No.

Main Activities

1 Depot Site Work

1.1 Concrete casting for piles in Tank-6 (7-piles)

1.2 Concrete casting for piles in Tank-5 (1-piles)

Final inspection for the removing of the remaining concrete in Part-5 of


1.3
Tank-4

1.4 Concrete casting for the wall of slop tank-4 (90m3)

1.5 Formwork inspection for part-2 in Tank-7

1.6 Lean concrete formwork inspection for water-tank-1

1.7 Excavation location and compaction test for pipe support

1.8 T-wall mold inspection for 6 PCs

1.9

1.10

1.11

0
Remarks
1.1 Concrete casting for piles in Tank-6 (7-piles) 1.2 Concrete casting for piles in Tank-5 (1-p

1.3 Final inspection for the removing of the remaining concrete in Part-5 of Tank-4
1.5 Formwork inspection for part-2 in Tank-7

1.7 Excavation location and compaction test for pipe support


1.9
1.2 Concrete casting for piles in Tank-5 (1-piles)

1.4 Concrete casting for the wall of slop tank-4 (90m3)


1.6 Lean concrete formwork inspection for water-tank-1

1.8 T-wall mold inspection for 6 PCs