MODULE 8 Learning Activity 1-8

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

TOPIC 1: INTRODUCTION PROCESS COSTING SYSTEMS - OVERVIEW OF THE PROCESS

COSTING
Learning Activity 8-1
1. Process costing is used in a manufacturing process of a single product on a Continuing basis
2. In process costing manufacturing costs is accumulated in each Processing Department until
completed and transferred to finished goods

TOPIC 2: NATURE AND CHARACTERISTICS OF PROCESS COSTING


Learning Activity 8-2
1. What are the characteristics of process costing?

2. List at least two (2) similarities of Job Order Costing and Process Costing?
a.
3. The nature of a product under Job Order Costing is each job is different and Process Costing is all
products are identical

TOPIC 3: PRODUCT FLOW IN PROCESS COSTING


Learning Activity 8-3
1. What are the three (3) product flow in process costing?
a. Sequential Product Flow
b. Parallel Product Flow
c. Selective Product Flow
2. Sequential Product Flow This product flow occurs when each manufactured product undergoes the
same set of operations
3. Parallel Product Flow This product flow occurs when processes are done simultaneously and then
brought together to the final process for completion
4. Selective Product Flow This product flow occurs when a product is transferred from the initial
processing department to different departments within the plant depending on the desired final product

TOPIC 4: METHODS OF PROCESS COSTING: FIRST-IN, FIRST-OUT METHOD AND AVERAGE


METHOD
Learning Activity 8-4
1. FIFO Method This is the method of process costing that assumes units that were first place into
process are the first units to be completed
2. Average Method This is the method of process costing that assumes that all units completed are all
processed at the same time?

TOPIC 5: EQUIVALENT PRODUCTION 


Learning Activity 8-5
1. What is the concept of equivalent production as used in the process costing system?
- Partially completed units are converted equivalent to fully completed units for purpose of
assigning costs
2. Equivalent production of an ending inventory of 100 units 50% completed is 50 units.

TOPIC 6. COST OF PRODUCTION REPORT


Learning Activity 8-6
1. What is the Cost of Production Report?
- It is the report used in process costing that shows the costs incurred by a given department
during the period
2. List the information shown in the Cost of Production Report.
a. Total unit costs from preceding department
b. Materials, Labor, and Overhead added by the department during the current period
c. Unit cost added by the department
d. Total and unit cost accumulated by the department to the end of operations
e. The cost of the beginning and ending work in process inventories
f. The total costs transferred to the succeeding processing department of finished goods

TOPIC 7. RECORDING OF MANUFACTURING COSTS


Learning Activity 8-7
1. What are the entries to record the assignment of manufacturing costs to departments?
Work in Process- Department xxx
Raw Materials xxx
Payroll xxx
Applied Factory Overhead xxx
2. What are the entries for the transfer of cost to a succeeding department assuming the whole process
was composed of three (3) departments?

3. What is the entry for the transfer of finished goods from the final department?

TOPIC 8. APPLICATION OF COST ELEMENTS TO PRODUCTION


Learning Activity 8-8
1. What are the two (2) kinds of application of cost elements to production?
a. Even Application of Cost Element
b. Uneven Application od Cost Element
2. Even Application of Cost Element This method considers that all cost elements are added uniformly
or proportionately at any stage during the production process
3. Uneven Application of Cost Element This method considers that each cost element incurred during
production varies at any stage

TOPIC 9: COMPREHENSIVE ILLUSTRATION – PROCESS COSTING 


Learning Activity 8-9
1. How to determine equivalent production when cost elements are applied evenly?
- It is determined by multiplying all cost element by the percentage of work done
2. Cost of production report has two parts. The 1st part is the Quantity Schedule that accounts for the
units in the production and the 2nd part is the Cost Analysis that accounts for the cost of the units in
the production
3. Cost of the completed units from department A when transferred to department B is debited to Work
in Process Department- B and credited to Work in Process- Department A

You might also like