Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

2018 International Conference on Electrical Engineering and Computer Science (ICEECS)

Determination of Critical Clearing Time in


Transient Stability Analysis
Gibson HM Sianipar Suwarno
Yurika
School of Electrical School of Electrical
School of Electrical
Engineering and Informatics Engineering and Informatics
Engineering and Informatics
Institut Teknologi Bandung Institut Teknologi Bandung
Institut Teknologi Bandung
Bandung, Indonesia Bandung, Indonesia
Bandung, Indonesia
gibson@power.ee.itb.ac.id suwarno@stei.itb.ac.id
yurikasjahrul@yahoo.co.id
Janson Naiborhu
Faculty of Mathematics and Natural
Sciences
Institut Teknologi Bandung
Bandung, Indonesia
janson@math.itb.ac.id

Abstract— Transient stability analysis is important in System stability depends on the load used, increasing the
planning and operating on power system. Several methods or load can trigger instability. The stability of the power system
approaches have been taken to analyze transient stability. One can be classified into several parts. Transient or large signal
approach to determining the transient stability of a power rotor angle stability is one of most important types of stability
system is critical clearing time. It provides information about
the level of stability of the existing system. When a disturbance
phenomena. Transient stability is the ability of power system
occurs, the power system must be able to maintain stable to maintain its synchronism under a severe fault such as three
conditions. Therefore in this paper, analysis of critical clearing phase short circuit [1]. Due to changes in the system
time calculation is needed as an alternative to determine the conditions immediately, the state of the system can change
transient stability of power system. For 9 buses and 3 from the old state to the new state. The short period between
machines, the critical clearing time of the system will vary the two conditions is called a transient period. Therefore an
depending on the location of the disturbance. electrical power system analysis is needed to determine
whether the system is stable or unstable when experiencing
Keywords— transient stability, stable, critical clearing time interference.

I. INTRODUCTION II. TRANSIENT STABILITY ASSESSMENT


An electric power system aims to maintain continuity and
availability of electric power to the increasing needs of the A. Energi Function
load. The more developed the electric power system can lead Based on the references [2]–[4] that the energy function
to increasingly complex systems when experiencing method is the result of the transformation of the Lyapunov
disturbance. In a power system, generally the disturbance that function into the energy function. This method is closely
occurs can be divided into two parts, namely small related to the kinetic energy and potential energy of the
disturbances and large disturbances. Small disturbances are generator, with kinetic energy strongly related to the relative
disturbances due to changes in load that occur at the side of motion of the generator while potential energy is strongly
the load or generator randomly and slowly. These related to network elements. The most critical energy is
disturbances can be analyzed using linear equations or using determined by the closest potential energy between the
small signal analysis. Whereas a large disturbance is a unstable equilibrium point and the stable equilibrium point.
disturbance that occurs suddenly on the system and must be
eliminated as quickly as possible because it can affect the Energy function theory in the analysis of multi-machine
stability of an existing system. Stability in the power system transient stability can be analogous to a ball rolling in a bowl
can be affected by the size of disturbance and the duration of where the coordinate is the generator rotor angle. The area in
disturbance that occurs in a power system. a bowl is a region of stability while the area outside the bowl
is an unstable area (region of instability). At the initial position
The stability of the electric power system is the ability of or normal conditions, the ball is at the bottom of the bowl and
the system to return to normal operation after the system is this state is called Stability Equilibrium Point (SEP). The
subject to a disturbance [1]. Instead the instability of an surface inside the bowl expresses potential energy while the
electric power system is a condition where the system losses peak of the bowl states Potential Energy Boundary Surface
synchronization. Stability analysis has an important role in the (PEBS). If the kinetic energy is converted to potential energy
power system. The more complex a system, the more complex before reaching the top, then the ball will return back to the
the ability to maintain synchronism between parts of the starting position (bottom of the bowl), this condition is called
system. For large systems with interconnections, power a stable condition. But if the kinetic energy is too large and
system results in changes in electrical parameters, including has not been completely converted to potential energy, the ball
voltage, current, power, rotor speed, frequency and power will pass through the top of the bowl and enter the unstable
angle. To analyze changes in these parameters to the length of region, this condition is called unstable.
the disturbance, from the beginning of the disturbance until
the system becomes stable again, it is necessary to calculate Reference [5] also shows the application of the energy
when the disturbance is decided without losing the function for the generator in a balanced condition and when
simultaneity of the generator. the generator is subject to a disturbance as shown in Fig. 1. It

115
shows also the trajectory for a stable and unstable area due to network matrix Y before a pre-fault occurs, determining the
the movement of the ball in the bowl. Y matrix is reduced when fault on and after the pre-fault,
determines the rotor angle when the fault is cleared for all
Mathematically the energy function can be written as in generators, determines the value of SEP (stable equilibrium
the equation below: point) and UEP (unstable equilibrium point), and determines
the energy margin (ΔV).
, = + (1)
B. Critical Clearing Time
The kinetic energy produced depends on the speed of the CCT (Critical Clearing Time) is the critical time or
generator, while the potential energy depends on the angle of maximum time needed by the synchronous generator to
the generator. When described again, equation (1) will be: maintain the condition of the generator remains in
synchronization. The electric power system becomes
= ∑ − ∑ − − unstable when the rotor angle becomes larger. This
∑ ∑ cos − cos − increase in greatly affects the change in power so that, by
(2) obtaining the rotor angle, the critical clearing time can be
determined. If a disturbance occurs and the system cannot
handle it, so the system is declared unstable. This instability
= cos − sin (3) affects the entire system. Therefore, it is necessary to
determine the critical clearing time to avoid any
disturbances.
where is kinetic energy, is potential energy, and is
the angle of the bus i post fault stable equilibrium point Various studies have been carried out in analyzing
(SEP). transient stability. Previously, transient stability analysis still
used numerical integration of nonlinear differential
ωθ ωθ equations. This method is quite accurate in calculating critical
clearing time in a multi-machine power system and is able to
ωθ ωθ ωθ ωθ
ωθ
ωθ provide an overview of the power system stability due to
ωθ transient symptoms. However, numerical integration that is
so long in the process of calculating critical clearing time
ωθ ωθ causes this method to take a long time in the iteration process.
SEP SEP
This is very ineffective when applied to transient stability
Forward movement Forward movement analysis. Because, the pattern of changes that occur due to
Backward movement Backward movement disturbances that occur very quickly in the system. Therefore,
we need a method that can calculate critical clearing time
ωθ ωθ with a faster and more accurate iteration, so that it can be
applied significantly to the system.
Determination of the critical clearing time in transient
stability analysis through stages, namely:
1. The process of power flow, by calculating the internal
R R voltage of all generators, calculating the admittance matrix
for each network condition, before, during and after a
disturbance.
2. Determine the location of the disturbance.
3. Determine the critical termination time based on the critical
System is stable System is unstable
clearing angle.

Fig. 1. Concept of energy function in the generator [5] III. CASE STUDY
The first step taken to determine the transient stability is to
To conduct a transient stability analysis, the reference simulate the power flow in the system. In power system 9
used is the difference between critical energy or critical buses and 3 machines, power flow simulations are carried out
unstable equilibrium point (Vcr) and energy when fault to determine the condition of the system before and after the
clearance (Vcl). If the fault clearing is negative then the disturbance occurs. The software used in this analysis is
system is declared to be in an unstable condition. Conversely, Digsilent Power Factory for manual analysis. Simulation is
if the result is positive, the system is declared to be in a stable carried out in each line, to determine the stability level of the
condition. The following equation shows the magnitude of system. The critical clearing time can be determined in each
the energy margin (ΔV) produced, namely: line, for this case the line used in the analysis is six lines. The
following will be discussed power system model and
∆ = − (4) simulation results.

If the positive stability index can be said to be a stable A. Power System Model
The steps in analyzing the stability of transients by using Fig. 2 shows a single line of power system that consist of
energy functions are: reading machine and network data to 9 buses and 3 machines.
determine the power flow, determining the matrix admittance

116
Load C TABLE IV. CRITICAL CLEARING TIME WITH VARIOUS FAULT
18 kV 230 kV 230 kV 13.8 kV LOCATIONS

2 3 No Fault Line (Fault) CCT (sec)


2 3
D 4–5 0.22 – 0.23
8
E 4–6 0.24 – 0.25
7 9
F 5–7 0.13 – 0.14
5 6 G 6–9 0.19 – 0.20
H 7–8 0.14 – 0.15
I 8-9 0.20 – 0.21
Load A Load B
230 kV
4
Based on Table IV above it can be concluded that:
• Among the disturbances that occur, disturbance that
18 kV 1 occur between bus 5 and bus 7 (F) have the fastest
clearing time.
1
• When the line between bus 4 and bus 5 is given a
disturbance (D), the critical clearing time is between
Fig. 2. IEEE 9 buses and 3 machines system 0.22 to 0.23 seconds. If the clearing time is set to more
than 0.23 seconds, the existing generator 2 and
Table I, II, and III show generator data, machine data, and generator 3 will be released from the system.
load data for 9 buses and 3 machines. • When the line between bus 4 and bus 6 is given a
disturbance (E), the clearing time is between 0.24 to
TABLE I. GENERATOR DATA 0.25 seconds. If the clearing time is set to more than
0.25 seconds, the existing generator 2 and generator 3
Parameter G1 G2 G3
will be released from the system.
Rated MVA 247.5 192 128
KV 16.5 18 13.8 • When the line between bus 5 and bus 7 is given a
disturbance (F), the clearing time is between 0.13 to
pf 1 0.85 0.85
0.14 seconds. If the clearing time is set to more than
Bus type SL PV PV
0.14 seconds then the existing generator 2 and
generator 3 will be released from the system.
TABLE II. MACHINE DATA
• When the line between bus 6 and bus 9 is given a
Parameter G1 G2 G3 disturbance (H), the clearing time is between 0.19 to
xd (pu) 0.36 1.72 1.68 0.20 seconds. If the clearing time is set to more than
xq (pu) 0.24 1.66 1.61
0.20 seconds, the existing generator 2 and generator 3
will be released from the system.
xd' (pu) 0.15 0.23 0.23
xq' (pu) 0 0.378 0.32 • When a line between bus 7 and bus 8 is given a
xd" (pu) 0.1 0.2 0.2 disturbance (G), the clearing time is between 0.14 to
xq" (pu) 0.1 0.2 0.2 0.15 seconds. If the clearing time is set to more than
0.15 seconds, the existing generator 2 and generator 3
Td' (s) 3.73 0.8 0.806
will be released from the system.
Tq' (s) 0 0.12 0.12
Td" (s) 0.05 0.05 0.05 • When the line between bus 8 and bus 9 is given a
Tq" (s) 0.05 0.05 0.05 disturbance (I), the clearing time is between 0.20 to
H (s) 9.55 4.165 2.765 0.21 seconds. If the clearing time is set to more than
0.21 seconds then the existing generator 2 and
generator 3 will be released from the system.
TABLE III. LOAD DATA

Bus Load Active Power (MW) Reactive Power (MVAR)


5 A 125 50
6 B 90 30
8 C 100 35

B. Simulation Results
For 9 buses and 3 machines, the location of the
disturbance is determined to vary on the transmission line.
There are 6 disturbance locations on the transmission line,
namely point D, E, F, G, H, and I.
Table IV shows the critical clearing times for various fault
locations in the 9 buses and 3 machines systems.
Fig. 3. Rotor angle response for CCT= 0.22 sec

117
Fig. 4. Rotor angle response for CCT= 0.23 sec Fig. 8. Rotor angle response for CCT= 0.25 sec

Fig. 5. Rotor angle response for CCT= 0.13 sec Fig. 9. Rotor angle response for CCT= 0.19 sec

Fig. 10. Rotor angle response for CCT= 0.20 sec


Fig. 6. Rotor angle response for CCT= 0.14 sec

Fig. 7. Rotor angle response for CCT= 0.24 sec Fig. 11. Rotor angle response for CCT= 0.14 sec

118
the system in front of it as a constant impedance. For this
reason, the superposition principle can be used to simplify the
modeling of existing systems. Based on previous research
and based on papers, the possible opportunity for further
research is to reverse the method used by researchers so far.
Completion in analyzing modeling dq0 was done with the
help of Closed Form method to analyze machines
individually [13].

V. CONCLUSION
Calculation of critical clearing time for 9 buses and 3
machine is known. Disturbance that occurs in transmission
line provides the results of calculating different critical
Fig. 12. Rotor angle response for CCT= 0.15 sec clearing time. The critical clearing time determines the
condition of the electric power system will be able to return to
a stable or unstable condition. If the disturbance is
disconnected more than the critical time, the system will be
unstable.

REFERENCES
[1] P. Kundur et al., “Definition and classification of power system
stability,” IEEE Trans. Power Syst., vol. 19, pp. 1387–1401, 2004.
[2] a. Fouad and S. Stanton, “Transient Stability of a Multi-Machine
Power System. Part II: Critical Transient Energy,” IEEE Trans. Power
Appar. Syst., vol. PAS-100, no. 7, pp. 3417–3424, 1981.
[3] A. Michel, A. Fouad, and V. Vittal, “Power system transient stability
using individual machine energy functions,” IEEE Trans. Circuits
Fig. 13. Rotor angle response for CCT= 0.20 sec
Syst., vol. 30, no. 5, pp. 266–276, 1983.
[4] H.-D. Chang, C.-C. Chu, and G. Cauley, “Direct stability analysis of
electric power systems using energy functions: theory, applications,
and perspective,” Proc. IEEE, vol. 83, no. 11, pp. 1497–1529, 1995.
[5] X. Kong, H. Jia, Y. Jiang, S. Zhao, and D. Fang, “Criterion to evaluate
power system online transient stability based on adjoint system energy
function,” IET Gener. Transm. Distrib., vol. 9, no. 1, pp. 104–112,
2015.
[6] E. W. Kimbark, Power System Stability Volume I. 1995.
[7] U. Karaagac, J. Mahseredjian, O. Saad, and S. Dennetière,
“Synchronous machine modeling precision and efficiency in
electromagnetic transients,” IEEE Trans. Power Deliv., vol. 26, no. 2,
pp. 1072–1082, 2011.
[8] L. Wang, J. Jatskevich, C. Wang, and P. Li, “A voltage-behind-
Fig. 14. Rotor angle response for CCT= 0.20 sec
reactance induction machine model for the EMTP-type solution,”
IEEE Trans. Power Syst., vol. 23, no. 3, pp. 1226–1238, 2008.
Based on Fig. 3, Fig. 5, Fig. 7, Fig. 9, Fig. 11 and Fig. 13
show rotor angle response for stable case. Fig. 4, Fig. 6, Fig. [9] J. Marti and K. Louie, “A phase-domain synchronous generator model
8, Fig. 10, Fig. 12 and Fig. 14 show rotor angle response for including saturationeffects,” IEEE Trans. Power Syst., vol. 12, no. 1,
unstable case. pp. 222–229, 1997.
[10] L. Wang, J. Jatskevich, and H. W. Dommel, “Re-examination of
synchronous machine modeling techniques for electromagnetic
IV. FUTURE RESEARCH
transient simulations,” IEEE Trans. Power Syst., vol. 22, no. 3, pp.
The electric power system consists of many elements. The 1221–1230, 2007.
most important element in controlling the transient
characteristics of a machine is the synchronous machine. To [11] G. H. M. Sianipar, “Closed Form Solution of Synchronous Machine
be able to analyze transients quickly requires proper Short Circuit Transients,” vol. 42, no. 1, pp. 91–102, 2010.
synchronous machine modeling. In addition to engine [12] G. H.M. Sianipar, “The All-DQ-Domain EMTP,” ITB J. Eng. Sci.,
modeling, overall system modeling also influences the vol. 43, no. 1, pp. 11–26, 2011.
transient stability analysis. Transient stability analysis is
carried out individually where each existing machine views

119

You might also like