Professional Documents
Culture Documents
Jawaban Quiz 4 - Investasi Proyek Dan Keuangan
Jawaban Quiz 4 - Investasi Proyek Dan Keuangan
Jawaban Quiz 4 - Investasi Proyek Dan Keuangan
The following CPM network has estimates of the normal time in weeks listed for the
activities:
Normal
Activity Predecessor ES EF LS LF Slack
Time
A - 7 0 7 0 7 0
B A 2 7 11 7 9 0
C A 4 7 11 7 11 0
D B,C 5 11 16 11 16 0
E D 2 16 20 18 20 2
F D 4 16 20 16 20 0
G E,F 5 20 25 20 25 0
d. Here is a table of normal and crash times and costs.
Activity Normal Time Crash Time Normal Cost Crash Cost
A 7 6 $ 7.000 $ 8.000
B 2 1 $ 5.000 $ 7.000
C 4 3 $ 9.000 $ 10.200
D 5 4 $ 3.000 $ 4.500
E 2 1 $ 2.000 $ 3.000
F 4 2 $ 4.000 $ 7.000
G 5 4 $ 5.000 $ 8.000
Which activities would you shorten to cut two weeks from the schedule in a
rational fashion?
Activity Normal Time Crash Time Normal Cost Crash Cost Cost per Week Weeks
A 7 6 $ 7.000 $ 8.000 $ 1.000,00 1
B 2 1 $ 5.000 $ 7.000 $ 2.000,00 1
C 4 3 $ 9.000 $ 10.200 $ 1.200,00 1
D 5 4 $ 3.000 $ 4.500 $ 1.500,00 1
E 2 1 $ 2.000 $ 3.000 $ 1.000,00 1
F 4 2 $ 4.000 $ 7.000 $ 1.500,00 2
G 5 4 $ 5.000 $ 8.000 $ 3.000,00 1
Normal
Activity Predecessor Time Crash Time (Weeks) Expediting Cost/Week
(Weeks)
A - 9 6 $ 3.000
B A 8 5 $ 3.500
C A 15 10 $ 4.000
D B,C 5 3 $ 2.000
E C 10 6 $ 2.500
F D,E 2 1 $ 5.000
Path :
A–B–D–F = 24 Minggu
A–C–D–F = 31 Minggu
A–C–E–F = 36 Minggu (Critical Path)
c. What is the project length if all activities are crashed to their minimum?
Crashed Project Length :
A–B–D–F = 15 Minggu
A–C–D–F = 20 Minggu
A–C–E–F = 23 Minggu
d. Bragg’s loses $3,500 in profit per week for every week the bakery is not
completed. How many weeks will the project take if we are willing to pay
crashing cost as long as it is less than $3,500?
Normal
Activity Predecessor Time Crash Time (Weeks) Expediting Cost/Week
(Weeks)
A - 9 6 $ 3.000
B A 8 5 $ 3.500
C A 15 10 $ 4.000
D B,C 5 3 $ 2.000
E C 10 6 $ 2.500
F D,E 2 1 $ 5.000
Dari keempat Aktivitas yang termasuk kedalam Critical Path, maka dapat
dipilih Aktivitas A dengan cost sejumlah $3000 dimana cost tersebut
dibawah dari $3500. Sehingga dapat crash sampai Minggu ke-29