Automatic batch valuation with inspection lot

The link between master inspection characteristics and class characteristics enables
inspection results from a quality inspection to be included in the batch valuation.

For the inspection results to be included in the batch valuation:


The material that is inspected with a material specification must be handled
in batches
The material must be assigned to a batch class (.Classification. tab page in
the material master)
The master inspection characteristics that are used must be linked to class
Characteristics when the inspection lot is created
When the inspection is completed, the results are forwarded to the class
Characteristics with the usage decision. They can also be forwarded during the
inspection point evaluation. The batch valuation also takes place during the
inspection completion.
The material specification is not mandatory for forwarding inspection results from
QM to the batch class characteristics. You can also carry out a batch valuation
without material specifications.
A general prerequisite for carrying out a batch valuation with the inspection results
from QM is the link between the master inspection characteristics and the class
characteristics of the batch class.

Process Flow.

1. Create Master inspection characteristic


2. Create class characteristic
3. Create Batch class
4. Assign class characteristic to class
5. Assign class to material
6. Assign class characteristic to Master inspection characteristic
7. Create Inspection Plan for material
8. Create inspection lot
9. Results recording for inspection lot
10. Usage decision for inspection lot
11. Inspection Results passed to batch class characteristic.
Create Master inspection characteristic
QS21
MIC Name: LENGTH66
Save MIC
Create class characteristic
Save characteristic

Create Batch class

CL01
SAVE

Assign class to material

SAVE
Assign class characteristic to Master inspection characteristic
Create inspection lot
Save inspection lot
Now do results recording
Now save

Now do UD

Save
Now Check in MSC3N for batch