Download as pdf or txt
Download as pdf or txt
You are on page 1of 36

Construction Traffic Management Plan

Construction Traffic Management Plan

(CTMP)

Turitea Transmission Line

This Construction Traffic Management Plan is the property of Electrix Limited.

This document is not to be reproduced to third parties without written authority from Electrix.

Job Manager: Kevin Small


Customer: Mercury
Electrix Job No: P.0242015.1.01
Date of Issue: 2nd July 2019

Version: 1.0 Page 1 of 20


DATE: 02/07/2019
Distribution Register

Name Designation Role Signature Date


Chartered Professional
Angie Crafer Chartered Engineer
Engineer (CPEng)
Peer Reviewer &
Kevin Small Project Manager
Approver
Emma Comrie- Environmental
Peer Review
Thomson Consultant (Electrix)
Chris Singleton Client Approver

Amendment Register

Issue Issue Date


No Description Author Reviewer Approver
01 2 July 2019 Version 1 Emma Comrie-Thomson

Management Plan Approval

The undersigned acknowledge they have reviewed the Turitea Transmission Construction Traffic
Management Plan (CTMP) and agree with the approach it presents. Changes to this CTMP will be
coordinated with and approved by the undersigned or their designated representatives.

Name Designation Role Signature Date


Kevin Small Job Manager Approver
Chris Singleton Client - Mercury Approver

Version: 1.0 Page 2 of 20


DATE: 02/07/2019
ACRONYMS

Acronyms Defined
AEE Assessment of Environmental Effects

CEMP Construction Environmental Management Plan

CLG Community Liaison Group

CoPTTM Code of Practice for Temporary Traffic Management

CNMP Construction Noise Management Plan

CTMP Construction Traffic Management Plan

PNCC Palmerston North City Council

SEMP Site Environmental Management Plan

STMS Site Traffic Management Supervisor

TDC Tararua District Council

TTMP Temporary Traffic Management Plan

VPD Vehicles Per Day

Version: 1.0 Page 3 of 20


DATE: 02/07/2019
TABLE OF CONTENTS
1. BACKGROUND 6
Chartered Professional Engineer Statement 7

2. LOCATION 7
3. PURPOSE OF THE CTMP 10
4. CONSTRUCTION OPERATIONS 10
Summary of Transmission Works 10
Site Access 10
Routes 10
Traffic Flows 11
4.4.1 Truck Movements 11
Signage 12
Storage of Materials 12
Hours of Operation 12
Construction Programming 13
Kahuterawa Road and Greens Road Upgrade 13

5. TRAFFIC MANAGEMENT 15
Monitoring 15
Pedestrians/Cyclist and Horses 15
Temporary Traffic Management Plans 15
Greens Road 15
Private property access 16

6. CONSULTATION AND COMMUNICATION 18


7. CONTACT DETAILS FOR PROJECT MANAGEMENT 19
8. DRIVER PROTOCOLS 19
Behaviour 19
Disciplinary procedures 19

9. COMPLAINTS PROCEDURE 19
10. UPDATES TO PLANS 20

List of Figures
Figure 1: General location of the site (Figure 1-1 of AEE)............................................................................................. 8
Figure 2: Transmission line route and access roads to site. ........................................................................................ 9
Figure 3: Driveways to 241 Kahuterawa Road. ........................................................................................................... 16
Figure 4: Entranceways to 131 and 132 Greens Road. ............................................................................................... 17
Figure 5: Linton Substation access.............................................................................................................................. 18

List of Tables
Table 1: Consent conditions relating to CTMP ............................................................................................................. 6
Table 2: Estimated Truck Movements. ....................................................................................................................... 11
Table 3: Vehicle restrictions: Greens Rd and Kahuterawa Road. ............................................................................... 12

Version: 1.0 Page 4 of 20


DATE: 02/07/2019
Table 4: Proposed Project programme. ...................................................................................................................... 14
Table 5: Vehicle access through Greens Road. ........................................................................................................... 16
Table 6: Contact details for Project Management. ..................................................................................................... 19

List of Appendices
Appendix A - Temporary Traffic Management Plan: Greens Road .................................................................................
Appendix B - Complaints Form .......................................................................................................................................

Version: 1.0 Page 5 of 20


DATE: 02/07/2019
1. Background
This Construction Traffic Management Plan (CTMP) (required by Schedule 3: condition 70 of the Resource
Consent) details the procedures to be implemented to manage, remedy and mitigate potential adverse
traffic effects during construction of a new 12km long 220kV transmission line to connect Transpower’s
existing Linton Substation to the “Plantation Substation” at Mercury’s Turitea Wind Farm (the Project),
near Palmerston North.

Consent conditions in relation to the CTMP are summarised in Table 1 below, along with the relevant
section of this CTMP in which these matters are addressed:
Table 1: Consent conditions relating to CTMP

CTMP
Number Condition
Section

At least 40 working days prior to any construction works commencing the Consent
Holder shall submit a CTMP to the Roading Manager of the respective Councils, for
review in a technical certification capacity. A response should be provided within 15
working days of receipt. Construction activities must not commence until written
70 certification has been obtained. The purpose of the CTMP shall be to set out in detail 1.1
matters relating to the extent and timing of construction traffic activity, and the traffic
management provisions to be put in place during this time to achieve a safe and efficient
road network. The CTMP shall be prepared by a Chartered Professional Engineer
following community consultation and shall cover at least the following matters:

Documentation of who has been consulted and involved in preparing the CTMP, which
shall include the CLG, residents on South Range Road, Greens Road, and Kahuterawa
70.1 Road, groups representing users of Hardings Park such as the Manawatu Mountain 6
Biking Club, and traffic engineers from Tararua District and Palmerston North City
Councils.

70.2 Project scheduling. 4.8

70.3 Travel routes. 4

70.4 Access details. 4.2

70.5 Roading upgrades, including those referred to in conditions 53-55. N/A 1

70.6 Traffic flows. 4.4

Vehicle speeds, including specific limits on South Range Road, Kahuterawa Road and
70.7 5
Greens Road.

70.8 Operating hours for each access, including those referred to in condition 63. 4.7

Measures to ensure trucks use the Pahiatua-Aokautere Road access(es) wherever


70.9 8
practical, and to ensure condition 61 is complied with.

1
A separate CTMP is to be prepared for the upgrade of Greens Road and Kahuterawa Road for use by construction
traffic
Version: 1.0 Page 6 of 20
DATE: 02/07/2019
70.10 Measures to reduce the amount of commuter traffic by construction personnel. 4.4

Piloting arrangements and operating procedures for over dimension turbine


70.11 N/A
component transporters.

70.12 Provisions for accommodating pedestrian, cycle and horse usage of the access roads. 5.2

Driver protocols, including prohibition on engine braking on Kahuterawa Road and the
flat portion of Greens Road, and “one in one out” arrangements for trucks on
70.13 8
Kahuterawa Road during particular peak days when more than 40 truck movements per
day are envisaged.

Disciplinary procedures to be followed in the event that any project drivers breach the
driver protocols on any other aspects of the CTMP, including that any project drivers
70.14 who are the subject of a credible complaint in respect of adherence to the road rules and 8.2
the CTMP shall have a vehicle tracking system (with driver behaviour functionality)
installed in their vehicles.

Full details of the temporary traffic management plans to be used, including the
70.15 5.3
conditions under which each plan would operate.

Procedures for communication with the local community and other road users regarding
traffic management issues, including notification techniques such as emails, a dedicated
70.16 6
website update, text messages, roadside notice boards, and/or newspaper
advertisements.

70.17 Project contacts including a driver comments free phone number. 7

Chartered Professional Engineer Statement

Lachlan Beban and Angie Crafer (Chartered Professional Engineer) from Flow Transportation Specialists
have reviewed this document throughout the development of this CTMP.

2. Location
The Turitea Wind Farm site is located approximately 10 kilometres south-east of Palmerston North
primarily along a 14-kilometre ridge in the northern Tararua Ranges. The environment includes a number
of existing wind farms to the north. The Turitea Wind Farm is located within the Turitea Reserve (owned
by Palmerston North City Council (PNCC)) and on adjoining private farmland.

The site is located within the PNCC and Tararua District Council (TDC) municipal boundaries and comes
under the jurisdiction of the Manawatu-Wanganui Regional Council (Horizons). The general location of
the site is shown in Figure 1. The approximate route for the transmission lines are shown Figure 2 along
with the direct roads that will be used for access to site.

Version: 1.0 Page 7 of 20


DATE: 02/07/2019
Figure 1: General location of the site (Figure 1-1 of AEE).

Version: 1.0 Page 8 of 20


DATE: 02/07/2019
Figure 2: Transmission line route and access roads to site.

Version: 1.0 Page 9 of 20


DATE: 02/07/2019
3. Purpose of the CTMP
The CTMP will, as far as reasonably practicable, avoid, remedy or mitigate the adverse effects of
construction traffic on the safe and efficient operation of the surrounding road network.

It includes:

• A description of the construction works to be undertaken, including site access routes


• The timing and extent of construction works, including hours of operation
• Temporary Traffic Management to be implemented
• Project contacts
• Consultation and Communications methodology
• Driver protocols, including disciplinary and complaints procedures

4. Construction Operations
Summary of Transmission Works

Works involved in the construction of the transmission network consist of the installation of poles and
cables between two substations to connect the Wind Farm to the national grid. These works will be
undertaken on private and public reserve land (Turitea Reserve), with machinery and materials
transported to and along the transmission route. To facilitate this, it is proposed to construct or upgrade
access tracks, which will also require access for machinery and materials for the construction of the tracks.

Cables and poles will be delivered and installed progressively throughout the project. This installation will
also cross Greens Road, which will be managed in accordance with the Temporary Traffic Management
Plan (TTMP) provided in Appendix A.

No over-dimensional nor overweight loads are expected in relation to the transmission works, with the
largest loads being carried in 40-foot shipping containers.

Site Access

Access to the transmission work sites will be from Greens Road, Kahuterawa Road, Harts Road and
Pahiatua-Aokautere Road (via South Range Road). However, until improvements are carried out on
Greens Road; Harts Road, Kahuterawa Road and South Range Road will be utilised.

The improvements on Greens Road (and Kahuterawa Road) will include widening tight bends on the hill
section, re-grading the surface, and sealing portions of the road to improve traction. The details of these
works and driver protocols along the local roads will be outlined in a separate CTMP for the Greens Road
and the Kahuterawa Road upgrade, once detailed engineering design plans have been finalised and
approved by Council. Should the works at Greens Road and Kahuterawa Road influence this CTMP a
review will be carried out.

Routes
Vehicles and goods will be coming locally from Palmerston North or Wellington or Auckland.

Greens Road and Kahuterawa Road will be accessed from State Highway 57.

Version: 1.0 Page 10 of 20


DATE: 02/07/2019
Harts Road will be accessed from State Highway 57 and Turitea Road.

South Range Road will be accessed from State Highway 57 and Paihiatua-Aokautere Road.

Traffic Flows
The site will keep a record of all vehicles travelling in and out of the site during construction, including the
date and time, the access used, whether the vehicles is entering or exiting, and whether it is a light vehicle
or truck. This record will be submitted to the Roading Managers of PNCC and TDC on a monthly basis.

Reporting will be submitted in accordance with the requirements of Schedule 3: Condition 73 of the
Resource Consent.

A significant amount of construction vehicle movement will be required, particularly truck movements to
transport fill, aggregate and concrete to site during construction of the project. Proactive measures to
reduce construction traffic will be rolled out across the project. These will include practices such as:

• Limiting site access movements / plant deliveries to off-peak periods;


• Ensuring, where possible, trucks arrive full and leave site full (removing waste etc.);
• Where possible, using resources available within property boundary e.g. quarry (subject to
appropriate authorisations being in place (e.g. landowner agreements, and where relevant,
resource consents));
• Development and distribution of site access plans specifying permitted access movements, times
and procedures; and
• Avoiding peak traffic flow periods where possible.

All site-based personnel, truck drivers in particular, will be made aware of the sensitive areas around the
project (e.g. low speed areas, narrow sections of road). Drivers will be required to take extra care while
passing these areas and be extra vigilant of children, cyclists and horses etc. This requirement will be
included in safety briefings once detailed planning is underway.

4.4.1 Truck Movements


Electrix has estimated the movements that will access site from each road, this is summarised in table 2.

• Numbers are movements in and movements out i.e. 1 trip = 2 movements;


• Numbers do not include light vehicles; and
• Numbers do not include movements required for the upgrade of Greens Road.

Table 2: Estimated Truck Movements over the duration of works.

Kahuterawa Rd Greens Rd Harts Rd South Range Rd Total

Civil works 30 40 10 40 120

Gravel 600 1,500 100 800 3,000

Steel 60 180 15 60 315

Plant and Equipment 50 200 20 100 370

Conductor/OPGW 20 80 12 30 142

Version: 1.0 Page 11 of 20


DATE: 02/07/2019
Drilling 12 40 8 20 80

Concrete 120 260 30 80 490

TOTAL 892 2,300 195 1,130 4,517

Signage
Traffic control and warning signs to be used on-site will conform to the standards specified in the Code
of Practice for Temporary Traffic Management (CoPTTM).

Storage of Materials
All materials will be stored on-site. No material will be stored within the public road reserve at any time.

Hours of Operation
In accordance with Schedule 3: condition 63 of the Resource Consent, vehicles entering or exiting the site
will only travel on Greens Road or Kahuterawa Road following their respective upgrades (required
pursuant to Schedule 3, Condition 53 of the Consents) at the following times:
Table 3: Vehicle restrictions: Greens Rd and Kahuterawa Road.

Time Period Light Vehicles Trucks

6.30am to 7.30am;
8.15am to 3.15pm; and
4.30pm to 6.00pm.
Except that trucks shall not use the roads
when particular events, notified through
Weekdays No restrictions community consultation, are held, and which
involve a peak in the presence of vulnerable
road users, such as equestrian or cycling
events.
In addition, the prohibition on access from
7.30am to 8.15am and 3.15pm to 4.30pm
only applies on school days.

6.30am to 7.30am; and


No truck access, except that up to 6 truck
Weekends and 5.00pm to 6.00pm;
movements per day may occur on weekends
statutory
Except that up to 10 other light vehicle and statutory holidays between the hours of
holidays*
movements may occur outside of these times 8am and 6pm.
each day.

*Light vehicle access is allowed at any time for the purposes of site security and site supervisors
(associated with the monitoring of health and safety and environmental effects). Additionally, light
vehicle and truck access is allowed at any time for the purpose of maintenance / emergency response, to
carry out emergency maintenance works or to respond to a health and safety matter that cannot
reasonable wait until a weekday.

Version: 1.0 Page 12 of 20


DATE: 02/07/2019
Construction Programming
Preliminary programming of the construction works has identified an overall work programme of
approximately 12 months. The detailed programme is still to be drafted and will be available on request.
An indicative schedule is illustrated in Table 4 for information.

Kahuterawa Road and Greens Road Upgrade


Kahuterawa Road and Greens Road upgrade works will be scoped, and once detailed engineering design
plans have been finalised and approved by Council, a separate CTMP will be submitted for approval prior
to the commencement of works.

Version: 1.0 Page 13 of 20


DATE: 02/07/2019
Table 4: Proposed Project programme.

Version: 1.0 Page 14 of 20


DATE: 02/07/2019
5. Traffic Management
Monitoring
Traffic will be monitored with the recording of:
• All vehicles travelling in and out of the site 2 during construction. Reporting will be submitted in
accordance with the requirements of Schedule 3: Condition 73 of the Resource Consent;
• Any record where truck access was required outside of the prescribed limits for the purpose of
carrying out emergency maintenance works or responding to a health and safety matter.
• Pavement surfaces on Greens Road shall be inspected by a suitably qualified engineer as required
and reported as per Schedule 3: Condition 75 of the Resource Consent; and
• Records will be kept by Mercury regarding calls received on the 0800-phone number (0800 201
520) about driver behaviour.

Pedestrians, Cyclists and Horses


As part of the Te Araroa trail (New Zealand's long-distance tramping route) Kahuterawa Road is likely have
tourists and trampers on the road.

On all roads, workers accessing the site will need to be aware of the potential presence of pedestrians,
cyclists and horses on the road. This will be reflected in the site induction for all Electrix (and sub-
contractors) workers. This is in accordance with condition 70.12.

Temporary Traffic Management Plans


Specific temporary traffic management plans (TTMP) will be required for the works for the stringing of
the transmission line over Greens Road only. This will be managed in accordance with the Temporary
Traffic Management Plan (TTMP) provided in Appendix A, through use of Manual Traffic Control to stop
traffic as required including a 30 km/hr temporary speed limit applied either side of the worksite.

Greens Road
Once Greens Road has been widened, as part of the requirements under the Resource Consent (Schedule
3: Condition 62), in total, no more than 5,800 truck 3 movements associated with the transmission network
installation shall occur through the Greens Road access during construction, with the maximum permitted
daily totals of vehicle access through the Greens Road access outlined in Schedule 3: Condition 67, as
shown in Table 5. Construction traffic movements on Greens Road (following its upgrade) will be
addressed in the CTMP for Greens Road.

2
Site is being defined as anywhere beyond a public road.
3
A truck is defined by the Board of Inquiry decision as “a vehicle with a gross vehicle mass exceeding 3,500kg
which requires a 2,3,4, or 5 drivers licence to operate.”
Version: 1.0 Page 15 of 20
DATE: 02/07/2019
Table 5: Vehicle access through Greens Road.

Period Vehicle Type Max. number of vehicle movements

First 5 months of construction, including 34vpd except for up to 4 occasions of


construction of the Greens Road upgrade, the Trucks 60vpd in the circumstances described in
central link of the internal road, the Browns Flat Schedule 3: Condition 61)
substation, and the roads and platforms for
turbine strings F, G, H, J and K; but excluding
investigation and design, may be extended with
the written approval of Council if circumstances
beyond the Consent Holders control delay Light vehicles 60vpd
construction in accordance with the
requirements of the CEMP
0vpd except for up to 6 days of 40vpd
when crane is moving, and 60vpd if an
Trucks
unforeseen circumstance closes the
Remainder of construction period
internal road for a whole day or more
Light vehicles 60vpd

These requirements will be reflected in the site induction for all Electrix (and sub-contractors) workers
accessing the site and will be monitored as described in Section 5.1.

Private property access


Access to private properties along the roads illustrated in Figure 2 (to be used for site access) will be
affected by construction traffic. The timing for their use is dependent on establishment works approvals
from Council. An indicative timeframe is given with each property description. Electrix is working with all
property owners on a weekly basis.

• 241 Kahuterawa Road: There are 2 access points for this property:
1) is the drive way to the house (seen below in Figure 3);
2) the other is a heavy transport access point for stock and other farm requirements. The project
vehicles will be using this access for all needs on this property. There is good line of sight for
this access making it safe for entry or exit onto Kahuterawa Road.
Access will be from July 2019 until July 2020.

Figure 3: Driveways to 241 Kahuterawa Road.

Version: 1.0 Page 16 of 20


DATE: 02/07/2019
• 132 Greens Road: This access is at the top of the rise on Greens Road. There is some restriction
in visibility due to it being at the top of a crest in the road. The driveway splits into two with one
path going to the house and wool shed/ stockyards and the other going up to Browns Flat where
the top-dressing airstrip is located. Heavy trucks use this driveway on a regular basis for farming
operations. Access will be from October 2019 until July 2020.
• 131 Greens Road: There is a single driveway that goes to the farm sheds and farm house. This
property is directly across the road from the entrance to 132 Greens Road (see Figure 4). There is
some restriction in visibility due to it being at the top of a crest in the road. The project will be
creating a new track that will come off this driveway 200 to 400 m before the house and going
either to the right or the left to avoid driving past the house. Options are being discussed with
the owners. Access will be from October 2019 until July 2020.

Figure 4: Entranceways to 131 and 132 Greens Road.

• 146 Harts Road: Transpower (Linton substation). This property is at the end of Harts Road. There
is ample room to enter and exit Harts Road and the entrance and driveway is constructed for
heavy vehicles used in Transpower’s business. The site is accessed is via a locked gate (Figure 5).
Access will be from July 2019 until July 2020.

Version: 1.0 Page 17 of 20


DATE: 02/07/2019
Figure 5: Linton Substation access.

6. Consultation and Communication


As part of the requirements under the Resource Consent (Schedule 1: Condition 14), Mercury has
facilitated the formation of a Community Liaison Group (CLG). This group is made up of various
community members from a pool of invited stakeholders 4 including:
• Manawatu-Wanganui Regional Council;
• Palmerston North City Council;
• Tararua District Council;
• Rangitane o Manawatu;
• Rangitane o Tamaki Nui a Rua;
• Owners of private land containing turbines;
• Residents in the Kahuterawa Valley (Kahuterawa Road and feeders including Greens Road);
• Residents in the Turitea Valley (Turitea Road and feeders, including Ngahere Park Road);
• Residents on Pahiatua Track (Pahiatua-Aokautere Road and feeders);
• Residents on Makomako Road;
• Manawatu Mountain Bikers; and
• Mercury.

Monthly CLG meetings were initiated in May 2019. As part of the group’s discussions (and terms of
reference), construction traffic impact has been discussed and remains on the ongoing agenda.

Upon submitting it to Council, the Draft CTMP will be made available to all stakeholders on Mercury’s
mailing list and the CLG for feedback. The CTMP will also be available to the general public via the
following website;

www.mercury.co.nz/windupdates

The Plan will be a living document and will be updated to incorporate schedule changes.

4
Not all stakeholders invited are represented at Community Liaison Group monthly meetings.
Version: 1.0 Page 18 of 20
DATE: 02/07/2019
7. Contact Details for Project Management
Table 6: Contact details for Project Management.

Position Name Organisation Phone Email

Environmental Emma Comrie-


Electrix Ph: 021 755 509 emmac@4sight.co.nz
Manager Thomson

Construction
Jon Edwards Electrix Ph: 021 953 336 jon.edwards@electrix.co.nz
Manager

Project Manager Kevin Small Electrix Ph: 021 312 796 kevin.small@electrix.co.nz

HSEQ Assessor Alison Gardiner Electrix Ph: 021 822 900 alison.gardiner@electrix.co.nz

Environmental
Mark Henry Mercury Ph: 027 479 7592 mark.henry@mercury.co.nz
Resource Manager

Consents and
Mason Jackson Mercury Ph: 027 230 8567 mason.jackson@mercury.co.nz
Compliance Manager

8. Driver Protocols
Behaviour
The Electrix Environmental Manager is responsible for undertaking a site induction with all transport
operators contracted to transport materials to the site. The induction is to cover (but not be limited to):
• the route of travel (including the requirement to enter and exit the site via the access(es) on
Pahiatua-Aokautere Road and only use the Greens Road access when it is impractical (for reasons
noted in condition 61) to use the access(es) on Pahiatua-Aokautere Road, provided that Greens
Road has been widened);
• requirement for and use of possible communication systems;
• requirements to abide by local speed restrictions for dust and detritus management;
• requirement for courteous driving;
• requirement to report hazards on the transport route; and
• discussion with workers on driver protocols, including prohibition on engine braking on
Kahuterawa Road and the flat portion of Greens Road, and “one in one out” arrangements for
trucks on Kahuterawa Road during particular peak days when more than 40 truck movements per
day are envisaged.

Disciplinary procedures
In accordance with the Resource Consent Schedule 3: Condition 70.14, disciplinary action will be followed
in the event that any project drivers breach the above protocols. In addition, any drivers who are subject
of a credible complaint, in respect to adherence to New Zealand Road Code or breaches of this CTMP,
shall have a vehicle tracking system (with driver behaviour functionality) installed in their vehicles.

9. Complaints Procedure
The procedure for keeping records of public complaints and any actions taken in response will be carried
out in accordance with the Resource Consent Schedule 1: Condition 19-21. In this regard Mercury has set

Version: 1.0 Page 19 of 20


DATE: 02/07/2019
up a phone number (0800 201 520) and an email address (turiteawindfarm@mercury.co.nz) for members
of the public to register inquiries or complaints. The publicity of this information has been communicated
via advertisements in local newspapers.

When an environmental complaint is received directly by Electrix, it will be communicated to Mercury,


and vice versa if received through Mercury’s 0800 number or website.

Complaint Form
The Complaint Form (Appendix B) will be used for all site-specific activities throughout the Project.
The Electrix Environmental Manager will ensure that the details of the investigations and any follow up
actions are completed and recorded for each complaint.
The form will contain but not be limited to:

• Name and address of complainant (if provided);


• Identification of the nature of the complaint;
• Date and time of the complaint and alleged event;
• Wind and weather at the time;
• Activity occurring on the site at the time;
• Details of whether the compliant was or was not able to be verified; and
• Any remedial actions undertaken.

The Electrix Environmental Manager will commence an inquiry within 1 hour of receiving the complaint.
Contact will be made with the complainant (if details have been provided) within the same working day -
an interim response advising that investigations are continuing is acceptable.
A formal written response will be provided to the complainant and appropriate regulatory authorities
within 10 days of complaint receipt.
Complaints Register
A Complaints Register will be controlled by the Mercury. It will contain all complaints received for the
Project.
The Electrix Environmental Manager will submit all data from completed environmental Complaints
Forms as soon as possible.
The Electrix Environmental Manager will summarise all complaints received throughout the site to on-
site staff members during weekly Tool Box sessions.
The Complaints Register will be discussed at regular meetings held between the Electrix Environmental
Manager, Electrix Construction Manager, Mercury and Electrix Project Manager.

10.Updates to Plans
During the works the CTMP and TTMPs will be reviewed by the Project Manager and Contracted STMS.
As a minimum, a one-off review, three months following construction start will occur and then as
required, to ensure that the documents remain relevant for use. Any changes to these plans will be
recorded and version controls shall be strictly adhered too.

Version: 1.0 Page 20 of 20


DATE: 02/07/2019
Appendix A - Temporary Traffic Management Plan: Greens Road
RCA consent (eg CAR/WAP) and/or
RCA contract reference

TRAFFIC MANAGEMENT PLAN (TMP) – FULL FORM

Use this form for complex activities. Refer to the NZ Transport Agency’s Traffic control devices manual, part 8 Code of practice for
temporary traffic management (CoPTTM), section E, appendix A for a guide on how to complete each field.

TMP reference: Contractor (Working space): Principal (Client):


Organisations (190302) Electrix Mercury Energy
/TMP
reference Contractor (TTM): RCA:
Traffic Management NZ Palmerston North City Council

Location details House no./RPs Road Permanent


Road names and suburb
and road (from and to) level speed
characteristics Greens Road, Turitea #182 Level LV 100kph

Traffic details AADT Peak flows


(main route) Greens Road – 18, 6% Heavy. 0700-0900 and 1600-1800 Monday to Friday
Description of work activity
This TMP is for Electrix to install a new HV power line and lay power conductors across the road at the location stated above.
Works are expected to take 5-6 months to complete, working from 8am to 5pm.
Planned work programme
Start date 10/06/2019 Time 0800 End date 30/06/2019 Time 1700
Consider significant Where works are expected to affect the carriageway, all traffic from both directions will be stopped while
stages, for example: running conductors.
 road closures Minimum lane width to be no less than 2.75m.
 detours L1 Mobile Operation to be used for the set up and the removal of the worksite.
 no activity periods.
Alternative dates if TBA
activity delayed
Road aspects affected (delete either Yes or No to show which aspects are affected)

Pedestrians affected? No Property access affected? No Traffic lanes affected? Yes


Cyclists affected? No Restricted parking affected? No Delays or queuing likely? No

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 1
RCA consent (eg CAR/WAP) and/or
RCA contract reference

Proposed traffic management methods


Once on site, the TMP will be implemented as follows;
 A traffic count to confirm traffic volumes are at an appropriate level for set up to begin
 Identify public safety and site safety hazards and how they will be addressed and place on the hazard
document for ‘toolbox’ briefing
 STMS to check the TMP is appropriate to the worksite. Where the TMP is not suitable, halt
proceedings until the necessary actions have been taken
 All vehicles are to have correct signage and flashing beacons. They also need to have continuous and
appropriate communication with the STMS and each other on an agreed channel at all times

Layout Procedure
Signs are to be installed on the left hand side of the road, then the right hand side of the road as required. Signs
should be erected by travelling around the road network in a clockwise direction setting up each side road as
they are passed. All turns in and out of side roads will be to the left which is easier and safer:
The first sign erected must be the advance warning sign.
Installation The remaining signs are placed in order from the advance warning sign until the end of works sign is reached as
(includes parking of per the approved TMP.
plant and materials The vehicle then makes a loop on a single direction carriageway or simply turns around on a bidirectional
storage) carriageway to make the next run. This process will continue until the sign network is complete.
Tapers and delineation devices must only be placed once all signs have been installed.

Before any construction, equipment or materials are brought onto the worksite a drive through check of the
worksite will be made in all directions including all side roads. This check must confirm that the worksite is:
– safe
– to the minimum standard shown in the approved TMP and that:
 the restriction to traffic flow is reasonable
 the signs and delineation devices give clear messages to road users, and
 the signs and delineation devices are securely erected and will remain in their correct position under
the expected traffic volumes and weather conditions.
Installation of the site will be done under a mobile closure with appropriate work vehicles and crew.
On completion of the site set up, the STMS shall undertake a drive-over inspection to check that the site is safe,
legal and complies with the TMP. The STMS then may give the okay for the work crew to enter the worksite and
carry out the work.
Closures, as per TMD01.
The site will be attended during the day by a minimum of a Level 1 STMS.
All staff on the site shall be briefed on the traffic management requirements before starting any work on site
Attended (day)
A site safety / tailgate meeting is to be held at the start of each day and all hazards, the control measure
implemented to control the hazards are to be noted on the Hazard ID form. The Hazard ID form must be signed
by all staff and sub-contractors on the work site.
Attended (night) No planned night works.
Unattended (day) Site not to be left unattended.
Unattended (night) N/A
No detour required.
Does detour route go into another RCA’s roading network? Yes No (delete either Yes or No)
Detour route
If Yes, has confirmation of acceptance been requested from that RCA? Yes No (delete either Yes or No)
Note: Confirmation of acceptance from affected RCA must be submitted prior to occupying the site.

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 2
RCA consent (eg CAR/WAP) and/or
RCA contract reference
Breakdown Procedure
Removal of the site will commence as soon as the client has finished with their work. The removal of TTM
measures must be in the reverse order of installation, i.e. delineation devices, direction and protection signs,
end of works signs, and then finally advanced warning signs.
Removal
The last signs to be removed from the site must be the advanced warning signs.
The STMS will carry out the final check and sign off before leaving the site.
Breakdown shall be done with appropriate work vehicles and crew.

Proposed TSLs (see TSL decision matrix for guidance)


TSL details as required Times Dates Diagram ref. no.s
Approval of Temporary Speed Limits (TSL) are in terms (From and to) (Start and finish) (Layout drawings or
of Section 6 of Land Transport Rule: Setting of Speed traffic management
Limits 2017, Rule 54001/2017 diagrams)
(List speed, length and location)
A temporary maximum speed limit of 30km/h is hereby fixed 08.00 06/01/2020
Attended for motor vehicles travelling over the length of 400m situated
- - TMD01
day/night between GREENS RD/2.300 and GREENS RD/2.500 on
Greens Rd, Turitea 17.00 31/05/2020
Unattended
No TSL required. ---------------------- ------------------------ N/A
day/night

Will the TSL be required for longer than 12 months?


TSL duration If yes, attach the completed checklist from section I-18: Guidance on TMP Monitoring No
Processes for TSLs to this TMP.

Positive traffic management measures


Positive Traffic management measures must be installed when installing TSL’s of less than 70kph in areas where there are permanent
speed limits of 100kph.
Positive traffic management to be installed:
 Placing cones from the TSL to the taper
Once the site has been installed additional measures available to the STMS if required are;
 Narrowing lane widths adjacent to the working space by the use of Side Friction cones
 Close spacing of delineation devices
 Cone offset delineation (where cones are placed either side of a lane(s), the cones on one side are placed longitudinally offset
from the other by a half cone spacing).

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 3
RCA consent (eg CAR/WAP) and/or
RCA contract reference
Contingency plans
Generic Major Incident Actions
contingencies for: A major incident is described as: The STMS must immediately conduct the following:
 major incidents  Fatality or notifiable injury - real or potential  stop all activity and traffic movement
 incidents  Significant property damage, or  secure the site to prevent (further) injury or damage
 pre planed  Emergency services (police, fire, etc) require  contact the appropriate emergency authorities
detours. access or control of the site.
 render first aid if competent and able to do so
 notify the RCA representative and / or the engineer
 under the guidance of the officer in charge of the
site, reduce effects of TTM on the road or remove
the activity if safe to do so
 re-establish TTM and traffic movements when
advised by emergency authorities that it is safe to
do so
 Comply with any obligation to notify WorkSafe.
Incident Actions
An incident is described as: The STMS must immediately conduct the following:
 excessive delays - real or potential  stop all activity and traffic movement if required
 minor or non-inquiry accident that has the  secure the site to prevent the prospect of injury or
potential to affect traffic flow further damage
 structural failure of the road.  notify the RCA representative and / or the engineer
 STMS to implement a plan to safely remove TTM
and to establish normal traffic flow if safe to do so
 re-establish TTM and traffic movements when it is
safe to do so and when traffic volumes have
reduced.

Detour Actions
If because of the on-site activity it will not be When it is necessary to implement the pre-planned
possible to remove or reduce the effects of TTM detour the STMS must immediately undertake the
once it is established a detour route must be following:
designed. This is likely for:  Notify the RCA and / or the engineer when the
 excessive delays when using an alternating detour is to be established
flow design for TTM  Drive through the detour in both directions to check
 redirecting one direction of flow and / or that it is stable and safe
 total road closure and redirection of traffic  Remove the detour as soon as it practicable and
until such time that traffic volumes reduce safe to do so and the traffic volumes have reduced
and tailbacks have been cleared. and tailbacks have cleared
The risks in the type of work being undertaken,  Notify the RCA and / or the engineer when the
the risks inherent in the detour, the probable detour has been disestablished and normal traffic
duration of closure and availability and suitability flows have resumed.
of detour routes need to be considered.
The detour and route must be designed including:
 pre- approval form the RCA’s whose roads
will be used or affected by the detour route
 ensure that TTM equipment for the detour -
signs etc are on site and pre-installed.

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 4
RCA consent (eg CAR/WAP) and/or
RCA contract reference
Note also the requirements for no interference at an accident scene:
In the event of an accident involving serious harm the STMS must ensure that nothing, including TTM
equipment, is removed or disturbed and any wreckage article or thing must not be disturbed or interfered with,
except to:
 save a life of, prevent harm to or relieve the suffering of any person, or
 make the site safe or to minimise the risk of a further accident; or
 maintain the access of the general public to an essential service or utility, or
 prevent serious damage to or serious loss of property, or
 follow the direction of a constable acting in his or her duties or act with the permission of an inspector.
Other contingencies Weather The STMS will suspend or re-evaluate the methodology of
to be identified by the the works if weather conditions e.g., rain, fog etc., will
applicant adversely affect safety, i.e., If CSD (3 x PSL) is not achieved
(i.e. steel plates to during site set-up, or sign visibility not achieved after site set
quickly cover up. Work can recommence only after the all clear has been
excavations)
given by the STMS.
Light STMS to evaluate whether light conditions are good enough
for daylight operations. If not, an artificial light source may
be needed or work be suspended until light conditions are
suitable.
Work running late Where the work may run over permitted hours, the STMS
will:
 Contact TMC on page 7.

Authorisations

Parking restriction(s) Will controlled street parking be affected? No Has approval been granted? N/A
alteration authority Not required.
Authorisation to work Will portable traffic signals be used or
No Has approval been granted? N/A
at permanent traffic permanent traffic signals be changed?
signal sites Not required.
Will full carriageway closure continue for
Road closure more than 5 minutes (or other RCA No Has approval been granted? N/A
authorisation(s) stipulated time)?
Not required.
Bus stop Will bus stop(s) be obstructed by the
No Has approval been granted? N/A
relocation(s) – activity?
closure(s) Not required.
Authorisation to use Make, model and Not required.
portable traffic description/number
signals NZTA compliant? N/A
EED
Is an EED applicable? No EED attached? N/A

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 5
RCA consent (eg CAR/WAP) and/or
RCA contract reference

Delay calculations/trial plan to determine potential extent of delays

Public notification plan


Not required.

Public notification plan attached? No

On-site monitoring plan


The first inspection must take place as soon as the equipment has been installed as per the approved TMP.
This verifies that all devices are correctly in place, no item has been omitted, all equipment meets its condition
requirements and no conflicting messages exist between permanent signs, temporary signs or other devices.
Monitoring the Site:
Constant monitoring of the worksite and a minimum of 2-hourly site checks must be carried out to ensure the
site is:
 fit for purpose
 suitable for the nature and duration of the work
 installed, set up and used correctly.
Attended
(day and/or night)
The STMS must ensure that:
 all traffic management devices function properly for the full duration of their installation
 the visibility and effectiveness of all devices and signs is maintained
 damaged equipment is repaired or replaced, as appropriate, and
 suitable equipment is available at short notice in case of un-programmed removal, alteration or
installation of a closure is necessary.

Level 1 - The STMS (if not remaining on site) is to be within 30min travel time of the attended site at all times,
the site will be delegated to a qualified TC.
Unattended Nil
(day and/or night)
Method for recording daily site TTM activity (eg CoPTTM on-site record)
STMS to complete on-site record forms attached to TMP.
Site safety measures
Personal Safety
Hard Hats, High Visibility Clothing, Long Sleeves, Long Pants, Safety Footwear, Safety Glasses and Cut Resistant Gloves at CoPTTM
standards.
All vehicles to have flashing lights and hazard lights.
STMS to wear a yellow high visibility vest compliant with CoPTTM specifications.
All other TMNZ personnel to wear orange/blue reflective overalls.
Visitors to site are to report to the STMS who will advise of site specific safety procedures and any hazards.
Plant and equipment
Plant and equipment is to be positioned off the live lanes as far as possible within the work area.
Hazard light and flashing beacons to be used on all vehicles within the work area.
All non-plant vehicles to be park off site.

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 6
RCA consent (eg CAR/WAP) and/or
RCA contract reference

Other information
All TMP changes are to be recorded and the TMC informed immediately of any significant modifications (e.g. change of detour) to TTM
measures not included in the approved TMP. All other changes are to be noted on the TMP and TMC to be advised as soon as possible
or no later than the following working day.
Site specific layout diagrams
Number Title
TMD01 Manual Traffic Control Setup
GTMD14 L1 Mobile Operation
Contact details
24/7 contact CoPTTM Expiry
Name Qualification
number ID date

Mercury Energy
Principal
Glen Twining – geln.twining@mercury.co.nz 027 685 2549

Palmerston North City Council


TMC
Pat Howard – pat.howard@pncc.govt.nz 027 491 8937

Engineers’ N/A
representative

Contractor
Electrix
TTM Contractor Jon Edwards – jon.edwards@electrix.co.nz 027 953 336

Aaron Frickleton 0274460095 85251 STMS 2/3NP 28/09/2020


Arona Williams 108688 STMS L1 22/02/2021
Brett Flyger 027 520 9861 55825 STMS L1 23/08/2021
John McGregor 021 945 102 118001 STMS L1 06/10/2021
Kelly Shelford 027 446 8059 111986 STMS L1 19/04/2021
STMS Leticia Claxton-Tume 027 491 9000 63254 STMS L1 28/05/2020
Maytrix Turnbull 204 147 0639 108696 STMS L1 22/02/2021
Paul Mather 022 464 7286 79250 STMS L1 09/11/2020
Shanan Beals 027 765 8993 117990 STMS L1 06/09/2021
Vaughan Kimura 027 446 0009 60495 STMS L1 19/05/2021
Zach Cook 027 768 6993 75089 STMS L1 22/10/2019
TC
Others as required
TMP preparation

Sameera L.A. 18/06/2019 92237 STMS L1 04/05/2022


Preparation
Name (STMS qualified) Date Signature ID no. Qualification Expiry date

This TMP meets CoPTTM requirements Number of diagrams attached 2

TMP returned for


correction
(if required) Name Date Signature ID no. Qualification Expiry date

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 7
RCA consent (eg CAR/WAP) and/or
RCA contract reference
Engineer/TMC to complete following section when approval or acceptance required

Approved
by TMC/engineer
(delete one)
Name Date Signature ID no. Qualification Expiry date

Acceptance by
TMC (only required
if TMP approved by
engineer)
Name Date Signature ID no. Qualification Expiry date

Qualifier for engineer or TMC approval

Approval of this TMP authorises the use of any regulatory signs included in the TMP or attached traffic management diagrams.
This TMP is approved on the following basis:
1. To the best of the approving engineer’s/TMC’s judgment this TMP conforms to the requirements of CoPTTM.
2. This plan is approved on the basis that the activity, the location and the road environment have been correctly represented by the
applicant. Any inaccuracy in the portrayal of this information is the responsibility of the applicant.
3. The TMP provides so far as is reasonably practicable, a safe and fit for purpose TTM system.
4. The STMS for the activity is reminded that it is the STMS’s duty to postpone, cancel or modify operations due to the adverse traffic,
weather or other conditions that affect the safety of this site.

Notification to TMC prior to occupying worksite/Notification completed


TMC to be notified of works by way of
email confirmation 48hrs prior to the Date
Type of notification commencement of the planned work. Notification
to TMC required completed Time

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 8
TMP or generic plan reference

ON-SITE RECORD Today’s date


On-site record must be retained with TMP for 12 months.

Location Road names(s): House number/RPs: Suburb:


details

Working space
Person
responsible
for working
space Name Signature
Where the STMS/TC is responsible for both the working space and TTM they sign above and in the appropriate TTM box below

TTM
STMS in
charge of
TTM Name TTM ID Number Warrant expiry date Signature Time
Worksite
handover
accepted by
replacement Name ID Number Warrant expiry date Signature Time
STMS Tick to confirm handover briefing
completed

Delegation
Worksite
control
accepted by Name ID Number Warrant expiry date Signature Time
TC/STMS-NP
Tick to confirm briefing completed

Temporary speed limit


Street/road name (RPs or street numbers): TSL action Date: Time: TSL speed: Length of TSL (m):
TSL installed
TSL remains in place
From: To: TSL removed
Street/road name (RPs or street numbers): TSL action Date: Time: TSL speed: Length of TSL (m):
TSL installed
TSL remains in place
From: To: TSL removed
Street/road name (RPs or street numbers): TSL action Date: Time: TSL speed: Length of TSL (m):
TSL installed
TSL remains in place
From: To: TSL removed
Street/road name (RPs or street numbers): TSL action Date: Time: TSL speed: Length of TSL (m):
TSL installed
TSL remains in place
From: To: TSL removed

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 9
TMP or generic plan reference

Worksite monitoring
TTM to be monitored and 2 hourly inspections documented below.
TTM 2 hourly 2 hourly 2 hourly 2 hourly 2 hourly TTM
Items to be inspected
set-up check check check check check removal

High-visibility garment worn by all?

Signs positioned as per TMP?

Conflicting signs covered?

Correct delineation as per TMP?

Lane widths appropriate?

Appropriate positive TTM used?

Footpath standards met?

Cycle lane standards met?

Traffic flows OK?

Adequate property access?

Add others as required

Time inspection completed:

Signature:
Comments:

Time Adjustment made and reason for change

Traffic control devices manual part 8 CoPTTM Section E, appendix A: Traffic management plans Edition 4, November 2018
Page 10
Appendix B - Complaints Form
Complaint Form
Name of site area:

Complaint source: Electrix Project Regulatory


Client Resident
(circle) Team member Authority

Complainant’s name:

Complainant’s address:

Complainant’s email and phone number:

Complaint received by:

Nature of complaint:

Wind and weather at the time:

Activity occurring on the site at the time:

Describe any remedial actions undertaken:

Details of whether the compliant was or was not able to be verified:

APPENDIX G: COMPLAINT FORM


pg. 1
Prevention: (what actions will be taken to prevent recurrence)

Action By Whom When

Have the environmental hazards been controlled (avoided, remedied or mitigated) and sent on to the
Environmental Manager to update the environmental risk register?

Yes No

Additional Information:

Complaint form completed by: Date:

Project Manager signature: Date:

Copy sent to: (circle)


Electrix Project Manager Electrix Construction Manager
Electrix Project Leadership Team Electrix Project Engineer
Electrix Project Coordinator Mercury’s Environmental Team
Electrix Environmental Manager Mercury Project Co-ordinator
Mercury Project Manager

APPENDIX G: COMPLAINT FORM


pg. 2

You might also like