Operative Instruction - Shut Down 16 June 2016

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 8

SONATRACH First Calgary Petroleum

Operative instruction MLE Field,11 June 2016

MLE CPF FACILITY

SHUT DOWN PROCEDURE

2 Comments Incorporated

1 Issued For Information


0 22/12/15 Issued For Comment
BY CDD EXPLOITATION APP’D
REV DATE DESCRIPTION CDS EXPLOITATION REVIEW (OWNER)
Shut down Procedure

CONTENTS

1. Introduction………………………………………………………………………………….. 3
2. Feed reduction and cold down……………………………………………………………. 3
3. Fuel gas back up……………………………………………………………………………. 4
4. Preliminary isolation of CPF and depressurization……………………………………… 4
5. Isolation of Hg, H2S and Sieves beds not involved in the activities of Total shut
down…………………………………………………………………………………………….. 6
6. Draining……………………………………………………………………………………… 7
7. Management of lines full of Hydrocarbons and not involved in the above phase of
draining. (Calibration TSV)……………………………………………………………………. 7
8. Fuel gas back up……………………………………………………………………………. 7
9. Purge machines……………………………………………………………………………… 7
10. Sequence of Handover units to Maintenance and Sequence of Coming back of
units to Exploitation at the end of maintenance activities………………………………….. 7
11. Start-up……………………………………………………………………………………… 7
12. Timing……………………………………………………………………………………….. 8

Issue Date : December 2015 2 of 8


Shut down Procedure

1. Introduction

The units included in both sections of CPF gas & liquid, shall be shutdown according to the
following sequence:

a) Shut down preparation (During normal operation)


b) Reduce feed flow to plant at 25-30% of the design maximum throughput (i.e.
turndown conditions) and recycle gas. Gas system remains on line at 60%;
c) Reduce equipment liquid level;
d) Stop feed flow from wells.
e) Stop gas section;
f) Stop liquid section;
g) First isolation;
h) Depressurization;
i) Draining;
a) Level of liquids in hereunder items lowered as much as possible:

 Off-Spec Oil Storage Tank RL-22-04;


 Off-Spec Condensate Storage Tank RL-35-02;
 Off-Spec LPG Storage Tank RD-33-02;
 Closed Drain Drum VD-57-01/2.

b) Reduction of operative levels in the units to the lowest operational level;


c) Few hours leading up to the shutdown levels of ON spec Oil and Condensate
storage tanks have to be minimised as much as possible. (All On spec. liquids
have to be exported) ;
d) Few hours, before to start the reduction of feed, residual LPG stored in ON spec
spheres in standby has to be retreated;
e) Residual LPG, stored in the last one sphere in filling, has to be exported
immediately after the cut of feed.

2. Feed reduction & Cold down

a) Reduce quickly feed of raw gas to turn down rate 25-30% from wells with the closure of
wells via DCS (Throttling choke valves and closure of manual vales of well heads will be
performed later on by Puit dept.) (Cut of raw gas has to be done quickly in the aim to
minimise production of liquids and to minimise saturation of OFF spec facilities)

b) Put in Hold sequences of regenerations and stop duty of hot oil to GA 24-03 A/B and GA
32-04 A/B (Regenerator compressor has to be kept in service to cold down the equipment
used for the service of regeneration)

 Align sequences of regeneration of LPG beds in the aim to avoid heating phase
during the activities of Feed reduction and shutdown of CPF (Both vessels have to
be kept in low temperature)
 Align sequences of regeneration of Gas beds in the aim to avoid heating phase
during the activities of Feed reduction and shutdown of CPF (All vessels have to be
kept in low temperature)

Align sequences in the aim to have also 1 gas bed regenerated (cold down phase
completed) Sequence of regeneration will start after the pressurization of system 24 in the
aim to perform the regeneration of the second beds before to feed gas in the system 25

Issue Date : December 2015 3 of 8


Shut down Procedure

c) Stop Expander in the aim to warm up cryogenic unit with the residual feed of gas.
Switch of Operation from Expander mode to J-T Valve mode.

d) Reduce / cut the heating of furnaces.

e) Reduce/close as soon as possible duty and temperature of Hot oil to re-boilers units 21,
25, 28 and 32 in order to cold down re-boilers and columns.
(At the same time reduce again the heating of furnaces until the shutdown of all burners)

(Reduce the delivery of hot oil in relation at the new density of hot oil (Low temperature)
When Temperature in hot oil network became low open for few minutes re-boilers of unit
21,25,28 and 32 in the aim to cold down also dead branches of network.

Stop Hot oil pump and avoid PSD of CPF

g) Cut the feed of gas inlet unit 28 and keep amine circulation in service to cold down
regeneration section of unit 28 until ambient temperature.
(Temperature profile must decreasing in a progressive manner in the aim avoid thermal
shocks to the exchangers)

h) Reduce residual feed of gas from wells until zero and stop the export gas compressor

i) Stop Off gas compressor and Regeneration gas compressor (without depressurization of
unit 24)

Before start to depressurize the CPF is important to override all following pressure and level
controller:

 Override slug catcher low low pressure interlock [Force 20 PI 00001A/B/C (2oo3)]
 Override MZLN1-9 low low pressure interlock [Force 20 PI 01C003A/B/C (2oo3)]
 Override CAFC wells low low pressure interlock [Force 20 PI 01C001A/B/C (2oo3)]
 Override slug catcher low low level interlock [Force 20 LI 00001A/B/C (2oo3)]
 Override export line low low pressure interlock [Force 27 PI 00007A/B/C (2oo3)]

Please confirm that no other pilots can generate PSD during the next phase of
depressurization

3. Fuel gas back up

Put in service fuel gas back up system in the aim to ensure the fully availability of flares
during the phases of depressurization and inerting of all CPF.
(Ref. to Operative instruction attached)

4. Preliminary isolation of CPF and depressurization.

 Well department put in place and confirm isolation of MLE CAFC networks.
 Perform and confirms isolation of Export pipe lines.
 Perform preliminary isolation of CPF in the follow sections.

a) 24” 10” 8” trunk lines and Slug catcher.

Isolation of 24” 10” and 8” trunk lines will be put in place as reported in the attached
WMS in charge by Puit Dept.

Issue Date : December 2015 4 of 8


Shut down Procedure

20-ESDV-00003 and manual valve


20-ESDV-00002 and manual valve

Performed the isolation of 24” 10” 8” trunk lines and slug catcher they have to be
depressurized with 20-PV-00009C operated by DCS only after the complete
depressurization of all CPF

b) Unit 27 Export gas compressors with the closure of:

27-ESDV-0X002
27-ESDV-0X007

Performed the isolation of unit 27 export gas compressors will be isolated,


depressurized and preserved as reported in Operative manual.

c) Off gas compressors with the closure of:

21-ESDV-0X001
21-ESDV-0X002
21-ESDV-0X003

Performed the isolation of off gas compressor they will be isolated, depressurized, as
reported in operative manual.

d) Regeneration gas compressors Isolate and depressurize as reported in operative


manual.

e) Turbo expander Isolate and depressurize as reported in operative manual.

f) Gas train with the closure of:

25-ESDV-00002
25-ESDV-00003

Performed the isolation of gas train it will be depressurized by DCS with the 25-PV-
00094 and 25-PV-00002 in Auto mode and reducing the pressure with the reduction of
SP of JT valve only (This will ensure that Max DP on cold boxes plates will never
exceed Operative DP and the worm up of unit 25 with the residual gas stored in the
units 20, 30, 28 and 24)

g) CX-25-01 and VD-25-04 with the closure of:

25-ESDV-00004
25-ESDV-00008
25-ESDV-00013

Performed the isolation of CX-25-01 and VD-25-04 they will be depressurized by 25-
PV-00035

h) VA-21-01, MA-21-01 and VJ-21-02 with the closure of:

21-ESDV-00004
Performed the isolation of VA-21-01, MA-21-01 and VJ-21-02 they will be
depressurized by 21-PV-00003A

Issue Date : December 2015 5 of 8


Shut down Procedure

i) CB-21-01 with the closure of:

21-ESDV-00006

Performed the isolation of CB-21-01 they will be depressurized by 21-PV-00014

j) CX-32-01 and VD-32-01 with the closure of:

32-ESDV-00021
32-ESDV-00005

Performed the isolation of CX-32-01 and VD-32-01 they will be depressurized by


32-PV-00046

k) MA-32-01, VK-32-04A/B, MA-32-02A, MB 32-03, MA-32-02B and line (6”-PL-32-


156-3L3A-V). (Pipe until to spheres ON SPEC RD-33-01A/B/C)

Performed the isolation all will be depressurized by

Opening by-pass 32-PSV-00060 (MA-32-02B), than drained to close drain from MA-
32-01, MA-32-02A and MA-32-02B

l) On spec LPG spheres RD-33-01A/B/C.

Will depressurized by 33-PV-00251B

m) Off spec LPG sphere and pipe from system 32 (6”-PL-33-031-3L3A-V)


Will be depressurized by 33-PV-00251B

n) Unit 28 with the closure of:

28-ESDV-00020
28-ESDV-00014
28-ESDV-00013
28-ESDV-00015

Performed the isolation of HP and LP of unit 28 it will be depressurized from by-pass


28-PSV-00002A/B and 28 PV0004A to flare

(Regeneration section will be kept at 1.5 bar to allow the drainage of liquid)

5. Isolation of Hg, H2S and Sieves beds not involved in the activities of Total shut
down

Hg RU

Completed the depressurization they will be preserved with the closure of:
Isolation Manual Valve by-pass VJ-30-01 (24”-PG-30-052-6S1A-N)
Isolation Manual Valves DB&B upstream MB-30-01 (24”-PG-30-016-6S1A-H)
Isolation Manual Valves DB&B downstream MB-30-01(24”-PG-30-018-6S1A-H)

H2S RU

Completed the depressurization it will be preserved with the closure of:

Issue Date : December 2015 6 of 8


Shut down Procedure

Isolation Manual Valves DB&B upstream MB-30-02A (24”-PG-30-018-6S1A-H)


Isolation Manual Valves DB&B downstream MB-30-02A (24”-PG-30-035-6S1A-N)

Dehydration beds of system 24

Completed the depressurization they will be preserved with the closure of:

Isolation Manual Valves DB&B upstream and downstream VK-24-02A (16”-PG-24-020-


9S1B-H / 8”-PG-24-020-9S1B-H / 16”-PG-24-025-6L3B-H and 8”-PG-24-046-6L3B-H)
Isolation Manual Valves DB&B upstream and downstream VK-24-02B (16”-PG-24-022-
9S1B-H / 8”-PG-24-022-9S1B-H / 16”-PG-24-026-6L3B-H and 8”-PG-24-047-6L3B-H)
Isolation Manual Valves DB&B upstream and downstream VK-24-02C (16”-PG-24-024-
9S1B-H / 8”-PG-24-024-9S1B-H / 16”-PG-24-027-6L3B-H and 8”-PG-24-044-6L3B-H)

6. Draining of equipment

During the final phases of depressurization is suggest to keep a small residual value of
pressure in each equipment (1-2 bar) in the aim to perform easily a preliminary activities
draining that will be however completed later as reported in the W.M.S.

7. Management of lines full of Hydrocarbons and not involved in the above phase of
draining. (Calibration TSV)

As reported in the attached procedure.

8. Purging machine

Purge with N2: Export gas compressors, Expander, Off gas and Regeneration gas
compressors

9. Fuel gas unit

Completed the activities of depressurization and inerting of process units fuel gas system 45
(Configured in back up mode) has to be isolated and depressurized.
(Only late will be star the activities of isolation and inerting of LP flare, HP warm flare and
Close drain VD 57 01 (Flares in service with LPG bottles)

10. Sequence of Handover units to Maintenance and Sequence of Coming back of


units to Exploitation at the end of maintenance activities:

Above mentioned sequences are dictated by the design of CPF and will be applied in the
aim to reduce drastically the down time of CPF through the coordination of the activities
assigned at Maintenance and Exploitation teams.

As detailed in the attached overall shut down plan.

11. Start up.

Activities of start up in ref to operative manuals

Issue Date : December 2015 7 of 8


Shut down Procedure

12. Timing.

Time requested for the execution of activities at the points 3, 4, 5, 6 and 7 “Five” hrs.
Therefore considering the start of Shut down at 07:00 am above points for the systems 20,
30, 28 and 21 has to be finalized at 12:00 am.

Depressurization of Slug catchers and 24” have to be performed:


a) when will be completed the depressurization of CPF.
b) slowly in the aim to avoid incoming of liquids in the Slug catcher

Issue Date : December 2015 8 of 8

You might also like