This chapter provides the Detailed Cost Estimate for construction/Upgrading of Existing
two lane to two lane with Paved Shoulder from Km 0/0 (TN/AP border) to Km 56/0
(Katpadi).
2. Methodology
The data for working out rate analysis, is based on the latest standard data
book as approved and communicated by MoRTH using Tamil Nadu PWD
Revised SOR 2017- 2018 (21/10/2017) for structures and TN Highways
Department SOR 2017-2018 for road works with Bitumen rate as on
16/12/2017. For non SOR items local market rates are used.
Also the rates for cement, reinforcement steel and structural steel as per
current SOR, Tamil Nadu schedule of rates 2017-2018 have been
incorporated.
The cost of labour is considered based on the Tamil Nadu PWD Revised
schedule of rates 2017-2018 and TN Highways Department SOR for road
works.
The quantities of earth work, pavement and other appurtenance works have
been worked out as per topo survey data, pavement design and typical cross
sections adopted respectively.
Cost of structures like Major Bridge, Minor bridges and Culverts has been
worked out from GADs and designs.
3. Unit Rates
GENERAL ABSTRACT
Amount (in
BILL NO. DESCRIPTION
Lakh.)
I CIVIL WORKS
5 Structure Works
Culverts
5.1 & 5.2 Pipe Culvert 132.23
Bridge - Minor
5.5 & 5.6 Minor Bridge Slab Type 204.26
Utility Shifting
Shitying of Lamp Posts, Electrical Junction Box,
453.85
Electrical Transformers etc.,
8 Shifting of Water and Drainge Pipe line 230.52
PAINTING
Painting Two coats with ready mixed plastic emulsion
paint of first class quality in black and white colour (Zebra
crossing) over a priming coat including thourough scrapping ,
5.1.7 389.400 cleaning removal of dirt and including necessary plaster paris Sqm 74.72 29095.97
wherever required etc complete with standard specifications,
for Crash barrier and medians etc., complete( for ordinary
plastered area)
PAINTING
Painting Two coats with ready mixed plastic emulsion
paint of first class quality in black and white colour (Zebra
crossing) over a priming coat including thourough scrapping ,
5.1.7 590.800 cleaning removal of dirt and including necessary plaster paris Sqm 74.72 44144.58
wherever required etc complete with standard specifications,
for Crash barrier and medians etc., complete( for ordinary
plastered area)
Sub Structure
Vibrated Reinforced Cement Concrete M30(Design mix),
using 20MM ISS graded HBG graded metal including cost
of cement at site, including formwork and centering, using soft
water, labour charges for mixing, transporting and placing in
5.3.4 287.800 position, vibrating and compacting, finishing and curing Cum 6303.43 1814127.15
concrete, working at heights, hire charges for tools and plants
including all other incidental charges etc., complete, as per
MORT&H specifications 1000,1500,1600,1700&2200 for
Box Walls Return Wall
Super Structure
Vibrated Reinforced Cement Concrete M30 (Design mix)
using 20MM ISS graded HBG metal including cost and
conveyance of all materials to site including cost of cement at
site, including formwork and centering, using soft water,
labour charges for mixing, transporting and placing in position,
5.3.5 76.000 vibrating and compacting, finishing and curing, concrete Cum 6303.43 479060.68
working at heights, hire charges for tools and plants including
all other incidental charges etc., complete as per MORT&H
specifications 1000,1500,1600,1700 &2300 for Box Top
Slab.
C. Production Work
Providing and fixing of Galvanized iron drainage spouts
100mm dia, as per GOI drawing SD/205 with grating
arrangements at top as shown in the drawing and 100mm dia
5.3.8 16.000 drainage spout projecting at least 600mm beyond the bottom of Nos 376.09 6017.44
decks slab as shown in the drawing including cost and
conveyance of Galvanized iron pipes and flats and fixing them
in position etc., complete as per MORT&H specifications 2705
5.3.14 PAINTING
Painting Two coats with ready mixed plastic emulsion
paint of first class quality in black and white colour (Zebra
crossing) over a priming coat including thourough scrapping ,
293.100 cleaning removal of dirt and including necessary plaster paris Sqm 74.72 21900.43
wherever required etc complete with standard specifications,
for Crash barrier and medians etc., complete( for ordinary
plastered area)
Sub Structure
Vibrated Cement Concrete of grade M20 Nominal mix
1:1.5:3 using 40mm ISS HBG metal including cost and
conveyance of all Materials to site and cement at site including
form work , using soft water, labour charges for mixing,
transporting and placing in position, compacting, finishing and
5.4.4 661.400 Cum 5716.45 3780860.03
curing, working at depths, Tools and Plants and incidental
charges such as maintening of protective bunds, cofferdams,
shoring, strutting etc., complete, as per relevant standard
specifications MORT&H specifications 1000&2200. (above
Sill Level)
Production Work
Providing and laying filter media with granular
materials/stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRT&H Specifications to
The thickness of filter is generally of the order of 200 mm to
300 mm. Where filter is provided in two layers, thickness of
5.4.11 197.900 Cum 779.46 154255.13
each layer shall be 150 mm. The smaller size towards the soil
and bigger size towards the wall and provided over the entire
surface behaind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per drawing
and Technical Specifications
Sub Structure
Super Structure
Production Work
Providing and laying filter media with granular
materials/stone crushed aggregates satisfying the requirements
laid down in clause 2504.2.2. of MoRT&H Specifications to
The thickness of filter is generally of the order of 200 mm to
300 mm. Where filter is provided in two layers, thickness of
5.4.11 24.600 Cum 779.46 19174.72
each layer shall be 150 mm. The smaller size towards the soil
and bigger size towards the wall and provided over the entire
surface behaind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per drawing
and Technical Specifications
Super Structure
Vibrated Reinforced Cement Concrete M30 (Design mix)
using 20MM ISS graded HBG metal including cost and
conveyance of all materials to site including cost of cement at
site, including formwork and centering, using soft water,
labour charges for mixing, transporting and placing in position,
5.5.9 228.800 Cum 7199.98 1647355.42
vibrating and compacting, finishing and curing, concrete
working at heights, hire charges for tools and plants including
all other incidental charges etc., complete as per MORT&H
specifications 1000,1500,1600,1700 &2300 for RCC Deck
Slab.
Protection Work
Providing and fixing of Galvanized iron drainage spouts
100mm dia, as per GOI drawing SD/205 with grating
arrangements at top as shown in the drawing and 100mm dia
drainage spout projecting at least 600mm beyond the bottom of
5.5.13 9.000 Nos 376.09 3384.81
decks slab as shown in the drawing including cost and
conveyance of Galvanized iron pipes and flats and fixing them
in position etc., complete as per MORT&H specifications 2705
Dismantling
5.5.26 164.000 Existing Structure RCC Structure Cum 788.71 129348.44
Sub Structure
Vibrated Cement Concrete M20 (Design mix), using
40MM ISS graded HBG graded metal including cost of
cement at site, including formwork and centering, using soft
water, labour charges for mixing, transporting and placing in
5.6.4 165.700 position, vibrating and compacting, finishing and curing Cum 5716.45 947215.765
concrete,hire charges for tools and plants including all other
incidental charges etc., complete, as per MORT&H
specifications 1000&2200. for Abutment Wall & Return
Wall
Super Structure
Vibrated Reinforced Cement Concrete M30 (Design mix)
using 20MM ISS graded HBG metal including cost and
conveyance of all materials to site including cost of cement at
site, including formwork and centering, using soft water,
labour charges for mixing, transporting and placing in position,
5.6.7 61.600 Cum 6911.98 425777.968
vibrating and compacting, finishing and curing, concrete
working at heights, hire charges for tools and plants including
all other incidental charges etc., complete as per MORT&H
specifications 1000,1500,1600,1700 &2300 for RCC Deck
Slab.
5.6.25 PAINTING
Painting Two coats with ready mixed plastic emulsion
paint of first class quality in black and white colour (Zebra
crossing) over a priming coat including thourough scrapping ,
62.000 cleaning removal of dirt and including necessary plaster paris Sqm 74.72 4632.640
wherever required etc complete with standard specifications,
for Crash barrier and medians etc., complete( for ordinary
plastered area)
Dismantling
5.6.26 55.000 Existing Structure RCC Structure Cum 788.71 43379.050
5.7.6 2.800 Masking Wall (RCC M35 Grade) Cum 6567.80 18389.84
C. Protection Work
5.7.32 Dismantling
114.020 RCC Structure Cum 788.71 89928.71
30.000 Cut Stone Masondry Cum 553.98 16619.40