Status Report For June 2020
Status Report For June 2020
Status Report For June 2020
Dates
Notification of Award 12th October 2018
Letter of Acceptance Issued 5th December 2018
Contract Signing Date 13th December 2018
Commencement Date 9th May 2018
Contractor’s Mobilization Period 4 months
Original Contract Period 36 Months (1095 Cal Days including mobilization
period)
Maintenance Period 24 Months from the issue of the Taking Over
Certificate
Contract Completion Date 9th May 2022
Approved Extended Calendar None
Days
Time Elapsed to date 418 Cal. Days (38.17%)
Financial Data
Currency Local
Contract Amount including VAT 2,114,048,067.84
Liquidated Damages 0.1% of the Contract price per day (if no completed
section handed over to Employer)
0.1% of the value of the remaining works per day (if
there is completed section handed over to Employer)
Limit of liquidated Damages 10% of the Contract price or 10% of value of the
remaining works
Advance Payments (20%) Birr 422,809,613.57
Advance payment Issued So far Net payment
clause 18.2
Expiry date of CAR Insurance Bond Not submitted (Under comment)
Professional Indemnity Insurance, as per
Sub Clause 18.1 Not Submitted
Dates (Supervision)
Notification of Award
Contract Signing Date 24th April 2019
Commencement Date 8th May 2019
Contract Period 36 months plus 24 months of DLP
Type of Contract Time base
This Monthly progress Report No.09 for the month of June 2020 covers the work progress of the
Contractor and the tasks performed by the Employer’s Representative for the period from
June 01 to June 30, 2020.
So far, 410 calendar days (i.e. 38.17% of the Contract period) has been elapsed and the
estimated to date accomplishment is 4.95% of the total work load. This is equivalent
to a weighted average of 3.71 km.
During the reporting period, the month of June 2020, the Contractor’s actual
estimated accomplishment is 0.64% (or 0.48km) of the Contract amount; for the
quarter from April to June 2020, the Contractor’s accomplishment is 1.03% (or
0.77km) of the Contract amount and for the year from July to June 2020, the
Contractor’s annual accomplishment is 4.95% (or 3.71km) of the Contract amount
According to the Agreed Action Plan for 2012 EFY, the Contractor has planned to
execute 2.40% for the month, 8.77% for the quarter and 30.47% of the work load for
the Year. The equivalent length of the plan is 1.8km for the month, 6.57km for the
quarter and 22.85km of the work load for the Year.
The following table shows the financial and physical progress of the works up to the
end of the reporting period:
Table: 1.2:- Financial and Physical progress (for the month, this FYS and to date)
Previous Year Up to Previous Month This Month Cumulative for this Fy To date
Description ETB in ETB in ETB in ETB in
%age '000,000 %age '000,000 %age '000,000 %age ETB in '000,000 %age '000,000
plan 0.00 0.00 28.06 260.28 2.40 53.75 8.77 314.03 30.47 109.04
Actual 0.00 0.00 4.31 48.65 0.64 10.67 1.03 59.33 4.95 9.65
Actual Vs plan 0.00% 15.36% 26.67% 11.75% 16.25%
Note: -
1. The Current and To-date plan is taken from the Agreed Action Plan for 2012 EFY
2. Rating of the financial progress is based on the Lump sum amount of 1,838,302,667.69 (Excluding of 15% VAT) for the entire project
length (approx. 75.00km).
To the end of this reporting period, the overall accomplishment of the project is 4.95%
(3.71km) while the to date planned work as per Agreed Action Plan for 2012 EFY is 30.47 %
(22.85km) and the time elapsed to date is 38.71 % (418 calendar days).
The actual to date accomplishment shows that the accomplishment is about 16.25% from the
Agreed Action Plan for 2012 EFY and it shows the accomplishment is much less with respect
to time elapsed; which is 30.47% of time elapsed to date and this shows that the
accomplishment is lagging from time.
This New fiscal year’s progress is also 4.95% (3.71 km) (from July 2019 up to end of this
reporting period), against the plan of 30.47 % (22.85 km).
In addition, the reporting period monthly progress is 0.64% (0.48km) against a plan of 2.40%
(1.80km) which is 26.67% of the monthly plan as well as 1.03% (0.77km) against a plan of 8.77%
(6.57km) which is 11.75% of the quarterly plan which is much behind the schedule.
Table 1.4: Major Work Items (bill group) of the Works Contract accomplishment with respect to
the submitted Agreed Action Plan for 2012 EFY
Previous This Month This Quarter To date
Item
Description of Works unit accomplishments accomplishment accomplishment accomplishment
No.
P A P A P A P A
Surveying, Investigation 2.00 0.78 0.00 0.03 0.00 0.07 2.00 0.81
1 %
and Design
Project/Employer’s 3.92 0.76 0.02 0.05 0.07 0.22 3.94 0.81
2 %
Representative facilities
Detour and Traffic 0.27 0.22 0.03 0.00 0.09 0.00 0.30 0.22
3 %
Management
Site Clearance and 15.23 2.54 1.27 0.55 5.58 0.73 16.50 3.10
4 %
Earthwork
5 Sub base % 1.01 0.00 0.32 0.00 0.55 0.00 1.33 0.00
6 Road Base % 1.00 0.00 0.20 0.00 0.60 0.00 1.20 0.00
7 Bituminous Surface % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Bridges, Culverts, 4.50 0.00 0.54 0.00 1.84 0.00 5.04 0.00
8 Drainages and %
Protection works
Road Furniture and 0.13 0.01 0.01 0.00 0.04 0.01 0.15 0.01
9 %
Environmental works
Subtotal (%) (%) 28.06 4.31 2.40 0.64 8.77 1.03 30.47 4.95
Subtotal(km) (km) 21.05 3.23 1.80 0.48 6.57 0.77 22.85 3.71
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work 100.00% 40.32% 59.68%
%age from total project cost 2.00% 0.81% 1.04%
The Employer’s Representative facilities have 4% weight from the total Project Values. Work
planned (according to Agreed Action Plan for 2012 EFY) was 3.94% (with respect to total project
cost), and contractor’s accomplishment to date is 0.81%.
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work
98.62% 20.28% 78.34%
%age from total project cost
3.94% 0.81% 3.13%
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work
30.30% 21.98% 8.32%
%age from total project cost
0.30% 0.22% 0.08 %
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work 38.37% 7.20% 31.17%
%age from total project cost 16.50% 3.10% 13.40%
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work
26.60% 0.00% 26.60%
%age from total project cost
1.33% 0.00% 1.33%
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work
17.14% 0.00% 17.14%
%age from total project cost 1.20% 0.00% 1.20%
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work 0.00%
0.0% 0.00%
%age from total project cost 0.00% 0.00% 0.00%
This item of works has 8% weight from the total project values. Work planned (according to
contractor’s Action Plan, which was submitted August 2019) was 5.04% (with respect to total
project cost), and contractor’s accomplishment to date was 0.00%.
The cumulative progress of the item to date with respect to its bill amount and total project
cost presented hereunder
Planned Actual
Description slippage
Accomplishment Accomplishment
% age from item of work 33.62% 0.00% 33.62%
%age from total project cost 5.04% 0.00% 5.04%
Planned Actual
Description slippage
Accomplishment Accomplishment
.
Delay in mobilization of the required Construction equipment’s (such as Grader,
Roller, Loader, Dump Truck and Water truck as per the work program
Delay in commencement of Structural work as per the work program
Embankment construction activity is almost nil due to persistent brake down of the
only available 1(one) grader and delay in mobilization of additional machineries.
Delay in camp construction
Delay in finalization of Design from km 35+000 up to 75+000(EOP)
Delay in provision of Engineer’s facilities as per the contract
Delay in provision of permanent Engineer’s vehicles (the provided rental temporary
vehicles were leaving the site due to delay in rental payment, only 6 temporary
vehicles are now available)
HIV/AIDS alleviation campaign is not commenced yet as per the contract, and sub-
consultant is not assigned yet
Traffic management Plan is not yet submitted
Final Environmental Management Plan incorporating the Consultant’s comment not
submitted
Project sign board is not installed yet
Right of way marker post is not produced
Relocation of Electric poles from the right of way limit shall be given attention by the
EELPA
No preparatory works has been carried out during this reporting month.
Total Avail. no
7 1 2 2 8 2 2 -
Working on avrg.
5 0.1 1.5 0.2 4 0.5 1 -
Note: At the end the reporting period the contractor has mobilized 2-Grade, 1-Roller and 1-Loader
The current status of insurance and Bonds to end of this month is shown below :-
2 Insurances
Insurance for
2.2 Works, equipment ETB Sub-Clause 18.2 Not submitted
and plant (CAR)
Third Party
2.3 Coverage, ETB 4,000,000.00 Sub-Clause 18.3 Under
sub clause 18.3 Comment
There is no claim submitted by the Contractor during this period and to-date.
Contractor's Staff
Employment and Gender Based Youth & Above Gender Based Beneficiaris' Report
Grand Total
Lube Sum (Permanent + Contract)
Project Employement
Plan in Permanent Contract Age≤29 Age≥30
Name by Skill
Number
Tot
Female Male Total Female Male Total Female Male Total Female Male Female Male Total
al
Skilled 1 9 10 4 9 13 5 18 23 3 7 10 2 11 13
Adishahu-
Dela- Semi- Skilled 30 30 10 74 84 10 104 114 5 52 57 6 52 58
Samre
Unskilled 16 223 239 16 223 239 18 102 120 -2 121 119
Prepared Approved
By Checked By by
Employment and Gender Based Youth & Above Gender Based Beneficiaris' Report
Grand Total
Lube Sum (Permanent + Contract)
Project Employment
Plan in Permanent Contract Age≤29 Age≥30
Name by Skill
Number
Female Male Total Female Male Total Female Male Total Female Male Tot Female Male Total
Skilled - - - - - -
- - - - - - - - - -
Adishahu-
Dela- Semi- Skilled - - - - - -
- - - - - - - - - -
Samre
Unskilled - - -
- - 10 4 14 10 4 14 10 4 14 - -
- - -
Total - - 10 4 14 10 4 14 10 4 14 - -