Professional Documents
Culture Documents
Practicum Report On Substation Operation and Maintenance of (33/11 KV) Substation Narsingdi Palli Biddyut Samity-2
Practicum Report On Substation Operation and Maintenance of (33/11 KV) Substation Narsingdi Palli Biddyut Samity-2
Practicum Report On Substation Operation and Maintenance of (33/11 KV) Substation Narsingdi Palli Biddyut Samity-2
on
Substation operation and maintenance of (33/11
kv)substation Narsingdi Palli Biddyut Samity-2
19thDecember, 2019
Dr. Bishwajit Saha
Professor and Coordinator
Department of Electrical and Electronic Engineering
IUBAT ̶ International University of Business Agriculture and Technology
4 Embankment Drive Road, Sector-10, Uttara Model Town
Uttara, Dhaka-1230
Dear Sir,
It is a great pleasure for me to submit the practicum report onSubstation operation and
maintenance of Narsingdi Palli Biddyut Samity-2. According to your requirement, I
have worked on the sector of distribution of power in Narsingdi Palli Biddyut Samity-
2. It was a challenging work because REB is a giant electrical supplier in our country.
I learnt about the distribution substation. Specially, I was trained in switchgear, CT,
PT relay and power transformer.
I express my gratitude to you to go through this report and make your valuable
comments.
Yours sincerely
---------------------
Yours sincerely
---------------------
Md. Nahidul Islam Naim
ID# 13105044
Program: BSEEE
Executive Summary
As technology is advancing the consumptions of power is steadily rising. There are
three steps for proper electrification. These are:
1. Electric Power generation.
2. Electric Power Transmission.
3. Electric Power Distribution
This report is defining the operation and maintenance at Narsingdi Pally Biddyut
Samity-2. This report Elaborately discusses about the operation and their maintenance
that are used in Narsingdi PBS-2. At Narsingdi Pally Biddyut Samity-2 I have
learned how to transformer convert high voltage to low voltage, low voltage to high
and also, I learned about how to test transformer. Then I learned about how to power
transformer works in substation and in Narsingdi pally Biddyut Samity-2 they have
two 3 phase transformers and one single phase transformer and this power
transformer convert 33kV to 11kV. Here I learned about automatic voltage regulator
(AVR) range upto ±10% from the AVR 11kV line pass to bus bar and bas bar send it
to feeders and from the feeders’ line it passes to current transformer and potential
transformer. I have collected practical knowledges about isolator, circuit breaker, air
breaker switch, automatic voltage regulator, auto circuit recloser, maintenance and
workshop etc. From my academic courses I learnt about these things theoretically,
which I saw and learned practically in my internship period. This report is prepared in
according to the operation and maintenance procedure of 33/11KV Sub-Station,
including emergency maintenance work.
Acknowledgement
In the process of doing and preparing my practicum report, I would like to pay my
gratitude and respect to some persons for their vast co-operation. First of all, I am
very much grateful to Dr. Bishwajit Saha, professor and coordinator of department of
electrical and electronic engineering who gave me the opportunity to do the
report.Also, I would like to give thanks to my practicum supervisor Dr. Bishwajit
Saha, professor and coordinator, who helps me to do my report properly.
After that I would like to express my special gratitude Md. Eusuf, general manager of
Narsingdy Palli Biddyut Samity-2, who helped me a lot by his brilliant guidelines to
make this report, without which it was not possible to conduct it. I would also like to
thank all the faculty members of IUBAT and for their critical advice and guidance.
Abbreviation………………………………………………………………………….58
List of Figures
Contents………………………………………………………………………..…..Page
List of Graph
Contents………………………………………………………………………..…..Page
Graph 3.1: Peak and off peak bar chart of Substation Chowala-1(25,August 2019)
……………………………………………………………………………….41
Graph 3.2: Peak and off peak bar chart of Substation Chowala-1(26,August 2019)
……………………………………………………………………………….42
Graph 3.3: Peak and off peak bar chart of Substation Chowala-1(27,August 2019)
……………………………………………………………………………….43
Chapter 1
Introduction
1.1 Origin of the report
This report on topic name is “Operation and Maintenance of Narsingdi Palli Biddyut
Samity-2” is prepared by Md. Nahidul Islam Naim for the Bachelor of Science in
Electrical & Electronics Engineering program at the department of Electrical &
Electronics Engineering, under IUBAT-International University of Business
Agriculture and Technology as an integral part of the internship. He has done this
practicum report based on power distribution, operation and maintenance at Narsingdi
Palli Biddyut Samity-2 under the instruction of (AGM) Md. Lutfor Rahman, Junior
Engineer (Technical) in Narsingdi Palli Biddyut Samity-2.
1.2 Objectives
The main objective of this report is to fulfill the academic requirements of EEN-490
course of the undergraduate program of International University of Business
Agriculture and Technology. Some other objectives are:
1.4 Methodology
The paper was checked by the authorized person of the Narsingdi Palli Biddyut
Samity-2 during preparation. The data was chosen accurately throughout the entire
period of the session. Although there were several sources but some of them are
mentioned here as the references. The information of this report has been collected
from the following sources:
1.5 Limitations
During practicum inNarsingdi Palli Biddyut Samity-2, a huge amount of information
has been accumulated from the company. The employees were very much
cooperative. They helped me a lot, thus it was very much easy to understand most of
the technical terms. But as it is a commercial organization, sometimes the employees
were busy with their official work. Therefore at all time it was not convenient to
communicate with them because of their hard work. Yet they tried to help me as much
as possible by them.
Chapter 2
Company Overview
2.1 Introduction
Bangladesh Power Development Board (BPDB) is the mother association in electric
power division. BPDB manage all organization in electric power sector. There are a
few organizations in electric power generation and distribution sector however in
transmission sector Power Grid Company of Bangladesh Ltd (PGCB) is the main
company in Bangladesh and Rural Electrification Board (REB) including Palli
Biddyut Samity (PBS) is one of the biggest distributer around this country.
2.3 Mission
Their mission is to provide electricity for all by the year 2020. There new slogan for
this mission is, “Sheikh Hasina's initiative, electricity in every house”.
2.4 Vision
Quality and uninterruptible power supply.
2.5 Activities of Narsingdi Palli Biddyut Samity-2
Every Forth month later in different area they arrange a meeting for awareness of use
of electricity. How they save the electricity. How reduce the load shedding. They not
only arrange the meeting for electricity but also they call the meeting in different
social work.Narsingdi Palli Biddyut Samity-2 is situated in Choyala, Norsingdi. It is
Organogram of NPBS-2
08.
Norsingdi
4 Included Upazila shador,Shibpur,Monohordi,Belab,Raipura,
Voirob the district of
Kisorgonj,Kuliarchor,Bajitpur.
7 No. of Union 87
8 No. of Municipality 07
06(Zonal
14 Zonal Office shador,Shibpur,Monohordi,Morjal,Raipura,
Kuliarchor.)
15 Complain Center 17
16 Substation Capacity 110 MVA
Narsingdi PBS-2 has some substation which helps to distribute the power to the
consumers. We visit Chowala -1 33/11KV(35MVA) substation. It was situated at 14-
04-1990. It has 4 sections. In first time it has single line sections. After sometime its
demands was increased. Then the substation size was increased.
Sub-station operation
3.1 Sub-stations
The majority of the sub-stations in the power system are concerned with the changing
of voltage level of electric supply. These are known as transformer sub-stations
because transformer is the main component employed to change the voltage level.
Depending upon the purpose served, transformer sub-stations may be classified into –
1) Step-up sub-station
2) Grid sub-station
3) Secondary sub-station
4) Distribution sub-station
From the step-up substation, electric power at 400KV, 220KV or 132KV etc. is
transmitted by 3-phase. 3 wire overhead system to the outskirts of the city. Here
electric power is received by the primary grid substation which reduces the voltage
level to 66KVor 33 KV or any another type for secondary transmission. Generally
grid substation is of outdoor type.
Bus-bars.
Air break switch.
Lightning arrester.
Insulators.
Isolators.
Instrument transformers.
Automatic circuit recloser (ACR).
Power transformers.
Automatic voltage regulator.
Power Fuses.
Metallic fence.
Feeder
Metering
3.3.1 Bus-bars
Generally, bus-bars are seen on the incoming and outgoing lines of a substation that
operate at the same voltage. For Chowala-1 substation, bus-bars are inserted for 11
kV outgoing lines.