Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

3/19/2020 How to Control Reinforcement Steel Wastage at Construction Projects - Civil4M

Piling In The Wake eld Area - Fast, Low Cost Mini Piling OPEN
12 Year Guarantee - ASUC Registered - 25 Years Experience - Speedy & Reliable minipiling.co.uk

Forums  C4M TECHNICAL DISCUSSION  Total Quality Management

How to Control Reinforcement Steel Wastage at Construction Projects


 Dnyan Deshmukh ·  Nov 15, 2017 ·  how to control steel wastage reinforcement steel wastage

Dnyan Deshmukh
Eternal Member  Staff member

 Sep 7, 2017  2,533  4,385  Pune

Nov 15, 2017  #1

How to Control Reinforcement Steel Wastage at Construction Projects


Wastage of steel is big factor at any construction project; many do reconciliation of steel received and used at project but fails to show the wastage quantity physically
and keep on thinking where that wastage steel gone and base on assumption make following statements.

Steel may have got stolen from site.


Contractor had thrown it inside the lling at plinth level and around building.
No records provided from site for use of extra steel and so on.

Today at Civil4M, I will put some lights on shadows, which makes your steel disappear without giving any clue to where it had gone.

You may be aware about the tolerances for mass of steel given in IS 1786
If you open IS 1786 and go to clause Number 7.2.2 Table Number 2, you will nd

For up to and including 10mm Dia bar – It allows +/- 7% deviation from standard weight.
For Over 10mm up to and including 16mm Dia Bar – It allows +/- 5% deviation from standard weight and,
For above 16mm Dia bar – it allows +/-3% deviation from standard weight.

What does it mean?


Example: I received a 12mm Dia bar lot at site and if I cut a bar of 1 meter length from it, then it weight should be 0.888 Kg/Meter as per standard.
If I weight it and nd its weight as 0.932 Kg/meter – Is it acceptable?

Yes, that rebar lot is acceptable as per IS 1786 and you can’t reject it. Manufacturer did production of steel within the tolerance limit speci ed in IS 1786.
Here in this example steel is overweight by 5% and is within tolerance limit speci ed in IS 1786.

If you receive overweight steel from supplier and it is blindly accepted, You lost your wastage % limit at the time when you accepted such lot and this steel becomes
unaccounted, You can’t even justify where your steel gone and you can only make above statements which I written at the start of this post.
If allowable wastage is 3% and my steel is overweight above 3% then I need to order more steel to complete the work as you going to make wastage during cutting of steel
due to standard length of bar from which you cut the steel (This is unavoidable unless you buy a precut length bar of your desired length. At Civil4M in my next post I will
write article on how to utilize those wasted steel bar and save the money)
This is the primary wastage cause without really wasting it.

How you can control it?


Buy steel from primary steel manufacturer, it is manufactured near to accurate standard weight or slightly underweight.
In primary steel too some manufacturer like RINL, you may also end up in buying overweight steel.
If you buy Secondary Re-rolled steel, the weight of steel depends on the quality of manufacturer and in most cases you will end up in buying overweight steel.

Do you mean I should not buy Secondary Steel?


No, but you should prefer Primary Steel and in both cases you should check the weight of steel received at site.

How I can control the overweight issue?


IS 1786 Never says you should follow tolerances given for mass strictly, unless otherwise it is agreed between manufacturer and purchaser.
This means if you specify the manufacturer, I will only accept steel if its within tolerance limit which is stated by us, then he is bound to supply you as per speci cation
provided by you and if it is not as per that, You can reject the lot of steel received at construction project.
Peoples, who understand it, can make miracle and do value addition to their company.

How I can specify them the tolerance limits?


I can specify them by adding it into the purchase order which I provide them for doing supply.
Example: (This is purely an example, you use your mind during specifying your requirements, you can use it but you should know, what you are doing)
Clause in Purchase order
We accept Reinforcement steel as per below Tolerance limits speci ed by us and you are bound to supply material as per this only.
For up to and including 10mm Dia bar – (-)7% and +2%.
For Over 10mm up to and including 16mm Dia Bar – (-)5% and +2%.
For above 16mm Dia bar – (-)3% and +1%.
Material received beyond overweight tolerance limit will be debited to you for same amount of weight.
Material received below underweight limit will be rejected.

What these clauses exactly do?


It ensure no wastage occurs when you receive steel at your project as manufacturer will tend to produce steel in limit which are more exible i.e.- he will try to produce
underweight so he will achieve at least a standard weight and never goes to overweight side.

https://civil4m.com/threads/how-to-control-reinforcement-steel-wastage-at-construction-projects.1075/#post-2581 1/5
3/19/2020 How to Control Reinforcement Steel Wastage at Construction Projects - Civil4M
Above thing is called Engineering, we should use Engineering on such points to keep project going on without need of extra spending. Civil4M tries to share such

knowledge will all. (Any members have good knowledge in any Civil Engineering eld can share it with other members and help all to become Better Civil Engineers).
So now we will not make above statement written at start of post and knows exactly where my steel is going.
To be more accurate on this Engineer should prepare a Rolling Margin sheet which convert all steel to theoretically exact weights and help in reconciliation of steel – its
again a big topic so will discuss this in another post.

Other factors of wastage in Reinforcement steel;


Rebar Cutting and Bending Gang
Have you ever wondered, why some tter keep on making stirrups / Rings.
If you look at it closely, you will nd that the tter makes rings without any calculations on how much required and what will happen if I make more stirrups than required
(Steel is free, so it does not make him to worry).
He only concern with how much he made, base on that he get paid.
Same with other tters too, they keep on cutting bars without thinking of wastage.

Reinforcement Bars should be cut and bend only in quantity speci ed on Bar Bending Schedule and to achieve this only speci ed number of bars given to contractor for
doing work and each day reconciliation of it to be done before providing him next number of bars required for next work.
If you had ever taken round on project site and observed it (I am not saying about just simply visiting by keeping mind at home), You will nd Cut steel bars, rings / stirrup
etc abandon everywhere, around building, on each oor (Even if work is going on at 20th oor you will nd steel on 1st oor, in any amount from less to large quantity and
not even stacked properly)

When Bell rang from top, all of sudden everyone get to task to clean oors and then those bars, stirrups are collected and thrown to one place just like it’s a waste (No one
goes to that stack to do sorting and using it, this happens for 2 or 3 days when issue is hot, later all goes into wastage and we scrap it).
Why steel bars seen everywhere when work is going on only at 1 oor?
We only see and do not observe. If we make observations, you will not have scrap at your project.

https://civil4m.com/threads/how-to-control-reinforcement-steel-wastage-at-construction-projects.1075/#post-2581 2/5
3/19/2020 How to Control Reinforcement Steel Wastage at Construction Projects - Civil4M

I hope this article will turn up a useful for you and you will make some value addition at you project, here at Civil4M will post some more articles regarding Reinforcement
steel

How to do rolling margin, achieve less wastage and proudly do reconciliation.


How to make use of wastage / scrap bars. Save the money, instead of selling it in scrap.
How we can make Bar Bending Schedule in simple steps - Click Here.
How we can control, cutting and bending of reinforcement steel.
Nimmy, Jitendra Geete, Imtiyaz Eraaf and 21 others

Srinivasan
Administrator Staff member

 Sep 7, 2017  1,025  1,503  mumbai

Nov 15, 2017  #2

sir
the article is really wonderful. i differ with you regarding the purchase arrangement of mentioning that thr buyer shall not accept any martial beyond the speci ed rolling
margin. sir this condition is not acceptable by any vendor. we are well aware that the the re rolling reinforcement made out of scrap etc. when this material is melted and
lled in pellets t never been uniform due to the movement of pellet on the conveyor resulting one bar is having a variation 5% other one having a variation of 7%. even if you
check a site from the two different bundles you will notice he variation. even though generally the variation in not exceed beyond he prescribed limit no vendor shall accept
he work order in case of the condition states if the reinforcement shall not be acceptable beyond the prescribed limit. i have gone thorough this issue on quiet lot of
occasion. otherwise its a fantastic article every one should read and understand
hamza shabbir, Khurram Shahzad, Teju9766 and 6 others

Dnyan Deshmukh
Eternal Member  Staff member

 Sep 7, 2017  2,533  4,385  Pune

Nov 15, 2017  #3

Thank You for your concern.


I will write in more detail on tolerance and rolling margin in my next article as i stated at the end.

We can nd good vendors who can accept this or else a buyer is spending more without getting actual quantity for work. The buyer (companies) who is smart enough and
knows value of his money do add such clauses in purchase orders.

Contractor (Smart enough contractors like L&T) who has nothing to do with purchasing, saves there life by doing rolling margin which shows original buyer(client) you are
providing me overweight steel and i am not accountable for that losses and never treat it as wastage done by me.

So once a buyer knows it, he takes appropriate actions on it. As no one like to give there money free of cost to others.

So if secondary steel manufacturer have issue with his setup, why i should suffer.

https://civil4m.com/threads/how-to-control-reinforcement-steel-wastage-at-construction-projects.1075/#post-2581 3/5
3/19/2020 How to Control Reinforcement Steel Wastage at Construction Projects - Civil4M
Khurram Shahzad, Josese Cavunisautu, VIDHYA SAGAR and 4 others

Abdul aziz kionywaki
Active Member

 Oct 3, 2017  131  107  Tanzania

Nov 17, 2017  #4

Thank you so much

Umamahesh
U Newbie

 Nov 6, 2017  9  8  India

Nov 18, 2017  #5

Very usefull thank you

Umesh Khimani
U Newbie

 Sep 8, 2017  2  0

Apr 9, 2018  #6

Thanks for information which can really shows our engineering skill.

Rakesh391
R Newbie

 Jun 17, 2019  3  0  Mp

Aug 4, 2019  #7

Dnyan Deshmukh said: 

How to Control Reinforcement Steel Wastage at Construction Projects


Wastage of steel is big factor at any construction project; many do reconciliation of steel received and used at project but fails to show the wastage quantity physically and keep
on thinking where that wastage steel gone and base on assumption make following statements.

Steel may have got stolen from site.


Contractor had thrown it inside the lling at plinth level and around building.
No records provided from site for use of extra steel and so on.
Click to expand...
T d Ci il4M I ill li h h d hi h k l di ih i i l h i h d

Dnyan Deshmukh said: 

How to Control Reinforcement Steel Wastage at Construction Projects


Wastage of steel is big factor at any construction project; many do reconciliation of steel received and used at project but fails to show the wastage quantity physically and keep
on thinking where that wastage steel gone and base on assumption make following statements.

Steel may have got stolen from site.


Contractor had thrown it inside the lling at plinth level and around building.
No records provided from site for use of extra steel and so on.
Click to expand...
T d Ci il4M I ill li h h d hi h k l di ih i i l h i h d

Very good article sir...

natarajan.balu
Junior Member

 Oct 4, 2017  23  24  Bangalore

Aug 6, 2019  #8

Yes, this is a very serious issue. Everyone right from top to bottom knows very well about this. But unfortunately , this issue has not been taken very seriously excepting
that at the end of the project a staff will be shown the door. I strongly feel every Bill the client should insist for reconciliation and should penalise the contractor with heavy
amount.Even after working for 34 years in execution I personally feel guilty for not getting any support from the management. Hope in future some development will
happen regarding this subject. Thanks for sharing this issue in post with all. Natarajan from Bengaluru. Natarajan.balu@rediffmail.com.
Dnyan Deshmukh and HockeyPuck

ranajit maikap
R Newbie

 Mar 6, 2019  4  0  kharagpur

https://civil4m.com/threads/how-to-control-reinforcement-steel-wastage-at-construction-projects.1075/#post-2581 4/5
3/19/2020 How to Control Reinforcement Steel Wastage at Construction Projects - Civil4M
Aug 21, 2019  #9

natarajan.balu said: 

Yes, this is a very serious issue. Everyone right from top to bottom knows very well about this. But unfortunately , this issue has not been taken very seriously excepting that at
the end of the project a staff will be shown the door. I strongly feel every Bill the client should insist for reconciliation and should penalise the contractor with heavy amount.Even
after working for 34 years in execution I personally feel guilty for not getting any support from the management. Hope in future some development will happen regarding this
subject. Thanks for sharing this issue in post with all. Natarajan from Bengaluru. Natarajan.balu@rediffmail.com.

very good articles

You must log in or register to reply here.

Piling In The Wake eld Area


12 Year Guarantee - ASUC Registered - 25 Years Experience - Speedy & Reliable

minipiling.co.uk OPEN

 Similar threads

Standared deviation Calculation


 Dhaval Thanki replied Tuesday at 1:47 PM 4

Core and Cube Test Procedure loading rate calculations as per IS 516
S  T Kolundu replied Feb 12, 2020 2

Project Quality Managers Weekly Quality Monitoring Report Format


 nagareddayya.s posted Nov 20, 2019 0

Project Quality Plan as per ISO Quality Management Systems for Construction Projects
 Civil4M replied Oct 6, 2019 2

quality control in structural steel


 Srinivasan posted Sep 22, 2019 0

Share:       

Contact us Terms and rules Privacy policy Help  

Forum software by XenForo® © 2010-2019 XenForo Ltd. | Civil4M © 2017-2019 | 

https://civil4m.com/threads/how-to-control-reinforcement-steel-wastage-at-construction-projects.1075/#post-2581 5/5

You might also like