9.

2 Inspection & Test Plan

Project: Construction of Two Health ITP No.


INSPECTION & TEST PLAN Activity: Hoarding Installation at Al Waab Care Centers at Al Waab & Qatar HC-P4-ITP-GN-
University 0004 Rev. 0

Inspection or Test Project Ref. Inspection by


No. Stage/Activity Test/Frequency Mace/ Record
(Guideline Ref.) Or/ Contract Ref. Sub-Con Gen-Con Consultant
Ashghal

1 Submittals
Shop Drawing containing all Review of QCS 2010 Section 16
details of material sizes, Documents & Part 1 / HC-P4-SD- Approved Shop
1.1 Every Submission N/A H H H
dimensions, connections, Approval from AW-GN-0003 Sheet Drawing
finishes etc. CEG/ASHGHAL. 02 of 02
Review of
QCS 2010 Section 16
Documents & Approved Method
1.2 Method of Statement Every Submission Part 1 / HC-P4-MS- N/A H H H
Approval from Statement
GN-0004
CEG/ASHGHAL.
2 Materials
Review of
QCS 2010 Section 16
Documents & It Approved Material
2.1 Framing (Post & Rail) Every Installation Part 2 / HC-P4-MS- N/A H H H
should comply with Submital
GN-0004
BS Standards 5950.
Review of
QCS 2010 Section 17
Documents & It Approved Material
2.2 Corrugated Sheeting Every Installation Part 1 / HC-P4-MS- N/A H H H
should comply with Submital
GN-0004
BS Standards 3083.
3 Execution
Visual check &
Reference point shall QCS 2010 Section 16
be agreed, joint Prior to Installation & Part 8 / HC-P4-SD- Approved Shop
3.1 Setting Out and Survey N/A H H S
Survey is required after installation AW-GN-0003 Sheet Drawing
before the start of 01 of 02
work.

1 of 2
9.2 Inspection & Test Plan

Project: Construction of Two Health ITP No.


INSPECTION & TEST PLAN Activity: Hoarding Installation at Al Waab Care Centers at Al Waab & Qatar HC-P4-ITP-GN-
University 0004 Rev. 0

Inspection or Test Project Ref. Inspection by


No. Stage/Activity Test/Frequency Mace/ Record
(Guideline Ref.) Or/ Contract Ref. Sub-Con Gen-Con Consultant
Ashghal

Visual check & It QCS 2010 Section 5


Approved Method
3.2 Precast Concrete should comply with Every Installation Part 1.1.2 / HC-P4- N/A H S S
Statement
ASTM C 94. MS-GN-0004
Visual check & It QCS 2010 Section 5
Approved Method
3.3 Curing of Concrete should comply with Every Installation Part 10.1.12 / HC-P4- N/A H S S
Statement
ACI308 / ASTM C309. MS-GN-0004
QCS 2010 Section 6
Approved Method
3.4 Rails and Hoarding Fixing Visual check. Every Installation Part 3 / HC-P4-MS- N/A H S S
Statement
GN-0004
QCS 2010 Section 1
Visual check & After Completion of Approved Method
3.5 Final Inspection Part 21.1.2 / HC-P4- N/A H H R
Owner's Acceptance. work. Statement
MS-GN-0004
4 Quality Control & Testing
Review of
Documents &
Compliance with QCS 2010 Section 6
Accuracy of Erected Frames and After Completion of Inspection
4.1 approved shop Part 3 / HC-P4-MS- N/A H S R
Fences work. Checklist
drawings and should GN-0004
be within acceptable
tolerances.

Reviewed by Name: Signature: Date:

Approved by Name: Signature: Date:


Note: The underline Nos indicate incorporated amendments made to previous revision
H = Hold Point (IR), W = Witness point (WPN), S = Surveillance, CI = Contractor's Inspection, R= Record Review