Professional Documents
Culture Documents
Method Statement - Benchmark
Method Statement - Benchmark
Method Statement - Benchmark
EQUIPMENT
TO USE THE MOST UPDATED TEMPLATE
MZ-000-CCX-HS-ZZZ-ZZZZZ-(WORD-QRCODE-SUPPLIER)
MOZAMBIQUE LNG
Company Project System Originator Discipline Doc. Type Sequence Language Revision
Document
No. MZ 000 CCX MA MTH ZZZZ - A
HOLD LOG
TABLE OF CONTENTS
1.0 INTRODUCTION ................................................................................................................. 4
2.0 SCOPE OF WORK .............................................................................................................. 4
2.1 Abbreviations.................................................................................................................... 4
3.0 PROGRAM .......................................................................................................................... 5
4.0 RESOURCES ...................................................................................................................... 5
4.1 Personnel ......................................................................................................................... 5
4.2 Equipment ........................................................................................................................ 6
4.3 Consumables ................................................................................................................... 6
4.4 Fabrication items .............................................................................................................. 6
4.5 Client Supplied ................................................................................................................. 6
5.0 MOBILISATION OF PEOPLE, MATERIALS AND EQUIPMENT......................................... 6
6.0 METHOD ............................................................................................................................. 7
6.1 Fabrication and Procurement ........................................................................................... 7
6.2 Mobilisation ...................................................................................................................... 7
6.3 Site Establishment ............................................................................................................ 7
7.0 REMOVAL OF SEP JACK-UP LEGS .................................................................................. 8
7.1 Locating the 2 SEP Jack-up legs ...................................................................................... 8
7.2 Preparations to remove the 2 SEP Jack-up legs ............................................................... 8
7.3 Removal and recovery of the 2 SEP Jack-up legs ............................................................ 9
7.4 Removal of the 2 SEP Jack-up legs not possible .............................................................. 9
7.5 Storage and disposal of the 2 of SEP Jack-up legs ........................................................ 10
8.0 REMOVAL OF GEOTECHNICAL EQUIPMENT ................................................................ 11
8.1 Locating the Geotechnical Equipment ............................................................................ 11
8.2 Preparations to remove the Geotechnical Equipment ..................................................... 12
8.3 Removal and recovery of the Geotechnical Equipment .................................................. 12
8.4 Removal of the Geotechnical Equipment not possible .................................................... 13
8.5 Storage and disposal of the Geotechnical Equipment ..................................................... 13
9.0 SITE DE-ESTABLISHMENT .............................................................................................. 14
10.0 WEATHER LIMITATIONS ................................................................................................. 14
11.0 SAFETY............................................................................................................................. 14
11.1 Risk Assessment ............................................................................................................ 14
12.0 ENVIRONMENTAL ............................................................................................................ 14
13.0 CLIENT COMMUNICATION .............................................................................................. 15
13.1 Delays ............................................................................................................................ 15
13.2 Reporting ........................................................................................................................ 15
13.3 Hold Points ..................................................................................................................... 15
14.0 APPENDIX ........................................................................................................................ 15
1.0 INTRODUCTION
The ZZZZZZ Group’s Inshore Diving and Project Divisions have been requested to provide a Method
Statement for the retrieval and removal of lost tools and equipment from the Bay of Tungue located
on the northern Mozambique coastline. The primary equipment for recovery will be 2 of SEP jack-
up legs as well as 104 lost items of geotechnical equipment.
The Scope of Work for this intervention is based on the client requirements outlined in the change
request document: “MZ-AM1-L-CCX-20056 Change Request 002 – Retrieval and Removal of Lost
Tools and Equipment”; dated 11 October 2019. Based on the client’s requirements the below scope
of work has been outlined for the project.
2.1 Abbreviations
3.0 PROGRAM
The below time frame is a summary of the program that ZZZZ will use to complete the project:
Task Time required (weeks)
Fabrication and procurement 4
Mobilisation 2
Removal and recovery of the 2 SEP Jack-up legs 1
Survey to locate the 104 items of Geotechnical Equipment 1
Removal and recovery of the 104 items of Geotechnical 3
Equipment
Site De-establishment and Demobilisation 2
Total 13
4.0 RESOURCES
The following resources will be utilised by ZZZZ in undertaking the work covered by this method
statement:
4.1 Personnel
4.2 Equipment
4.3 Consumables
The operations team will be comprised of local personnel as well as South African expatriates. The
management team, dive team, support personnel and a portion of the marine team will travel to site
from the various ZZZZ offices in Mozambique and South Africa. The Tug crew will travel from Durban
to site on the tug towing the crane barge to site.
The plant and equipment for the project will be sourced from various ZZZZ offices in Mozambique
and South Africa. The crane barge will be towed by the tug from Durban to Pemba where the vessels
will complete customs processes. The barge’s mooring system will be prepared in Durban and
Transported with the barge. The dive system and deck decompression chamber will be transported
by truck from ZZZZ’s Pemba office to the Port of Pemba where they will be loaded onto the crane
barge using the barge’s crane. The Tug will then tow the barge to site in the Bay of Tungue to begin
operations.
6.0 METHOD
6.2 Mobilisation
• The mooring system, crane and rigging equipment and assorted support equipment will be
loaded onto the crane barge and sea fastened in Durban.
• Project material required for the EBL/TBL project will be loaded onto the barge to utilise the
remaining deck space. The barge will be loaded in accordance with the approved deck plan for
ocean transport.
• A SAMSA pre-towing inspection will be completed on the barge and towing arrangement.
• The tug will transport the crane barge from the Port of Durban to the Port of Pemba.
• On arrival at the Port of Pemba the vessel will complete the customs processes for operations
in Mozambique.
• The portable dive system and deck decompression chamber will be transported from ZZZZ’s
Pemba office to the Port of Pemba where it will be loaded onto the crane barge using the barges
crane. The dive system and chamber will be temporarily sea fastened on deck.
• The tug will transport the barge from the Port of Pemba to the project area in the Bay of Tungue.
sea fastened accordingly. The barge’s deck will be arranged and secured in accordance with
the approved deck plan for operations.
• A vessel readiness inspection will be completed on the barge to ensure it is ready for safe marine
operations.
• An IMCA dive system audit will be completed on both the dive system and the decompression
chamber to ensure both systems are ready for safe diving operations. In addition, a test dive and
diver recovery drill will be completed before the start of operations to ensure the diver can be
recovered safely in an emergency.
• Diving operations will be conducted from the Port Bow of the barge; crane and lifting operations
will be conducted form the port quarter (stern) of the barge. No lifting will be conducted over the
diver’s work area or the dive control station.
• If it is possible then dredging will begin between the spud legs as to expose both spud legs
simultaneously. Should this not be possible the spud legs will be exposed one at a time. Regular
dive inspections will be completed to monitor the progress of the dredging.
• Dredging will continue until the one or both spud legs have been exposed to approximately 60%.
There after the Drag Flow will be recovered and secured.
There after the spud leg will be slacked off completely until it is resting horizontally on the sea
bottom. The water jet probe will be extracted by the crane simultaneously with the spud leg; once
the water jet is clear of the sea bottom it will be recovered onto deck by the crane. There after
the spud leg will be recovered as per point 7.4.3 above.
• Should no movement be noted the water jet probe will be retracted by the crane until clear of the
sea bottom; there after it will be made “cold”. The water jet probe will be recovered onto deck
• The drag flow will be rigged for dredging and dredging will continue until the entire spud leg has
been exposed or a depth of 1.5m below design depth has been reached; whichever comes first.
• Should the entire spud leg be exposed the diver will enter the water and inspect the spud leg.
The rigger and dive supervisor will assess the spud leg and determine the safest method for
lifting depending on the spud leg’s orientation. The diver will rig the spud leg in accordance with
the rigger instructions. The diver will exit the water and the spud leg will be recovered as per the
method described in point 7.4.3 above.
• Should the spud leg remain embedded in the sea bottom after reaching 1.5m below design depth
then dredging will be suspended and the Drag Flow recovered.
• Two further attempts will be made to extract the spud leg. Firstly, the deck winch will increase
tension to try and extract the spud leg. Should this attempt fail the water jet will be installed as
previously described and the final attempt to extract the spud leg will be made. The spud leg will
be monitored for movement using a marked pencil buoy as detailed above and should movement
be noted the spud leg will be recovered as per point 7.4.3 above.
• Hold Point 1: A client representative is to witness the final attempts to extract the spud legs and
to confirm the cutting of the SEP jack-up legs can proceed as well as to confirm the level for the
cut to be completed.
• Should it still not be possible to extract the spud legs then divers will cut them off as close to sea
bottom as possible using a Broco underwater cutting system. The rigging will remain under
tension during cutting to ensure the spud leg does not pose a hazard to the diver once cut off.
An additional tie back line will be secured to the spud leg directly above the cut line and secured
onto a bollard. Divers will follow safe work procedures for Broco cutting ensuring that all waste
gasses from the cutting are vented either naturally or through a vent hole cut into the spud leg
above the cut line. Once the spud leg is cut off the diver will immediately move clear to safety
on the dive ladder. The spud leg will be recovered as per point 7.6 above. The diver will remain
clear until the lift is completed and there after recover the Broco cutting system and exit the
water.
• The same series of methods will be used to recover both spud legs.
to be in the correct location and dredged to the correct level by completing a multi-beam
bathometric survey after dredging has been completed.
• Hold Point 3: A client representative is to witness the bathometric survey to confirm that the
level of the dredging has reached the level of design depth plus 1.5m. The client representative
must also witness the final inspection dive to confirm if an object is present at that location or
not. The client representative is to confirm that that particular item can be abandoned.
• The above procedure will be used to locate all 104 lost items of geotechnical equipment.
• The above procedure will be used to remove and recover all 104 lost items of geotechnical
equipment.
Maximum weather limits for diving and marine operations listed below
• Wind = 15 knots
• Wave = 1m at a 10second period
• Swell = 1.5m at a 12 second period
• Current = 0.7 knots
11.0 SAFETY
All personnel will adhere to the client’s site-specific regulations as well as with ZZZZ’s policies and
procedures. ZZZZ is an IMCA registered contractor, and as such is bound to comply with IMCA
regulations.
The following baseline risk assessments will be valid for this project:
• RA-DIV-002 – Lift Bags
• RA-DIV-003 – General Diving Operations
• RA-DIV-004 – Hand Dredging
• RA-DIV-006 – Diver Safe Entry and Exit
• RA-DIV-008 – Diving Operations Adjacent to Structures
• RA-DIV-009 – Fuelling Equipment
• RA-DIV-011 – Dive System Connection and Setup
• RA-DIV-016 – Surface Swimming Inspection
• RA - DIV - 013 - Loading equipment into a DSV
12.0 ENVIRONMENTAL
At ZZZZ our commitment to protecting the environment goes beyond regulations policies and
procedures. Our staff members are all keen water enthusiasts whose career choice is influenced by
a love of the ocean and we each take personal interest in protecting its natural heritage.
Portable plant such as compressors will be provided with drip trays to prevent fuel or spills from
reaching the water. Plant will undergo timely maintenance to ensure it is in good working order to
prevent any potential environmental incidents.
The barge will be equipment with sufficient spill control and containment spill kits and materials and
all waste materials will be managed as per the approved waste management plan.
Turbidity monitoring will occur through the strategic placement of the monitoring buoys.
13.1 Delays
Unforeseen delays to be reported and acknowledged by client on daily basis to avoid confusion and
misunderstandings.
13.2 Reporting
The channels of reporting are to be agreed upon prior to commencement of the job. The client is to
be kept informed of daily progress and acknowledge.
All hold points must be adhered to and signed off by all relevant parties before the project can
continue. Client Representatives are to ensure they are satisfied with the final outcome and quality
of all pertinent task items and/or services.
14.0 APPENDIX
The following specification sheets of the equipment intended for the project are attached as
appendixes to provide addition information of the equipment ZZZZ will utilise on the project.
Specifications Sheets: