The document outlines a schedule for a streetscape project in Haram City. It lists activities with original start and finish dates from July 2020 through January 2021. The project includes construction and side work like curb forming. Work is broken into zones B3, B4, B2, B1, and 08, with various road construction activities assigned to dates within each zone's scheduled timeframe. The overall project is scheduled to start on July 22, 2020 and finish on January 7, 2021.
The document outlines a schedule for a streetscape project in Haram City. It lists activities with original start and finish dates from July 2020 through January 2021. The project includes construction and side work like curb forming. Work is broken into zones B3, B4, B2, B1, and 08, with various road construction activities assigned to dates within each zone's scheduled timeframe. The overall project is scheduled to start on July 22, 2020 and finish on January 7, 2021.
The document outlines a schedule for a streetscape project in Haram City. It lists activities with original start and finish dates from July 2020 through January 2021. The project includes construction and side work like curb forming. Work is broken into zones B3, B4, B2, B1, and 08, with various road construction activities assigned to dates within each zone's scheduled timeframe. The overall project is scheduled to start on July 22, 2020 and finish on January 7, 2021.