Structure Description Unit Qty Remarks

Pilecaps - Blinding m³ 3.58


Pilecaps - Structural Concrete m³ 548.73 excluding precast shells

Abutments - Blinding m³ 9.28


Abutments - Structural Concrete m³ 515.78
MEASUREMENT SHEET
Pr oject New Br idge
Str uctur e Pile caps, and Abutments
Refer ence Dr awing

Item # Item Descr iption Unit Factor Length Width Depth Qty Remar ks

Pier Pile Caps

Pile cap 1 -
note. Blinding/Mass Concrete 20MPa allow 100mm off set each side
Blinding m3 1. 00 13. 00 3. 30 0. 05 2. 15
Allow deduction of Piles - DN1. 8m -3. 00 2. 54 0. 05 -0. 38
Total Blinding 1. 76

Pilecap No1
note. Structural concrete= 55mpa - C2
m3 1. 00 12. 80 3. 10 2. 50 99. 20
Total Pile cap 1 conc vol m3 100. 96

Pile cap 2, 3 and 4 -

Pile cap No 2, 3, and 4 pr ecast shell not taken


m3 3. 00 14. 60 3. 10 2. 55 346. 24 infill volume taken
Total Pile cap 2, 3, and 4 conc vol m3 346. 24

Pier 5 Pilecap -
Blinding m3 1. 00 13. 30 3. 30 0. 05 2. 19
Allow deduction of Piles - DN1. 8m -3. 00 2. 54 0. 05 -0. 38
Total Blinding 1. 81

Pile cap No 5
m3 1. 00 13. 10 3. 10 2. 50 101. 53
Total Pile cap 5 conc vol m3 103. 34
Total Pile caps conc vol 550. 54
Abutments

Abutment A-
note. Blinding mpa=20
Blinding m3 1. 00 20. 31 5. 00 0. 05 5. 08
Allow deduction of Piles - DN1. 5m -4. 00 1. 77 0. 05 -0. 35
Total blinding 4. 72
note. Structural concrete= 40mpa -B2
Ar ea 1 Base m3 1. 00 20. 11 4. 80 2. 00 193. 06

cur tain wall 20. 11 0. 60 2. 34 28. 29


20. 11 1. 27 0. 33 8. 39
20. 11 0. 90 0. 60 10. 86
allow deduction for squar e ar ea -1. 00 20. 11 0. 50 0. 30 -3. 02
total cur tain wall 44. 53
Masking wall 1. 00 6. 86 0. 20 2. 45 3. 36
1. 00 6. 70 0. 20 3. 09 4. 15

total masking wall 7. 50


Wing wall 1. 00 4. 36 0. 40 3. 00 5. 23
1. 00 4. 34 0. 40 3. 00 5. 21
total wing wall 10. 44
Total Abutment A conc vol 255. 52
Abutment B-
Blinding m3 1. 00 20. 00 5. 00 0. 05 5. 00
Allow deduction of Piles - DN1. 5m -5. 00 1. 77 0. 05 -0. 44
Total binding 4. 56

Ar ea 1 Base m3 1. 00 19. 79 4. 80 2. 00 189. 98

cur tain wall 1. 00 19. 79 0. 60 2. 53 30. 04


1. 00 19. 79 1. 25 0. 93 23. 03
1. 00 19. 79 1. 25 0. 60 14. 84
Allow deduction of squar e ar ea -1. 00 19. 79 0. 49 0. 30 -2. 91
Total cur tain wall 65. 01

Wing wall 1. 00 1. 20 0. 75 2. 57 2. 31
1. 00 2. 40 0. 40 3. 09 2. 97
Total wing wall 5. 27
Total Abutment B conc vol 260. 26

Total Abutment concr ete Volume 515. 78

John Holland Confidential 2020/ 6/ 21 Page 2