Wa’ MITSUBISHI ELECTRIC CORPORATION PROJECT : MEW PREVENTIVE MAINTENANCE DATE SUBSTATION: MINA ABDULLA ‘C’ 432/14kV ‘TEST REPORT No : AIRCON ‘TEST REPORT FOR AIR CONDITIONING SYSTEM Location Make Unit No. Mode! | Serial No. Status Control Room York ‘AIC UnitNo.1 | ss240-6e | 10060m | OM faulty Office Room Dunham Bush | SpitUnit No.2 : = ok Store Room Dunham Bush | Split UnitNo. 3 c : ok savestey Craver | pan | soaunenea |mumani| | Networng ee Dakin | split Unit No.5 | RUSKATY 7 Not working 220 Battery Charger Room g Split Unit No.6 | RU3KATY1 - OK Clean all filters ( washing with water jet ) Remove side covers and clean all units Tighten all connections Check the evaporator fan belt (Where Applicable) Replace if necessary Check gas pressure Top up if needed Check for gas leak Clean the Control Panel Tighten all connections Clean all contacts Clean Isolator Panel Clean Contacts Tighten Connections Comments:- MELCO ENGINEER: ome MEW ENGINEER: se? ¢