SOP - Operational Planning During Bunk House Replacement (Rev - 0) PDF
SOP - Operational Planning During Bunk House Replacement (Rev - 0) PDF
Location: LBDP
1. Purpose/Scope
This document outlines and describes a sequential and safe operating procedure of LBDP production
operation during portable cabin replacement at LBDP.
2. References
3. HSE Considerations
PPE (Personal Protective Equipment) are mandatory.
Toolbox talk to be given prior to start of the operation. Each involved personnel to be clear about
respective roles and responsibilities.
Any observation of gas leakage should be promptly notified to Control Room.
Leak check to be carried out for all HC openings before lined up.
Emergency scenario should be taken care during bypass situation.
4. Responsibilities
Position Responsibility
Installation Manager Responsible for safe execution
Responsible for safe execution of all activities / jobs complying with
PTW system.
Offshore Supervisor
Ensure all isolation is done as per isolation sheet.
Providing instruction to field and DCS engineer/operator.
Continuous monitoring of process parameters during the shutdown and
DCS Engineer/Operator
coordinating with field engineer/operator.
Safe execution of the job by following SOP and instruction of field
Field Technician
engineer and supervisor.
STANDARD OPERATING PROCEDURE
Operational Planning During Pota Cabin Replacement
5. System Description
Land based drilling platform is unmanned & being monitored through DCS & routine round followed
by 24X7 security. It has 3 no’s bunkhouse (Spares, electrical and instrument) which is to be replaced
due to heavy corroded and roof are bulging, water ingress during rainy season, Therefore replacement
of bunk house is planned & accordingly operation of LBDP to be monitor , control & smooth
operational planning to be carried out during unavailability of required control.
Presently, we are utilizing 3 no’s of portable bunk for operation support at LBDP.
1) Instrument bunk house –LBDP Control room
2) Electrical bunk house –UPS room/power supply
3) Spare bunk house-Store room
In order to carry out replacement of portable bunk as per requirement, isolation sheets and sequence
of activities has been finalized.
6. Procedure
Well flow monitoring will be carried out based on sales gas pressure and flow rate, In case of
deviation in well flow will cause of any well flow upset & accordingly necessary action be taken to
observed flow behavior during field round.
We do have schedule of three time visit to LBDP in a day during that those visit all the
parameter monitoring and recording can be done.
We can monitor flow through sales gas pressure continuously from DCS, In case of any
deviation visit can be planned accordingly.
Visual visit of available security at LBDP, if any leakage or anything happened then he will
inform to control room immediately also.
Flow and parameter will be recorded from transmitter available on field during field round.
Isolation of all the wells should be carried out to keep flowing during bunk replacement work.
Wireless radio and landline phone should be readily available to communicate from LBDP to
Hazira control room and vice versa.
To avoid any faulty emergency shutdown all the interlock has been by passed and Isolation sheet has
been prepared, same will be used before starting the work at LBDP.
All ESDV of every flowing wells should be forcefully open, as we don’t have any access to
DCS system from Hazira control room.
LBDP to Hazira plant header and Hazira plant to LBDP injection header ESDV valve should be
STANDARD OPERATING PROCEDURE
Operational Planning During Pota Cabin Replacement
Please note that in case of emergency, auto shutdown will not be happened with help of DCS in that
case, operational team have to reach immediately using emergency vehicle to LBDP & necessary steps
to be taken for manual isolation of well X-tree valves or headers valve based on situation /emergency
requirement.
We do have security guard available at LBDP for administrative monitoring of LBDP platform and
Operator will do visit thrice during the day.
Note: Electrical department has confirmed that they will arrange alternative source for power
requirement.
Instructions:
ESDV Isolation details has been mentioned details that will be followed during bunk replacement
work.
7. Annexures
i. P&ID’s
a. Phase – 1 P&IDs
b. Phase – 1 P&IDs
c. Injection & Flowing header P&IDs
ii. SOP’s
iii. JSA for operation during bunk replacement activity.