Faruk Construction provides an offer to Fakir Knitwear for damp and roof treatment work at their Mirpur DOHS site. The offer includes injection grouting leakages in the RCC roof slab for 8,000 TK, plaster removing and damping for 2,500 TK, and new plaster making for 6,000 TK, totaling 16,500 TK excluding VAT and taxes. Payment will be 50% cash with work order and 50% cash within 7 days after submitting the bill.
Faruk Construction provides an offer to Fakir Knitwear for damp and roof treatment work at their Mirpur DOHS site. The offer includes injection grouting leakages in the RCC roof slab for 8,000 TK, plaster removing and damping for 2,500 TK, and new plaster making for 6,000 TK, totaling 16,500 TK excluding VAT and taxes. Payment will be 50% cash with work order and 50% cash within 7 days after submitting the bill.
Faruk Construction provides an offer to Fakir Knitwear for damp and roof treatment work at their Mirpur DOHS site. The offer includes injection grouting leakages in the RCC roof slab for 8,000 TK, plaster removing and damping for 2,500 TK, and new plaster making for 6,000 TK, totaling 16,500 TK excluding VAT and taxes. Payment will be 50% cash with work order and 50% cash within 7 days after submitting the bill.
To, Managing Director Fakir Knitwear Fatullah Narayonganj.
Subject: Offer for damp and roof treatment at Mirpur DOHS.
Sir, after visiting your site at mirpur DOHS here we placed an offer for your kind information.
SL Work details Unit price Quantity Total
01 Injection grouting for leakages 400/point 20point(approx) 8,000 tk
of RCC roof slab
02 Plaster removing and damping 25tk/sft 100sft(approx.) 2,500 tk
03 New plaster making with 60tk/sft 100sft(approx) 6,000 tk essential chemicals apply Total 16,500 tk
Note: 1) This is without vat and tax.
2) This offer including all materials and chemicals. 3) This offer is excluding of any kind of paint and paint related works. 4) Client will provide all the site facilities like water, electricity, table or macha at site. We will provide the labors and materials and working equipment.
Payment: 1) 50% cash with work order.
2) 50% cash within 7days after submitting the bill.