296 0.921 1.382
23.835 16.9904 6.815 10.227
Therefore use; 6.815
No. of commercial length: 6.815 ;say. . . ........ ........ 7
Materials Estimated
MARK CALCULATION Quantity Required
6m
CHB - STEEL
GROUND FLOOR
Total Area (m2): 442.62
Total Area of Openings (m2): 31.902
Total Net Area (m2): 410.718
Bar Spacing (mm): 400
CHB No. of Vertical Bar (Area x 2.93)
STEEL 410.718 x 2.93 = 1203.404
BARS No. of Horizontal Bar (Area x 3.30)
410.718 x 3.3 = 1355.369
Therefore;
Total no. of Bars 2558.773
= = 426.4622 ;say. . . 427
6.00 6.00
SECOND FLOOR
2
Total Area (m ): 458.82
Total Area of Openings (m2): 31.902
Total Net Area (m2): 426.918
Bar Spacing (mm): 400
CHB No. of Vertical Bar (Area x 2.93)
STEEL 426.918 x 2.93 = 1250.86974
BARS No. of Horizontal Bar (Area x 3.30)
426.918 x 3.3 = 1408.8294
Therefore;
Total no. of Bars 2659.699
= = 443.2832 ;say. . . 444
6.00 6.00
THIRD FLOOR
Total Area (m2): 458.82
Total Area of Openings (m2): 31.902
Total Net Area (m2): 426.918
Bar Spacing (mm): 400
CHB No. of Vertical Bar (Area x 2.93)
STEEL 426.918 x 2.93 = 1250.86974
BARS No. of Horizontal Bar (Area x 3.30)
426.918 x 3.3 = 1408.8294
Therefore;
Total no. of Bars 2659.699
= = 443.2832 ;say. . . 444
6.00 6.00
BILL OF MATERIALS
BAR CUTTING LIST

Length Diameter Wt/Meter Total Wt. Source


Description Quantity Bend Bar Type
(m) (mm) (kg/m) (kg) (m)
FOUNDATION

5.93 20 120 2.47 1757.652 6


CF-1
3.35 20 120 2.47 992.940 10.5

3.33 20 120 2.47 987.012 10.5


CF-2
3.25 20 120 2.47 963.300 10.5

0.234 10 650 0.62 94.302 7.5


WF-1
16.05 10 39 0.62 388.089 6

0.138 10 4 0.62 0.342 6


WF-2
0.45 10 3 0.62 0.837 9

1.499 20 12 2.47 44.430 7.5

FTB-1 1.908 20 12 2.47 56.553 6

2.207 20 12 2.47 65.415 9

3.149 20 12 2.47 93.336 10.5

FTB-2 4.858 20 12 2.47 143.991 10.5

6.632 20 12 2.47 196.572 7.5

2.295 20 12 2.47 68.024 12

FTB-3 (A) 3.2 20 12 2.47 94.848 10.5

4.145 20 12 2.47 122.858 12

2.362 20 12 2.47 70.010 12

FTB-3 (B) 3.333 20 12 2.47 98.790 10.5

4.345 20 12 2.47 128.786 9

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
COLUMN (VERTICAL BARS)
FOUNDATION - GROUND FLOOR

C-1 1.623 12 72 0.89 104.002 12

C-2 1.623 12 72 0.89 104.002 12

C-3 1.623 12 72 0.89 104.002 12


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
COLUMN (VERTICAL BARS)
GROUND FLOOR - SECOND FLOOR

C-1 3.3 12 72 0.89 211.464 10.5

C-2 3.3 12 72 0.89 211.464 10.5

C-3 3.3 12 72 0.89 211.464 10.5

SECOND FLOOR - THIRD FLOOR

C-1 3.3 12 72 0.89 211.464 10.5

C-2 3.3 12 72 0.89 211.464 10.5

C-3 3.3 12 72 0.89 211.464 10.5

THIRD FLOOR - ROOF LEVEL

C-1 2.6 12 72 0.89 166.608 10.5

C-2 2.6 12 72 0.89 166.608 10.5

C-3 2.6 12 72 0.89 166.608 10.5

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
COLUMN (LATERAL TIES)
FOUNDATION - GROUND FLOOR

C-1 3.439 12 90 0.89 275.464 10.5

C-2 5.073 12 90 0.89 406.347 10.5

C-3 4.839 12 90 0.89 387.604 10.5

GROUND FLOOR - SECOND FLOOR

C-1 3.113 12 162 0.89 448.832 10.5

C-2 4.746 12 162 0.89 684.278 10.5

C-3 4.513 12 162 0.89 650.684 10.5


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
COLUMN (LATERAL TIES)
SECOND FLOOR - THIRD FLOOR

C-1 3.113 12 162 0.89 448.832 10.5

C-2 4.513 12 162 0.89 650.684 10.5

C-3 4.513 12 162 0.89 650.684 10.5

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
COLUMN (LATERAL TIES)
THIRD FLOOR - ROOF LEVEL

C-1 3.113 12 162 0.89 448.832 10.5

C-2 3.579 12 162 0.89 516.020 10.5

C-3 3.579 12 162 0.89 516.020 10.5

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
SECOND FLOOR

2.172 20 8 2.47 42.919 9


G-1 (A)
4.33 20 16 2.47 171.122 9

1.338 20 2 2.47 6.610 6


G-1 (B)
1.83 20 4 2.47 18.080 7.5

2.238 20 2 2.47 11.056 9


G-1 (C)
4.53 20 4 2.47 44.756 10.5

2.288 20 16 2.47 90.422 12


G-2 (A)
4.155 20 16 2.47 164.206 9

1.455 20 4 2.47 14.375 6


G-2 (B)
1.655 20 4 2.47 16.351 12

2.355 20 4 2.47 23.267 12


G-2 (C)
4.355 20 4 2.47 43.027 9

2.272 20 16 2.47 89.789 12


G-3 (A)
4.18 20 16 2.47 165.194 9

2.363 20 4 2.47 23.346 12


G-3 (B)
4.38 20 4 2.47 43.274 9
Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
SECOND FLOOR

2.051 20 5 2.47 25.330 10.5

G-4 1.932 20 2 2.47 9.544 6

2.242 20 4 2.47 22.151 9

3.676 20 5 2.47 45.399 7.5

G-5 4.882 20 2 2.47 24.117 10.5

6.667 20 4 2.47 65.870 7.5

2.051 20 30 2.47 151.979 10.5

G-6 1.932 20 10 2.47 47.720 6

2.242 20 20 2.47 110.755 9

3.767 25 9 2.47 83.740 12

G-7 5.006 25 2 2.47 24.730 10.5

6.721 25 4 2.47 66.403 7.5

3.767 25 24 2.47 223.308 12

G-8 5.006 25 6 2.47 74.189 10.5

6.721 25 12 2.47 199.210 7.5

THIRD FLOOR

G-1 (A) 4.33 20 8 2.47 85.561 9

G-1 (B) 1.83 20 4 2.47 18.080 7.5

G-1 (C) 4.53 20 4 2.47 44.756 10.5

2.272 20 8 2.47 44.895 12


G-2 (A)
4.18 20 16 2.47 165.194 9

1.53 20 2 2.47 7.558 12


G-2 (B)
1.955 20 4 2.47 19.315 6

2.338 20 2 2.47 11.550 7.5


G-2 (C)
4.38 20 4 2.47 43.274 9

2.272 20 8 2.47 44.895 7.5


G-3 (A)
4.18 20 16 2.47 165.194 9

2.363 20 2 2.47 11.673 12


G-3 (B)
4.38 20 4 2.47 43.274 9

2.03 20 5 2.47 25.071 9

G-4 1.94 20 2 2.47 9.584 6

2.255 20 4 2.47 22.279 12


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
THIRD FLOOR

3.105 20 16 2.47 122.710 9

G-5 4.89 20 6 2.47 72.470 10.5

6.68 20 8 2.47 131.997 7.5

2.03 20 20 2.47 100.282 9

G-6 1.94 20 10 2.47 47.918 6

2.255 20 20 2.47 111.397 12

3.212 25 6 3.85 74.197 10.5

G-7 5.047 25 2 3.85 38.862 10.5

6.784 25 4 3.85 104.474 7.5

3.212 25 12 3.85 148.394 7.5

G-8 5.047 25 6 3.85 116.586 10.5

6.784 25 12 3.85 313.421 7.5

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (SECONDARY BEAMS - HORIZONTAL BARS)
SECOND FLOOR

B-1 4.384 25 16 3.85 270.054 9

2.238 20 2 2.47 11.056 9

B-2 3.457 20 2 2.47 17.078 7.5

4.53 20 4 2.47 44.756 10.5

B-3 3.984 25 4 3.85 61.354 12

THIRD FLOOR

B-1 4.384 25 16 3.85 270.054 9

2.238 20 2 2.47 11.056 9

B-2 3.457 20 2 2.47 17.078 7.5

4.53 20 4 2.47 44.756 10.5

B-3 3.984 25 4 3.85 61.354 12

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (ROOF BEAMS - HORIZONTAL BARS)
ROOF LEVEL

2.099 16 16 1.58 53.063 10.5

RG-1 (A) 3.224 16 8 1.58 40.751 10.5

4.287 16 16 1.58 108.375 9

2.166 16 4 1.58 13.689 9

RG-1 (B) 3.357 16 2 1.58 10.608 10.5

4.487 16 4 1.58 28.358 9


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (ROOF BEAMS - HORIZONTAL BARS)
ROOF LEVEL

2.132 16 32 1.58 107.794 9

RG-1 (C) 3.191 16 16 1.58 80.668 7.5

4.237 16 32 1.58 214.223 9

2.199 16 8 1.58 27.795 9

RG-1 (D) 3.324 16 4 1.58 21.008 10.5

4.437 16 8 1.58 56.084 9

1.874 16 4 1.58 11.844 7.5

RG-2 (A) 1.874 16 2 1.58 5.922 7.5

2.262 16 8 1.58 28.592 12

2.966 16 4 1.58 18.745 6

RG-2 (B) 4.857 16 2 1.58 15.348 10.5

6.737 16 8 1.58 85.156 7.5

1.874 16 2 1.58 5.922 7.5


RG-3 (A)
2.262 16 8 1.58 28.592 12

2.966 16 2 1.58 9.373 9


RG-3 (B)
6.737 16 8 1.58 85.156 7.5

RG-4 (A) 6.012 16 8 1.58 75.992 7.5

2.716 16 2 1.58 8.583 6


RG-4 (B)
5.987 16 8 1.58 75.676 6

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (STIRRUPS)
FOUNDATION

FTB-1 0.703 10 216 0.62 94.146 12

FTB-2 0.703 12 216 0.89 135.145 12

FTB-3 0.703 12 1080 0.89 675.724 12

MAIN BEAMS

G-1 0.703 10 1104 0.62 481.189 12

G-2 0.653 12 960 0.89 557.923 10.5

G-3 0.653 12 450 0.89 261.527 10.5

G-4 0.703 10 38 0.62 16.563 12


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
BEAM (STIRRUPS)
MAIN BEAMS

G-5 0.803 12 232 0.89 165.803 10.5

G-6 0.703 12 190 0.89 118.877 12

G-7 0.803 12 116 0.89 82.902 10.5

G-8 0.803 12 348 0.89 248.705 10.5

SECONDARY BEAMS

B-1 0.503 10 296 0.62 92.311 12

B-2 0.603 12 76 0.89 40.787 10.5

B-3 0.503 12 68 0.89 30.442 12

ROOF BEAMS

RG-1 0.603 10 1110 0.62 414.985 10.5

RG-2 0.503 10 276 0.62 86.073 12

RG-3 0.503 10 138 0.62 43.037 12

RG-4 (A) 0.503 10 92 0.62 28.691 12

RG-4 (B) 0.503 10 92 0.62 28.691 12

Length Diameter Wt/Meter Total Wt.


Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
STAIRS
STAIRS FOUNDATION

STAIRS 0.48 10 5 0.62 1.488 12


FOUNDATION
BARS 1.37 10 3 0.62 2.548 6

GROUND FLOOR - SECOND FLOOR

LATERAL TIES 0.414 10 19 0.62 4.877 7.5

CLOSED TIES 3.16 12 19 0.89 53.436 10.5

NOSING BARS 1.37 10 19 0.62 16.139 6

TOP BARS 0.7 10 190 0.62 82.460 10.5

BOTTOM BARS 0.7 10 190 0.62 82.460 10.5


Length Diameter Wt/Meter Total Wt.
Description Quantity Source Bend Bar Type
(m) (mm) (kg/m) (kg)
STAIRS
GROUND FLOOR - SECOND FLOOR

LONGITUDINAL
3.76 16 20 1.58 118.816 12
BARS

SECOND FLOOR - THIRD FLOOR

LATERAL TIES 0.414 10 19 0.62 4.877 7.5

CLOSED TIES 3.16 12 19 0.89 53.436 10.5

NOSING BARS 1.37 10 19 0.62 16.139 6

TOP BARS 0.7 10 190 0.62 82.460 10.5

BOTTOM BARS 0.7 10 190 0.62 82.460 10.5

LONGITUDINAL
3.76 16 20 1.58 118.816 12
BARS
BILL OF MATERIALS
EXCESS CUTTING LIST

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
FOUNDATION
0.012 120 2.47 3.499 WASTE
20mmØ, CF-1
0.134 40 2.47 13.272 WASTE
0.153 40 2.47 15.132 WASTE
20mmØ, CF-2
0.231 40 2.47 22.800 USABLE
0.051 21 0.62 0.668 WASTE
10mmØ, WF-1
0.374 39 0.62 9.039 USABLE
0.478 1 0.62 0.297 USABLE
10mmØ, WF-2
0 1 0.62 0 WASTE
0.003 3 2.47 0.025 WASTE
10mmØ, FTB-1 0.145 4 2.47 1.429 WASTE
0.078 3 2.47 0.577 WASTE
0.334 4 2.47 3.304 USABLE
10mmØ, FTB-2 0.161 6 2.47 2.392 WASTE
0.131 12 2.47 3.879 WASTE
0.229 3 2.47 1.695 USABLE
10mmØ, FTB-3 (A) 0.281 4 2.47 2.779 USABLE
0.895 6 2.47 13.265 WASTE
0.080 3 2.47 0.596 WASTE
10mmØ, FTB-3 (B) 0.150 4 2.47 1.485 WASTE
0.071 6 2.47 1.057 WASTE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
COLUMN (VERTICAL BARS)
FOUNDATION - GROUND FLOOR
12mmØ, C-1 0.738 11 0.89 7.225 USABLE
12mmØ, C-2 0.738 11 0.89 7.225 USABLE
12mmØ, C-3 0.738 11 0.89 7.225 USABLE
GROUND FLOOR - SECOND FLOOR
12mmØ, C-1 0.629 24 0.89 13.426 USABLE
12mmØ, C-2 0.629 24 0.89 13.426 USABLE
12mmØ, C-3 0.629 24 0.89 13.426 USABLE
SECOND FLOOR - THIRD FLOOR
12mmØ, C-1 0.629 24 0.89 13.426 USABLE
12mmØ, C-2 0.629 24 0.89 13.426 USABLE
12mmØ, C-3 0.629 24 0.89 13.426 USABLE
THIRD FLOOR - ROOF LEVEL
12mmØ, C-1 0.829 18 0.89 13.274 USABLE
12mmØ, C-2 0.829 18 0.89 13.274 USABLE
12mmØ, C-3 0.829 18 0.89 13.274 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
COLUMN (LATERAL TIES)
FOUNDATION - GROUND FLOOR
12mmØ, C-1 0.477 30 0.89 12.740 USABLE
12mmØ, C-2 0.483 45 0.89 19.338 USABLE
12mmØ, C-3 0.477 45 0.89 19.110 USABLE
Length Wt/Meter Total Wt.
Description Quantity REMARKS
(m) (kg/m) (kg)
COLUMN (LATERAL TIES)
GROUND FLOOR - SECOND FLOOR
12mmØ, C-1 0.029 54 0.89 1.401 WASTE
12mmØ, C-2 0.224 81 0.89 16.148 USABLE
12mmØ, C-3 0.629 81 0.89 45.355 USABLE
SECOND FLOOR - THIRD FLOOR
12mmØ, C-1 0.029 54 0.89 1.401 WASTE
12mmØ, C-2 0.629 81 0.89 45.355 USABLE
12mmØ, C-3 0.629 81 0.89 45.355 USABLE
THIRD FLOOR - ROOF LEVEL
12mmØ, C-1 0.029 54 0.89 1.401 WASTE
12mmØ, C-2 0.219 81 0.89 15.777 USABLE
12mmØ, C-3 0.219 81 0.89 15.777 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
SECOND FLOOR
0.931 2 2.47 4.597 USABLE
20mmØ, G-1 (A)
0.698 8 2.47 13.788 USABLE
0.446 1 2.47 1.102 USABLE
20mmØ, G-1 (B)
0.976 1 2.47 2.411 USABLE
0.497 1 2.47 1.228 USABLE
20mmØ, G-1 (C)
0.726 2 2.47 3.585 USABLE
0.051 4 2.47 0.501 WASTE
20mmØ, G-2 (A)
0.387 8 2.47 7.641 USABLE
0.970 1 2.47 2.396 USABLE
20mmØ, G-2 (B)
0.552 1 2.47 1.363 USABLE
0.785 1 2.47 1.939 USABLE
20mmØ, G-2 (C)
0.936 2 2.47 4.622 USABLE
0.029 4 2.47 0.290 WASTE
20mmØ, G-3 (A)
0.431 8 2.47 8.519 USABLE
0.788 1 2.47 1.946 USABLE
20mmØ, G-3 (B)
0.947 2 2.47 4.677 USABLE
0.977 1 2.47 2.412 USABLE
20mmØ, G-4 0.644 1 2.47 1.591 USABLE
0.996 1 2.47 2.461 USABLE
0.451 3 2.47 3.339 USABLE
20mmØ, G-5 0.930 1 2.47 2.297 USABLE
0.556 4 2.47 5.491 USABLE
0.860 6 2.47 12.745 USABLE
20mmØ, G-6 0.220 4 2.47 2.174 USABLE
0.982 5 2.47 12.130 USABLE
0.825 1 2.47 2.038 USABLE
25mmØ, G-7 0.954 1 2.47 2.355 USABLE
0.585 4 2.47 5.775 USABLE
0.534 8 2.47 10.552 USABLE
25mmØ, G-8 0.861 3 2.47 6.377 USABLE
0.754 12 2.47 22.337 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
THIRD FLOOR
20mmØ, G-1 (A) 0.849 4 2.47 8.387 USABLE
20mmØ, G-1 (B) 0.976 1 2.47 2.411 USABLE
Length Wt/Meter Total Wt.
Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (MAIN BEAMS - HORIZONTAL BARS)
THIRD FLOOR
20mmØ, G-1 (C) 0.726 2 2.47 3.585 USABLE
0.515 2 2.47 2.542 USABLE
20mmØ, G-2 (A)
0.431 8 2.47 8.519 USABLE
0.255 1 2.47 0.630 USABLE
20mmØ, G-2 (B)
0.303 2 2.47 1.498 USABLE
0.623 1 2.47 1.540 USABLE
20mmØ, G-2 (C)
0.947 2 2.47 4.677 USABLE
0.423 3 2.47 3.138 USABLE
20mmØ, G-3 (A)
0.431 8 2.47 8.519 USABLE
0.394 1 2.47 0.973 USABLE
20mmØ, G-3 (B)
0.947 2 2.47 4.677 USABLE
0.128 2 2.47 0.631 WASTE
20mmØ, G-4 0.647 1 2.47 1.597 USABLE
0.752 1 2.47 1.857 USABLE
0.520 8 2.47 10.275 USABLE
20mmØ, G-5 0.794 3 2.47 5.886 USABLE
0.125 8 2.47 2.477 WASTE
0.511 5 2.47 6.312 USABLE
20mmØ, G-6 0.233 4 2.47 2.305 USABLE
0.758 4 2.47 7.492 USABLE
0.835 2 3.85 6.433 USABLE
25mmØ, G-7 0.961 1 3.85 3.701 USABLE
0.618 4 3.85 9.519 USABLE
0.139 1 3.85 0.536 WASTE
25mmØ, G-8 0.884 3 3.85 10.210 USABLE
0.854 12 3.85 39.473 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (SECONDARY BEAMS - HORIZONTAL BARS)
SECOND FLOOR
25mmØ, B-1 0.794 8 3.85 24.448 USABLE
0.497 1 2.47 1.228 USABLE
20mmØ, B-2 0.922 1 2.47 2.277 USABLE
0.726 2 2.47 3.585 USABLE
25mmØ, B-3 0.328 2 3.85 2.526 USABLE
THIRD FLOOR
25mmØ, B-1 0.794 8 3.85 24.448 USABLE
0.497 1 2.47 1.228 USABLE
20mmØ, B-2 0.922 1 2.47 2.277 USABLE
0.726 2 2.47 3.585 USABLE
25mmØ, B-3 0.328 2 3.85 2.526 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (ROOF BEAMS - HORIZONTAL BARS)
ROOF LEVEL
0.198 4 1.58 1.254 WASTE
16mmØ, RG-1 (A) 0.456 3 1.58 2.163 USABLE
0.621 1 1.58 0.982 USABLE
0.963 1 1.58 1.521 USABLE
16mmØ, RG-1 (B) 0.639 1 1.58 1.010 USABLE
0.994 2 1.58 3.142 USABLE
Length Wt/Meter Total Wt.
Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (ROOF BEAMS - HORIZONTAL BARS)
ROOF LEVEL
0.580 8 1.58 7.337 USABLE
16mmØ, RG-1 (C) 0.807 2 1.58 2.552 USABLE
0.065 16 1.58 1.640 WASTE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (ROOF BEAMS - HORIZONTAL BARS)
ROOF LEVEL
0.955 2 1.58 3.017 USABLE
16mmØ, RG-1 (D) 0.266 2 1.58 0.841 USABLE
0.944 4 1.58 5.966 USABLE
0.999 3 1.58 4.737 USABLE
16mmØ, RG-2 (A) 0.500 1 1.58 0.790 USABLE
0.508 2 1.58 1.605 USABLE
0.977 2 1.58 3.088 USABLE
16mmØ, RG-2 (B) 0.925 1 1.58 1.462 USABLE
0.186 4 1.58 1.176 USABLE
0.500 1 1.58 0.790 USABLE
16mmØ, RG-3 (A)
0.508 2 1.58 1.605 USABLE
0.659 1 1.58 1.041 USABLE
16mmØ, RG-3 (B)
0.186 8 1.58 2.353 WASTE
16mmØ, RG-4 (A) 0.413 5 1.58 3.261 USABLE
0.905 1 1.58 1.430 USABLE
16mmØ, RG-4 (B)
0.983 8 1.58 12.421 USABLE

Length Wt/Meter Total Wt.


Description Quantity REMARKS
(m) (kg/m) (kg)
BEAM (STIRRUPS)
FOUNDATION
10mmØ, FTB-1 0.654 13 0.62 5.271 USABLE
12mmØ, FTB-2 0.654 13 0.89 7.567 USABLE
12mmØ, FTB-3 0.270 1 0.89 0.240 USABLE
MAIN BEAMS
10mmØ, G-1 0.676 65 0.62 27.243 USABLE
12mmØ, G-2 0.703 60 0.89 37.533 USABLE
12mmØ, G-3 0.986 2 0.89 1.755 USABLE
10mmØ, G-4 0.226 3 0.62 0.421 USABLE
12mmØ, G-5 0.742 18 0.89 11.894 USABLE
12mmØ, G-6 0.131 12 0.89 1.397 WASTE
12mmØ, G-7 0.871 9 0.89 6.979 USABLE
12mmØ, G-8 0.614 3 0.89 1.639 USABLE
SECONDARY BEAMS
10mmØ, B-1 0.407 13 0.62 3.283 USABLE
12mmØ, B-2 0.365 5 0.89 1.622 USABLE
12mmØ, B-3 0.850 4 0.89 3.027 USABLE
ROOF BEAMS
10mmØ, RG-1 0.746 66 0.62 30.515 USABLE
10mmØ, RG-2 0.569 12 0.62 4.233 USABLE
10mmØ, RG-3 0.785 5 0.62 2.432 USABLE
10mmØ, RG-4 (A) 0.856 4 0.62 2.124 USABLE
10mmØ, RG-4 (B) 0.856 4 0.62 2.124 USABLE
Length Wt/Meter Total Wt.
Description Quantity REMARKS
(m) (kg/m) (kg)
STAIRS
STAIRS FOUNDATION
0.200 1 0.62 0.124 WASTE
10mmØ, STAIRS FOUNDATION
0.685 1 0.62 0.425 USABLE
FIRST FLOOR - SECOND FLOOR
10mmØ, LATERAL TIES 0.049 2 0.62 0.061 WASTE
12mmØ, CLOSED TIES 0.718 7 0.89 4.474 USABLE
10mmØ, NOSING BARS 0.338 5 0.62 1.049 USABLE
10mmØ, TOP BARS 0.667 13 0.62 5.373 USABLE
10mmØ, BOTTOM BARS 0.667 13 0.62 5.373 USABLE
16mmØ, LONGITUDINAL BARS 0.267 7 1.58 2.949 USABLE
SECOND FLOOR - THIRD FLOOR
10mmØ, LATERAL TIES 0.049 2 0.62 0.061 WASTE
12mmØ, CLOSED TIES 0.718 7 0.89 4.474 USABLE
10mmØ, NOSING BARS 0.338 5 0.62 1.049 USABLE
10mmØ, TOP BARS 0.667 13 0.62 5.373 USABLE
10mmØ, BOTTOM BARS 0.667 13 0.62 5.373 USABLE
16mmØ, LONGITUDINAL BARS 0.267 7 1.58 2.949 USABLE
BILL OF MATERIALS
BAR ORDER LIST

Total Wt.
Description Quantity Wt / pc
(kg)
25 mm Ø, 7.5 m 33 2.47 81.51
25 mm Ø, 9 m 16 2.47 39.52
25 mm Ø, 10.5 m 10 2.47 24.7
25 mm Ø, 12 m 13 2.47 32.11
20 mm Ø, 6 m 138 2.47 340.86
20 mm Ø, 7.5 m 59 2.47 145.73
20 mm Ø, 9 m 87 2.47 214.89
20 mm Ø, 10.5 m 157 2.47 387.79
20 mm Ø, 12 m 27 2.47 66.69
16 mm Ø, 6 m 11 1.58 17.38
16 mm Ø, 7.5 m 24 1.58 37.92
16 mm Ø, 9 m 35 1.58 55.3
16 mm Ø, 10.5 m 11 1.58 17.38
16 mm Ø, 12 m 18 1.58 28.44
12 mm Ø, 10.5 m 1077 0.89 958.53
12 mm Ø, 12 m 63 0.89 56.07
10 mm Ø, 6 m 1366 0.62 846.92
10 mm Ø, 7.5 m 25 0.62 15.5
10 mm Ø, 9 m 399 0.62 247.38
10 mm Ø, 10.5 m 118 0.62 73.16
10 mm Ø, 12 m 120 0.62 74.4
BILL OF ESTIMATES
MASONRY WORKS

Materials Estimated Quantity Required


MARK CALCULATIONS Cement Sand CHB (5") CHB (4")
(bags) (cu.m) (pcs) (pcs)
WALLS
GROUND FLOOR
2
Area of wall (m ): 134.27
2
Area of Openings ( doors & windows ) (m ): 12.381
Plus: 5% allowance for wastage: 6.7135
Total Area (m3): 128.6025
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 128.6025 x 1 = 128.6025 ; say. . . 129
Sand: 128.6025 x 0.5 = 64.30125 ; say. . . ............ 65
CHB: 128.6025 x 12.5 = 1607.5313 ; say. . . ........................ 1608
Area of wall (m2) 87.04
Area of Openings ( doors & windows ) (m2) 3.57
Plus: 5% allowance for wastage 4.352
Total Area (m3) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 1 = 87.822 ; say. . . 88
Sand: 87.822 x 0.5 = 43.911 ; say. . . ............ 44
CHB 87.822 x 12.5 = 1097.775 ; say. . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 1098
SECOND FLOOR
Area of wall (m2) 142.37
2
Area of Openings ( doors & windows ) (m ) 12.381
Plus: 5% allowance for wastage 7.1185
3
Total Area (m ) 137.1075
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 137.1075 x 1 = 137.1075 ; say. . . 138
Sand: 137.1075 x 0.5 = 68.55375 ; say. . . ............ 69
CHB 137.1075 x 12.5 = 1713.8438 ; say. . . ........................ 1714
2
Area of wall (m ) 87.04
Area of Openings ( doors & windows ) (m2) 3.57
Plus: 5% allowance for wastage 4.352
Total Area (m3) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 1 = 87.822 ; say. . . 88
Sand: 87.822 x 0.5 = 43.911 ; say. . . ............ 44
CHB 87.822 x 12.5 = 1097.775 ; say. . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 1098
THIRD FLOOR
2
Area of wall (m ) 142.37
Area of Openings ( doors & windows ) (m2) 12.381
Plus: 5% allowance for wastage 7.1185
3
Total Area (m ) 137.1075
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 137.1075 x 1 = 137.1075 ; say. . . 138
Sand: 137.1075 x 0.5 = 68.55375 ; say. . . ............ 69
CHB 137.1075 x 12.5 = 1713.8438 ; say. . . ........................ 1714
Area of wall (m2) 87.04
Area of Openings ( doors & windows ) (m2) 3.57
Plus: 5% allowance for wastage 4.352
3
Total Area (m ) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 1 = 87.822 ; say. . . 88
Sand: 87.822 x 0.5 = 43.911 ; say. . . ............ 44
CHB 87.822 x 12.5 = 1097.775 ; say. . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . 1098
Materials Estimated
Quantity Required
MARK CALCULATIONS
Cement Sand
(bags) (cu.m)
MORTAR
GROUND FLOOR
No. of CHB 1608

EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 1608 x 0.098 = 157.584 ; say. . . 158
Sand: 1608 x 0.05 = 80.4 ; say. . . ............ 81
No. of CHB 1098

INTERIOR Class: A ( 1:2:4) 40kg / bag


Cement: 1098 x 0.098 = 107.604 ; say. . . 108
Sand: 1098 x 0.05 = 54.9 ; say. . . ............ 55
SECOND FLOOR
No. of CHB 1714

EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 1714 x 0.098 = 167.972 ; say. . . 168
Sand: 1714 x 0.05 = 85.7 ; say. . . ............ 86
No. of CHB 1098

INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 1098 x 0.098 = 107.604 ; say. . . 108
Sand: 1098 x 0.05 = 54.9 ; say. . . ............ 55
THIRD FLOOR
No. of CHB 1714

EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 1714 x 0.098 = 167.972 ; say. . . 168
Sand: 1714 x 0.05 = 85.7 ; say. . . ............ 86
No. of CHB 1098

INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 1098 x 0.098 = 107.604 ; say. . . 108
Sand: 1098 x 0.05 = 54.9 ; say. . . ............ 55
Materials Estimated Quantity Required
MARK CALCULATIONS Cement Sand Lime
(bags) (cu.m) (bags)
PLASTERING
GROUND FLOOR
Area of wall (m2) 134.27
Area of Openings ( doors & windows ) (m2) 12.381
Plus: 5% allowance for wastage 6.7135
3
Total Area (m ) 128.6025
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 128.6025 x 0.098 = 12.603045 ; say. . . 13
Sand: 128.6025 x 0.01 = 1.286025 ; say. . . ............ 2
Lime 128.6025 x 0.098 = 12.603045 ; say. . . ........................ 13
2
Area of wall (m ) 87.04
2
Area of Openings ( doors & windows ) (m ) 3.57
Plus: 5% allowance for wastage 4.352
3
Total Area (m ) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 0.098 = 8.606556 ; say. . . 9
Sand: 87.822 x 0.01 = 0.87822 ; say. . . ............ 1
Lime 87.822 x 0.098 = 8.606556 ; say. . . ........................ 9
SECOND FLOOR
2
Area of wall (m ) 142.37
Area of Openings ( doors & windows ) (m2) 12.381
Plus: 5% allowance for wastage 7.1185
Total Area (m3) 137.1075
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 137.1075 x 0.098 = 13.436535 ; say. . . 14
Sand: 137.1075 x 0.01 = 1.371075 ; say. . . ............ 2
Lime 137.1075 x 0.098 = 13.436535 ; say. . . ........................ 14
2
Area of wall (m ) 87.04
2
Area of Openings ( doors & windows ) (m ) 3.57
Plus: 5% allowance for wastage 4.352
Total Area (m3) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 0.098 = 8.606556 ; say. . . 9
Sand: 87.822 x 0.01 = 0.87822 ; say. . . ............ 1
Lime 87.822 x 0.098 = 8.606556 ; say. . . ........................ 9
THIRD FLOOR
Area of wall (m2) 142.37
Area of Openings ( doors & windows ) (m2) 12.381
Plus: 5% allowance for wastage 7.1185
Total Area (m3) 137.1075
EXTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 137.1075 x 0.098 = 13.436535 ; say. . . 14
Sand: 137.1075 x 0.01 = 1.371075 ; say. . . ............ 2
Lime 137.1075 x 0.098 = 13.436535 ; say. . . ........................ 14
2
Area of wall (m ) 87.04
2
Area of Openings ( doors & windows ) (m ) 3.57
Plus: 5% allowance for wastage 4.352
3
Total Area (m ) 87.822
INTERIOR
Class: A ( 1:2:4) 40kg / bag
Cement: 87.822 x 0.098 = 8.606556 ; say. . . 9
Sand: 87.822 x 0.01 = 0.87822 ; say. . . ............ 1
Lime 87.822 x 0.098 = 8.606556 ; say. . . ........................ 9
BILL OF MATERIALS
CARPENTRY WORKS

Material Estimated Quantity Required


MARK CALCULATION
PLYWOOD LUMBER
4' x 8' x 1/4" 2" X 2" bd. Ft.
CEILING
GROUND FLOOR
2
Area of the Ceiling (m ): 15.75
Quantity: 8
2
Total Area (m ): 126
COMPUTATION
CEILING
1 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 806.022 ;say. . . ............... 807
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 126
= = 43.75 ;say. . . 44
Effective Covering 2.88
2
Area of the Ceiling (m ): 11.25
Quantity: 4
Total Area (m2): 45
COMPUTATION
CEILING
1 (B) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 287.865 ;say. . . ............... 288
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 45
= = 15.625 ;say. . . 16
Effective Covering 2.88
Area of the Ceiling (m2): 14.1
Quantity: 1
2
Total Area (m ): 14.1
COMPUTATION
CEILING
2 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 90.1977 ;say. . . ............... 91
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 14.1
= = 4.8958333 ;say. . . 5
Effective Covering 2.88
Area of the Ceiling (m2): 7.6
Quantity: 1
Total Area (m2): 7.6
COMPUTATION
CEILING
2 (B) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 48.6172 ;say. . . ............... 49
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 7.6
= = 2.6388889 ;say. . . 3
Effective Covering 2.88
SECOND FLOOR
Area of the Ceiling (m2): 15.75
Quantity: 8
Total Area (m2): 126
COMPUTATION
CEILING
1 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 806.022 ;say. . . ............... 807
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 126
= = 43.75 ;say. . . 44
Effective Covering 2.88
Material Estimated Quantity Required
MARK CALCULATION
PLYWOOD LUMBER
4' x 8' x 1/4" 2" X 2" bd. Ft.
CEILING
SECOND FLOOR
Area of the Ceiling (m2): 11.25
Quantity: 4
2
Total Area (m ): 45
COMPUTATION
CEILING
1 (B) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 287.865 ;say. . . ............... 288
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 45
= = 15.625 ;say. . . 16
Effective Covering 2.88
Area of the Ceiling (m2): 14.1
Quantity: 1
Total Area (m2): 14.1
COMPUTATION
CEILING
2 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 90.1977 ;say. . . ............... 91
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 14.1
= = 4.8958333 ;say. . . 5
Effective Covering 2.88
2
Area of the Ceiling (m ): 7.6
Quantity: 1
Total Area (m2): 7.6
COMPUTATION
CEILING
2 (B) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 48.6172 ;say. . . ............... 49
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 7.6
= = 2.6388889 ;say. . . 3
Effective Covering 2.88
THIRD FLOOR
2
Area of the Ceiling (m ): 63
Quantity: 2
2
Total Area (m ): 126
COMPUTATION
CEILING
1 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 806.022 ;say. . . ............... 807
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 126
= = 43.75 ;say. . . 44
Effective Covering 2.88
Area of the Ceiling (m2): 22.5
Quantity: 2
Total Area (m2): 45
COMPUTATION
CEILING
1 (B) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 287.865 ;say. . . ............... 288
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 45
= = 15.625 ;say. . . 16
Effective Covering 2.88
Material Estimated Quantity Required
MARK CALCULATION
PLYWOOD LUMBER
4' x 8' x 1/4" 2" X 2" bd. Ft.
CEILING
THIRD FLOOR
Area of the Ceiling (m2): 44.65
Quantity: 1
2
Total Area (m ): 44.65
COMPUTATION
CEILING
2 Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 285.62605 ;say. . . ............... 286
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 44.65
= = 15.503472 ;say. . . 16
Effective Covering 2.88
Area of the Ceiling (m2): 6.75
Quantity: 8
Total Area (m2): 54
COMPUTATION
CEILING
3 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 345.438 ;say. . . ............... 346
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 54
= = 18.75 ;say. . . 19
Effective Covering 2.88
2
Area of the Ceiling (m ): 7.05
Quantity: 2
Total Area (m2): 14.1
COMPUTATION
CEILING
3 (A) Ceiling Joist using 40 x 40 cm spacing
Area of Ceiling x 6.397 = 90.1977 ;say. . . ............... 91
Ceiling Board using 40 x 40 cm board size
Area of Ceiling 14.1
= = 4.8958333 ;say. . . 5
Effective Covering 2.88
BILL OF MATERIALS
FORM WORKS

Materials Estimated Quantity Required


PLYWOOD LUMBER 4D
MARK CALCULATIONS COMMON
4' x 8' x 4' x 8' x 2'x2' 2'x3' NAIL
1/4" 1/2" (bd. ft) (bd. ft) (kg)
COLUMNS
GROUND FLOOR
Area of Columns (m2): 37.562
Plus: 10% allowance for wastage: 3.756
Total Net Area (m3): 41.318
No. of Plywood
Total Net Area 41.318
= = 14.347 ; say. . . 15
2.88 2.88
COLUMNS
No. of Wood Frame
No. of Lumber x 29.67
= 425.664 ; say. . . ........ ........ 426
14.347 x 29.67
Nails
Length to be nailed x 4 1702.654
= = 2.838 ; say. . . ........ ........ ........ ........ 3
6 x 100 600
SECOND FLOOR
Area of Columns (m2) 37.282
Plus: 10% allowance for wastage 34.073
Total Net Area (m3) 71.355

Total Net Area 71.355


= = 24.776 ; say. . . 25
2.88 2.88
COLUMNS

No. of Lumber x 29.67


= 735.105 ; say. . . ........ ........ 736
24.776 x 29.67

Length to be nailed x 4 2940.421


= = 4.901 ; say. . . ........ ........ ........ ........ 5
6 x 100 600
THIRD FLOOR
Area of Columns (m2) 4.378
Plus: 10% allowance for wastage 0.438
Total Net Area (m3) 4.816

Total Net Area 4.816


= = 1.672 ; say. . . 2
2.88 2.88
COLUMNS

No. of Lumber x 29.67


= 49.613 ; say. . . ........ ........ 50
1.672 x 29.67

Length to be nailed x 4 198.451


= = 0.331 ; say. . . ........ ........ ........ ........ 1
6 x 100 600

Materials Estimated Quantity Required


PLYWOOD LUMBER 4D
MARK CALCULATIONS COMMON
4' x 8' x 4' x 8' x 2'x2' 2'x3' NAIL
1/4" 1/2" (bd. ft) (bd. ft) (kg)
BEAMS
GROUND FLOOR
Area of Beams (m2) 108.735
Plus: 5% allowance for wastage 5.437
Total Net Area (m3) 114.172

Total Net Area 114.172


= = 39.643 ; say. . . 40
2.88 2.88
BEAMS

No. of Lumber x 29.67


= 1176.207 ; say. . . ........ ........ 1177
39.643 x 29.67

Length to be nailed x 4 4704.828


= = 7.841 ; say. . . ........ ........ ........ ........ 8
6 x 100 600
Materials Estimated Quantity Required
PLYWOOD LUMBER 4D
MARK CALCULATIONS COMMON
4' x 8' x 4' x 8' x 2'x2' 2'x3' NAIL
1/4" 1/2" (bd. ft) (bd. ft) (kg)
BEAMS
SECOND FLOOR
Area of Beams (m2) 172.921
Plus: 5% allowance for wastage 8.646
Total Net Area (m3) 181.567

Total Net Area 181.567


= = 63.044 ; say. . . 64
2.88 2.88
BEAMS

No. of Lumber x 29.67


= 1870.519 ; say. . . ........ ........ 1871
63.044 x 29.67

Length to be nailed x 4 7482.076


= = 12.470 ; say. . . ........ ........ ........ ........ 13
6 x 100 600
THIRD FLOOR
Area of Beams (m2) 172.921
Plus: 5% allowance for wastage 8.646
Total Net Area (m3) 181.567

Total Net Area 181.567


= = 63.044 ; say. . . 64
2.88 2.88
BEAMS

No. of Lumber x 29.67


= 1870.519 ; say. . . ........ ........ 1871
63.044 x 29.67

Length to be nailed x 4 7482.076


= = 12.470 ; say. . . ........ ........ ........ ........ 13
6 x 100 600

Materials Estimated Quantity Required


PLYWOOD LUMBER 4D
MARK CALCULATIONS COMMON
4' x 8' x 4' x 8' x 2'x2' 2'x3' NAIL
1/4" 1/2" (bd. ft) (bd. ft) (kg)
SLABS
SECOND FLOOR
Area of Slabs (m2): 37.562
Plus: 5% allowance for wastage: 1.8781
Total Net Area (m3) 39.440
SLAB
No. of Plywood
Total Net Area 39.440
= = 13.694 ; say. . . . . . . . . . . . . 14
2.88 2.88
THIRD FLOOR
Area of Slabs (m2): 37.562
Plus: 5% allowance for wastage: 1.8781
Total Net Area (m3): 39.440
SLAB
No. of Plywood
Total Net Area 39.440
= = 13.694 ; say. . . . . . . . . . . . . 14
2.88 2.88
BILL OF MATERIALS
SCAFFOLDING AND STAGING

Materials Estimated Quantity Required


MARK CALCULATION LUMBER LUMBER CWL NAIL
2" x 2" (bd. Ft.) 2" x 3" (bd. Ft.)20d (kg)
COLUMN
GROUND FLOOR
Total length of columns (m): 57.6
COMPUTATIONS
Vertical 57.60 x 7.00 = 403.2 ;say. . . . . . . . . . . . . . . 404
COLUMNS SUPPORT Horizontal 57.60 x 21.00 = 1209.6 ;say. . . 1210
Brace 57.60 x 11.70 = 673.92 ;say. . . 674
Total length of columns x 0.73
NAILS
57.60 x 0.73 = 42.05 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 43
SECOND FLOOR
Total length of columns (m): 57.6
COMPUTATIONS
Vertical 57.60 x 7.00 = 403.2 ;say. . . . . . . . . . . . . . . 404
COLUMNS SUPPORT Horizontal 57.60 x 21.00 = 1209.6 ;say. . . 1210
Brace 57.60 x 11.70 = 673.92 ;say. . . 674
Total length of columns x 0.73
NAILS
57.60 x 0.73 = 42.05 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 43
THIRD FLOOR
Total length of columns (m): 57.6
COMPUTATIONS
Vertical 57.60 x 7.00 = 403.2 ;say. . . . . . . . . . . . . . . 404
COLUMNS SUPPORT Horizontal 57.60 x 21.00 = 1209.6 ;say. . . 1210
Brace 57.60 x 11.70 = 673.92 ;say. . . 674
Total length of columns x 0.73
NAILS
57.60 x 0.73 = 42.05 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 43
ROOF LEVEL
Total length of columns (m): 45.0
COMPUTATIONS
Vertical 45.00 x 7.00 = 315 ;say. . . . . . . . . . . . . . . 315
COLUMNS SUPPORT Horizontal 45.00 x 21.00 = 945 ;say. . . 945
Brace 45.00 x 11.70 = 526.5 ;say. . . 527
Total length of columns x 0.73
NAILS
45.00 x 0.73 = 32.85 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 33

Materials Estimated Quantity Required


MARK CALCULATION LUMBER LUMBER CWL NAIL
2" x 2" (bd. Ft.) 2" x 3" (bd. Ft.)20d (kg)
BEAM
GROUND FLOOR
Total length of beams (m): 125.1
COMPUTATIONS
Vertical 125.10 x 7.00 = 875.7 ;say. . . . . . . . . . . . . . . 876
BEAMS SUPPORT Horizontal 125.10 x 21.00 = 2627.1 ;say. . . 2628
Brace 125.10 x 11.70 = 1463.67 ;say. . . 1464
Total length of columns x 0.73
NAILS
125.10 x 0.73 = 91.32 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 92
SECOND FLOOR
Total length of beams (m): 125.1
COMPUTATIONS
Vertical 125.10 x 7.00 = 875.7 ;say. . . . . . . . . . . . . . . 876
BEAMS SUPPORT Horizontal 125.10 x 21.00 = 2627.1 ;say. . . 2628
Brace 125.10 x 11.70 = 1463.67 ;say. . . 1464
Total length of columns x 0.73
NAILS
125.10 x 0.73 = 91.32 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 92
Materials Estimated Quantity Required
MARK CALCULATION LUMBER LUMBER CWL NAIL
2" x 2" (bd. Ft.) 2" x 3" (bd. Ft.)20d (kg)
BEAM
THIRD FLOOR
Total length of beams (m): 125.1
COMPUTATIONS
Vertical 125.10 x 7.00 = 875.7 ;say. . . . . . . . . . . . . . . 876
BEAMS SUPPORT Horizontal 125.10 x 21.00 = 2627.1 ;say. . . 2628
Brace 125.10 x 11.70 = 1463.67 ;say. . . 1464
Total length of columns x 0.73
NAILS
125.10 x 0.73 = 91.32 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 92
ROOF
Total length of beams (m): 106.1
COMPUTATIONS
Vertical 106.10 x 7.00 = 743 ;say. . . . . . . . . . . . . . . 743
BEAMS SUPPORT Horizontal 106.10 x 21.00 = 2228 ;say. . . 2229
Brace 106.10 x 11.70 = 1241.4 ;say. . . 1242
Total length of columns x 0.73
NAILS
106.10 x 0.73 = 77.45 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 78

Materials Estimated Quantity Required


MARK CALCULATION LUMBER LUMBER CWL NAIL
2" x 2" (bd. Ft.) 2" x 3" (bd. Ft.)20d (kg)
SLAB
SECOND FLOOR
Total Area of slabs (m): 215.7
COMPUTATIONS
Vertical 215.65 x 7.00 = 1509.6 ;say. . . . . . . . . . . . . . . 1510
SLABS SUPPORT Horizontal 215.65 x 21.00 = 4528.7 ;say. . . 4529
Brace 215.65 x 11.70 = 2523.11 ;say. . . 2524
Total length of columns x 0.73
NAILS
215.65 x 0.73 = 157.42 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 158
THIRD FLOOR
Total Area of slabs (m): 215.7
COMPUTATIONS
Vertical 215.65 x 7.00 = 1509.6 ;say. . . . . . . . . . . . . . . 1510
SLABS SUPPORT Horizontal 215.65 x 21.00 = 4528.7 ;say. . . 4529
Brace 215.65 x 11.70 = 2523.11 ;say. . . 2524
Total length of columns x 0.73
NAILS
215.65 x 0.73 = 157.42 ;say. . . . . . . . . . . . . . . . . . . . . . . . . . . 158
BILL OF MATERIALS
ROOF WORKS

Materials Estimated QuantityRequired


G.I. CORR G.26 G.I. PLAIN
MARK CALCULATIONS Rivets G.I. Washer
32' x 12' 32' x 8' 36' x 12'
(pcs) (pcs) Gauge (kg) (kg)
Length of Gutter (m)1: 23.9
Length of Gutter (m)2: 12.5
Covering Side Lapping: 0.7
G.I. COMPUTATION
SHEETS 23.9
Length of Gutter = 34.143 ;say. . . 35
0.7
12.5
Covering Side Lapping = 17.857 ;say. . . .......... 18
0.7
Total length of Gutter (m): 23.9
Covering Side Lapping: 12.5
COMPUTATION
RIVETS For 8ft. long: 430.2 ;say. . .
For 9ft. long: 525.8 ;say. . .
Total Rivets CONVERTION
430.2 + 525.8
= 5.311 ;say. . . .......... .......... .......... 6
180
Total length of Gutter (m): 23.9
Covering Side Lapping: 12.5
COMPUTATION
G.I. Double the
WASHER 956 x 2 = 1912
number of Rivets
Total Rivets CONVERTION
1912
= 10.622 ;say. . . .......... .......... .......... .......... 11
180
Total number of Rivets (pcs): 956
PLAIN
Using 2" x 5" C Purlins
G.I.
Total Plain G.I. Washer 956
STRAP = 3.064 ;say. . . .......... .......... 4
312
Total number of Rivets (pcs): 956
LEAD Using 2" x 5" C Purlins
WASHER Total Plain G.I. Washer 956
= 12.747 ;say. . . .......... .......... 13
75
Length of Gutter (m)1: 23.9
Length of Gutter (m)2: 12.5
COMPUTATION
Length of Gutter 23.9+12.5
GUTTER Number of Gutter = 15.489
Effective length of one Gutter 2.35
Width of Plain G.I. Sheets 90
= 2
Total number of G.I. Total width of Gutters 45
Sheets for Gutter 15.489
Therefore; = 7.745 ;say. . . . . . . . . . . . . . . . . . . . . . . 8
2
Length of Flashing (m): 6.91
COMPUTATION
FLUSHING Total length of Flashing: 6.91 x 4 = 27.64
Standard Corrugated Sheets of Therefore; 27.64
= 12.09 ;say. . . . . . . . . . . . . . . . . . . . . . . 13
Outside Flashing: 2.286 2.286
Length of Top Chord (m): 13.82
Spacing of Purlins (m): 0.5
COMPUTATION
PURLINS Number of Purlins in 1 Length of Top Chord 13.82
= 27.64
row Spacing of Purlins 0.5
Combination of 2 pcs. Therefore;
;say. . . . . . . . . . . . . . . . . . . . . . . 56
6m (12') C Purlins 27.64 x 2 = 55.28
BILL OF MATERIALS
TIE WIRES

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
FOUNDATION
No. of intersection to be tied: 2400
Total ties of Footing: 2400
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(CF-1) Total length of Ties
2400 x 0.40 = 960
960
Kilo of Tie Wire = 18.113 ;say. . . 19
53
No. of intersection to be tied: 2400
Total ties of Footing: 2400
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(CF-2) Total length of Ties
2400 x 0.40 = 960
960
Kilo of Tie Wire = 18.113 ;say. . . 19
53
No. of intersection to be tied: 1950
Total ties of Footing: 1950
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(WF-1) Total length of Ties
1950 x 0.40 = 780
780
Kilo of Tie Wire = 14.717 ;say. . . 15
53
No. of intersection to be tied: 12
Total ties of Footing: 12
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(WF-2) Total length of Ties
12 x 0.40 = 4.8
4.8
Kilo of Tie Wire = 0.091 ;say. . . 1
53
No. of intersection to be tied: 1296
Total ties of Footing: 1296
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(FTB-1) Total length of Ties
1296 x 0.40 = 518.4
518.4
Kilo of Tie Wire = 9.781 ;say. . . 10
53
No. of intersection to be tied: 1296
Total ties of Footing: 1296
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(FTB-2) Total length of Ties
1296 x 0.40 = 518.4
518.4
Kilo of Tie Wire = 9.781 ;say. . . 10
53
No. of intersection to be tied: 6480
Total ties of Footing: 6480
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(FTB-3) Total length of Ties
6480 x 0.40 = 2592
2592
Kilo of Tie Wire = 48.906 ;say. . . 49
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
COLUMN
FOUNDATION - GROUND FLOOR
No. of intersection to be tied: 1080
Total ties of Column: 1080
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-1) Total length of Ties
1080 x 0.40 = 432
432
Kilo of Tie Wire = 8.151 ;say. . . 9
53
No. of intersection to be tied: 1080
Total ties of Column: 1080
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-2) Total length of Ties
1080 x 0.40 = 432
432
Kilo of Tie Wire = 8.151 ;say. . . 9
53
No. of intersection to be tied: 1080
Total ties of Column: 1080
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-3) Total length of Ties
1080 x 0.40 = 432
432
Kilo of Tie Wire = 8.151 ;say. . . 9
53
GROUND FLOOR - SECOND FLOOR
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-1) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-2) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-3) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
SECOND FLOOR - THIRD FLOOR
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-1) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
COLUMN
SECOND FLOOR - THIRD FLOOR
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-2) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-3) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
COLUMN
THIRD FLOOR - ROOF LEVEL
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-1) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-2) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53
No. of intersection to be tied: 1944
Total ties of Column: 1944
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(C-3) Total length of Ties
1944 x 0.40 = 777.6
777.6
Kilo of Tie Wire = 14.672 ;say. . . 15
53

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
BEAMS
MAIN BEAMS
No. of intersection to be tied: 7728
Total ties of Beam: 7728
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-1) Total length of Ties
7728 x 0.40 = 3091.2
3091.2
Kilo of Tie Wire = 58.325 ;say. . . 59
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
BEAMS
MAIN BEAMS
No. of intersection to be tied: 8960
Total ties of Beam: 8960
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-2) Total length of Ties
8960 x 0.40 = 3584
3584
Kilo of Tie Wire = 67.623 ;say. . . 68
53
No. of intersection to be tied: 4320
Total ties of Beam: 4320
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-3) Total length of Ties
4320 x 0.40 = 1728
1728
Kilo of Tie Wire = 32.604 ;say. . . 33
53
No. of intersection to be tied: 418
Total ties of Beam: 418
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-4) Total length of Ties
418 x 0.40 = 167.2
167.2
Kilo of Tie Wire = 3.155 ;say. . . 4
53
No. of intersection to be tied: 3712
Total ties of Beam: 3712
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-5) Total length of Ties
3712 x 0.40 = 1484.8
1484.8
Kilo of Tie Wire = 28.015 ;say. . . 29
53

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
BEAMS
MAIN BEAMS
No. of intersection to be tied: 2280
Total ties of Beam: 2280
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-6) Total length of Ties
2280 x 0.40 = 912
912
Kilo of Tie Wire = 17.208 ;say. . . 18
53
No. of intersection to be tied: 1740
Total ties of Beam: 1740
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-7) Total length of Ties
1740 x 0.40 = 696
696
Kilo of Tie Wire = 13.132 ;say. . . 14
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
BEAMS
MAIN BEAMS
No. of intersection to be tied: 1740
Total ties of Beam: 1740
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-8) Total length of Ties
1740 x 0.40 = 696
696
Kilo of Tie Wire = 13.132 ;say. . . 14
53
SECONDARY BEAMS
No. of intersection to be tied: 1184
Total ties of Beam: 1184
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(B-1) Total length of Ties
1184 x 0.40 = 473.6
473.6
Kilo of Tie Wire = 8.936 ;say. . . 9
53
No. of intersection to be tied: 608
Total ties of Beam: 608
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(B-2) Total length of Ties
608 x 0.40 = 243.2
243.2
Kilo of Tie Wire = 4.589 ;say. . . 5
53
No. of intersection to be tied: 272
Total ties of Beam: 272
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(B-3) Total length of Ties
272 x 0.40 = 108.8
108.8
Kilo of Tie Wire = 2.053 ;say. . . 3
53
ROOF BEAMS
No. of intersection to be tied: 11100
Total ties of Beam: 11100
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(RG-1) Total length of Ties
11100 x 0.40 = 4440
4440
Kilo of Tie Wire = 83.774 ;say. . . 84
53
No. of intersection to be tied: 1932
Total ties of Beam: 1932
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(RG-2) Total length of Ties
1932 x 0.40 = 772.8
772.8
Kilo of Tie Wire = 14.581 ;say. . . 15
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
BEAMS
ROOF BEAMS
No. of intersection to be tied: 1380
Total ties of Beam: 1380
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(RG-3) Total length of Ties
1380 x 0.40 = 552
552
Kilo of Tie Wire = 10.415 ;say. . . 11
53
No. of intersection to be tied: 368
Total ties of Beam: 368
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(RG-4A) Total length of Ties
368 x 0.40 = 147.2
147.2
Kilo of Tie Wire = 2.777 ;say. . . 3
53
No. of intersection to be tied: 368
Total ties of Beam: 368
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(RG-4B) Total length of Ties
368 x 0.40 = 147.2
147.2
Kilo of Tie Wire = 2.777 ;say. . . 3
53

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
STAIRS
STAIRS FOUNDATION
No. of intersection to be tied: 15
Total ties of Stairs: 15

TIE Compuation using 0.40m Ties


WIRES Total ties of Footing x 0.40
Total length of Ties
15 x 0.40 = 6
6
Kilo of Tie Wire = 0.113 ;say. . . 1
53
GROUND FLOOR - SECOND FLOOR
No. of intersection to be tied: 477
Total ties of Stairs: 477

TIE Compuation using 0.40m Ties


WIRES Total ties of Footing x 0.40
Total length of Ties
477 x 0.40 = 190.8
190.8
Kilo of Tie Wire = 3.600 ;say. . . 4
53
SECOND FLOOR - THIRD FLOOR
No. of intersection to be tied: 477
Total ties of Stairs: 477
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(G-1) Total length of Ties
477 x 0.40 = 190.8
190.8
Kilo of Tie Wire = 3.600 ;say. . . 4
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
SLAB
GROUND FLOOR
No. of intersection to be tied: 32250
Total ties of Stairs: 32250
Compuation using 0.40m Ties
TIE WIRES
(SLAB-FILL) Total ties of Footing x 0.40
Total length of Ties
32250 x 0.40 = 12900
12900
Kilo of Tie Wire = 243.396 ;say. . . 244
53
SECOND FLOOR
No. of intersection to be tied: 8600
Total ties of Beam: 8600
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-1) Total length of Ties
8600 x 0.40 = 3440
3440
Kilo of Tie Wire = 64.906 ;say. . . 65
53

Materials Estimated
MARK CALCULATIONS Quantity Required
#16
SLAB
SECOND FLOOR
No. of intersection to be tied: 8400
Total ties of Beam: 8400
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-2) Total length of Ties
8400 x 0.40 = 3360
3360
Kilo of Tie Wire = 63.396 ;say. . . 64
53
No. of intersection to be tied: 8800
Total ties of Beam: 8800
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-3) Total length of Ties
8800 x 0.40 = 3520
3520
Kilo of Tie Wire = 66.415 ;say. . . 67
53
No. of intersection to be tied: 2200
Total ties of Beam: 2200
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-4) Total length of Ties
2200 x 0.40 = 880
880
Kilo of Tie Wire = 16.604 ;say. . . 17
53
No. of intersection to be tied: 2050
Total ties of Beam: 2050
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-5) Total length of Ties
2050 x 0.40 = 820
820
Kilo of Tie Wire = 15.472 ;say. . . 16
53
Materials Estimated
MARK CALCULATIONS Quantity Required
#16
SLAB
SECOND FLOOR
No. of intersection to be tied: 2200
Total ties of Beam: 2200
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-6) Total length of Ties
2200 x 0.40 = 880
880
Kilo of Tie Wire = 16.604 ;say. . . 17
53
THIRD FLOOR
No. of intersection to be tied: 8600
Total ties of Beam: 8600
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-1) Total length of Ties
8600 x 0.40 = 3440
3440
Kilo of Tie Wire = 64.906 ;say. . . 65
53
No. of intersection to be tied: 8400
Total ties of Beam: 8400
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-2) Total length of Ties
8400 x 0.40 = 3360
3360
Kilo of Tie Wire = 63.396 ;say. . . 64
53
No. of intersection to be tied: 8800
Total ties of Beam: 8800
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-3) Total length of Ties
8800 x 0.40 = 3520
3520
Kilo of Tie Wire = 66.415 ;say. . . 67
53
No. of intersection to be tied: 2200
Total ties of Beam: 2200
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-4) Total length of Ties
2200 x 0.40 = 880
880
Kilo of Tie Wire = 16.604 ;say. . . 17
53
No. of intersection to be tied: 2050
Total ties of Beam: 2050
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-5) Total length of Ties
2050 x 0.40 = 820
820
Kilo of Tie Wire = 15.472 ;say. . . 16
53
No. of intersection to be tied: 2200
Total ties of Beam: 2200
TIE Compuation using 0.40m Ties
WIRES Total ties of Footing x 0.40
(S-6) Total length of Ties
2200 x 0.40 = 880
880
Kilo of Tie Wire = 16.604 ;say. . . 17
53
BILL OF ESTIMATES
PAINT WORKS

Materials Estimated Quantity Required


MARK CALCULATION Surface Primer Final Coat Neutralizer
(gal) (gal) (L)
GROUND FLOOR
Area of wall (m²): x 2 268.54
Area of openings (m²): x 2 24.762
Plus: 5% allowance for wastage: 13.427
Total Area (m3): 257.205

Computation using fine to smooth surface formula


EXTERIOR 257.205
Surface Primer = 6.430 ; say. . . 7
40
257.205
Final Coat = 6.430 ; say. . .. ........... 7
40
7
Neutralizer = 2.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 3
2.5
Area of wall (m²): x 2 174.08
Area of openings (m²): x 2 7.14
Plus: 5% allowance for wastage: 8.704
Total Area (m3): 175.644

Computation using fine to smooth surface formula


INTERIOR
175.644
Surface Primer = 4.391 ; say. . . 5
40
175.644
Final Coat = 4.391 ; say. . .. ........... 5
40
5
Neutralizer = 2.000 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 2
2.5
Area of ceiling (m²): x 2 431.30
Area of openings (m²): x 2 0.00
Plus: 5% allowance for wastage: 21.57
Total Area (m3): 452.87

Computation using fine to smooth surface formula


CEILING 452.865
Surface Primer = 11.322 ; say. . . 12
40
452.865
Final Coat = 11.322 ; say. . .. ........... 12
40
12
Neutralizer = 4.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 5
2.5
SECOND FLOOR
Area of wall (m²): x 2 284.74
Area of openings (m²): x 2 24.762
Plus: 5% allowance for wastage: 14.237
Total Area (m3): 274.215

Computation using fine to smooth surface formula


EXTERIOR 274.215
Surface Primer = 6.855 ; say. . . 7
40
274.215
Final Coat = 6.855 ; say. . .. ........... 7
40
7
Neutralizer = 2.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 3
2.5
Materials Estimated Quantity Required
MARK CALCULATION Surface Primer Final Coat Neutralizer
(gal) (gal) (L)
SECOND FLOOR
Area of wall (m²): x 2 174.08
Area of openings (m²): x 2 7.14
Plus: 5% allowance for wastage: 8.704
Total Area (m3): 175.644

Computation using fine to smooth surface formula


INTERIOR 175.644
Surface Primer = 4.391 ; say. . . 5
40
175.644
Final Coat = 4.391 ; say. . .. ........... 5
40
5
Neutralizer = 2.000 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 2
2.5
Area of ceiling (m²): x 2 431.30
Area of openings (m²): x 2 0.00
Plus: 5% allowance for wastage: 21.57
Total Area (m3): 452.87

Computation using fine to smooth surface formula


CEILING 452.865
Surface Primer = 11.322 ; say. . . 12
40
452.865
Final Coat = 11.322 ; say. . .. ........... 12
40
12
Neutralizer = 4.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 5
2.5
THIRD FLOOR
Area of wall (m²): x 2 284.74
Area of openings (m²): x 2 24.762
Plus: 5% allowance for wastage: 14.237
Total Area (m3): 274.215

Computation using fine to smooth surface formula


EXTERIOR 274.215
Surface Primer = 6.855 ; say. . . 7
40
274.215
Final Coat = 6.855 ; say. . .. ........... 7
40
7
Neutralizer = 2.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 3
2.5
Area of wall (m²): x 2 174.08
Area of openings (m²): x 2 7.14
Plus: 5% allowance for wastage: 8.704
Total Area (m3): 175.644

Computation using fine to smooth surface formula


INTERIOR 175.644
Surface Primer = 4.391 ; say. . . 5
40
175.644
Final Coat = 4.391 ; say. . .. ........... 5
40
5
Neutralizer = 2.000 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 2
2.5
Area of ceiling (m²): x 2 431.30
Area of openings (m²): x 2 0.00
Plus: 5% allowance for wastage: 21.57
Total Area (m3): 452.87

Computation using fine to smooth surface formula


CEILING 452.865
Surface Primer = 11.322 ; say. . . 12
40
452.865
Final Coat = 11.322 ; say. . .. ........... 12
40
12
Neutralizer = 4.800 ; say. . . . . . . . . . . . . .. .. . . . . . . . . . . 5
2.5
BILL OF MATERIALS
TILE WORKS

Materials Estimated Quantity Required


20x20cm TILE WHITE INTERNAL INTERNAL
MARK CALCULATIONS
GLAZED ADHESIVE CEMENT CAPPING CORNER CORNER
WALL TILES (bags) (kg) COVE BEAD

WALLS
GROUND FLOOR - THIRD FLOOR
2
Area of floor (m ): 3.7
Plus: 10% allowance for wastage: 0.37
2
Total Net Area (m ): 4.07
COMPUTATION
Using 20 x 20 cm glazed wall tiles
FLOOR TILES Total net Area x 25.307
= 102.99949 103
4.07 x 25.307
TILE Total net Area x 0.501
ADHESIVE
= 2.03907 ................. 3
4.07 x 0.501
CR (PWD) WHITE Total net Area x 1.75
= 7.1225 ................. ................. 8
CEMENT 4.07 x 1.75
Perimeter = 7.7
CAPPING perimeter 7.7
= = 6.416667 ................. ................. ................. 7
length of cap 1.2
INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL
CORNER COVE CORNERS. THEREFORE; 4 PCS. ................. ................. ................. ................. 4 PCS

INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL


CORNER BEAD CORNERS. THEREFORE; 5 PCS. ................. ................. ................. ................. ................. 4 PCS

GROUND FLOOR - THIRD FLOOR


Area of floor (m2) 2.9
Plus: 10% allowance for wastage 0.29
Total Net Area (m2) 3.19

Using 20 x 20 cm glazed wall tiles


FLOOR TILES Total net Area x 25.307
= 80.72933 81
3.19 x 25.307
TILE Total net Area x 0.501
ADHESIVE
= 1.59819 ................. 2
3.19 x 0.501
WHITE Total net Area x 1.75
CR 1 = 5.5825 ................. ................. 6
CEMENT 3.19 x 1.75
Perimeter = 6.9
CAPPING perimeter 6.9
= = 5.75 ................. ................. ................. 6
length of cap 1.2
INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL
CORNER COVE CORNERS. THEREFORE; 4 PCS. ................. ................. ................. ................. 4 PCS

INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL


CORNER BEAD CORNERS. THEREFORE; 5 PCS. ................. ................. ................. ................. ................. 4 PCS

GROUND FLOOR - THIRD FLOOR


2
Area of floor (m ) 4.2
Plus: 10% allowance for wastage 0.42
2
Total Net Area (m ) 4.62

Using 20 x 20 cm glazed wall tiles


FLOOR TILES Total net Area x 25.307
= 116.91834 117
4.62 x 25.307
TILE Total net Area x 0.501
ADHESIVE
= 2.31462 ................. 3
4.62 x 0.501
CR 2 WHITE Total net Area x 1.75
= 8.085 ................. ................. 9
CEMENT 4.62 x 1.75
Perimeter = 8.8
CAPPING perimeter 8.8
= = 7.333333 ................. ................. ................. 8
length of cap 1.2

INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL


CORNER COVE CORNERS. THEREFORE; 4 PCS. ................. ................. ................. ................. 4 PCS

INTERNAL BY DIRECT COUNTING, THERE ARE 4 INTERNAL


CORNER BEAD CORNERS. THEREFORE; 5 PCS. ................. ................. ................. ................. ................. 4 PCS
BILL OF ESTIMATES
EARTH WORKS

Materials Estimated Quantity


MARK CALCULATIONS Required
Earthfill
Original Soil Volume (m³) 63
Excavated Loose Soil Volume (m³) 78.75
Net Backfill Volume (m³) 52.5
Excess Soil (Loose) (m³) 13.125
CF-1
Additional Soil for Compaction (m³) 5.25
Net Excess Soil (m³) 7.875
Quantity 6
3
Total Volume (m ): 1323 1323
Original Soil Volume (m³) 34.68
Excavated Loose Soil Volume (m³) 43.35
Net Backfill Volume (m³) 28.9
Excess Soil (Loose) (m³) 7.225
CF-2
Additional Soil for Compaction (m³) 2.89
Net Excess Soil (m³) 4.335
Quantity 6
Total Volume (m3): 728.28 729
Original Soil Volume (m³) 3.888
Excavated Loose Soil Volume (m³) 4.86
Net Backfill Volume (m³) 2.592
Excess Soil (Loose) (m³) 1.62
WF-1
Additional Soil for Compaction (m³) 0.2592
Net Excess Soil (m³) 1.3608
Quantity 13
Total Volume (m3): 189.54 190
Original Soil Volume (m³) 0.144
Excavated Loose Soil Volume (m³) 0.18
Net Backfill Volume (m³) 0.096
Excess Soil (Loose) (m³) 0.06
WF-2
Additional Soil for Compaction (m³) 0.0096
Net Excess Soil (m³) 0.0504
Quantity 2
Total Volume (m3): 1.08 2
Original Soil Volume (m³) 2.2125
Excavated Loose Soil Volume (m³) 2.765625
Net Backfill Volume (m³) 1.8375
Excess Soil (Loose) (m³) 0.46875
FTB-1
Additional Soil for Compaction (m³) 0.18375
Net Excess Soil (m³) 0.285
Quantity 6
Total Volume (m3): 46.51875 47
Original Soil Volume (m³) 6.195
Excavated Loose Soil Volume (m³) 7.74375
Net Backfill Volume (m³) 5.145
Excess Soil (Loose) (m³) 1.3125
FTB-2
Additional Soil for Compaction (m³) 0.5145
Net Excess Soil (m³) 0.798
Quantity 6
Total Volume (m3): 130.2525 131
Materials Estimated Quantity
MARK CALCULATIONS Required
Earthfill
Original Soil Volume (m³) 3.9825
Excavated Loose Soil Volume (m³) 4.978125
Net Backfill Volume (m³) 3.3075
Excess Soil (Loose) (m³) 0.84375
FTB-3
Additional Soil for Compaction (m³) 0.33075
Net Excess Soil (m³) 0.513
Quantity 6
Total Volume (m3): 83.73375 84
BILL OF MATERIALS
DOORS AND WINDOWS

MARK CALCULATIONS

DOORS
GROUND FLOOR - THIRD FLOOR
FIGURE DESCRIPTION QUANTITY

MAHOGANY PANEL DOOR ON 50 X 150 MM


THK. MAHOGANY JAMB WITH FIXED
D-1 CLEAR GLASS TRANSFORM COMPLETE 12 Sets
WITH HARDWARE AND ACCESSORIES
CYLINDER TYPE LOCKSET

HOLLOW CORE FLUSH TYPE SWING DOOR ON


50 X 150MM MAHOGANY JAMB W/ MARINE
D-2 PLYWOOD FACING INSIDE AND ORDINARY 1 Set
OUTSIDE COMPLETE W/ HARDWARE AND
ACCESSORIES PROVIDE KICK PLATE.

HOLLOW CORE FLUSH TYPE SWING DOOR ON


50 X 150MM MAHOGANY JAMB W/ MARINE
D-3 PLYWOOD FACING INSIDE AND ORDINARY 6 Sets
OUTSIDE COMPLETE W/ HARDWARE AND
ACCESSORIES.

SWING DOOR ON 50 X 100MM MAHOGANY


D-4 DOOR JAMB COMPLETE WITH HARDWARE 8 Sets
ACCESSORIES.
MARK CALCULATIONS

WINDOWS
GROUND FLOOR - THIRD FLOOR
FIGURE DESCRIPTION QUANTITY

JALOUSIE WINDOWS WITH CLEAR GLASS


BLADES ON STANDARD JALOUPLUS
CASING AND FIXED CLEAR GLASS
W-1 TRANSOM ON 50 X 150 MM MAHOGANY
12 Sets
JAMB COMPLETE WITH HARDWARE AND
ACCESSORIES

JALOUSIE WINDOWS WITH CLEAR GLASS


BLADES ON STANDARD JALOUPLUS
CASING AND FIXED CLEAR GLASS
W-2 TRANSOM ON 50 X 150 MM MAHOGANY
12 Sets
JAMB COMPLETE WITH HARDWARE AND
ACCESSORIES

JALOUSIE WINDOWS WITH CLEAR GLASS


BLADES ON STANDARD JALOUPLUS
W-3 CASING ON 50 X 150 MM MAHOGANY 9 Sets
JAMB COMPLETE WITH HARDWARE AND
ACCESSORIES
BILL OF ESTIMATES
PLUMBING

CALCULATION
MARK
QUANTITY DESCRIPTION
GROUND FLOOR
1 3m - 20 mm Ø COLD WATERLINE (CWL)
4 3m - 25 mm Ø COLD WATERLINE (CWL)
WATER LINE 1 3m - 32 mm Ø COLD WATER RISER (CWR)
1 25 mm Ø GATE VALVE
1 25 mm Ø WATER METER
1 3m - 100 mm Ø U-PVC SOIL PIPE
WASTE LINE 1 50 mm Ø VENT (V)
5 50 mm Ø FLOOR DRAIN (FD)
6 1.5 m - 100 mm Ø DOWNSPOUT (DS)
2 3m - 100 mm Ø DRAIN PIPE (DP)
DRAINAGE
3 150 mm Ø DRAIN PIPE (DP)
2 AREA DRAIN (AD)
3 TEE-JOINT
3 TRAP
4 90° ELBOW
JOINTS
4 90° LATERAL
8 45° ELBOW
1 CROSSES
3 LAVATORY
FIXTURES
3 WATER CLOSET
SECOND FLOOR
3 1m - 25 mm Ø COLD WATERLINE (CWL)
WATER LINE
3 1.5 m - 25 mm Ø COLD WATER RISER (CWR)
1 3m - 100 mm Ø U-PVC SOIL PIPE
WASTE LINE 1 50 mm Ø VENT (V)
4 50 mm Ø FLOOR DRAIN (FD)
10 1.5 m - 100 mm Ø DOWNSPOUT (DS)
DRAINAGE
3 3m - 25 mm Ø DRAIN PIPE (DP)
2 TEE-JOINT
3 TRAP
JOINTS 9 90° ELBOW
4 90° LATERAL
10 45° ELBOW
2 LAVATORY
FIXTURES
3 WATER CLOSET
THIRD FLOOR
3 1m - 25 mm Ø COLD WATERLINE (CWL)
WATER LINE
3 1.5 m - 25 mm Ø COLD WATER RISER (CWR)
1 3m - 100 mm Ø U-PVC SOIL PIPE
WASTE LINE 1 50 mm Ø VENT (V)
4 50 mm Ø FLOOR DRAIN (FD)
10 1.5 m - 100 mm Ø DOWNSPOUT (DS)
DRAINAGE
3 3m - 25 mm Ø DRAIN PIPE (DP)
2 TEE-JOINT
3 TRAP
JOINTS 9 90° ELBOW
4 90° LATERAL
10 45° ELBOW
2 LAVATORY
FIXTURES
3 WATER CLOSET
BILL OF ESTIMATES
ELECTRICAL

QUANTITY Materials Estimated Quantity


ITEM DIVIDER TOTAL
(m) (pc) Required
Panel Board (12 Slots) 4 2 8 8 pcs
Circuit Breaker @ 15AT/20AT 9 2 18 18 pcs
Circuit Breaker @ 30AT/40AT 5 2 10 10 pcs
Circuit Breaker @ 150AT 2 2 4 4 pcs
Wires @3.5mm2 7453 300 7500 50 boxes @ 150m per box
Wires @5.5mm2 3754 300 4000 27 boxes @ 150m per box
Conduit @15mm 4286 20 260 26 pcs @ 10m
Conduit @20mm 1753 20 120 120 pcs @ 10m
Junction Box w/ Cover 134 2 280 280 pcs
Utility Box 94 2 140 140 pcs
Weather Proof Duplex Outlet 15 2 30 30 pcs
Switch (2-Gang Set) 17 2 40 40 pcs
Switch (1-Gang Set) 6 2 20 20 pcs
Switch (3-Way Set) 15 2 30 30 pcs
18W LED 13 2 30 30 pcs
36W LED (box type) 20 2 40 40 pcs
36W LED (box type w/ canopy base) 24 2 30 30 pcs
Fan Control Outlet 12 2 30 30 pcs
Circuit homerun 8 2 20 20 pcs
Fire Alarm Station Outlet 3 2 10 10 pcs
Fire Alarm Control Panel 3 2 10 10 pcs
Electrical Tape 200 2 200 200 pcs
TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila, Philippines
COLLEGE OF ENGINEERING
Civil Engineering Department

MATERIAL
COST
BILL OF MATERIALS
CONCRETE WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
FOUNDATION
1 CF - 1
1.1 Cement (Class A) bags 577 215 124055
1.2 Sand cu. m 33 800 26400
1.3 Gravel cu. m 65 1310 85150
2 CF - 2
2.1 Cement (Class A) bags 318 215 68370
2.5 Sand cu. m 18 800 14400
2.3 Gravel cu. m 36 1310 47160
3 WF - 1
3.1 Cement (Class A) bags 153 215 32895
3.2 Sand cu. m 9 800 7200
3.3 Gravel cu. m 17 1310 22270
4 WF - 2
4.1 Cement (Class A) bags 1 215 215
4.2 Sand cu. m 1 800 800
4.3 Gravel cu. m 1 1310 1310
5 FTB - 1
5.1 Cement (Class A) bags 21 215 4515
5.2 Sand cu. m 2 800 1600
5.3 Gravel cu. m 3 1310 3930
6 FTB - 2
6.1 Cement (Class A) bags 57 215 12255
6.2 Sand cu. m 4 800 3200
6.3 Gravel cu. m 7 1310 9170
7 FTB - 3
7.1 Cement (Class A) bags 37 215 7955
7.2 Sand cu. m 3 800 2400
7.3 Gravel cu. m 5 1310 6550

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
COLUMN
GROUND FLOOR - SECOND FLOOR
8 C -1
8.1 Cement (Class A) bags 15 215 3225
8.2 Sand cu. m 1 800 800
8.3 Gravel cu. m 2 1310 2620
9 C-2
9.1 Cement (Class A) bags 30 215 6450
9.2 Sand cu. m 2 800 1600
9.3 Gravel cu. m 4 1310 5240
10 C-3
10.1 Cement (Class A) bags 28 215 6020
10.2 Sand cu. m 2 800 1600
10.3 Gravel cu. m 4 1310 5240

SECOND FLOOR -THIRD FLOOR


11 C-1
11.1 Cement (Class A) bags 15 215 3225
11.2 Sand cu. m 1 800 800
11.3 Gravel cu. m 2 1310 2620
12 C-2
12.1 Cement (Class A) bags 28 215 6020
12.2 Sand cu. m 2 800 1600
12.3 Gravel cu. m 4 1310 5240
13 C-3
13.1 Cement (Class A) bags 28 215 6020
13.2 Sand cu. m 2 800 1600
13.3 Gravel cu. m 4 1310 5240
AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
COLUMN
THIRD FLOOR - ROOF
14 C-1
14.1 Cement (Class A) bags 12 215 2580
14.2 Sand cu. m 1 800 800
14.3 Gravel cu. m 2 1310 2620
15 C- 2
15.1 Cement (Class A) bags 15 215 3225
15.2 Sand cu. m 1 800 800
15.3 Gravel cu. m 2 1310 2620
16 C-3
16.1 Cement (Class A) bags 15 215 3225
16.2 Sand cu. m 1 800 800
16.3 Gravel cu. m 2 1310 2620

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAM
MAIN BEAMS
17 G-1
17.1 Cement (Class A) bags 54 215 11610
17.2 Sand cu. m 3 800 2400
17.3 Gravel cu. m 6 1310 7860
18 G-2
18.1 Cement (Class A) bags 61 215 13115
18.2 Sand cu. m 4 800 3200
18.3 Gravel cu. m 7 1310 9170
19 G-3
19.1 Cement (Class A) bags 56 215 12040
19.2 Sand cu. m 4 800 3200
19.3 Gravel cu. m 7 1310 9170
20 G -4
20.1 Cement (Class A) bags 15 215 3225
20.2 Sand cu. m 1 800 800
20.3 Gravel cu. m 2 1310 2620
21 G-5
21.1 Cement (Class A) bags 52 215 11180
21.2 Sand cu. m 3 800 2400
21.3 Gravel cu. m 6 1310 7860
22 G-6
22.1 Cement (Class A) bags 30 215 6450
22.2 Sand cu. m 2 800 1600
22.3 Gravel cu. m 4 1310 5240
23 G-7
23.1 Cement (Class A) bags 27 215 5805
23.2 Sand cu. m 2 800 1600
23.3 Gravel cu. m 3 1310 3930
24 G-8
24.1 Cement (Class A) bags 77 215 16555
24.2 Sand cu. m 5 800 4000
24.3 Gravel cu. m 9 1310 11790
SECONDARY BEAMS
25 B-1
25.1 Cement (Class A) bags 53 215 11395
25.2 Sand cu. m 3 800 2400
25.3 Gravel cu. m 6 1310 7860
26 B-2
26.1 Cement (Class A) bags 11 215 2365
26.2 Sand cu. m 1 800 800
26.3 Gravel cu. m 2 1310 2620
27 B-3
27.1 Cement (Class A) bags 7 215 1505
27.2 Sand cu. m 1 800 800
27.3 Gravel cu. m 1 1310 1310
AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAM
ROOF BEAMS
28 RG - 1
28.1 Cement (Class A) bags 75 215 16125
28.2 Sand cu. m 5 800 4000
28.3 Gravel cu. m 9 1310 11790
29 RG - 2
29.1 Cement (Class A) bags 21 215 4515
29.2 Sand cu. m 2 800 1600
29.3 Gravel cu. m 3 1310 3930
30 RG - 3
30.1 Cement (Class A) bags 15 215 3225
30.2 Sand cu. m 1 800 800
30.3 Gravel cu. m 2 1310 2620
31 RG - 4a
31.1 Cement (Class A) bags 4 215 860
31.2 Sand cu. m 1 800 800
31.3 Gravel cu. m 1 1310 1310
32 RG - 4b
32.1 Cement (Class A) bags 11 215 2365
32.2 Sand cu. m 1 800 800
32.3 Gravel cu. m 2 1310 2620

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
SLAB
SECOND FLOOR & THIRD FLOOR
33 S -1
33.1 Cement (Class A) bags 115 215 24725
33.2 Sand cu. m 7 800 5600
33.3 Gravel cu. m 13 1310 17030
34 S -2
34.1 Cement (Class A) bags 59 215 12685
34.2 Sand cu. m 4 800 3200
34.3 Gravel cu. m 7 1310 9170
35 S-3
35.1 Cement (Class A) bags 103 215 22145
35.2 Sand cu. m 6 800 4800
35.3 Gravel cu. m 12 1310 15720
36 S-4
36.1 Cement (Class A) bags 23 215 4945
36.2 Sand cu. m 2 800 1600
36.3 Gravel cu. m 3 1310 3930
37 S-5
37.1 Cement (Class A) bags 27 215 5805
37.2 Sand cu. m 2 800 1600
37.3 Gravel cu. m 3 1310 3930
38 S-6
38.1 Cement (Class A) bags 14 215 3010
38.2 Sand cu. m 1 800 800
38.3 Gravel cu. m 2 1310 2620

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
STAIRS
GROUND FLOOR - THIRD FLOOR
39 STAIRS
39.1 Cement (Class A) bags 66 215 14190
39.2 Sand cu. m 4 800 3200
39.3 Gravel cu. m 8 1310 10480

SUBTOTAL: 982670
BILL OF MATERIALS
STEEL WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
REINFORCED BARS
40 25 mm Ø, 7.5 m pcs. 33 577.95 19072.35
41 25 mm Ø, 9 m pcs. 16 693.54 11096.64
42 25 mm Ø, 10.5 m pcs. 10 809.13 8091.30
43 25 mm Ø, 12 m pcs. 13 924.72 12021.36
44 20 mm Ø, 6 m pcs. 138 295.92 40836.96
45 20 mm Ø, 7.5 m pcs. 59 369.9 21824.10
46 20 mm Ø, 9 m pcs. 87 443.88 38617.56
47 20 mm Ø, 10.5 m pcs. 157 517.86 81304.02
48 20 mm Ø, 12 m pcs. 27 591.84 15979.68
49 16 mm Ø, 6 m pcs. 11 189.36 2082.96
50 16 mm Ø, 7.5 m pcs. 24 236.7 5680.80
51 16 mm Ø, 9 m pcs. 35 284.04 9941.40
52 16 mm Ø, 10.5 m pcs. 11 331.38 3645.18
53 16 mm Ø, 12 m pcs. 18 378.72 6816.96
54 12 mm Ø, 10.5 m pcs. 1077 186.48 200838.96
55 12 mm Ø, 12 m pcs. 63 213.12 13426.56
56 10 mm Ø, 6 m pcs. 1366 73.92 100974.72
57 10 mm Ø, 7.5 m pcs. 25 92.4 2310.00
58 10 mm Ø, 9 m pcs. 399 110.88 44241.12
59 10 mm Ø, 10.5 m pcs. 118 129.36 15264.48
60 10 mm Ø, 12 m pcs. 120 147.84 17740.80

SUBTOTAL: 671807.91
BILL OF MATERIALS
MASONRY WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
WALL
GROUND FLOOR
61 EXTERIOR WALL
61.1 Cement (Class A) bags 129 215 27735
61.2 Sand cu. m 65 800 52000
61.3 CHB ( 5" ) pcs 1608 15 24120
62 INTERIOR WALL
62.1 Cement (Class A) bags 88 215 18920
62.2 Sand cu. m 44 800 35200
62.3 CHB ( 4" ) pcs 1098 10 10980
SECOND FLOOR
63 EXTERIOR WALL
63.1 Cement (Class A) bags 138 215 29670
63.2 Sand cu. m 69 800 55200
63.3 CHB ( 5" ) pcs 1714 15 25710
64 INTERIOR WALL
64.1 Cement (Class A) bags 88 215 18920
64.2 Sand cu. m 44 800 35200
64.3 CHB ( 4" ) pcs 1098 10 10980
THIRD FLOOR
65 EXTERIOR WALL
65.1 Cement (Class A) bags 138 215 29670
65.2 Sand cu. m 69 800 55200
65.3 CHB ( 5" ) pcs 1714 15 25710
66 INTERIOR WALL
66.1 Cement (Class A) bags 88 215 18920
66.2 Sand cu. m 44 800 35200
66.3 CHB ( 4" ) pcs 1098 10 10980

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
MORTAR
GROUND FLOOR
67 EXTERIOR WALL
67.1 Cement (Class A) bags 158 215 33970
67.2 Sand cu. m 81 800 64800
68 INTERIOR WALL
68.1 Cement (Class A) bags 108 215 23220
68.2 Sand cu. m 55 800 44000
SECOND FLOOR
69 EXTERIOR WALL
69.1 Cement (Class A) bags 168 215 36120
69.2 Sand cu. m 86 800 68800
70 INTERIOR WALL
70.1 Cement (Class A) bags 108 215 23220
70.2 Sand cu. m 55 800 44000
THIRD FLOOR
71 EXTERIOR WALL
71.1 Cement (Class A) bags 168 215 36120
71.2 Sand cu. m 86 800 68800
72 INTERIOR WALL
72.1 Cement (Class A) bags 108 215 23220
72.2 Sand cu. m 55 800 44000
AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
PLASTERING
GROUND FLOOR
73 EXTERIOR WALL
73.1 Cement (Class A) bags 13 215 2795
73.2 Sand cu. m 2 800 1600
73.3 Lime bags 13 150 1950
74 INTERIOR WALL
74.1 Cement (Class A) bags 9 215 1935
74.2 Sand cu. m 1 800 800
74.3 Lime bags 9 150 1350
SECOND FLOOR
75 EXTERIOR WALL
75.1 Cement (Class A) bags 14 215 3010
75.2 Sand cu. m 2 800 1600
75.3 Lime bags 14 150 2100
76 INTERIOR WALL
76.1 Cement (Class A) bags 9 215 1935
76.2 Sand cu. m 1 800 800
76.3 Lime bags 9 150 1350
THIRD FLOOR
77 EXTERIOR WALL
77.1 Cement (Class A) bags 14 215 3010
77.2 Sand cu. m 2 800 1600
77.3 Lime bags 14 150 2100
78 INTERIOR WALL
78.1 Cement (Class A) bags 9 215 1935
78.2 Sand cu. m 1 800 800
78.3 Lime bags 9 150 1350

SUBTOTAL: 1062605
BILL OF MATERIALS
CONCRETE WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
CEILING
GROUND FLOOR
79 Ceiling -1 (A)
79.1 4' x 8' x 1/4" Plywood pcs. 44 450 19800
79.2 2" x 2" bd. Ft. Lumber pcs. 807 180 145260
80 Ceiling -1 (B)
80.1 4' x 8' x 1/4" Plywood pcs. 16 450 7200
80.2 2" x 2" bd. Ft. Lumber pcs. 288 180 51840
81 Ceiling -2 (A)
81.1 4' x 8' x 1/4" Plywood pcs. 5 450 2250
81.2 2" x 2" bd. Ft. Lumber pcs. 91 180 16380
82 Ceiling -2 (B)
82.1 4' x 8' x 1/4" Plywood pcs. 3 450 1350
82.2 2" x 2" bd. Ft. Lumber pcs. 49 180 8820
SECOND FLOOR
83 Ceiling -1 (A)
83.1 4' x 8' x 1/4" Plywood pcs. 44 450 19800
83.2 2" x 2" bd. Ft. Lumber pcs. 807 180 145260
84 Ceiling -1 (B)
84.1 4' x 8' x 1/4" Plywood pcs. 16 450 7200
84.2 2" x 2" bd. Ft. Lumber pcs. 288 180 51840
85 Ceiling -2 (A)
85.1 4' x 8' x 1/4" Plywood pcs. 5 450 2250
85.2 2" x 2" bd. Ft. Lumber pcs. 91 180 16380
86 Ceiling -2 (B)
86.1 4' x 8' x 1/4" Plywood pcs. 3 450 1350
86.2 2" x 2" bd. Ft. Lumber pcs. 49 180 8820
SECOND FLOOR
87 Ceiling -1 (A)
87.1 4' x 8' x 1/4" Plywood pcs. 44 450 19800
87.2 2" x 2" bd. Ft. Lumber pcs. 807 180 145260
88 Ceiling -1 (B)
88.1 4' x 8' x 1/4" Plywood pcs. 16 450 7200
88.2 2" x 2" bd. Ft. Lumber pcs. 288 180 51840
89 Ceiling -2
89.1 4' x 8' x 1/4" Plywood pcs. 16 450 7200
89.2 2" x 2" bd. Ft. Lumber pcs. 286 180 51480
90 Ceiling -3 (A)
90.1 4' x 8' x 1/4" Plywood pcs. 19 450 8550
90.2 2" x 2" bd. Ft. Lumber pcs. 346 180 62280
91 Ceiling -3 (B)
91.1 4' x 8' x 1/4" Plywood pcs. 5 450 2250
91.2 2" x 2" bd. Ft. Lumber pcs. 91 180 16380

SUBTOTAL: 878040
BILL OF MATERIALS
FORM WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
COLUMN
GROUND FLOOR
92 COLUMNS
92.1 Plywood ( 4' x 8' x 1/4" ) pcs 15 360 5400
92.2 Lumber ( 2' x 2') bd. ft 426 55 23430
92.3 4d Common nail kg 3 62 186
SECOND FLOOR
93 COLUMNS
93.1 Plywood ( 4' x 8' x 1/4" ) pcs 25 360 9000
93.2 Lumber ( 2' x 2') bd. ft 736 55 40480
93.3 4d Common nail kg 5 62 310
THIRD FLOOR
94 COLUMNS
94.1 Plywood ( 4' x 8' x 1/4" ) pcs 2 360 720
94.2 Lumber ( 2' x 2') bd. ft 50 55 2750
94.3 4d Common nail kg 1 62 62

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAM
GROUND FLOOR
95 BEAMS
95.1 Plywood ( 4' x 8' x 1/4" ) pcs 40 360 14400
95.2 Lumber ( 2' x 2') bd. ft 1177 55 64735
95.3 4d Common nail kg 8 62 496
SECOND FLOOR
96 BEAMS
96.1 Plywood ( 4' x 8' x 1/4" ) pcs 64 360 23040
96.2 Lumber ( 2' x 2') bd. ft 1871 55 102905
96.3 4d Common nail kg 13 62 806
THIRD FLOOR
97 BEAMS
97.1 Plywood ( 4' x 8' x 1/4" ) pcs 64 360 23040
97.2 Lumber ( 2' x 2') bd. ft 1871 55 102905
97.3 4d Common nail kg 13 62 806

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
SLAB
GROUND FLOOR
98 SLABS
98.1 Plywood ( 4' x 8' x 1/4" ) pcs 14 360 5040

SECOND FLOOR
99 SLABS
99.1 Plywood ( 4' x 8' x 1/4" ) pcs 14 360 5040

SUBTOTAL: 425551
BILL OF MATERIALS
SCAFFOLFING AND STAGING WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
COLUMN
GROUND FLOOR
100 Column
100.1 Coco Lumber ( 2" x 2" ) bd. ft 1884 88 165792
100.2 Coco Lumber ( 2" x 3" ) bd. ft 404 132 53328
100.3 CWL Nail 20d kg 43 120 5160
SECOND FLOOR
101 Column
101.1 Coco Lumber ( 2" x 2" ) bd. ft 1884 88 165792
101.2 Coco Lumber ( 2" x 3" ) bd. ft 404 132 53328
101.3 CWL Nail 20d kg 43 120 5160
THIRD FLOOR
102 Column
102.1 Coco Lumber ( 2" x 2" ) bd. ft 1884 88 165792
102.2 Coco Lumber ( 2" x 3" ) bd. ft 404 132 53328
102.3 CWL Nail 20d kg 43 120 5160
ROOF LEVEL
103 Column
103.1 Coco Lumber ( 2" x 2" ) bd. ft 1472 88 129536
103.2 Coco Lumber ( 2" x 3" ) bd. ft 315 132 41580
103.3 CWL Nail 20d kg 33 120 3960

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAMS
GROUND FLOOR
104 Beam
104.1 Coco Lumber ( 2" x 2" ) bd. ft 4092 88 360096
104.2 Coco Lumber ( 2" x 3" ) bd. ft 876 132 115632
104.3 CWL Nail 20d kg 92 120 11040
SECOND FLOOR
105 Beam
105.1 Coco Lumber ( 2" x 2" ) bd. ft 4092 88 360096
105.2 Coco Lumber ( 2" x 3" ) bd. ft 876 132 115632
105.3 CWL Nail 20d kg 92 120 11040
THIRD FLOOR
106 Beam
106.1 Coco Lumber ( 2" x 2" ) bd. ft 4092 88 360096
106.2 Coco Lumber ( 2" x 3" ) bd. ft 876 132 115632
106.3 CWL Nail 20d kg 92 120 11040
ROOF LEVEL
107 Beam
107.1 Coco Lumber ( 2" x 2" ) bd. ft 3471 88 305448
107.2 Coco Lumber ( 2" x 3" ) bd. ft 743 132 98076
107.3 CWL Nail 20d kg 78 120 9360

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
SLAB
SECOND FLOOR
108 Beam
108.1 Coco Lumber ( 2" x 2" ) bd. ft 7053 88 620664
108.2 Coco Lumber ( 2" x 3" ) bd. ft 1510 132 199320
108.3 CWL Nail 20d kg 158 120 18960
THIRD FLOOR
109 Beam
109.1 Coco Lumber ( 2" x 2" ) bd. ft 7053 88 620664
109.2 Coco Lumber ( 2" x 3" ) bd. ft 1510 132 199320
109.3 CWL Nail 20d kg 158 120 18960

SUBTOTAL: 4398992
BILL OF MATERIALS
ROOF WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
ROOF
110 G.I CORR G.26 ( 32' x 12' ) pcs 35 373 13055
111 G.I CORR G.26 ( 32' x 8' ) pcs 18 254 4572
112 Rivets kg 6 82 492
113 G.I WASHER kg 11 93 1023
114 G.I PLAIN 36' x 12' Gauge pcs 94 184 17296

SUBTOTAL: 36438
BILL OF MATERIALS
TIE WIRE

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
FOUNDATION
115 CF - 1
115.1 G.I. Tie Wire #16 kg 19 71.37 1356.03
116 CF - 2
116.1 G.I. Tie Wire #16 kg 19 71.37 1356.03
117 WF - 1
117.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
118 WF - 2
118.1 G.I. Tie Wire #16 kg 1 71.37 71.37
119 FTB - 1
119.1 G.I. Tie Wire #16 kg 10 71.37 713.7
120 FTB - 2
120.1 G.I. Tie Wire #16 kg 10 71.37 713.7
121 FTB - 3
121.1 G.I. Tie Wire #16 kg 49 71.37 3497.13

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
COLUMN
FOUNDATION - GROUND FLOOR
122 C-1
122.1 G.I. Tie Wire #16 kg 9 71.37 642.33
123 C-2
123.1 G.I. Tie Wire #16 kg 9 71.37 642.33
124 C-3
124.1 G.I. Tie Wire #16 kg 9 71.37 642.33
GROUND FLOOR - SECOND FLOOR
125 C-1
125.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
126 C-2
126.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
127 C-3
127.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
THIRD FLOOR - ROOF LEVEL
128 C-1
128.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
129 C-2
129.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
130 C-3
130.1 G.I. Tie Wire #16 kg 15 71.37 1070.55

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAM
MAIN BEAM
131 G-1
131.1 G.I. Tie Wire #16 kg 59 71.37 4210.83
132 G-2
132.1 G.I. Tie Wire #16 kg 68 71.37 4853.16
133 G-3
133.1 G.I. Tie Wire #16 kg 33 71.37 2355.21
134 G-4
134.1 G.I. Tie Wire #16 kg 4 71.37 285.48
135 G-5
135.1 G.I. Tie Wire #16 kg 29 71.37 2069.73
AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
BEAM
MAIN BEAM
136 G-6
136.1 G.I. Tie Wire #16 kg 18 71.37 1284.66
137 G-7
137.1 G.I. Tie Wire #16 kg 14 71.37 999.18
138 G-8
138.1 G.I. Tie Wire #16 kg 14 71.37 999.18
SECONDARY BEAM
139 B-1
139.1 G.I. Tie Wire #16 kg 9 71.37 642.33
140 B-2
140.1 G.I. Tie Wire #16 kg 5 71.37 356.85
141 B-3
141.1 G.I. Tie Wire #16 kg 3 71.37 214.11
ROOF BEAM
142 RG - 1
142.1 G.I. Tie Wire #16 kg 84 71.37 5995.08
143 RG - 2
143.1 G.I. Tie Wire #16 kg 15 71.37 1070.55
144 RG - 3
144.1 G.I. Tie Wire #16 kg 11 71.37 785.07
145 RG - 4 (A)
145.1 G.I. Tie Wire #16 kg 3 71.37 214.11
146 RG - 4 (B)
146.1 G.I. Tie Wire #16 kg 3 71.37 214.11

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
STAIRS
STAIRS FOUNDATION
147 Stairs Foundation
147.1 G.I. Tie Wire #16 kg 1 71.37 71.37
GROUND FLOOR - SECOND FLOOR
148 Stairs Foundation
148.1 G.I. Tie Wire #16 kg 4 71.37 285.48
SECOND FLOOR - THIRD FLOOR
149 Stairs Foundation
149.1 G.I. Tie Wire #16 kg 4 71.37 285.48

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
SLAB
GROUND FLOOR
150 Slab on Fill
150.1 G.I. Tie Wire #16 kg 244 71.37 17414.28
SECOND FLOOR
151 S-1
151.1 G.I. Tie Wire #16 kg 65 71.37 4639.05
152 S-2
152.1 G.I. Tie Wire #16 kg 64 71.37 4567.68
153 S-3
153.1 G.I. Tie Wire #16 kg 67 71.37 4781.79
154 S-4
154.1 G.I. Tie Wire #16 kg 17 71.37 1213.29
155 S-5
155.1 G.I. Tie Wire #16 kg 16 71.37 1141.92
156 S-6
156.1 G.I. Tie Wire #16 kg 17 71.37 1213.29
AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
SLAB
THIRD FLOOR
157 S-1
157.1 G.I. Tie Wire #16 kg 65 71.37 4639.05
158 S-2
158.1 G.I. Tie Wire #16 kg 64 71.37 4567.68
159 S-3
159.1 G.I. Tie Wire #16 kg 67 71.37 4781.79
160 S-4
160.1 G.I. Tie Wire #16 kg 17 71.37 1213.29
161 S-5
161.1 G.I. Tie Wire #16 kg 16 71.37 1141.92
162 S-6
162.1 G.I. Tie Wire #16 kg 17 71.37 1213.29

SUBTOTAL: 96849.09
BILL OF MATERIALS
MASONRY WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
WALL
GROUND FLOOR
163 EXTERIOR WALL
163.1 Surface Primer gal 7 635 4445
163.2 Final Coat gal 7 540 3780
163.2 Neutralizer L 3 422 1266
164 INTERIOR WALL
164.1 Surface Primer gal 5 635 3175
164.2 Final Coat gal 5 540 2700
164.3 Neutralizer L 2 422 844
165 CEILING
165.1 Surface Primer gal 12 635 7620
165.2 Final Coat gal 12 540 6480
165.3 Neutralizer L 5 422 2110
SECOND FLOOR
166 EXTERIOR WALL
166.1 Surface Primer gal 7 635 4445
166.2 Final Coat gal 7 540 3780
166.2 Neutralizer L 3 422 1266
167 INTERIOR WALL
167.1 Surface Primer gal 5 635 3175
167.2 Final Coat gal 5 540 2700
167.3 Neutralizer L 2 422 844
168 CEILING
168.1 Surface Primer gal 12 635 7620
168.2 Final Coat gal 12 540 6480
168.3 Neutralizer L 5 422 2110
THIRD FLOOR
169 EXTERIOR WALL
169.1 Surface Primer gal 7 635 4445
169.2 Final Coat gal 7 540 3780
169.2 Neutralizer L 3 422 1266
170 INTERIOR WALL
170.1 Surface Primer gal 5 635 3175
170.2 Final Coat gal 5 540 2700
170.3 Neutralizer L 2 422 844
171 CEILING
171.1 Surface Primer gal 12 635 7620
171.2 Final Coat gal 12 540 6480
171.3 Neutralizer L 5 422 2110

SUBTOTAL: 97260
BILL OF MATERIALS
TILE WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
GROUND FLOOR - THIRD FLOOR
172 COMFORT ROOM ( PWD )
172.1 Tiles 20x20 cm bags 103 40 4120
172.2 Tile Adhesive bags 3 40 120
172.3 White Cement kg 8 454 3632
172.4 Capping pcs 7 140 980
172.5 Internal Corner Cove pcs 4 400 1600
172.6 Internal Corner Bead pcs 4 220 880
173 COMFORT ROOM 1 ( SHE )
173.1 Tiles 20x20 cm bags 81 40 3240
173.2 Tile Adhesive bags 2 40 80
173.3 White Cement kg 6 454 2724
173.4 Capping pcs 6 140 840
173.5 Internal Corner Cove pcs 4 400 1600
173.6 Internal Corner Bead pcs 4 220 880
174 COMFORT ROOM 2 ( HE )
174.1 Tiles 20x20 cm bags 117 40 4680
174.2 Tile Adhesive bags 3 40 120
174.3 White Cement kg 9 454 4086
174.4 Capping pcs 8 140 1120
174.5 Internal Corner Cove pcs 4 400 1600
174.6 Internal Corner Bead pcs 4 220 880

SUBTOTAL: 33182
BILL OF MATERIALS
EARTH WORKS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
FOUNDATION
175 CF - 1
175.1 Eath fill (Common Borrow) m3 1323 384.4 508561.2
176 CF - 2
176.1 Eath fill (Common Borrow) m3 729 384.4 280227.6
177 WF - 1
177.1 Eath fill (Common Borrow) m3 190 384.4 73036
178 WF - 2
Eath fill (Common Borrow) 3
178.1 m 2 384.4 768.8
179 FTB - 1
Eath fill (Common Borrow) 3
179.1 m 47 384.4 18066.8
180 FTB - 2
180.1 Eath fill (Common Borrow) m3 131 384.4 50356.4
181 FTB - 3
181.1 Eath fill (Common Borrow) m3 84 384.4 32289.6

SUBTOTAL: 963306.4
BILL OF MATERIALS
DOORS AND WINDOWS

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
DOORS
182 D -1
182.1 MAHOGANY PANEL DOOR Set 12 7500 90000
183 D-2
183.1 HOLLOW CORE FLUSH TYPE SWING DOOR (PROVIDE
Set KICK PLATE.)
1 2300 2300
184 D-3
184.1 HOLLOW CORE FLUSH TYPE SWING DOOR Set 6 1500 9000
185 D-4
185.1 SWING DOOR Set 8 2500 20000
WINDOWS
186 W-1
186.1 JALOUSIE WINDOWS (2.5 x 1.5m) Set 12 2475 29700
187 W-2
187.1 JALOUSIE WINDOWS (1.4 x 1.5 m) Set 12 1386 16632
188 W-3
188.1 JALOUSIE WINDOWS (0.6 x 0.635m) Set 9 252 2268

SUBTOTAL: 169900
BILL OF MATERIALS
PLUMBING

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
189 PVC pcs. 11 234.84 2583.24
190 PPR pcs. 7 260 1820
191 TEE - JOINT pcs. 7 38.1 266.7
192 90° ELBOW pcs. 22 27.2 598.4
193 90° LATERAL pcs. 12 81.6 979.2
194 45° ELBOW pcs. 28 62.5 1750
195 CROSSES pcs. 1 190 190
196 P - TRAP pcs. 9 117.9 1061.1
197 GV pcs. 1 155 155
198 Water Closet pcs. 9 2650 23850
199 Lavatory pcs. 7 1990 13930
200 Faucet pcs. 7 135 945
201 Drainage pcs. 24 40 960

SUBTOTAL: 49088.64
BILL OF MATERIALS
ELECTRICAL

AMOUNT
ITEM No. DESCRIPTION UNIT QUANTITY UNIT COST
(php)
202 Panel Board (12 Slots) pcs. 8 3500 28000
203 Circuit Breaker @ 15AT/20AT pcs. 18 600 10800
204 Circuit Breaker @ 30AT/40AT pcs. 10 600 6000
205 Circuit Breaker @ 150AT pcs. 4 1650 6600
206 Wires @3.5mm2 pcs. 50 4000 200000
207 Wires @5.5mm2 pcs. 27 6300 170100
208 Conduit @15mm pcs. 26 55 1430
209 Conduit @20mm pcs. 120 75 9000
210 Junction Box w/ Cover pcs. 280 100 28000
211 Utility Box pcs. 140 85 11900
212 Weather Proof Duplex Outlet pcs. 30 200 6000
213 Switch (2-Gang Set) pcs. 40 170 6800
214 Switch (1-Gang Set) pcs. 20 120 2400
215 Switch (3-Way Set) pcs. 30 300 9000
216 18W LED pcs. 30 225 6750
217 36W LED (box type) pcs. 40 409 16360
218 36W LED (box type w/ canopy base) pcs. 30 1250 37500
219 Fan Control Outlet pcs. 30 200 6000
220 Fire Alarm Station Outlet pcs. 10 2900 29000
221 Fire Alarm Control Panel pcs. 10 15950 159500
223 Electrical Tape pcs. 200 50 10000

SUBTOTAL: 761140
nTECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila, Philippines
COLLEGE OF ENGINEERING
Civil Engineering Department

SUMMARY
BILL OF MATERIALS
SUMMARY

MATERIAL COST
MARK DESCRIPTION
(Php)
I Concrete Works 982,670.00
II Steel Works 671,807.19
III Masonry Works 1,030,585.00
IV Carpentry Works 878,040.00
V Form Works 425,551.00
VI Scaffolding and Staging 4,398,992.00
VII Roof Works 36,438.00
VIII Tie Wires 96,849.09
VIX Paint Works 97,260
X Tile Works 33,182
XI Earthworks 963,306.40
XII Doors and Windows 169,900
XIII Plumbing 49,088.64
XIV Electrical 761,140

TOTAL: Php 10,594,809.32


TECHNOLOGICAL UNIVERSITY OF THE PHILIPPINES
Ayala Blvd., Ermita, Manila, Philippines
COLLEGE OF ENGINEERING
Civil Engineering Department

PRICE LIST
PRICE LIST
Unit Cost
Item Unit
(Php)
Cement (Class A) bags 215.000
Sand cu.m 800.000
Gravel cu.m 1310.000
CHB (4") pcs 10.000
CHB (5") pcs 15.000
25 mm Ø, 7.5 m pcs. 577.950
25 mm Ø, 9 m pcs. 693.540
25 mm Ø, 10.5 m pcs. 809.130
25 mm Ø, 12 m pcs. 924.720
20 mm Ø, 6 m pcs. 295.920
20 mm Ø, 7.5 m pcs. 369.900
20 mm Ø, 9 m pcs. 443.880
20 mm Ø, 10.5 m pcs. 517.860
20 mm Ø, 12 m pcs. 591.840
16 mm Ø, 6 m pcs. 189.360
16 mm Ø, 7.5 m pcs. 236.700
16 mm Ø, 9 m pcs. 284.040
16 mm Ø, 10.5 m pcs. 331.380
16 mm Ø, 12 m pcs. 378.720
12 mm Ø, 10.5 m pcs. 186.480
12 mm Ø, 12 m pcs. 213.120
10 mm Ø, 6 m pcs. 73.920
10 mm Ø, 7.5 m pcs. 92.400
10 mm Ø, 9 m pcs. 110.880
10 mm Ø, 10.5 m pcs. 129.360
10 mm Ø, 12 m pcs. 147.840
Plywood ( 4' x 8' x 1/4" ) pcs 360.000
Lumber ( 2' x 2') pcs 130.000
4d Common nail kg 62.000
G.I CORR G.26 ( 32' x 12' ) pcs 373.000
G.I CORR G.26 ( 32' x 8' ) pcs 254.000
Rivets kg 82.000
G.I WASHER kg 93.000
G.I PLAIN 36' x 12' Gauge pcs 184.000
Surface Primer gal 635.000
Final Coat gal 540.000
Neutralizer L 422.000
Tiles 20x20 cm bags 40.000
Tile Adhesive bags 40.000
White Cement kg 454.000
Capping pcs 140.000
Internal Corner Cove pcs 400.000
Internal Corner Bead pcs 220.000
Mahogany Panel Door with Clear Glass set 7500.000
Hollow Core Flush Type Door w/ kick plate set 2300.000
Hollow Core Flush Type Door set 1500.000
PRICE LIST
Unit Cost
Item Unit
(Php)
Swing Door set 2500.000
Jalousie Windows (2.5x1.5m) set 2475.000
Jalousie Windows (1.4x1.5m) set 1386.000
Jalousie Windows (0.6x0.653m) set 252.000
PVC pcs 234.840
PPR pcs 260.000
TEE-JOINT pcs 38.100
90° Elbow pcs 27.200
90° Lateral pcs 81.600
45° Elbow pcs 62.500
Crosses pcs 190.000
P-Trap pcs 117.900
GV pcs 155.000
WC pcs 2650.000
LAV pcs 1990.000
Faucet pcs 135.000
Drain pcs 3500.000
Panel Board (12 Slots) pcs 600.000
Circuit Breaker @ 15AT/20AT pcs 600.000
Circuit Breaker @ 30AT/40AT pcs 1650.000
Circuit Breaker @ 150AT pcs 4000.000
Wires @3.5mm2 pcs 6300.000
Wires @5.5mm2 pcs 55.000
Conduit @15mm pcs 75.000
Conduit @20mm pcs 100.000
Junction Box w/ Cover pcs 85.000
Utility Box pcs 1604.496
Weather Proof Duplex Outlet pcs 1630.914
Switch (2-Gang Set) kg 1657.332
Switch (1-Gang Set) pcs 1683.750
Switch (3-Way Set) pcs 1710.168
18W LED kg 1736.586
36W LED (box type) kg 1763.003
36W LED (box type w/ canopy base) pcs 1789.421
Fan Control Outlet gal 1815.839
Fire Alarm Station Outlet gal 1842.257
Fire Alarm Control Panel L 1868.675
Electrical Tape
G.I. Tie Wire #16 kg 71.370
4' x 8' x 1/4" Plywood pcs. 450.000
2" x 2" bd. Ft. Lumber pcs. 180.000
Eath fill (Common Borrow) m3 384.400