Excavation and Development of 100' Wide Khal along Both side of Purbachal Link

Road (From Kuril to Balu River) Project


Contactor: Infratech Idea JV (Package-3)
Total Length 3.22 km (Chainage 3+604.88 to 6+822.84)

Length
SL No. Description Chainage Working Length Non-working
(m) Length (m)
1 Main Road 3+600 to 3+780 180
2 Intersection (IS-5) 3+780 to 4+200 420
3 BR-05 (Ex) 4+200 to 4+260 60
4 UP-05 (Ex) 4+260 to 4+290 30
5 BR-04 (Ex) 4+290 to 4+350 60
6 Main Road 4+350 to 4+670 320
7 Intersection (IS-4) 4+670 to 5+180 510
8 Main Road 5+180 to 5+720 540
9 UP-04 (Ex) 5+720 to 5+850 130
10 BR-03 (Ex) On Baulai Canal 5+850 to 5+920 70
11 Intersection (IS-3) 5+920 to 6+820 900
Total 1040 2180
3220