Professional Documents
Culture Documents
Industrial Technology Final PDF
Industrial Technology Final PDF
INDUSTRIAL
TECHNOLOGY
Khalid A. Gaber
2018
4- Flow sheet.
5- Layout.
6- Classifications. “Wortmann Classifications”:
Engineer-to-Order (ETO): the product is designed and built to customer’s
specifications. This approach is most common for one-off products (very complex or
specialized or unique products), such as Formula 1 cars.
Purchasing-to-Order (PTO): the product is already designed, but materials for
production are still not in inventory, then they should be ordered.
Make-to-Order (MTO): the product is based on a standard design, but the
manufacturing of the final product is linked to the order placed by the customer's
specifications. This approach is typical for high-end motor vehicles and aircraft.
Assemble-to-Order (ATO): the basic parts of the product according to customer’s
specifications are already manufactured but not yet assembled. A typical example for
this approach is Dell's approach to customizing its computers.
Make-to-Stock (MTS): the product is built according to a sales forecast, and sold to
the customer from finished goods stock such as the grocery and retail sectors.
We shall assume that the given space is rectangular shaped and every department is
either rectangular shaped or composed of rectangular pieces.
1) Heuristic CRAFT “Computerized Relative Allocation of Facilities Technique”:
It is layout improvement procedure (not a construction of new layout procedure),
that attempts to find a better layout by pair-wise interchange when a layout is given.
Inputs:
1- Initial Layout.
2- From-to table.
3- Cost of the movements.
4- Number of departments to be allocated and their constrains.
5- Given a layout, CRAFT first finds the total distance traveled.
6- CRAFT then attempts to improve the layout by pair-wise interchanges. If some
interchange results some savings in the total distance traveled, the interchange
that saves the most (total distance traveled) is selected.
7- Interchanges can be done on one way, with departments of that are next to
themselves (one side at least should be connected).
• Notes:
1- Sometimes, an interchange may result in a peculiar shape of a department; a
shape that is composed of some rectangular pieces.
2- Estimated cost reduction may not be obtained after interchange.
3- An approximation estimate of average walking required is obtained from the
distance between centroids of two departments.
.
SOLUTION
EXAMPLE
You have to design a continuous flow plant for the production of nylon. The data are:
Production Target: 22.000 ton. Theoretical Production Capacity: 23 ton/day
Opening days: 200 days/year, 24h/day Availability (A): 0,98 Scheduling Efficiency (SE): 0,95
For the Scrap Rate, you have to consider the following values, correlated to the saturation of the plant
Saturation (%) 95-100% 90-95% 85-90% 80-85% 75-80%
Scrap Rate 0 0,02 0,04 0,07 0,1
To calculate:
a) The Actual Production Capacity
b) The number of the lines
c) The average saturation
Solution
THIRD: WEAKNESSES:
1- Limitations in machines efficiency because machine flexibility causes penalties
in setup time, effort, cost or performance. That leads to productivity reduction.
2- Qualitative characteristics of products can vary for different pieces because the
tolerance of different machines could be not the same.
3- Production management and scheduling is complex because of the high number
of machines, product types and alternative process plans for each product.
That causes:
A. High WIP.
B. Long and high variability of the lead times.
C. Low utilization rate of machines in short time because of the bottlenecks.
4- It is difficult to calculate production capacity of the machines that depends on:
A. Changing in production mix of jobs.
B. Different process plans of jobs and using alternative routings.
C. Number of machines and their state.
D. Lot sizes.
E. Ability to schedule jobs.
Because it causes changes in the machine workloads → changes in the utilization rates of
machines → different bottleneck machines → different production capacity.
STEP10: Evaluate the number of shifts/day, computing the yearly costs. As a result two possible
choices when evaluating the alternatives of system design under the economical dimension:
Same shifts/day for all the departments vs. optimal shift for each department
Solution
A mechanical SME has to plan a new production system, based on a job shop layout. It will produce 4 pieces (A, B,
C, D), in the following expected demand.
Piece type Expected demand (p/y) Piece type No. lots/y
A 15000 A 200
B 24000 B 100
C 75000 C 125
D 25000 D 150
Piece type M1 (sec) M2 (sec) M3 (sec) Piece type M1 (sec) M2 (sec) M3 (sec)
A 70 80 200 A 600 200 1000
B 75 100 0 B 900 600 0
C 100 50 75 C 300 500 750
D 150 90 80 D 300 400 400
Production times Setup times
Then we know what follow:
The system will work 220 days/y.
If it will work for just one shift, it will be active 8 h/day.
For 2 shifts, it will work 8 h/shift 1 and 7,5 h/shift2.
For 3 shifts, it will work 8 h/shift 1 and 7,5 h/shift2, and 7 h/shift3.
A = 0.95 for all the machines
HC = 0.95.
SR = 0.05 (the yield is 0.95, the scraps are 0.05).
SE = 0.80.
Requirements:
1. Design the system with 1, 2 and 3 working shifts.
2. Calculate the expected saturation.
3. With the following cost information, determine the best solution (minimization of the total cost).
M1 M2 M3
Acquisition cost (k€/machine) 150 250 150
k€ (for each machine) M1 M2 M3
Energy and service costs for 1 shift 50 75 70
Energy and service costs for 2 shifts 100 100 100
Energy and service costs for 3 shifts 200 300 250
M1 M2 M3
Number of machines to be handled by one operator 2 1 2
Annual operator cost for 1 shift k€ 44 36 36
Annual operator cost, if we work with 2 shifts 55 45 45
Annual operator cost, if we work with 3 shifts 66 54 54
Solution
Exercise
The following matrix identifies the bill of process of 9 products on 7 machines. The cycles have been defined
with the objective of designing a manufacturing cells system:
Products
1 2 3 4 5 6 7 8 9
1 1 1 1 1
2 1 1
Machines
3 1 1 1
4 1 1 1
5 1 1
6 1 1
7 1 1 1
Solution
Products
1 8 2 4 6 7 9 3 5
1 1 1 1 1
5 1 1
Machines
4 1 1 1
7 1 1 1
3 1 1 1
6 1 1
2 1 1
Products
1 8 2 4 6 7 9 3 5
1 1 1
5 1 1
4 1 1 1
Machines
1 1 1
7 1 1 1
3 1 1 1
6 1 1
2 1 1
From / To Chart:
From \ To RM WC 3 WC 5 WC 7 WC 8 WC 9 WC 10 WC 20 FG
RM - 5,000 20,000
WC 3 - 8,000 3,000 6,000
WC 5 - 7,000 1,000
WC 7 1,500 - 18,500
WC 8 - 10,000 4,000
WC 9 - 25,000
WC 10 7,000 8,000 -
WC 20 1,500 7,000 7,000 -
FG -
U-shaped may reduce employee movement and space requirements while enhancing
communication, reducing the number of workers, and facilitating inspection.
Virtual Manufacturing Cell:
Virtual Manufacturing Cell (VMC) is an alternative to traditional manufacturing cells,
with the purpose to be more effective with production mix variability. In VCM the
machines that belong to a cell are not physically located together, but are identified as a
group only by the Production Planning and Control system. Virtual cells can achieve the
benefits of repetitive processes without the layout re-arrangement of a job shop.
Which are the methods for balancing a transfer line? “Models for line balancing”
The main point of designing the transfer line is allocating operations and balancing the line.
In order to do this, the methods as:
1- Linear Programming (optimal):
Main assumptions of the model:
A. Times to perform operation are known in order to minimize the probability
of no-completion.
B. Requested production capacity is PC identified in order to minimize the CT
(as it is given as a constraint based on PC).
C. System composed of m parallelized assembly lines;
D. Absence of waste (defective products are reworked in a hospital station).
Once given the CT, we can limit the total idle time, by minimizing the number of stations.
2- Maximum fixed utilization rate (heuristic):
Without priority rules (i.e. the first available operation is assigned).
With local priority rules for assigning priorities, such as:
MaxDur (longest processing time).
MaxNFol (largest number of immediately following operations).
With global priority rules for assigning priorities, such as:
Ranked Positional Weighting.
MaxFol (largest number of following operations).
Different approaches (using the same rule) can be adopted:
Task-oriented: when the remaining idle time is not sufficient to assign
the operation, a new workstation is opened → simpler, but less efficient.
Station-oriented: when the remaining idle time is not sufficient to assign
the operation, before opening a new station, other available operations
are taken into consideration to fill-up → less simple, but more efficient.
Rough design of a mono-product transfer line (single-model):
1- Define the yearly demand, technological routing and operations of the product type.
2- Identify the machine types needed based on the product routing and balance the line
(allocation of operations) on the given Cycle Time CT (seconds / piece).
3- Calculate the theoretical production capacity → TPC = 3600 / CT [piece/hr].
4- Calculate the actual production capacity → APC = TPC × A × (1 – SR) [piece/hr].
5- Compare the actual production capacity and the demand. If APC < Demand, modify
the line and go back to step 2 by including additional machines or parallelization of
more machines for the same operations to reduce CT.
Example:
Assumption:
Pieces are manufactured in batches (batch A, B, and so on); changing production
from one batch to another requires a setup.
Setup times do not depend on the production (batch) sequence because there is
no sequence dependence, or it is the result of an optimization procedure that
enabled to identify best batch sequencing to reduce set-up times.
Design steps:
1- Identify the product type mix estimating the yearly demand.
2- Define the technological routing and operations of the product types.
3- Identify all the machine types needed and balance the line for each product type.
4- Calculate the cycle time for each product type j → CTj = maxh {TLjh} [seconds/piece]
Where: TLjh = unit working time of product type j at workstation [seconds/piece]
3. Assembly Systems:
GENERAL FEATURES:
Assembly system consists of assembly equipment and the workforce, which is used to
assemble a product parts that has been already manufactured to identify final product.
In manual assembly systems, the main resource is the workforce:
• PROS: High flexibility thanks to the operators’ skills.
• CONS: variability of the manual assembly time that determines challenges in the
balancing and sequencing problem.
Technology:
• Free technology route, with degrees of freedom.
• Operation can be reversible (or irreversible, e.g., welding).
• Process flow is synthetic.
Cost structure:
• Low relevance of fixed assets depending on utilization & customization of machinery.
• A lot of manual operations that cause workforce utilization.
Assembly tasks do not usually require specific tools.
Three independent axes for classification:
• Layout configuration [Fixed position–Assembly shop–Assembly cell–Assembly line].
• Production mix management [Single model - Multi models - Mixed models].
• Task organization.
• Reciprocal movement of assembly, operator & components.
Single-model system establishes one assembly line for each product which is
suitable for high volumes and stability of product demand.
• PROS: Low management issues.
• CONS: Low flexibility.
More products are assembled on the same SYSTEM: batch production:
• Setup time is relevant.
• Cycle time and number of workstations depend on the products to be assembled.
• Need of good line balancing.
More products are assembled in the same LINE:
• They are often implemented with continuous flow and unpaced (asynchronous) lines.
• PROS: Opportunity to follow the demand.
• CONS: Need to reduce setup time & Need to balance the line & Difficult to manage
component flows & Difficult to manage parallel workstations.
Example:
A company assemblies 3 different products (A, B and C), which need dedicated fixed position assembly
stations. The requested production capacity for product A is 10 pieces/h, for B is 15 pieces/h, while for C is 8
pieces/h. For assembling product A, 3 operations are necessary: one lasts 0.3 h, the other one 0.4 h and the last
one 0.6h. For product B, 4 operations are requested: one lasts 0.4 h, the other ones last 0.3, 0.2 and 0.1 h.
Finally, product C requires 3 operations to be assembled: one lasts 0.2 h, the other two operations last 0.3 h.
how many stations needed?
Solution:
NA = 10 x 1.3 = 13 stations, NB = 15 x 1 = 15 stations, NC = 8 x 0.8 = 6.4 = 7 stations
Example:
A company assemblies 3 different products (A, B and C), which need dedicated the same fixed position
assembly stations. The requested production capacity for product A is 9 pieces/h, for B is 12 pieces/h, while
for C is 7 pieces/h. For assembling product A, 3 operations are necessary: one lasts 0.2 h, the other one 0.4 h
and the last one 0.6h. For product B, 4 operations are requested: one lasts 0.2 h, the other ones last 0.5, 0.3 and
0.1 h. Product C requires 3 operations to be assembled: one lasts 0.2 h, the other two operations last 0.3 h. how
many stations needed?
Solution:
NTOTAL = (9 x 1.2) + (12 x 1.1) + (7 x 0.8) = 29.6 = 30 stations
EXAMPLE
In the following station 4 operations are realized:
Oper. Precedence Mean time Std. dev.
(min) (min)
1 - 6 1
2 1 3 1
3 1 2 1
4 3 7 1
The cycle time (CT) is equal to 20 minutes. Which is the probability of no-completion?
SOLUTION
EXAMPLE
To organize the line respecting the constraints of maximum saturation (85%) and of probability of no-completion
(10%). The volume is 500 pieces/day, and the available time is 420 min.
Oper. Precedence Mean time (sec) Std. dev. (sec)
A - 20 5
B A 1 1
C B 2 0,9
D C 17 7
E - 15 3
F E 12 3
G F 12 3
H D,G 12 2
I D,G 12 2
J D,G 10 2
K D,G 10 2
SOLUTION “Saturation”
Task Precedence Duration (s) Sum Ti Res Time Saturation StdDev (s)
A 20 20 30.4 40% 5
B A 1 21 29.4 42% 1 Station
C B 2 23 27.4 46% 0.9 1
D C 17 40 10.4 79% 7
E 15 15 35.4 30% 3
Station
F E 12 27 23.4 54% 3
2
G F 12 39 11.4 77% 3
H D,G 12 12 38.4 24% 2
Station
I D,G 12 24 26.4 48% 2
3
J D,G 10 34 16.4 67% 2
K D,G 10 44 6.4 87% 2
The operation K saturates Station 3 over the constraint. So, it is necessary to create a (Station 4)
V 500 unit/day
AH 420 min
S 85% max
Pk 10% max
Tk 123 sec
Tc (CT) 50.4 sec
Nmin 2.44047619 3
TH vs. WIP: Best-, practical worst- and worst-case performance TTP vs. WIP: Best, practical worst- and worst-case
Work Content model (hr): it is a measure of the working time required by an operation
on a workstation. Working time or process time is used as synonymous.
Operating time TOP (SCD): it expresses the time needed in order to complete the job.
ROUTmax (hr/SCD): it expresses the maximum working hours per day provided by a
workstation to perform the requested jobs without performance losses.
EXAMPLE
The VITE Spa Company that is specialized in the production of metal parts for the oil & gas sector decided to
install a new production system to realize some specific products. The new system will be configured as a flow
shop with two s hops (R1 and R2) where different machining operations will be carried out (M1 for R1, M2 for
R2). In the first shop metal parts are cut; in the second shop drilling operations will be carried out. The two shops
will process different products and a buffer will be located between the two shops. The capacity of the buffer can be
considered “infinite”.
The following are the data about production mix: Working time and setup time are provided:
Working time M1 Working time M2
Product type Yearly demand Lot size per order Product type
machine (min/piece) machine (min/piece)
X 5000 20
X 3 10
Y 10000 40
Y 4 14
Z 8000 50
Z 5 11
Opening time will be 7 hours on 200 days per year. Setup time R1 Setup time R2
Product type
The mix will be realized homogeneously along the year. shop (min/order) shop (min/order)
X 3 10
You are required to identify: Y 3 7
1) Number of resource (i.e. number of machines) for Z 3 8
each shop to satisfy the demand;
2) The minimum value of WIP to let the bottleneck working for the required annual demand.
SOLUTION
4.2 Availability:
Maintenance policy:
A. Corrective Maintenance CM (after the failure):
maintenance intervention is performed after failure occurrence.
B. Preventive Maintenance PM (before the failure):
maintenance intervention is performed before failure occurence.
We have 3 types of PM:
B.1) Cyclic “Time based Maintenance TBM”: Actions are carried out at set-times
(clock-based) or at a fixed age of usage of the component (age-based). It requires the
statistical knowledge of the failure mode. It is well suited if:
- the failure rate has a well defined and growing shape.
- the cost of the TBM policy is lower than the cost of the CM policy.
B.2) Condition Based Maintenance CBM: Actions that monitor the actual condition of
the asset to decide what maintenance needs to be done. It is well suited if:
- the cost of the CBM policy is lower than the cost of the CM and TBM policy.
B.2.1) Predictive Maintenance PdM: Actions that help to determine the condition
of in-service equipment to estimate when maintenance should be performed.
C. Opportunistic maintenance:
maintenance actions that made on secondary components of a stand-by machine due to
a corrective or preventive maintenance operation.
D. Productive maintenance:
It is the set of continuous improvement actions in order to improve equiment reliability
and maintainability.
System availability – problem setting:
In manufacturing systems, the occurrence of failures leads to performance losses at each
machine (downtime state), thus; the impact of failures can be different depending on the
configuration of the system. The impact at system level may be partial, not totally leading
to zero production rate in case if there are parallel machines.The system availability can
analyze the configuration of the system based on the availability of each single machine.
The availability depends on many factors, such as:
Technological characteristics of product types.
Number of machines and their state.
Ability to schedule preventive maintenance.
EXAMPLE
A transfer line works 220 days/year, 8 h/shift, 2 shifts/day. The number of stations in the line is 4. In station 2 and 4
there are 2 machines that work in parallel. Working time at each machine of the line (unmanned):
Single Machine in Station 1: 35 [sec/piece];
Single Machine in Station 2: 72 [sec/piece];
Single Machine in Station 3: 37 [sec/piece];
Single Machine in Station 4: 70 [sec/piece].
The availability, equal for all machines, is 0,99. Some hypotheses are:
The line is an asynchronous transfer line; its buffers have the function to decouple the operations, allowing
parallelization (station 2 and 4); the size of the buffers is not enough to completely avoid propagation of the
effect of machine downtimes;
other causes of production capacity loss are not considered (setups, scraps, blockages);
Machine failures are independent of each other.
Evaluate the expected hourly production capacity of the line, the annual production capacity of the line, and
the availability of the line.
SOLUTION
EXAMPLE
Transfer line working 240 days/year; 7.5 hours/shift; 1 shift/day. Number of stations in the line: 4; in station 2 there
are 3 machines working in parallel; in other stations there is only 1 machine working; total of 6 machines in the
line. Working time at each machine of the line (unmanned):
Single Machine in Station 1: 35 [sec/piece];
Single Machine in Station 2: 108 [sec/piece];
Single Machine in Station 3: 37 [sec/piece];
Single Machine in Station 4: 35 [sec/piece].
Availability (equal for all machines): 0,985. Hypotheses:
The line is an asynchronous transfer line; its buffers have the function to decouple the operations of station 2
from the other stations (thus allowing parallelization); the size of the buffers is not enough to avoid
propagation of the effect of machine downtimes from station 2 to others;
Other causes of production capacity loss are not considered (setups, scraps, blockages);
Machine failures are independent of each other.
Evaluate the expected hourly production capacity of the line, the annual production capacity of the line,
and the availability of the line.
• 1 state with all machines functioning: CT = 37 [sec/piece];
• 3 states with 1 faulty machine in station 2: CT = 54 [sec/piece];
• 3 states with 2 faulty machines in station 2: CT = 108 [sec/piece];
Exercise
A transfer line works 220 days/year, 8 h/shift, 2 shifts/day. The number of stations in the line is 3. In station 2 there
are 2 machines that work in parallel, in station 3 there are 3 machines that work in parallel. Working time at each
machine of the line (unmanned):
Single Machine in Station 1: 35 [sec/piece];
Single Machine in Station 2: 78 [sec/piece];
Single Machine in Station 3: 108 [sec/piece];
The availability, equal for all machines, is 0,98. Some hypotheses are:
The line is an asynchronous transfer line; its buffers have the function to decouple the operations, allowing
parallelization (station 2 and 3); the size of the buffers is not enough to completely avoid propagation of the
effect of machine downtimes;
Other causes of production capacity loss are not considered (setups, scraps, blockages);
Machine failures are independent of each other.
Evaluate the expected hourly production capacity of the line, the annual production capacity of the line, and
the availability of the line.
• 1 state with all machines functioning: CT = 39 [sec/piece];
• 2 states with 1 faulty machine in station 2: CT = 78 [sec/piece];
• 3 states with 1 faulty machine in station 3: CT = 54 [sec/piece];
• 6 states with 2 faulties (1 in st.2 and 1 in st.3): CT = 78 [sec/piece];
• 3 states with 2 faulties in station 3: CT = 108 [sec/piece];
• 6 states with 3 faulties (1 in st.2 and 1 in st.3): CT = 108 [sec/piece];
D. Variables and Attributes: data and information about entities or resources (e.g.
warehouse capacity, cycle time).
E. Status: Description of all the values attributes of an entity or a resource, in a specific
instant of time.
F. Event: The time in which the model status of entity or resource is changing.
G. Activities: Operations has been done during an event (started and ended).
Examples of DES: Call center / Gas station / Restaurant / Airport / Factory / …
Simulation supports:
A. Design of new systems.
B. Improvement of actual systems.
C. Performance analysis (e.g. productivity, bottlenecks, resources saturation).
D. WHAT-IF analysis: how outputs change according to variation of process parameters.
E. Training.
Evaluation Criteria of the chosen software:
A. Flexibility / Ease of development / Model execution speed / Animation / Statistics /
Output visualization / Interface with other data / Reusability / Customer support / Cost.
Simulation Phases: