Installation Work: Discipline Activity Work Hampered Days (No's)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

INSTALLATION WORK

Work
Sr No Discipline
Hampered
Activity DAYS
(No's)

1 Civil Civil work Execution 32

2 Mechanical Mechanical work Execution 32


INSTALLATION WORK

Reason Action Remarks

Since 28th November all civil works have


We tried for Dewatering but due
been hampered due to heavy rain fall
to high frequency we not able to
specially in the month of Dec'19 we
execute the job
could not able execute job as planned

Since 28th November all civil works have


We tried for Dewatering but due
been hampered due to heavy rain fall to high frequency we not able to
specially in the month of Dec'19 we
execute the job
could not able execute job as planned