Indwell Constructions Private Limited Bhel/Nttps/U#8/Vijayawada Erection Programme For The Month of October'18

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

INDWELL CONSTRUCTIONS PRIVATE LIMITED

BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

SL. NO. DESCRIPTION UNIT#1 REMARKS


1 STRUCTURE 201.000
2 PRESSURE PARTS 867.000
3 NON PRESSURE PARTS 248.000
4 APH 0.000
5 ROTARY PARTS 139.000
GRAND TOTAL 1455.00

LIFT STRUCTURE BACK FILLING IS REQ. IMMEDIATELY FOR WINCH OPERATION


1
PURPOSE.
2 ROADS REQ. FOR MATERIAL MOVEMENT.
3 BALANCE PRESSURE PARTS AND DUCT MATERIAL REQUIRED IMMEDIATELY.
4 APH LUBE OIL SKIDS REQ. IMMEDIATELY
INDWELL CONSTRUCTIONS PRIVATE LIMITED
BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

WEIGHT
SL. NO. PGMA DESCRIPTION REMARKS
IN MT
1 36-110 BOILER MIDDLE COLUMNS 30.000
2 35-441 2.000
3 35-442 2.000
4 35-443 5.000
5 35-444 2.000
6 36 GROUP ALL PLATFORMS 140.000
7 38-510 10.000
8 38-710 10.000

201.000

TOTAL 201.000
INDWELL CONSTRUCTIONS PRIVATE LIMITED
BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

WEIGHT
SL. NO. PGMA DESCRIPTION REMARKS
IN MT
NON PRESSURE PARTS
CRANE MOVEMENT REQ.
1 20-051 SOOT BLOWERS 35.000 FOR RHS
2 48-012 FD DISCHARGE DUCT 8.000 PG 39 STRUCTURE REQ.
3 48-142 TEMPERING DUCT 15.000
4 48-222 HOT PRIMARY DUCT 14.000
5 48-112 PA DISCHARGE DUCT 5.000 PG 39 STRUCTURE REQ.
6 48-384 EXPANSION JOINTS FOR FLUE GAS DUCT 6.000 MATERIAL REQ.
FLUE GAS DUCT FROM ECO HOPPER TO
7 48-388 APH 75.000 MATERIAL REQ.
8 48-432 APH O/L TO BOF DUCT 20.000
9 48-434 EXPANSION BELLOWS 4.000
AREA REQ. FOR HYDRA
10 48-662 MILL DUCT 20.000 MOVEMENT
11 48-664 3.000
12 57-010 FD DISCHARGE GATE 13.000 PG 39 STRUCTURE REQ.
13 57-110 PA DISCHARGE GATE 10.000 PG 39 STRUCTURE REQ.
AREA REQ. FOR HYDRA
14 57-270 GATES FOR MILL DUCT 5.000 MOVEMENT
AREA REQ. FOR HYDRA
15 57-273 DAMPERS FOR MILL DUCT 1.000 MOVEMENT
16 45-801 SOFA ATTACHMENT 1.000
17 45-804 WIND BOX FOR SOFA 6.000
18 42-010 HSD PUMP SET 3.000 MATERIAL REQ.
19 42-020 HFO PUMP SET 4.000 MATERIAL REQ.
26 42-030 HEATER ASSEMBLY 15.000 MATERIAL REQ.
27 42-065 DRAIN OIL TANK 3.000 DE-WATERING REQ.

248.000

TOTAL 248.000
INDWELL CONSTRUCTIONS PRIVATE LIMITED
BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

WEIGHT
SL. NO. PGMA DESCRIPTION REMARKS
IN MT
PPARTS
1 05-350 FURNACE INTERMEDIATE RIGHT HEADER 11.000
2 06-753 FURNACE UPPER SIDE SPIRAL PANELS 55.000
3 06-755 FURNACE LOWER SIDE SPIRAL PANELS 17.000
4 06-453 SIDE TENSION BARS 4.000
5 06-455 SIDE TENSION BARS 2.000
6 06-500 SOFA PANEL 2.000
7 07-231 FURNACE VERTICAL LOOSE TUBES 2.000
8 08-006 MIDDLE BUCK STAYS 15.000
9 08-606 MIDDLE BUCK STAYS 20.000
10 08-007 FURNACE LOWER BUCK STAYS 10.000
11 08-501 II PASS REAR BUCK STAYS 40.000
12 11-991 FIRST PASS ROOF LOOSE TUBES 5.000 MATERIAL REQ.
13 15-136 LTRH INLET HEADER 11.000
14 16-202 LTRH INTERMEDIATE COILS 215.000
15 16-203 LTRH LOWER COILS 300.000
16 17-903 RH MISC COMPONENTS 40.000
17 19-753 ECO JUNCTION HEADER 12.000
18 19-763 ECO JUNCTION HEADER 12.000
19 19-783 ECO JUNCTION HEADER 12.000
20 19-793 ECO JUNCTION HEADER 12.000
21 19-802 ECO LOWER HANGER TUBES 5.000
22 19-851 ECO LINKS 45.000
23 24-811 LINK PIPE 20.000

867.000

TOTAL 867.000
INDWELL CONSTRUCTIONS PRIVATE LIMITED
BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

WEIGHT
SL. NO. PGMA DESCRIPTION REMARKS
IN MT
AIR PRE HEATER
1 0.000

0.000

TOTAL 0.000
INDWELL CONSTRUCTIONS PRIVATE LIMITED
BHEL/NTTPS/U#8/VIJAYAWADA
ERECTION PROGRAMME FOR THE MONTH OF OCTOBER'18

WEIGHT
SL. NO. PGMA DESCRIPTION REMARKS
IN MT
ROTARY PARTS
1 61-001 JOURNAL SHAFT ASSY 18.000
2 61-002 JOURNAL HEAD 6.000
3 61-308 JOURNAL SPRING ASSY 7.000
4 61-311 ROTOR SUPPORT ASSY 5.000
5 61-314 DRIVE ASSY 4.000
6 55-227 ID FAN ROTOR 14.000
7 ID FAN-B MOTOR 30.000
8 55-911 FD FAN SILENCER 30.000
9 55-931 PA FAN ASSY 25.000

139.000

TOTAL 139.000