Professional Documents
Culture Documents
Amaravathi Capital Master Plan Images
Amaravathi Capital Master Plan Images
Project Proponent:
Andhra Pradesh
Capital Region Development Authority
Lenin Center, Governorpet,
Vijayawada - 520002
Environment Consultant:
Sri Sai Manasa Nature Tech Pvt. Ltd
Head Office: Plot no: 74/A, Flat no: 102,
Central bank Building, Kalyan Nagar,
Hyderabad- 500 038.
Phone No: 040-2381 6333 Amaravati Capital City
Mobile: +91-9010896661, 9912976976.
Andhra Pradesh
Table of Contents
Content Page No
Chapter 1 Introduction
1.1 Purpose of the Report 1
1.2 Identification of Project & Project Proponent 1
1.3 Importance of the Project 3
1.4 Scope of the Study 4
1.5 Applicable Environmental Standards and Regulation 5
1.6 Benefits of the Project 6
Chapter 2 Project Description
2.1 Type of Project 7
2.2 Need for the Project 7
2.3 Location of the Project 7
2.4 Size or Magnitude of Operation 12
2.5 Proposed Schedule of Operation 14
2.6 Requirements of the project 14
Chapter 3 Description of the Environment
3.1 Study Area 18
3.2 Scope & Methodology of EIA Study 18
3.3 Description of the Baseline Environment 19
Chapter 4 Anticipated Environmental Impacts and Mitigation Measures
4.1 Introduction 39
4.2 Land Environment 40
4.3 Air Environment 41
4.4 Water Environment 47
4.5 Noise Environment 49
4.6 Solid Waste Generation 49
4.7 Storm Water Management & Rainwater Harvesting 50
4.8 Greenbelt Development 51
4.9 Hazardous Waste 51
4.10 E-Waste 51
4.11 Parking Place 52
4.12 Socio Economic Environment 52
4.13 Energy Conservation & Green Building Measures 54
4.14 Fire Fighting System 56
4.15 Impact on Traffic 59
Chapter 5 Analysis of Alternatives (Technology & Site)
5.1 Analysis of Alternative Sites 60
Chapter 6 Environmental Monitoring Programme
6.1 Environmental Monitoring Programme 61
6.2 Monitoring of Environmental Parameters 61
6.3 Budgets for Environmental Management Plan 62
Chapter 7 Additional Studies
7.1 Public Consultation 63
7.2 Safety Management Plan 63
7.3 Safety Organization 65
7.4 Fire Fighting Systems 65
Chapter 8 Project Benefits
8.1 Project Benefits 67
8.2 Employment Potential 67
Chapter 9 Environmental Cost Benefit Analysis
68
Chapter 10 Environmental Management Plan
10.1 Environmental Management Plan – Construction Phase 69
10.2 Environmental Management Plan during Operation Phase 70
10.3 Environmental Monitoring Plan 80
Chapter 11 Summary and Conclusions 83
Chapter 12 Disclosure of Consultant 84
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 1
Introduction
APCRDA has applied for Environmental Clearance from SEIAA for proposed project vide
proposal SIA/AP/NCP/82122/2018 dated 11.10.2018 to construct “Amaravati Happy Nest”
with 6 Blocks and 2 Amenities blocks as part of Amaravati Capital City with a plot area of
14.29 Acres and built-up area of 1,40,756.19 Sq.m. Presently APCRDA is intended to amend
the earlier proposal of “Amaravati Happy Nest” with 12 Blocks and 2 Amenities blocks with
a plot area of 14.46 Acres and built-up area of 2,82,426.33 Sq.m.
1
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
The summary of project is given in Table 1.1 and ground coverage statement is given in
Table 1.2.
Table 1.1
Project Summary
S. No Description Earlier Proposed for EC
Proposal Amendment
1 Total plot area (Acres) 14.29 14.46
2 Total built up area, sq.m 1,40,756.19 2,82,426.33
3 Landscape & greenbelt area, sq.m 16,451.82 30,336.92
4 Total no. of blocks 6 12
5 Total no. of floors per block Basement +
Podium + Basement +
Ground+18 Podium +
Ground+18 Floors
Floors + + Terrace Floor
Terrace Floor
6 No. of amenity blocks provided 2 2
7 Built up area of 2 amenity blocks (included
3781.37 4803.6
in total built-up area), sq.m
8 Provision for basement parking area, sq.m 46,617.94 73,955.01
9 No. of four wheeler parking’s provided 942 1631
10 No. of two wheeler parking’s provided 600 1200
Table 1.2
Ground Coverage Statement
Description Area Details
Acres Sq.m
Plinth area of blocks 2.41 9756.30
Plinth area of amenities 0.19 779.32
Landscape & greenbelt 7.49 30336.92
Roads 3.58 14476.53
Ramps, ventilation cut outs, shafts etc. 0.79 3201.81
Land area (Total) 14.46 58550.88
The estimated capital investment for the development of the project is Rs. 558.50 Crores.
2
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Government to declare by Notification the “Capital Region” and “Capital City Area” for the
State of Andhra Pradesh.
Section 4 of the Act enables establishment of Capital Region Development Authority for the
purpose of planning, co-ordination, execution, supervision, financing, funding and for
promoting and securing the planned development of the Capital Region and Capital City
Area for the State of Andhra Pradesh and for the matters ancillary thereto.
In this context, as resolved by the Cabinet, the State Government was of the opinion that
the interests of the entire state and its balanced development can be best served by
locating the capital city at a central place around Vijayawada. This would enable equal
access to people from all regions of the State.
As regards the new Capital, the Government is deeply committed to ensuring that the
process of building the new capital involves the participation of people. It is in this context
that the cabinet has suggested the use of Land Pooling schemes to consolidate the land
required for the capital. This will enable the local landholders to proactively participate and
benefit from the development of the capital city, and will create a win-win situation for the
landholders, citizens and the Government. As a result, the new capital city of the State of
Andhra Pradesh can proudly call itself a “People’s Capital”. The creation of a world-class
capital city at a central location is essential to create a level-playing field for the new State.
As experience from across the world demonstrates, a vibrant capital city can act as a
catalyst for economic development for the entire state and become an iconic city that is a
source of pride for all its citizens.
The Government of AP has decided to establish the new capital city as a livable,
environmentally sustainable and people’s capital. For this purpose, the location of the
capital was identified between Vijayawada and Guntur cities upstream of Prakasam Barrage
on the river Krishna.
The approved Master Plan of Amaravati Capital City is shown in Figure1.1. APCRDA
proposes to construct “Amaravati Happy Nest” with 12 Towers and 2 Amenities blocks as
part of Amaravati Capital City.
3
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 1.1
Approved Master Plan
Monitroing data collected during the month of May, 2018 and online ambient air quality
station at Interim Government Complex, Velagapudi have been used to assess the existing
environmental status of various environmental parameters within the study area of the
project. The report presents the baseline scenario, prediction of impacts of the proposed
project as per the guidelines of MoEF&CC/CPCB along with a detailed environmental
management plan, which will be implemented during the construction and operation phase
of the project.
The various steps involved in EIA study of the project site are divided into the following
phases:
Assessing the existing baseline status of air, water, noise, land and socio-
economic environments within the study area of the project site (buffer zone)
Identifying and quantifying significant impacts due to various operations of the
proposed project on various environmental components through prediction of
impacts.
Evaluating the beneficial and adverse impacts of the proposed Project.
Preparing Environmental Management Plan (EMP) for mitigation of adverse
impacts if any, as a consequence of the proposed Project.
Preparing post project monitoring programme for checking and regulating the
environmental quality of the proposed project and help in sustainable
development of the area.
EIA report with the above scope incorporating the standard TOR is presented in subsequent
chapters.
5
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
6
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 2
Project Description
The proposed capital city is being planned to accommodate a population of 4.5 million by
2050. The proposed capital city is being developed with ‘state-of-the-art’ infrastructure
including world class roads, water supply facilities, administrative and institutional
complexes, drainage, sanitation, Solid Waste Management (SWM) facilities, river front
development etc., among others.
The project site is part of the Survey of India Topo sheet No E44/U/7 with an average
altitude of 24m above MSL. Figure 2.1 shows the location map of the project site. The
coordinates of the project site is given in Table 2.1.
Table 2.1
Site Coordinates
Longitude Latitude
80° 28' 51.267" E 16° 30' 6.416" N
80° 28' 52.175" E 16° 30' 7.297" N
80° 28' 57.896" E 16° 30' 7.311" N
80° 28' 57.922" E 16° 29' 57.548" N
80° 28' 51.311" E 16° 29' 57.532" N
7
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 2.2 gives the salient features of the site. There are no wild life sanctuaries, national
parks, elephant/tiger reserves within 10km radius of the study area. Coordinates of the
project site on Topo sheet are shown in Figure 2.2. Google earth imagery of the project site
is shown in Figure 2.3.
Table 2.2
Salient Features of the Project
Feature Details
Altitude 24 m above MSL
Temp., oC 9.4 - 47.2
Relative Humidity,% 35-83
Annual rainfall, 1031.6 mm
Nearest Water Bodies Krishna River – 6.6 km – N
Nearest Highway The National Highway (NH-65) connecting Hyderabad -
Vijayawada at a distance of 9.5 km in NE direction and NH-16
connecting Vijayawada – Guntur – 14.7 km – E direction
Nearest Railway Station Krishna Canal Railway Station RS – 13.5 km – E
Nearest Industries Vijayawada Thermal Power Plant – 12 km – NE
Nearest Village Nelapadu – 0.75 km – N
Sakhamuru –0.74 km –SW
Nearest Town Vijayawada - 11 km - NE
Inter State Boundary Andhra Pradesh – Telangana – 52.5 km – NW
Nearest Air port Gannavaram ( Vijayawada ) – 33.3 km – ENE
Bird Sanctuary/National Uppalapadu Bird Sanctuary – 22 km – S
Parks
Nearest Forest Kondapalle RF – 11.0 km – NNE
Motadaka RF – 9.0 km – WSW
Karlapudi RF – 8.5 km – W
Tadepalli RF-9.9 km - SE
PeddaMadduru RF – 9.6 km – NW
Historical places Undavalli Caves – 10.7 km - E
*All distances mentioned in the above table are aerial distances from the Boundary of the
proposed project.
8
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.1
Location Map
9
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.2
Topographical Map
10
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.3
Google Image
11
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 2.3
Salient Details of the Project
S. No Description
1 Total plot area (Acres) 14.46
2 Total built up area, sq.m 2,82,426.33
3 Landscape & greenbelt area, sq.m 30,336.92
4 Total no. of blocks 12
5 Total no. of floors per block Basement + Podium + Ground+18
Floors + Terrace Floor
6 No. of amenity blocks provided 2
7 Built up area of 2 amenity blocks (included in
4803.6
total built-up area), sq.m
8 Provision for basement parking area, sq.m 73,955.01
9 No. of four wheeler parking’s provided 1631
10 No. of two wheeler parking’s provided 1200
The project would have 12 Blocks and 2 Amenities blocks with a total built-up area of
2,82,426.33 Sq.m.
The site layout of the project along with greenbelt and internal roads is shown in Figure 2.4.
12
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.4
Site Layout
13
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.5
Pictorial View
A. Construction Machinery
A site office will be established at the project site. The following equipment/machinery
would be mobilized during the construction of the project.
14
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
C. Power
The power requirement is about 2 MVA (maximum demand) for the project during
construction phase and it will be sourced from the Andhra Pradesh Southern Power
Distribution Company Limited (APSPDCL)/ APTRANSCO from 33 kV substation.
DG sets of capacity 2x180 kVA, 2x650kVA and 2x500 kVA will be provided at the site. This
will be for a temporary period and limited to the construction phase only.
D. Water
Water for construction will be sourced from Thulluru lift irrigation scheme being
operated by Andhra Pradesh Irrigation Development Corporation (APIDC). Currently the
Government Complex buildings and other educational institutes like VIT, SRM are
receiving the water supply from the Thulluru lift irrigation scheme.
The consumption of water per day during peak construction period is estimated to be
about 450-500 KLD. The water requirement during construction phase has been worked
out considering concrete curing, mortar mixing and curing for block work, mortar mixing
and curing for plastering, floor finishes, roof works/screed, sprinkling for dust
suppression and domestic use in labour colony.
E. Manpower
It is estimated that about 900 persons are required during construction phase. The labour
would be sourced through local contractors.
A. Power
The estimated total connected demand is 12 MVA and the maximum demand is 11 MVA
of power for the proposed project will be sourced from the APSPDCL/APTRANSCO
through 33 kV substations.
Standby Power
During periods of power outages, it is proposed to supply emergency power through
standby DG sets. CPCB Type approved DG sets will be provided in the project. The details
of the DG sets proposed to be provided are given below:
B. Water Supply
The total water requirement for the project during operation phase is estimated to be
1284 KLD (includes 472 KLD of recycled water). The freshwater requirement of 812 KLD
will be met from the Thulluru lift irrigation scheme until the city level water supply
system comes into operation.
The treated waste water of about 472 KLD will be recycled for various requirements like
flushing of toilets, landscaping. Dual plumbing system is proposed to utilize the treated
waste water for flushing. Excess treated waste water will be reused for greenery and
landscape development/ maintenance and for dust suppression measures for nearby
capital city construction works.
A well designed sewer system will be provided to collect the sewage from all the
facilities. The network will be provided with inspection chamber’s as per the
requirement. The sewage collected through the network will be routed to the proposed
sewage treatment plant
D. Manpower
The project would accommodate 7056 people during operation and provide
employment to nearly 750 to 1000 people directly.
16
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 2.6
Storm Water Drainage Layout
17
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 3
Description of the Environment
The study area is covered in Survey of India Topo sheet no.E44/U/7 with an average altitude
of 24 m above MSL.
The environmental monitoring studies were done in the month of May, 2018 for the entire
Amaravati Capital City. For the proposed project a 2 km radius is considered as study area
and water, noise, soil, air samples are collected within the study area. The AAQ studies has
been done for the capital city EIA and one of the AAQ locations i.e. Shakamuru village is
18
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
within the study area in the Southwest direction and data pertaining to that AAQ station is
considered.
The Ecological studies and the traffic studies done for the Capital city EIA are considered for
this project.
The identified impacts on air, water, land, noise, solid waste have been studied and the
quantification/predictions are made based on standard methodology, scientific knowledge
and experience.
The quantified incremental impacts were correlated with baseline environmental status and
checked for compliance with standards.
Relative humidity-
The Relative humidity during the months March to May is observed to be in the range of
36.0 to 83.37
19
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Wind rose-
The data of the Capital city EIA studies and CAAQM are used to arrive at the predominant
wind directions specific to the project site – from the wind rose diagrams of the met data
observed in Ananthavaram and Tadepalli the predominant wind directions are South and
second predominant direction is in South East. As per the CAAQM the predominant wind
direction is in SE and SSE.
Ananthavaram Tadepalli
(Secondary) (Secondary)
(Existing CAAQM)
20
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.1
Map Showing Location of AAQ stations
AAQ 2 AAQ 3
AAQ 1
21
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 3.1
Location wise Ambient Air Quality data
Location PM10 PM2.5 SO2 NOX CO
Sakhamuru (Capital City baseline -
48.0 28.86 17.72 28.86
data)
Sakhamuru (24.05.2018) 42.6 19.2 10.4 17.9 <1
Nelapadu (24.05.2018) 52.3 28.1 9.6 14.8 <1
CAAQM Secretariat Building 0.49
56.43 25.73 7.24 10.92
(24.05.2018)
CAAQM Secretariat Building 1.07
105.90 54.42 16.35 24.58
(Season)
NAAQ Standards for Industrial, 2
100 60 80 80
Residential, Rural and Other (8 hourly)
[µg/m3] [µg/m3] [µg/m3] [µg/m3]
Areas (24 hourly standard) [mg/m3]
Source: APCRDA
The three months (March to May – 2018) hourly data of existing CAAQMS station at
Secretariat building is attached as Annexure – 2.
22
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.2
Noise Sampling Locations
N1
N2
Table 3.2
Noise Sampling Results
Ambient Air Quality 22.06.2018 22.06.2018
Standards w.r.t
Time
Noise for Nelapadu Sakhamuru
Residential Area
Day Time
06:00 55 47.6 49.7
07:00 55 47.5 51
08:00 55 49 53.2
09:00 55 54.4 48.8
10:00 55 50.3 51.2
11:00 55 45.6 51.7
12:00 55 47.8 48.8
13:00 55 48.2 48.3
14:00 55 50.1 45.9
15:00 55 52.3 49.1
16:00 55 47.5 50.4
17:00 55 47.7 51.4
18:00 55 45.9 45.3
19:00 55 47.8 54.1
20:00 55 48.9 53.2
23
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
It is observed that the Day Equivalent and Night Equivalent are within the standards in the
two villages.
24
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.3
Ground Water Sampling Location Map
GW 1
GW 2
Table 3.3
Ground Water Quality Analysis
S. Tests Nelapadu Sakhamuru IS 10500 -2012
No (GW1) (GW2) Acceptable Permissible Limits
Limits
1 PH at 25 oC 7.24 7.18 6.5-8.5 No Relaxation
2 Turbidity <1 <1 1 5
3 Electrical Conductivity 3140 3180 - -
4 Total Dissolved Solids 2045 2064 500 2000
5 Total Hardness as CaCO3 675 710 200 600
6 Calcium as Ca 163 147 75 200
7 Magnesium as Mg 65 83 30 100
8 Chlorides as Cl 475 390 250 1000
9 Sulphate as SO4 378 327 200 400
10 Fluoride as F- 0.98 1.07 1.0 1.5
11 Nitrate as NO3 78 118 45 No Relaxation
12 Total Alkalinity as CaCO3 433 569 200 600
13 Boron as B 0.28 0.25 0.5 1
14 Sodium as Na 396 209 - -
15 Potassium as K 27 320 - -
16 Iron as Fe 0.24 0.13 1.0 No relaxation
25
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
From the ground water sample analysis for the villages Nelapadu and Sakamuru within the
study area except TDS and total hardness, remaining all other parameters are within the
permissible limits. The TDS and total hardness in Nelapadu and Shakamuru are above the
permissible limits 2045mg/l, 2064mg/l and 675mg/l, 710mg/l respectively.
Figure 3.4
Surface Water Sampling Locations
SW 1
SW 2
26
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 3.4
Surface Water Quality Analysis
S.No Parameters Nelapadu Sakhamarru IS 10500 -2012
Tank Water Tank Water Acceptable Permissible
(SW1) (SW2) limits limits
1 PH at 25 oC 7.30 7.83 6.5-8.5 No Relaxation
2 Turbidity 11 7 1 5
3 Electrical Conductivity 590 850
4 Total Dissolved Solids 385 554 500 2000
`5 Total Suspended Solids 30 20 - -
6 Total Hardness as CaCO3 126 191 200 600
7 Calcium as Ca 28 40 75 200
8 Magnesium as Mg 13 22 30 100
9 Chlorides as Cl 43 135 250 1000
10 Sulphate as SO4 18 78 200 400
11 Fluoride as F- 0.75 0.59 1.0 1.5
12 Nitrate as NO3 5.2 3.1 45 No Relaxation
13 Total Alkalinity as CaCO3 202 141 200 600
14 Boron as B < 0.1 0.20 0.5 1
15 Sodium as Na 74 105 - -
16 Potassium as K 5.8 4.1 - -
17 Iron as Fe 0.13 0.22 1.0 No Relaxation
18 Copper as Cu < 0.02 < 0.02 0.05 1.5
19 Manganese as Mn < 0.03 < 0.03 0.1 0.3
20 Zinc as Zn < 0.02 < 0.02 5 15
21 Cadmium as Cd < 0.003 < 0.003 0.003 No relaxation
22 Lead as Pb < 0.01 < 0.01 0.01 No relaxation
23 Mercury as Hg < 0.001 < 0.001 0.001 No relaxation
24 Total Arsenic as As < 0.01 < 0.01 0.01 No relaxation
25 Nickel as Ni < 0.02 < 0.02 0.02 No relaxation
26 Total Chromium as Cr < 0.02 < 0.02 0.05 No Relaxation
27 Phosphate as P < 0.1 < 0.1 - -
28 Salinity 0.39 0.55 - -
29 Dissolved Oxygen 4.9 4.9 - -
30 Chemical Oxygen 38 32 - -
Demand
31 BOD for 3 days at 27oC 12 10 - -
32 Total Nitrogen as N 7.0 5.3 - -
33 Ammonical Nitrogen N 3.1 2.5 - -
In the study area all the parameters of the surface water analysis are within the acceptable
limits except the turbidity and TDS. In the Nelapadu and Shakamuru village the observed
turbidity levels are 11NTU and 7NTU respectively. In the Shakamuru village the TDS value is
554 mg/l which is over the acceptable limit and is within the permissible limits
27
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
As part of the planning the drainage has to be planned for the site to avoid any water
logging situations during storm events within the site and in its vicinity. The project
development is an interlinked project of the capital city development and the capacities of
the storm sewers including the natural drains in the capital city are designed considering the
1 in 100 year storm events to avoid water logging conditions on the roads.
All the construction in the capital city are as per the proposed levels of the hydrological
studies conducted for the capital city to avoid any water logging situation on the roads and
any development.
The drain network proposed within the project site with ground water recharge pits will
drain the surface runoff from the site to the city storm sewers proposed on the East side
access road.
Figure 3.5 shows the land use and land cover map and Figure 3.6 shows the satellite
imagery of the 10 km radius from the project site. Land use land cover categories identified
in the area are built-up area, agricultural and vegetation, open area and water bodies.
28
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.5
Land Use/ Land Cover Map
The land use pattern of the Amaravati Capital City is given below.
Table 3.5
Land Use Pattern of the Study Area
Colour Classification Name Area Ha *PGA %
Water Bodies 2533.9 8.1
Built-up Area 1519.3 4.8
Open Area 13809.2 44.0
Agriculture & Vegetation 13553.0 43.1
Total 31415.4 100.0
29
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.6
Satellite Imagery
Table 3.6
Soil Quality Analysis
S. No Parameters Units Nelapadu (S1) Sakhamuru (S2)
1 pH of 1.2 Soil water Extract ----- 7.38 8.21
2 Available Nitrogen as N kg/ha 403 428
3 Available Phosphorous as P2O5 kg/ha 101 96
4 Available Potassium as K2O kg/ha 763 1173
5 Available Calcium as Ca mg/kg 3968 3507
6 Available Magnesium as Mg mg/kg 936 851
30
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 3.7
Soil Sampling Locations Map
S1
S2
Soil Monitoring
31
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
3.3.7.2 Fauna
Based on the information obtained from secondary sources, the study area has not
recorded presence of any endangered/threatened/ endemic species. The list of Fauna of the
study area is presented in Annexure – 3.
32
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
33
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chlorophyceae: Cholorella sp., Eudorina sp., Pediastrum sp. Spirogyra sp., Ulothrix sp.,
Zygnema sp.,
Cyanophyceae: Microcystis sp., Nostoc sp.,
Bacillariophyceae: Diatoma sp., Fragilaria sp., Nitzschia sp., Naviculacuspidata
34
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
studies done for the Capital city. Presently, the study area falls in Guntur district of Andhra
Pradesh state.
The census data has been analyzed with respect to various demographic and socio-economic
parameters for the study area and the results are represented in the following sections.
Population
The population profile shows that total population of the villages in the capital city area is
97906. The villages falling in the capital city area are Lingayapalem, Uddandarayunipalem,
Velagapudi, Nelapadu, Sakhamur, Ainavolu, Malkapuram, Mandadam, Venkatapalem,
Ananthavaram, Nekkallu, Thullur, Dondapadu, Abbarajupalem, Rayapudi etc.
In the study area 2 km of the project site, the population of the two villages – Nelapadu and
Shakamuru are 1028 and 1218 respectively.
The demographic details of the villages in the capital city are given in Annexure – 4.
The percentage of ST population for state and district is 6.9% and 5.9% respectively. The
percentage of ST population for the capital city is 3.49%, which is lower than state and district
when compared ST population percentage.
35
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Literacy
The literacy level for the state and district is 67% and 55.5% respectively. The literacy
percentage of the capital city is 60.65%, which is lower than state and higher than district
level.
The literacy level of the male population for the state and district is 56.5% and 56.58%
respectively. The literacy level of male population for the study area is 33.31%, which is lower
than the state and district.
The literacy level of the female population for the state and district is 43.4% and 43.41 %
respectively. The literacy level of female population for the capital city is 27.33% which is
lower than state and district level.
The total literacy rate of the Nelapadu village and Shakamuru village are 59.6% and 59.03%
respectively which are above the total literacy rates of the district.
The male and female literacy rates of the villages Nelapadu are 69.23% and 50.07% and the
male and female literacy rates of the village Shakamuru are 67.58% and 51.18%.
The employment pattern in the villages suggest that only 7.14% as cultivators, 26.85% are
agricultural labors, 11.12% as other workers and 0.63% as household industry workers. Most
of the villagers are agriculturists.
Drinking Water
Availability and access to safe drinking water has been the most crucial factor involving
serious health concerns in the area. All the sample villages have drinking water facility.
36
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Market Facilities
Commercial activities form the backbone of the economy. The proposed project requires
various services and generates direct and indirect employment to the residents of the nearby
villages and also it creates market facilities in the nearby the villages.
Health Facilities
Government facilities are the only available sources for curative care in the area. The
surveys of the sample villages reveal that these villages didn't have access to the primary
health centres (PHCs) and the majority of the PHCs were available at a distance of more
than 5 km. Overall, it is reflected that access to health facilities is not easy in most of the
villages. The proposed project will create health care facilities and thereby improves the
health services in the nearby villages.
Educational Facilities
The survey of sample villages reveals that there is less number of exclusive schools in the
area. However all villages have at least one primary school within each village of the study
area, but higher education facility is not available in most of the villages, most of the schools
are found to be approachable through kaccha roads and within the 2-5km away from their
village.
Electricity
As per the survey information 90% of the sample villages have the power supply facility. All
the HHs will be provided with power supply on par with the Capital city Master plan
development.
37
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Amaravati to Thullur Road: The highest no. of total vehicles on this road was found to be
from 6.6.15 to 7.6.15. The trend reflected that the highest no. of vehicles by category were
2 wheelers (66%) followed by light motor vehicles (15%) , heavy motor vehicles (13%) and
lastly 3 wheelers (6%) in descending order.
Thulluru to Tadikonda Road: The highest no. of total vehicles on this road was found to be
from 1.6.15 to 2.6.15. The trend reflected that the highest no. of vehicles by category were
2 wheelers (66%) followed by light motor vehicles (14%), heavy motor vehicles (11%) and
lastly 3 wheelers (9%) in descending order.
Pedaparimi to Mangalgiri Road: The highest no. of total vehicles on this road was found to
be from 1.6.15 to 2.6.15. The trend reflected that the highest no. of vehicles by category
were 2 wheelers (65%) followed by light motor vehicles (15%), heavy motor vehicles (12%)
and lastly 3 wheelers (8%) in descending order.
Thulluru to Undavalli Road: The highest no. of total vehicles on this road was found to be
from 6.6.15 to 7.6.15. The trend reflected that the highest no. of vehicles by category were
2 wheelers (64%) followed by heavy motor vehicles (10%), 3 wheeler (9%) and lastly light
motor vehicles (2%) in descending order.
The proposed project is connected through the collector road 25 m wide connected to the
arterial roads 50 m wide and the proposed capital city roads are designed as per the norms
and can cater to the traffic demand for the design population 4.5 million by 2050 and capital
city roads are under construction with greenery and services along all the roads and
therefore the proposed project will not affect the existing communities and pollution
generated will be attenuated by the proposed greenery on either sides.
38
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 4
Anticipated Environmental Impacts and Mitigation
Measures
4.1 Introduction
The environmental impacts are categorized as primary and secondary. Primary impacts are
those which are attributed directly by the project, secondary impacts are those which are
indirectly induced due to the changed patterns of social and economic activities with the
development of the proposed project.
The environmental impacts due to the proposed “Amaravati Happy Nest” project have been
assessed for the following two phases of the project:
a. Construction Phase
b. Operational Phase
Identified impacts based on the significance have been quantified to assess and formulate a
suitable Environmental Management Plan (EMP).
EMP has been formulated keeping in view the current regulatory standards issued by the
State Pollution Control Board and MoEF&CC.
The emphasis on the EMP development is on mitigation measures for each of the activities
causing the environmental impact and formulating monitoring plans for effective
monitoring.
The following mitigation measures are proposed in order to synchronize the economic
development of the project with the environmental protection.
The impacts during construction phase are mostly short term, restricted to the plot area and
limited to the construction Phase.
In the operational phase the environmental impacts are due to use of DG sets, waste water,
solid waste generation and traffic movement. Hence, the emphasis in the formulation of
EMP is to minimize such impacts.
Following sections describes the environment impacts and management plan proposed for
the project during the construction and operation phases.
39
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
a. Land Environment
b. Air environment
c. Water Environment
d. Noise Environment
e. Solid waste generation
The project involves excavation of about 29,972 Cum earth work excluding top soil and
about 30,920 Cum of earth work would be required within the project for backfilling and
raising the site level. The top soil quantity is about 14,724 cum and will be stored separately
for reuse for greenery development within the project site and along the access roads to the
site.
Mitigation Measures
The construction project site should be barricaded using screens or walls of at least 3m
height.
Regular sprinkling of water preferably STP treated waste water along the roads and
construction areas to minimize the fugitive dust
The construction and demolition debris shall be stored at the site properly and should not
be dumped on the roads or open spaces outside the project area. They should properly
dispose to comply with Construction and Demolition Waste Rules, 2016.
All workers working at the construction site and involved in loading, unloading, carriage of
construction material and construction debris or working in any area with dust pollution
shall be provided with personal protective equipment (PPE).
Safety shall be given utmost importance during the construction phase. All the construction
workers shall be given proper training regarding workplace hazard and usage of site specific
PPE.
40
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Habitat and other welfare requirements for construction workers as per NBC code will be
provided at the site with the following facilities:
Mitigation Measures
The construction project site should be barricaded using screens or walls of at least 3m
height.
The vehicles transporting construction material like sand, cement etc. and construction
debris should be covered properly with tarpaulin sheets.
All the vehicles which are used for transportation of construction material should be
maintained in good condition and regularly certified for the vehicular emission norms.
41
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Regular sprinkling of water along the roads and construction areas to minimize the fugitive
dust
The construction and demolition debris shall be stored at the site properly and should not
be dumped on the roads or open spaces outside the project area. They should be properly
disposed off to comply with Construction and Demolition Waste Rules, 2016.
All workers working at the construction site and involved in loading, unloading, carriage of
construction material and construction debris or working in any area with dust pollution
shall be provided with personal protective equipment.
DG sets at site shall be complied with the emission standards as specified by CPCB shall be
provided during the construction phase. Periodical monitoring of emission and noise levels
shall be undertaken.
Vehicular Movement
The emission from vehicular movement is mainly from the exhaust of Scooters, motorcycles,
cars and buses.
Table 4.1
Typical Stack Details
S.No Details
1 DG set capacity 500 kVA
2 Quantity of fuel (HSD) at 80% load Around 80 lit/hr
3 Sulphur content of HSD 0.005 %
4 Stack height proposed (m) 3 m above the Lift head room
5 Diameter of Stack (m) as per standards
42
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
S.No Details
1 DG set capacity 320 kVA
2 Quantity of fuel (HSD) at 80% load Around 58 lit/hr
3 Sulphur content of HSD 0.005 %
4 Stack height proposed (m) 3 m above the Lift head room
5 Diameter of Stack (m) as per standards
The stack height has been designed as per CPCB formula
Table 4.2
Emission Details
Particular Unit DG Set 500 DG Set 320
kVA kVA
No. of Stacks Nos 8 1
Height of Stack Mtrs 66 66
Diameter of Stack Mtrs 0.75 0.75
Temperature of Flue Gas oC 150 150
Velocity of Flue Gas m/s 20 18
Volumetric Flow Rate Nm3/sec 6.23 5.6
l/hr 80 58
Fuel Requirement each DG Set (@80% load)
Kg/hr 66.4 48.14
Emission from each Stack
Particulate matter at outlet (@ 30 mg/Nm3) g/sec 0.19 0.17
Sulphur Dioxide Emission (@ 0.005%sulphur) g/sec 0.002 0.001
Oxides of Nitrogen g/sec 0.42 0.36
The air pollution modeling carried out represents the worst case operating scenarios. The
pollutants considered for modeling include SO2, NOx and Particulate Matter.
Meteorological Data
The meteorological data recorded continuously during the months of March on hourly basis
on wind speed, wind direction and temperature has been processed to extract the 24–
hourly mean meteorological data as per the guidelines of IMD and MoEF&CC for application
of ISCST3 model. Stability classes computed for the mean hours are based on guidelines
issued by CPCB on modeling. Mixing heights representative of the region have been taken
from the available published literature. The hourly meteorological data recorded at site is
converted to the mean hourly meteorological data as specified by CPCB and the same has
been used in the mode. In absence of site-specific mixing depths, mixing depths published in
“Spatial Distribution of hourly Mixing Depths over Indian Region” by Mr. R.N. Gupta and
recommended by CPCB have been used.
Model Employed
Prediction of cumulative ground level concentration due to emissions from the proposed
project has been computed using EPA approved ISCST3 model.
44
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Calm winds recorded during the study period were also taken into consideration
24 hourly (for 24 – hour mean meteorological data as per guidelines of IMD and
MoEF&CC) mean ground level concentrations were estimated for the summer
season.
The resultants values are compared with National Ambient Air Quality (NAAQ) Standards
issued by Ministry vide G.S.R no. 826 (E) dated November 16, 2009. Figure 4.1 to Figure 4.3
represents the spatial distribution of the predicted ground level concentrations of PM, SO2
and NOx due to emissions from the proposed project.
Table 4.3
Overall Scenarios within the Study Area
24 Hourly Concentrations PM SO2 NOx
(µg/m3) (µg/m3) (µg/m3)
Baseline Scenario (Max) 105.90 16.35 24.58
Predicted Ground Level Concentration (Max) 0.977 0.00982 2.15
Overall Scenario 106.877 16.35982 26.73
NAAQ Standards 100 80 80
Observations
It is observed from the model output that the incremental concentrations for PM10, SO2 and
NOx levels, maximum GLCs were observed to be 1 km in North West direction. It is noted
that after adding the incremental concentrations to maximum baseline values also, the
ambient levels will be within the specified limits. Hence, it can be concluded that, though
there will be an increase in GLC levels, no major significant impact on the air quality due to
the proposed project is envisaged.
45
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 4.1
Ground Level Concentrations of Particulate Matter
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
10000.00 10000.00
8000.00 8000.00
6000.00 6000.00
4000.00 4000.00
2000.00 2000.00
0.00 0.00
-2000.00 -2000.00
-4000.00 -4000.00
-6000.00 -6000.00
-8000.00 -8000.00
-10000.00 -10000.00
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
Figure 4.2
Ground Level Concentrations of SO2
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
10000.00 10000.00
8000.00 8000.00
6000.00 6000.00
4000.00 4000.00
2000.00 2000.00
0.00 0.00
-2000.00 -2000.00
-4000.00 -4000.00
-6000.00 -6000.00
-8000.00 -8000.00
-10000.00 -10000.00
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
46
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 4.3
Ground Level Concentrations of NOx
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
10000.00 10000.00
8000.00 8000.00
6000.00 6000.00
4000.00 4000.00
2000.00 2000.00
0.00 0.00
-2000.00 -2000.00
-4000.00 -4000.00
-6000.00 -6000.00
-8000.00 -8000.00
-10000.00 -10000.00
-10000.00 -6000.00 -2000.00 2000.00 6000.00 10000.00
Mitigation Measures
Diesel generator sets at site shall be complied with the emission standards as specified by
CPCB for catering to 100% standby power.
DG Sets shall be run with High Speed Diesel (HSD) with low sulphur content & mounted
inside DG room with room acoustic as per Central Pollution Control Board norms.
Diesel storage – Bulk oil storage is proposed to cater to the DG sets with 48 hours storage
capacity. Day tank with secondary containment and low / high limit switches shall be
provided for each DG set.
Suitable ventilation shall be arranged on site as per the location of the DG installation. The
users will be encouraged to maintain the vehicles and comply with the vehicular emission
norms.
47
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
work, mortar mixing and curing for plastering, floor finishes, roof works/screed, sprinkling
for dust suppression and domestic use.
Table 4.4
Water Requirement, Treatment and Recycling (KLD)
Flushing/
S. Number of Domestic Total Water
Description Treated
No persons Water Requirement
Water
1 Population 7056 741 317.5 1058.5
2 Filter Backwash - 50 0 50
3 Club House - 2.5 2.5 5
4 Swimming Pool - 18.5 0 18.5
5 Greenbelt
requirement @ - 0 152 152
30336.92Sq.m
TOTAL 7056 812 472 1284
Source: NBC Code, 2016 - Population (Domestic: 105 LPCD, Flushing: 45 LPCD)
The wastewater generation from the project will be around 963 KLD which will be routed to
2 STPs each of capacity 520 KLD located within the site. The treated waste water of about
867 KLD will be recycled for flushing and greenbelt/ landscaping within the site and for dust
suppression measures for the nearby capital city construction works.
48
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Mitigation Measures
The construction workers who are operating the machinery or working near the noise prone
areas will be provided with personal protective equipment like ear muffs and plugs.
Mitigation Measures
The noise due to operation of DG sets will be mitigated as follows:
DG sets at site shall be complied with the emission standards as specified by CPCB
DG set enclosures shall be provided as per the specification of the manufacturer to
comply with the CPCB guidelines
Acoustic dampeners in foundations and isolators for DG sets will be provided to
reduce the vibrations.
Personnel operating DG sets will be provided with ear muffs/plugs.
Noise levels will be checked periodically.
49
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 4.5
Details of Solid Waste
Description Number of Per-capita Waste Organic Inorganic Total
Persons Generation waste in waste in waste in
kg/person/day kg/day kg/day kg/day
Population 7056 0.5 1940 1588 3528
Club House 1350 0.3 223 182 405
Garden waste 7.49 Acres 15 kg/Acre 112 0 112
TOTAL 2275 1770 4045
Source: NBC Code, 2016
Table 4.6
Runoff Calculation
S.No Description Area in Sq.m Rainfall in Runoff Total Runoff
mm/hr Coefficient Cum/hr
1 Roof 10535.62 80 0.9 758.56
2 Unpaved Ground 1739.96 80 0.3 41.75
3 Roads & Pavers 14476.53 80 0.9 1042.31
4 Paved Podium 28596.96 80 0.8 1830.20
Total Runoff 3672.82
4.10 E-Waste
MoEF&CC has notified e –Waste Management Rules vide Notification G.S.R 338(E) Dated
23.03.2016. E-waste is considered as dangerous as certain component of electronic
products contains material that is hazardous.
51
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Table 4.7
Parking Requirement (Cars)
Area Norm as per NBC Area required in Area provided
Sq.m/car (A) (Sq.m) as per NBC in (Sq.m)
Total parking in basement and
32 64000 73955.01
podium
As per NBC, considering the built-up area of the project (2,00,009.33 Sq.m), required parking
area is provided. The master plan of the project provides space for parking at basement and
podium for about 1631 cars and about 1200 two wheelers.
52
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 4.1
Parking Plan – Podium & Basement Level
53
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
ECBC Compliance:
ECBC
S. No. Code Description Code Compliance
Code No
Mandatory Provisions
Energy saving light fixtures – 4FT- LED, DL-
1 7.2.1 Lighting
LED,
Use of 50 w LED - External Lighting spaces
are controlled by Photo Voltaic sensor or
Exterior Lighting
2 7.2.1.4 astronomical time switch that is capable
Control
of automatically turning On / Off the
lights depending on the day light
LED exit signs considered with built in
3 7.2.2 Exit Signs
backup power supplies
Exterior Building High Pressure Sodium Vapour Lights
4 7.2.3
Lights considered with efficiency more than 70%
Prescriptive Interior Lighting Power Compliance
As per ECBC, Building Area method the
Interior Lighting Lighting Power Density (LPD) the required
6 7.3.1
Power w/sqm will be provided in the amenity
blocks.
The parking area LPD level is achieved 1.4
W/Sq.m against recommended level of
3.2 W/Sq.m
Prescriptive Exterior Lighting Power Compliance
Exterior Lighting 1 W/ Sq.ft LPD considered and achieved
7 7.3.5
Power for Building Entrances with canopy
For Building Facades - 0.1 W/Sq.ft LPD
54
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
ECBC
S. No. Code Description Code Compliance
Code No
Considered
Electrical Power
Dry type Transformers meeting the
Transformer requirements as per IS 2026/1180, Part -
8 8.2.1.1
Losses 2 and meeting the requirements as per
ECBC Table 8.2, with Efficiency of 98.4 %
Energy Efficient Efficiency more than 92% and meeting
9 8.2.2
Motors the requirements of Table 8.4
Power Factor
10 8.2.3 Power Factor Improvement upto 0.99
Correction
All the Energy Meters considered In Main
& Sub LT Panels will provide the complete
information regarding Demand Load (in
Check Metering &
11 8.2.4 KVA), Energy Consumption (kWH), Line to
Monitoring
Line & Line to Neutral Voltages, Current
Consumption (Amps), Reactive Power
(kVARh), THD etc.
Cable size selection considering the
Power Distribution Voltage Drop limited to 3% at farthest
12 8.2.5
Losses point and max. distribution losses limited
to 1% of total power usage
Using the energy conservation measures the total energy savings proposed are 2247.5MWH
per year i.e. 56.5% of the total consumption per year.
monitor the electrical services, pumping equipment, water storage and fire alarm system in
order to reduce the running and energy costs and to improve the quality of information on
air conditioning, electrical and other allied systems in the building.
Water flow meters shall be provided in identified areas for monitoring to ascertain the
recycled water consumption for the above said purposes.
56
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Fire Extinguishers
Automatic Fire alarm and detection systems
Two-way talkback system
Signages
Terrace tank system
Fire tender movement path of 8meters shall be provide all-round the building
Refuge area of 15 Sqm or an area equivalent to 0.3 Sqm per person to
accommodate the occupants of two consecutive floors, whichever is higher.
57
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Sprinklers have been designed with sprinkler riser, piping network, sprinkler control valve,
floor control valves, sprinkler alarm valve etc, complete.
Different types of fire extinguishers have different characters and therefore, an appropriate
type of fire extinguisher is required to be used.
a) ABC powder type fire extinguisher of capacity 6 kilograms fitted with gun metal cap, high
pressure carbon- dioxide cartridge, with suitable mounting brackets conforming to IS:
15683:2006 all stair case areas, main switch board room, transformer, generator room, lifts,
parking areas, laundry, engineering and mechanical spaces, kitchen and storage rooms.
b) Carbon dioxide type fire extinguishers of capacity 4.5 kilograms fitted with valve,
discharge horn, conforming to IS: 15683:2006, located in electrical panel room and lift
machine room.
c) AFFF foam type fire extinguishers of 9 lts. Capacity fitted with all accessories shall be
provided at D.G. Rooms and Firewater pump house.
4.14.5 Signage
The descriptive photo luminescent safety signage in different sizes/graphics/colours/texts
can be made according to the standard for the following fire equipment’s/accessories/areas.
Fire hose reel, lifts, fire extinguishers, emergency exits, analogue addressable main fire
alarm panel & sprinkler control valves & MCP’s etc.
Photo luminescent safety signage plays a vital safety role in risk-prone areas and panic
causing situation. When the source of light suddenly goes off, photo luminescent materials
glow settles to a near continuous intensity
58
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Novec 1230 system shall be discharged on all levels (ceiling void, Room proper and below
floor) simultaneously. System will have feature of manual release / abort. Also the status of
the system will be monitored to monitor in the Fire alarm panel
59
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 5
Analysis of Alternatives (Technology & Site)
60
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 6
Environmental Monitoring Programme
Table 6.1
Environmental Monitoring Parameters
S.No Parameters To Be Sub-Description Number Of Sampling
Monitored Locations
1 PM10, PM2.5, SO2, NOx AAQ (As per NAAQ 2009
1*
standards)
2 PM, SO2 and NOx Stack Emissions from DG
1*
sets
3 pH, Electrical conductivity,
Total soluble salts,
Available Nitrogen as N,
Available Phosphorous as
(P2O5), Available Sodium as
Na2O, Available Potassium
Soil Quality 1*
as (K2O), Available Calcium
as Ca, Available
Magnesium as Mg,
Available Chlorides as Cl,
Total Organic carbon, SAR,
Texture of Soil.
pH, Colour, Turbidity, Total
4 Hardness as CaCO3, Iron as
Fe, Chlorides as Cl, 1 *Surface
Dissolved solids, Calcium as
Required parameters for
Ca, Magnesium as Mg,
both Ground and surface As
Copper as Cu, Manganese
per IS 10500 – 2012/IS 2292
as Mn, Sulphate as SO4,
Nitrate as NO3, Fluoride as 1 *Ground
F, Mercury as Hg, Cadmium
as Cd, Selenium as Se,
61
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Greenbelt Development
APCRDA will develop the green belt and will be maintained by the Residents of the Project.
Table 6.2
EMP Budget
S.No Description Capital Cost Recurring Cost
(Rs. in Crores ) (Rs. in Crores )
1 Sewage Treatment Plant (520 KLD ) – 2 No’s 2 0.2
2 Dual Plumbing 7.10 0.71
3 Greenery/Landscaping 13 1.3
4 Storm water drains 0.5 0.05
5 Rain Water Harvesting System 1.8 0.18
6 Solid Waste Management 1 0.1
7 Solar power 1.85 0.18
Total 27.25 2.72
62
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 7
Additional Studies
Over-exertion, ergonomic injuries and illnesses caused due to repetitive motion and
manual handling are among the most common during construction. The proper steps for
their prevention and control include:
a) Policy
The employee’s safety policy includes the following:
Contact their immediate supervisors according to individual department policies.
63
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
a. Obtain the names, addresses, and phone numbers (work and home) of any
witnesses. Interview the witnesses and prepare a report including statements from
the witnesses. The report should include any suggestions to prevent a similar
accident or incident from occurring in the future.
b. Take photographs of the property damage or defect. Enough photos should be taken
to fully describe the damage to a person who has not been at the scene.
c. Prepare a report of the incident with all necessary information. The reports should be
prepared to reflect the seriousness of the incident.
To control communicable and vector-borne diseases attributable in the proposed site are
not potentially serious health threat to project personnel and residents of local
communities. The investigation facilities are available to monitor all the employees for
the occupational health diseases expected due the production activities in the project
premises and also maintaining periodical check-up of our all workers from certified
industrial & occupational health physician. The establishments within the project will
maintain the first aid box with sufficient medicines to face any emergency in the premises.
The working personnel will be given the following personnel protective equipment as
appropriate to their working environment.
Industrial safety helmet
Face shield with replacement acrylic vision
Zero power plain goggles with cut type filters on both ends
Welders equipment for eye and face protection
Ear muffs
Canister gas mask
64
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Emergency action plan will be developed with respect to emergency conditions evaluated,
evacuation policies and procedures, emergency reporting mechanisms, and alarm systems.
Mock exercises will be carried out at least once in a year to train the employees, update the
plan, observe and rectify deficiencies. The plan will cover all types of major
accident/occurrences and identify the risk involved in the industry.
The emergency action plan will include employees in the planning process specifying what
employees should do during an emergency. It will be ensured that employees receive proper
training for emergencies.
After developing the plan, it will be reviewed with employees to make sure everyone knows
what to do before, during, and after an emergency. Emergency action plan will be kept at a
convenient location for access to all employees.
65
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Provision for overhead Fire Water reservoir pumping system and hydrant system will be
provided as per as per NBC 2016 based on height of the building. External hydrants shall be
provided at the street level from the Water supply distribution network as per norms.
66
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 8
Project Benefits
Roads
Integrated Storm Water Management
Water Supply
Municipal Solid Waste
Power Supply
Fire Protection
Building Automation Systems
The project will improve the economic activities in the surroundings as it will be providing
direct and indirect employment to locals based on their skills both during construction and
operational phases. Employees recruited during operational phase will be trained as
required by their respective duties which add to their personal endeavors.
The architecture of the new buildings and landscape development will improve the
aesthetics of the area.
The project will house 1200 families at one place. It is estimated that about 7,056 people
will be residing in the flats. The entire residential housing project has been designed to be
Platinum Rated as per Green Building Norms, thus the entire residential complex would be
energy efficient and environmentally sustainable.
67
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 9
Environmental Cost Benefit Analysis
68
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 10
Environmental Management Plan
Environmental Management Plan of the proposed project has been formulated keeping in
view of current environmental guidelines/standards for building projects formulated by
Ministry of Environmental, Forests and Climate Change (MoEF&CC).
The following management measures are proposed to synchronize the development of the
project with the environmental protection. The construction phase impacts are mostly short
term, restricted to the plot area and not envisaged on the larger scale. In the operation
phase the environmental impacts are due to operation of the project and hence, the
emphasis in the Environment Management Plan (EMP) is to minimize such impacts.
Following sections describe the environment management plan proposed for construction
and operation phases.
70
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
a. Land Environment
b. Water Environment
c. Air environment
d. Noise Environment
e. Solid waste generation
The wastewater generated from the Amaravati Happy Nest will be collected through
network of pipes. The collected wastewater will be routed to the sewage treatment plant
through pipes provided with inspection chambers. Wastewater generation from the project
is about 963 KLD. 2 No. STP’s of 520 KLD capacity comprising the following units is proposed
is shown in Figure 10.1.
The gaps between the bars may vary between 10 and 25 mm. Larger STPs may have two
screens: A coarse bar screen with larger gaps between bars, followed by a fine bar screen
with smaller gaps between bars. In smaller STPs, a single fine bar screen may be adequate. If
this unit is left unattended for long periods of time, it will generate a significant amount of
odor: it will also result in backing of sewage in the incoming pipelines and chambers.
71
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
The equalized and neutralized waste together with return sludge shall be pumped into the
aeration tank.
Settling Tank:
After the biological treatment the clarified water passing through settling tank, where the
sludge will be settled at the bottom and the clear supernatant would overflow into the clear
72
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
water Tank and then hypochlorite solution will be dosed in the clear water tank to kill
pathogenic microorganisms. The sludge will be taken to sludge holding tank. In most STPs,
the common form of Chlorine used is Sodium Hypochlorite (Hypo) available commercially at
10-12 % strength, being safe, easy to handle and having a reasonable shelf life.
The tank is provided with a retention time of 2-3 hours of average hourly flow in the STP.
This unit is essentially a pressure vessel that is filled with graded media (sand and gravel).
The upper layers of the sand perform the actual filtration function. The gravel layers merely
provide physical support to the upper sand layers. The sand used in the PSF is not ordinary
construction sand: It has particle size in a specific range, and is specially sieved for this
purpose.
Here, the filtration occurs along the entire depth of the sand layer. The solid particles in the
water get entrapped and enmeshed in the spaces between the sand particles. Gradually, the
pace between sand particles gets filled with incoming solids. This blocks the passage of
water through the sand layer.
73
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
As a result, the pressure at the outlet drops rapidly sand wastes the pumping power, and
reduces the throughput of the filter. When the pressure drops beyond a limit, the sand is
cleaned by backwashing of the filter (back flushing) with water, in which water is passed in
the reverse direction (from outlet to inlet). This process agitates, fluidizes and expands the
sand bed. The backwash water carries away the lighter pollutant solid particles as backwash
waste.
Pressure sand filter shall be sized based on design filtration rate is 12 m3/ m2/hr of filter
cross-sectional area,
water purification technology used for production of high-purity water. UF is effective in the
removal of colloids, proteins, bacteria, pyrogens. An ultra filtration filter has a pore size
around 0.01 microns.
Ultra filtration is a pressure-driven purification process in which water and low molecular
weight substances permeate a membrane while particles, colloids, and macromolecules are
filtered.
The primary removal mechanism is size exclusion. A properly designed UF cartridge allows
efficient rising of ionic residue from the cleaning and rapidly returns to optimal resistivity
and organic purity. The following benefits
Sludge Removal:
Biological treatment of wastewater produces excess biological solids due to the growth and
multiplication of bacteria and other microorganisms in the system. The excess biomass thus
produced needs to be bled out of the system, and disposed off efficiently. This is a five-step
process: sludge removal, storage, conditioning, dewatering and disposal. Sludge is removed
(“bled”) from the system from the sludge recirculation pipeline (through a branch). The
sludge is in the form of thick slurry. It is taken into a sludge-holding tank and kept under
aeration (to prevent the living organisms from putrefying) until dewatering operations can
be carried out. Before dewatering, polymer or other chemicals may be added for
conditioning the sludge to facilitate the process. Sludge is then dewatered in a centrifuge.
Sludge cake collected and disposed as per norms.
About 472 KLD of treated waste water will be reused for flushing and landscaping and
excess treated waste water will be reused for greenery and landscape development/
maintenance and for dust suppression measures for nearby capital city construction works.
The details of the water balance and wastewater generation are given in Annexure – 7.
75
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Figure 10.1
STP – MBBR Process flow chart
Vehicular movement
The emission from vehicular movement is mainly from the exhaust of two and four
wheelers. However, all the vehicles will undergo pollution check to control vehicular
emission. The regular maintenance of vehicles will be done
76
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
DG sets will be operated only during emergency and are not in continuous
operation.
CPCB approved DG sets conforming to noise and emission standard will be
provided.
Stacks of adequate height will be provided as per applicable norms.
Rooftop rain water harvesting is the technique through which rain water is
captured from the roof catchments and stored in reservoirs.
Usually the storm water that initially runs off an area will be more polluted than the
storm water that runs off later, after the rainfall has 'cleansed' the catchment. The
storm water containing this high initial pollutant load is called the 'first flush'.
This polluted first flush will be discharging out to external storm water drain.
Roof rain water from terrace is being diverted to roof rain water collection sumps &
used for domestic purposes after necessary treatment.
Figure 10.2
Rain water Harvesting Pit
77
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
The details of the solid waste generation calculation are given in Annexure – 8.
ii. Power factor of the complete electrical system shall be maintained close to
unity. This will reduce electrical power distribution losses in the installation.
iii. Energy Efficient V3F lifts
iv. Higher efficient UPS shall be used (95%)
v. Variable speed drives, wherever possible.
vi. All ceiling fans shall be minimum BEE 3 star rated
vii. Timers and Photo-electric sensors shall be used to switch ON/OFF lights used
for landscaping
viii. Providing LED lights everywhere as a part of conservation.
ix. 52% of the external lighting load will be met from the solar
x. For the 12 blocks a total of 360 KW roof top solar plant is planned.
Provision for overhead fire water reservoir pumping system and hydrant system will be
provided as per as per NBC 2016 based on height of the building. External hydrants shall be
provided at the street level from the water supply distribution network as per norms.
It is to confirm that in any of the above mentioned suppression systems, it is NOT intended
to use HALON based agents. However most of the cases WATER is used as base medium for
79
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
suppression and in special case like electrical panels, computer server room, it is proposed
to use gas suppression system, where medium of suppression is FM 200 gas or NOVEC gas,
the chemical composition of gases are “Hepta Fluro Propane (HFC-227ea) or Fluro Keton”.
This is designed per NFPA 2000 standards.
Also portable fire extinguishers are intended to be used per IS 15683 standards, majorly
using ABC type extinguishers of different size/ capacity based on requirement.
80
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Environmental Cell
81
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
82
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 11
Summary & Conclusion
The APCRDA is intended to take up the Amaravati Happy Nest housing project with 12
towers with each tower of G+18 floors + terrace floor and 2 amenity blocks with each block
of G+3 floors+ terrace floor is planned in the Nelapadu Village of the Thullur Mandal,
Amaravati.
The proposed project is located in west of Amaravati Government Complex area and is
accessible with capital city roads which are under construction.
The city is planned with underground systems like sewers, water supply, storm water,
communications lines, electricity lines, reuse lines. The roads are developed with foot paths
and bicycle tracks with greenery. The development of the underground systems and
greenery are already tendered out and works have been initiated. The proposed project will
be connected to the city services stated above to avoid any environment pollution and for
healthy living.
The proposed project will be developed with state of art amenities like swimming pool,
badminton courts, squash courts, pool board, restaurants, spa, saloon, sauna, community
hall, grocery store, library etc
The proposed project is provided with adequate parking spaces for the four wheelers and
two wheelers both for the resident and visitors.
The proposed project is planned with all environment management facilities like STPs, waste
composting facility, storm water drains, rain water harvesting, greenery development etc.
The proposed project is developed as per the IGBC norms, ECBC norms to conserve the
energy and roof top solar plant is proposed.
The greenery development will be done with native plant species and the greenery spaces
will be developed to enhance community interactions. For the development and
maintenance of the greenery treated waste water from the STP will be used.
83
Amaravati Happy Nest Project, Amaravati Capital City, Andhra Pradesh
Chapter 12
Disclosure of Consultant
12.1 Introduction
The consultant engaged for the preparation of the EIA/EMP of the project is M/s Sri Sai
Manasa Nature Tech Pvt. Ltd. Realizing the need for multi-disciplinary and pragmatic
approach To environment management, a few dedicated experience started M/s Sri Sai
Manasa Nature Tech Pvt. Ltd. company as a consultancy organization in 2006 registered as
company and ISO 9001:2008 Certified Company and accreditation by NABET. Our team
consists of specialists in environmental consulting, regulatory compliance and review, site
investigation, emergency response, environmental laboratory, site assessment, and data
usability-related experience. These individuals have worked together on similar projects,
and the leaders have been commended by their clients for accomplishment on other
successful projects.
M/s Sri Sai Manasa Nature Tech Pvt. Ltd. has its own Environmental laboratory with a
name of KIWIS Eco Laboratory at Pragathi Nagar Hyderabad under EPA (Environmental
Protection Act) from the MoEF&CC, Govt. of India, New Delhi and by National Accreditation
Board for testing and Calibration Laboratories (NABL). The list of the project team has been
summarized below:
--------------
85