Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

OBLIGATION WITH PERIOD RTC Ruling: Dismissed. Reason.

RTC Ruling: Dismissed. Reason. Respondent bound to the quotation it submitted to petitioner particularly with respect
to the terms of payment and delivery of the cylinder liners. It also declared that respondent had agreed to the
Lorenzo Shipping vs. BJ Marthel cancellation of the contract of sale when it returned the postdated checks issued by petitioner.

Facts: CA: Reversed. brushed aside petitioner's claim that time was of the essence in the contract of sale between the parties
herein considering the fact that a significant period of time had lapsed between respondent's offer and the issuance by
Petitioner Lorenzo is a domestic corporation engaged in coastwise shipping. It used to own the cargo vessel M/V petitioner of its purchase orders; that respondent did not incur delay in the delivery as no demand, judi or extra, was
Dadiangas Express. While respondent BJ Marthel International, Inc. is a business entity engaged in trading, marketing, made by respondent upon petitioner.
and selling of various industrial commodities. It is also an importer and distributor of different brands of engines and
spare parts. Issue: Whether there is late delivery of the subjects of the contract of sale to justify petitioner to disregard the terms of
the contract considering that time was of the essence thereof
From 1987 up to the institution of this case, respondent supplied petitioner with spare parts for the latter's marine
engines. Sometime in 1989, petitioner asked respondent for a quotation for various machine parts in which respondent Ruling:
did. In the quotation it was stated that: DELIVERY: Within 2 months after receipt of firm order. And TERMS: 25% upon
delivery, balance payable in 5 bi-monthly equal. No.

Petitioner thereafter issued Purchase Order (PO1) on Nov. 2, 1989 for the procurement of one set of cylinder liner, In determining whether time is of the essence in a contract, the ultimate criterion is the actual or apparent intention of
valued at P477,000, to be used for M/V Dadiangas. The PO was co-signed by Jose Go, Jr., petitioner's vice-president, and the parties and before time may be so regarded by a court, there must be a sufficient manifestation, either in the
Henry Pajarillo. Instead of paying the 25% down payment, petitioner issued ten (10) postdated checks to be drawn contract itself or the surrounding circumstances of that intention. Petitioner insists that although its POs did not
against the former's account with Allied Banking Corporation. The checks were supposed to represent the full payment specify the dates when the cylinder liners were supposed to be delivered, nevertheless, respondent should abide by the
of the aforementioned cylinder liner. term of delivery appearing on the quotation it submitted to petitioner.

Petitioner issued another PO(2) on Jan 15, 1990 for another cylinder liner. This PO stipulates the term of payment to be While the quotation provided by respondent evidently stated that the cylinder liners were supposed to be delivered
25% downpayment and 5 bi-monthly equal instalments. Like the 1st PO, the second purchase order did not state the within two months from receipt of the firm order of petitioner and that the 25% down payment was due upon the
date of the cylinder liner's delivery. cylinder liners' delivery, the POs prepared by petitioner clearly omitted these significant items. The petitioner's PO1
made no mention at all of the due dates of delivery of the first cylinder liner and of the payment of 25% down payment.
On 26 January 1990, respondent deposited one of petitioner's postdated check, however, it was dishonored due to Its PO2 likewise did not indicate the due date of delivery of the second cylinder liner.
insufficiency of funds. The remaining nine postdated checks were eventually returned by respondent to petitioner.
Petitioner claimed that it replaced said check with a good one, the proceeds of which were applied to its other In the case of Bugatti v. Court of Appeals, we reiterated the principle that "[a] contract undergoes three distinct stages -
obligation to respondent. For its part, respondent insisted that it returned said postdated check to petitioner. preparation or negotiation, its perfection, and finally, its consummation. Negotiation begins from the time the
prospective contracting parties manifest their interest in the contract and ends at the moment of agreement of the
Respondent thereafter placed the order for the two cylinder liners with its principal in Japan by opening a letter of parties. The perfection or birth of the contract takes place when the parties agree upon the essential elements of the
credit on 23 February 1990 under its own name with the First Interstate Bank of Tokyo. contract. The last stage is the consummation of the contract wherein the parties fulfill or perform the terms agreed
upon in the contract, culminating in the extinguishment thereof."
On 20 April 1990, Pajarillo delivered the two cylinder liners at petitioner's warehouse with a notation in sales invoice
“subject to verification.” In the instant case, the formal quotation provided by respondent represented the negotiation phase of the subject
contract of sale between the parties. As of that time, the parties had not yet reached an agreement as regards the
Respondent sent a statement of account to petitioner and it appears that only the 2 cylinder liners delivered remained terms and conditions of the contract of sale of the cylinder liners. Petitioner could very well have ignored the offer or
unsettled. A demand letter was sent by respondent thru its VP, Mr. Kanaan. Instead of paying, petitioner offered to pay tendered a counter-offer to respondent while the latter could have, under the pertinent provision of the Civil Code,
only P150,000 for the cylinder liners; that since the delivery was late, and due to the scrapping of the M/V Dadiangas withdrawn or modified the same. The parties were at liberty to discuss the provisions of the contract of sale prior to its
Express, it (petitioner) would have to sell the cylinder liners in Singapore and pay the balance from the proceeds of said perfection.
sale.
The testimonies however of Kanaan and Pajarillo revealed that the parties renegotiated the proposed terms of the
Another demand letter was sent by respondent’s counsel. contract of sale. As the obscurity in the terms of the contract between respondent and petitioner was caused by the
latter when it omitted the date of delivery of the cylinder liners in the purchase orders and varied the term with respect
Due to the failure of the parties to settle the matter, respondent filed an action for sum of money and damages before to the due date of the down payment, said obscurity must be resolved against it.
the RTC alleging that despite oral and written demands, petitioner obstinately refused to settle its obligations.
Respondent later filed amended complaint with preliminary attachment. Relative to the above discussion, it was held in Smith, Bell & Co., Ltd. v. Matti that

Prelim attachment granted. Petitioner posted a counter bond to discharge attachment. When the time of delivery is not fixed or is stated in general and indefinite terms, time is not of the essence of the
contract. . . .
Petitioner answer: that time was of the essence in the delivery of the cylinder liners and that the delivery on 20 April
1990 of said items was late as respondent committed to deliver said items "within two (2) months after receipt of firm In such cases, the delivery must be made within a reasonable time.
order" from petitioner.
The law implies, however, that if no time is fixed, delivery shall be made within a reasonable time, in the absence of
Respondent filed a second amended complaint with prelim attachment that claiming petitioner actually issued ten anything to show that an immediate delivery intended. . . .
postdated checks. Admitted.
We also find significant the fact that while petitioner alleges that the cylinder liners were to be used for dry dock repair
Prior trial, petitioner filed a Motion (For Leave To Sell Cylinder Liners) since the cylinder liners run the risk of and maintenance of its M/V Dadiangas Express between the later part of December 1989 to early January 1990, the
obsolescence and deterioration. Granted record is bereft of any indication that respondent was aware of such fact. The failure of petitioner to notify respondent
of said date is fatal to its claim that time was of the essence in the subject contracts of sale.
In the purchase orders issued by the petitioner, dated November 2, 1989 and January 15, 1990, no specific date of
delivery was indicated therein. If time was really of the essence, they should have stated the same in the said purchase
orders, and not merely relied on the quotation issued by the appellant considering the lapse of time between the
quotation issued by the appellant and the purchase orders of the appellee. Petitioner should have provided for an
allowance of time and made the purchase order earlier if indeed the said cylinder liner was necessary for the repair of
the vessel scheduled on the first week of January, 1990. Further, the earliest maturity date of the checks was 18 January
1990. As delivery of said checks could produce the effect of payment only when they have been cashed, respondent's
obligation to deliver the first cylinder liner could not have arisen as early as 02 January 1990 as claimed by petitioner
since by that time, petitioner had yet to fulfill its undertaking to fully pay for the value of the first cylinder liner. As
explained by respondent, it proceeded with the placement of the order for the cylinder liners with its principal in Japan
solely on the basis of its previously harmonious business relationship with petitioner.

As an aside, let it be underscored that "[e]ven where time is of the essence, a breach of the contract in that respect by
one of the parties may be waived by the other party's subsequently treating the contract as still in force."Petitioner's
receipt of the cylinder liners when they were delivered to its warehouse on 20 April 1990 clearly indicates that it
considered the contract of sale to be still subsisting up to that time. Indeed, had the contract of sale been cancelled
already as claimed by petitioner, it no longer had any business receiving the cylinder liners even if said receipt was
"subject to verification." By accepting the cylinder liners when these were delivered to its warehouse, petitioner
indisputably waived the claimed delay in the delivery of said items.

We, therefore, hold that in the subject contracts, time was not of the essence. The delivery of the cylinder liners on 20
April 1990 was made within a reasonable period of time considering that respondent had to place the order for the
cylinder liners with its principal in Japan and that the latter was, at that time, beset by heavy volume of work.

There having been no failure on the part of the respondent to perform its obligation, the power to rescind the contract
is unavailing to the petitioner.

You might also like