Professional Documents
Culture Documents
Costs and Resources - Informatics Project Management
Costs and Resources - Informatics Project Management
Estimate Costs
Steps :
Estimate Costs
Why to estimate ?
Estimate Costs
Estimate Costs
activity
i.j.n
The costs are estimated bottom-up
Labour cost
based on activities
Material Cost
…
Project Management
PHASE 1 – 15.000 PHASE 2 – 30.000 PHASE n – 40.000
– 5.000
WP 2.n – 10.000
Develop Budget
Develop Budget
Resource Name Type Material Label Initials Group Max. Units Std. Rate
Team Leader Work TL 100% 300,00 €/day
Consultant 1 Work C1 100% 150,00 €/day
Consultant 2 Work C2 100% 200,00 €/day
50%
ID Task Name Duration Total Cost 15 Oct '12 22 Oct '12 29 Oct '12 05 Nov '12 12 Nov '12
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 WP A 10 days 3.800,00 €
2 ACT 1 4 days 1.200,00 € Team Leader[50%];Consultant 1
3 ACT 2 2 days 600,00 € Team Leader[50%];Consultant 1
4 ACT 3 6 days 1.200,00 € Team Leader[50%];Consultant 2
5 ACT 4 4 days 800,00 € Team Leader[50%];Consultant 2
6 MA 0 days 0,00 € 01-11
Resources Allocation
• Resources – detailed activities assignment
• Assignments 100%; 50%; 20%
Pedro
Histogram
Assign Manuel
Activities to Pedro
Resource Levelling
Nivelar Recursos
Optimized
Pedro
Assignments
Resources Allocation
Transversal :
• Project management
• Infra-structures
• All needed to support the execution resources
PM Costs
PM Costs
• Subcontracts cost
– Base on a daily tax (represent as a normal team resource)
– Fixed price (the costs will be input using project milestones,
according to payment conditions)
• Materials, Equipments, …
WP A 10 days 13.800,00 €
ACT 1 4 days 1.200,00 €
50% MA
ACT 2 2 days 600,00 € 50% MB
ACT 3 6 days 1.200,00 €
ACT 4 4 days 800,00 €
MA 0 days 10.000,00 €
WP B 12 days 10.000,00 €
B1 5 days 0,00 €
B2 5 days 0,00 €
B3 2 days 0,00 €
MB 0 days 10.000,00 €
Accumulative costs
Balancing Costs
Develop Budget
Cash Flow
Travel expenses 0€
Products 20 000 € 20 000 €
Subcontracts
Kms 0,36 € 0€ 0,00 € 0€ 0€ 0€ 600 216 €
Ajuda Custo 62,75 € 0€ 0,00 € 0€ 0€ 0€ 0€ 0€
20 000 €
Costs 136 216 € 27 000 € 23 000 € 23 000 € 23 000 € 23 000 € 17 216 €
Cash Flow 1 000 € -22 000 € -3 000 € -26 000 € -49 000 € 3 784 € 140 000 €