SUMMAR (ALEGRIA

Y   NGCP)       
           
    LABOR   183595.55  
    EQPT RENTAL  (20 days rental of zoomlion rig) 933333.4  
    MATERIAL      
      -fuel 97280  
      -direct materials and others 136454.05  
    MOBILIZATION/DEMOBILIZATION 590000  
    TOTAL COST   ₱1,940,663.00  
           
PILES          
pc
3 s 21 m depth 63  
pc
  s   m depth 0  
        63 lm
           
    COST PER LM   ₱30,804.17  

SUMMARY   (BALET)       
           
    LABOR   233991.64  
 (45 days rental of zoomlion rig and
EQPT RENTAL
    1 month rental of mobile crane) 2750000.15  
    MATERIAL      
      -fuel 103680  
      -direct materials and others 175802  
    MOBILIZATION/DEMOBILIZATION 400000  
LABOR COST FOR REBAR FABRICATION 619365
    TOTAL COST   ₱4,282,838.79  
           
PILES          
pc
6 s 40 m depth 240  
4 pc 40
s m depth 160  
        400 lm
           
    COST PER LM   ₱10,707.10  

COSTS OF NEWLY PURCHASED GENSETS


1 un 300kVA genset 1400000
1 un 50kVA genset 420000
₱1,820,000.0
TOTAL 0
SUMMARY
CONTRACT AMOUNT
₱3,153,480.0
-ALEGRIA** 0
₱22,335,944.
-BALET 00
₱25,489,424.00
COSTS
₱1,940,663.0
-ALEGRIA 0
₱4,282,838.7
-BALET 9
₱1,820,000.0
-NEW GENSETS 0
₱8,043,501.79
NET TOTAL ₱17,445,922.21

NEW GENSET as of Nov 11, 2017

1 un 238kVA genset cummins silent type 1100000

SUMMARY   (PADADA BRIDGE)       


           
    LABOR   2,087,723.11  
EQPT RENTAL  (1 lump sum rental Rig from
    Fabre) 531,600.00  
    MATERIAL      
    -fuel 315,760.00  
    -direct materials 53841.50  
-accessories 53,117.75
-consumables 490,842.00
  -tools 185,072.00
  -others 0.00
    MOBILIZATION/DEMOBILIZATION 500,000.00  
REPAIR & MAINTENANCE 334,211.00
LABOR COST FOR REBAR FABRICATION 1,777,533.60
    TOTAL COST   ₱6,412,313.21  
           
PILES          
pc
10 s 60 m depth 600  
pc
 6 s  60 m depth 360  
        960 lm
           
    COST PER LM   ₱6,679.49  

SUMMARY (MALASILA BRIDGE)       


           
    LABOR   618,122.31  
    EQPT RENTAL   0.00  
    MATERIAL      
    -fuel 0.00  
    -direct materials 4,200.00  
    -accessories 10,071.00  
 
    -consumables 96,667.50  
    -tools 16,770.20  
    -others 540.00  
    MOBILIZATION/DEMOBILIZATION 146,300.00  
    REPAIR & MAINTENANCE    
    TOTAL COST   ₱892,671.01  
           
PILES          
pc
12 30 m depth 360  
s
        360 lm
           
    COST PER LM   ₱2,479.64  

SUMMARY (LASANG BRIDGE)       


           
    LABOR   4,123,927.45  
    EQPT RENTAL (42 days 90ton crane & 50days rig) 3,243,333.33  
    MATERIAL      
    -fuel 675,422.69  
    -direct materials 148870.06  
    -accessories 624,912.97  
 
    -consumables 171,080.00  
    -tools 938,133.62  
    -others 0  
    MOBILIZATION/DEMOBILIZATION 500,100.00  
    UNRECOVERED STEEL CASINGS 509,114.00  
    TOTAL COST   ₱10,934,894.12  
           
PILES          
pc
4 52.5 m depth 210  
s
pc
4 50 m depth 200  
s
        410 lm
           
    COST PER LM   ₱26,670.47  

SUMMARY (TIGATTO BRIDGE)     


         
    LABOR   1,726,121.41
    EQPT RENTAL   0.00
    MATERIAL    
    -fuel 18,400.00
    -direct materials 23,607.00
    -accessories 38,969.70
 
    -consumables 82,151.00
    -tools 72,861.00
    -others 0
    MOBILIZATION/DEMOBILIZATION 110,000.00
    REPAIR & MAINTENANCE 301,041.53
    LABOR COST FOR REBAR FABRICATION -
    TOTAL COST   ₱2,373,151.64
         
PILES        
6 pcs 49 m depth 294
4 pcs 49 m depth 196
        490
       
    COST PER LM   ₱4,843.17
   
SUMMARY (LICUP BRIDGE) 
         
    LABOR   1,269,636.69
    EQPT RENTAL   0.00
    MATERIAL    
    -fuel 441,000.00
    -direct materials 62,695.00
    -accessories 10,360.20
 
    -consumables 56,677.50
    -tools 224,936.00
    -others 0
    MOBILIZATION/DEMOBILIZATION 734,000.00
    REPAIR & MAINTENANCE 91,015.51
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱2,890,320.90
         
PILES        
43 pcs 15 m depth 645
2 pcs 28 m depth 56
        701
    COST PER LM   ₱4,123.14
SUMMARY (TUBO-TUBO BRIDGE)     
         
    LABOR   424,623.32
    EQPT RENTAL   0.00
    MATERIAL    
    -fuel 126,000.00
    -direct materials 23645
    -accessories 12,680.30
 
    -consumables 105,047.00
    -tools 28,023.00
    -others 0
    MOBILIZATION/DEMOBILIZATION 418,000.00
    REPAIR & MAINTENANCE 2,342.86
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱1,140,361.48
         
PILES        
4 pcs 30 m depth 120
4 pcs 30 m depth 120
        240
         
    COST PER LM   ₱4,751.51

SUMMARY (QUITULAO BRIDGE)     


         
    LABOR   286,123.05
    EQPT RENTAL 0.00
    MATERIAL    
    -fuel 63,144.00
    -direct materials 13492
    -accessories 5,435.50
 
    -consumables 13,295.00
    -tools 24,240.00
    -others 0
    MOBILIZATION/DEMOBILIZATION 24,000.00
    REPAIR & MAINTENANCE  
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱429,729.55
PILES        
4 pcs 30 m depth 120
0 pcs 50 m depth 0
        120
         
    COST PER LM   ₱3,581.08
SUMMARY (F. TORRES BRIDGE)     
         

    LABOR   986,243.43

    EQPT RENTAL  (90 T Crane) 1,200,000.00

    MATERIAL    

    -fuel 18,900.00

    -direct materials 27703.75

    -accessories 137,323.40
 
    -consumables 262,645.00

    -tools 286,691.00

    -others 0

    MOBILIZATION/DEMOBILIZATION 232,000.00

    REPAIR & MAINTENANCE 9,213.18

    LABOR COST FOR REBAR FABRICATION  

    TOTAL COST   ₱3,160,719.76

         
PILES        

6 pcs 40 m depth 240

2 pcs 40 m depth 80

        320
         

    COST PER LM   ₱9,877.25

SUMMARY (MANDAHICAN BRIDGE)     


         
    LABOR   612,005.61
    EQPT RENTAL   0.00
    MATERIAL    
    -fuel 154,240.00
    -direct materials 28525
      -accessories 66,614.00
    -consumables 42,215.00
    -tools 22,980.00
    -others 0
    MOBILIZATION/DEMOBILIZATION 566,000.00
    REPAIR & MAINTENANCE 11,269.29
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱1,503,848.90
PILES        
1 pcs 20 m depth 20
0 pcs 0 m depth 0
        20
         
    COST PER LM   ₱75,192.45
SUMMARY (BAJADA CONDO AND HOTEL)   
         
    LABOR   1,696,005.84
    EQPT RENTAL (50 Ton Crane) 3,000,000.00
    MATERIAL    
    -fuel 720,750.00
    -direct materials 214331.31
    -accessories 644,693.07
 
    -consumables 211,156.00
    -tools 1,991,682.62
    -others 0
    MOBILIZATION/DEMOBILIZATION 250,000.00
    REPAIR & MAINTENANCE 5,000.00
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱8,733,618.84
PILES        
57 pcs 26.5 m depth 1510.5
54 pcs 26.5 m depth 1431
        2941.5
         
    COST PER LM   ₱2,969.10

SUMMARY (GLOBE CDO)     


         
    LABOR   371,706.58
    EQPT RENTAL 0.00
    MATERIAL    
    -fuel 0.00
    -direct materials 4200
    -accessories 10,071.00
 
    -consumables 96,667.50
    -tools 49,521.00
    -others 540
    MOBILIZATION/DEMOBILIZATION 464,000.00
    REPAIR & MAINTENANCE 52,748.71
    LABOR COST FOR REBAR FABRICATION  
    TOTAL COST   ₱1,049,454.79
PILES        
12 pcs 30 m depth 360
0 pcs 0 m depth 0
        360
         
    COST PER LM   ₱2,915.15