Professional Documents
Culture Documents
Tributary Loadings Computation
Tributary Loadings Computation
Tributary Loadings Computation
SOLUTION:
1 Check if the system is one – way or two – way:
Longer (b)/shorter (a) = 5/2 = 2.5 > 2 (it’s a one way system, loads are distributed in one direction only.)
A 1m B 1m C
2 Sketching tributary area for beam BE:
Since it’s a one – way system, Beam BE will directly carry half of
slab ABEF and half of slab BCDE. Thus, the tributary area
supported by beam BE is as shown:
5m
F E D
2m 2m
A 1m B 1m C
3 Solving for loads (per unit length) acting on beam BE:
o for dead load (WDL):
Referring to table 1.2 from our previous lesson:
Reinforced stone concrete (unit weight) = 23.6 kN/m3
5m WDL = unit weigh (ϒ ) x thickness of slab (t) x width of tributary area (w)
WDL = (23.6kN/m3) (0.20m) (2.0m)
WDL = 9.44 kN/m
B E
5m
RB = 35.5kN RE = 35.5kN
35.5kN
***Note B
To draw the tributary area of a two – way slab: 1.5m 1.5m
A B C
1) Draw lines parallel to the beam at midspan
(like beam BE), dividing the slabs into two 4m
equal parts ( like beam BE as shown).
2) Draw diagonals bisecting (so, the angle would
4m
be 45o) the vertices of the slabs.
3) Then the area inside the intersecting lines (lines
mentioned above) will be the tributary area.
E F E D
3m 3m
B 1.5m
A 1.5m C
45o 3 Solving for loads (per unit length) acting on beam BE:
1.5m o for dead load (WDL):
Referring to table 1.2 from our previous lesson:
4m Reinforced stone concrete (unit weight) = 23.6 kN/m3
WDL = unit weigh (ϒ ) x thickness of slab (t) x width of tributary area (w)
4m
WDL = (23.6kN/m3) (0.20m) (3.0m)
WDL = 14.16 kN/m
1m
21.36kN/m
5 Solving for reactions at B and E:
B E Since the load is rectangle (symmetrical), reactions at B and
E are equal (RB = RE), the load will be divided equally
4m between them.
Σ fy = 0
RB *** to find the resultant load: RE RB + RE - (1/2)[(1+4)m] (21.36kN/m)= 0
Total load = area of trapezoid 2RE = 53.40 kN
RE = 26.70 kN
(You can also use summation of moments)
1.5m 1.5m
A B C
6 Solving for loading acting on beam FED:
Since the slab acts on two – way action, beam FED will
also directly carry the slab, the tributary area of loads
that will act on the beam will be as shown: 4m
1.5m
F E D
3m 3m
7 Solving for loads (per unit length) acting on beam FED:
TRIBUTARY LOADING o For dead load (WDL)
Referring to table 1.2 from our previous lesson:
1.5m 1.5m Reinforced stone concrete (unit weight) = 23.6 kN/m3
A B C WDL = unit weigh (ϒ ) x thickness of slab (t) x width of tributary area (w)
WDL = (23.6kN/m3) (0.20m) (1.50m)
WDL = 7.08kN/m
4m
o For live load (WLL):
Referring to table 1.4 from our previous lesson:
1.5m
Office Buildings (Offices) = 2.4 kN/m2
F E D WLL = unit weigh (ϒ ) x width of tributary area (w)
3m 3m
WDL = (2.4kN/m2) (1.50m)
WLL = 3.60 kN/m
Total load per unit length : 7.08 + 3.60
Total load per unit length : 10.68 kN/m
(peak load)
26.70kN
10.68kN/m 10.68kN/m
8 We can now sketch the loadings on beam FED:
Beam FED will also directly carry the slab and will suffer a
F D
concentrated load on its center / midspan caused by beam E
BE (equal to magnitude of RE but opposite direction) at the
same time. 3m 3m
6m
RF RD
Sketch required by the problem:
For beam BE:
1m
21.36kN/m
B E
4m
RB =26.70kN RE = 26.70kN