Professional Documents
Culture Documents
Section 800 - Quarries, Borrow Pits, Stockpile and Spoil Areas Page No
Section 800 - Quarries, Borrow Pits, Stockpile and Spoil Areas Page No
Page No.
801 GENERAL 8-1
802 DEFINITIONS 8-1
803 LOCATING MATERIAL SOURCES 8-2
804 SAFETY AND PUBLIC HEALTH REQUIREMENTS 8-4
805 ACCESS ROADS AND TRAFFIC CONTROL 8-5
806 SITE CLEARANCE AND REMOVAL OF TOPSOIL AND
OVERBURDEN 8-5
807 SELECTION, MIXING AND STOCKPILING OF MATERIALS 8-5
808 PRE-SELECTION OF MATERIALS 8-6
809 PROCESSING 8-7
810 MATERIAL UTILISATION 8-9
811 MEASUREMENT AND PAYMENT 8-9
SECTION 800 – QUARRIES, BORROW PITS, STOCKPILE AND SPOIL AREAS
801. GENERAL
802. DEFINITIONS
A rock quarry is an open surface working in massive rock form which stone
is removed by drilling and blasting for use in the works.
(2) Quarry
A quarry is an open surface working form which stone or aggregate for sub
base, base and surfacing are extracted for use in the works.
An alluvial deposit is a site where gravel and aggregate of alluvial origin are
extracted for use in the works.
A borrow pit is a site from which loose material, other than stone, is
removed for use in the works.
A spoil area is a site upon which surplus or unsuitable materials arising out
of works are dumped within or beyond the road reserve as indicated on the
Drawing or directed by the Engineer.
(1) The Contractor shall be responsible for locating all material sources and for
the acquisition or renting of all land required for rock quarries, quarries,
alluvial deposit, borrow pits, spoil and stockpile areas and for access thereto
in accordance with the Conditions of Contract.
The location and size of rock quarries, quarries, alluvial deposit borrow pits,
spoil and stockpile areas proposed by the Contractor shall be subject to the
approval of the Engineer.
The Engineer shall withhold his approval, if in his opinion the rock quarry,
quarry, alluvial deposit, borrow pit, spoil and stockpile area, or access into
them.
(2) The Contractor shall submit for the Engineer’s approval full information
regarding the proposed location of the material source not later than 30 days
after issue the order to commence the works of all rock quarries, quarries,
alluvial deposits, borrow pits, spoil and stockpile areas that the Contractor
will require for the whole the works.
The Contractor’s written notice shall include the following for each rock
quarry, quarry, alluvial deposit, borrow pit, spoil and stockpile areas:
i) plot boundaries;
ii) owners names and addresses, and if appropriate identification
numbers;
iii) the District, Location, Registration Section and Number for each
plot;
iv) local details such as building, fences, types and areas of cultivation
and services, all agreed with the Land Owners; and
v) areas to be used for working areas, stockpile areas, safety blasting
zones etc;
(3) Where the Contractor uses a rock quarry, quarry, alluvial deposit, or a
borrow pit identified or instructed by the Engineer he shall obtain the
Engineer’s approval of the areas required for the rock quarry, quarry,
alluvial deposit, or borrow pit and of the siting of the access roads into the
rock quarry, quarry, alluvial deposit, or borrow pit. The Engineer may
required the Contractor to modify his requirements for any of the reasons
outlined in Sub-clause 803 (1) (a), (b), (c), (d) or (f).
Where rock quarries, quarries, alluvial deposits, or borrow pits, available for
inspection at the time of the Tender, are instructed by the Engineer the
Contractor shall satisfy himself as to the quality and quantity of materials
available before providing the information required in this Clause. Should
such investigations reveal tat there is insufficient suitable material for the
use for which such material sources were intended, the Contractor shall
immediately inform the Engineer in writing and the Engineer shall either
direct that such sources are extended or that new sources shall be used.
(4) When a rock quarry, quarry, alluvial deposit, borrow pit spoil or stockpile
area has insufficient suitable material or area for the use for which it was
intended the Contractor shall propose in writing that either any existing rock
quarry, quarry, alluvial deposit, borrow pit, spoil or stockpile area be
extended or that a new rock quarry, quarry, alluvial deposit, borrow pit spoil
or stockpile area shall be used. The approval and acquisition of such new or
extended rock quarries, quarries, alluvial deposits, borrow pits, spoil or
stockpile areas shall in accordance with all the above provisions of this
Clause for the acquisition of the original rock quarries, quarries, alluvial
deposits, borrow pits, spoil or stockpile areas.
The Contractor shall comply with the prevalent laws and Regulations including
those of the Local Authority regarding public health and safety in respect of the
operation of rock quarries, quarries, alluvial deposit, borrow pits, spoil or
stockpile areas, and in the absence of, or in addition to such Regulations, shall
comply with the following conditions :-
(1) All areas of work, if they are not naturally under water, shall be drained and
kept drained where a quarry or borrow pit has been excavated such that it
will not drain naturally, it shall be kept pumped dry while being used.
(2) The Contractor shall confine his operations solely to the areas provided and
shall demarcate the boundary of the area and erect temporary or permanent
fencing as instructed by the Engineer.
(3) Where the height of any face exceeds 1 metre, the Contractor shall provide,
erect and maintain at his own expense stock proof fencing and gates to
prevent unauthorized access to the top of the working face.
(4) On completion of the work all faces shall be neatly trimmed to a slope
flatter than 1:4. Where this is impracticable or where the working face is to
be left exposed, the edge shall be permanently fenced, as instructed by the
Engineer and measurement and payment for such fencing shall be in
accordance with Section 400.
(5) On completion of work temporary fences and all temporary structures shall
be demolished and removed. All latrine pits shall be filled in and drained.
The site shall be topsoiled and left neat and tidy.
The Contractor shall comply with the provisions of Clause 103 and with the
Conditions of Contract with regard to the construction and maintenance of access
roads to rock quarries, quarries, alluvial deposits, borrow pits spoil and stockpile
areas and with regard to traffic operations thereon.
806. SITE CLEARANCE AND REMOVAL OF TOPSOIL AND OVERBURDEN
Unless otherwise directed by the Engineer, the Contractor shall remove topsoil
and/or overburden from rock quarries, quarries, alluvial deposits, borrow pits and
spoil and stockpile areas. The Engineer shall direct whether topsoil shall be
stripped and stockpiled separately or shall be excavated and spoiled together with
the overburden. If suitable, the Engineer may direct for the use of overburden in
the works.
On completion of the work in any rock quarry, quarry, alluvial deposit, borrow
pit, spoil or stockpile area the overburden and/or topsoil which has not been used
in the works shall be pushed back, spread and landscaped over the area of the rock
quarry, quarry, alluvial deposit, borrow pit, spoil or stockpile area. Where topsoil
has been stockpiled separately, it shall be pushed back and spared over the rock
quarry, quarry, alluvial deposit, borrow pit, spoil or stockpile area after
landscaping unless the Engineer has instructed that it shall be used for topsoiling
in accordance with Section 600.
Before a quarry, alluvial deposit or borrow pit is opened, the Engineer shall
instruct the Contractor as to the type of material to be excavated and the areas and
depth to be worked. The Engineer may require specific operations of equipment
according to the characteristics of the raw material and the characteristics of the
final product to be obtained in accordance with Clause 808 and 809 or other
relevant Section of those Specifications.
The Contractor shall ensure that oversize material, clay humus or unsuitable
material encountered in the working operations is separated from the materials
proposed for use in the works and such inferior material shall be removed tot
spoil.
A separate stockpile shall be used for each type and grading of material.
When removing material from stockpiles, none of the underlying material shall be
mixed with it, and generally at least the bottom 100 mm layer shall be left behind.
Should any stockpile prove surplus to requirements, the Contractor shall spread
the material over the area of the quarry or borrow pit unless directed otherwise by
the Engineer.
The size selection shall be carried out by unloading the material through
appropriate grids to select the size fraction which contains the required
fraction of the required type of stone specified in the Specifications, based
on the identification of the petrographic composition of the various size
classes of the raw material through laboratory trials in accordance with
Clause 506.
The size selection shall be carried out provided the conditions given in
Table 8.1 are fulfilled where:
A 40 7,500 35 4,000
B 70 85,000 60 20,000
(2) Quality Control of the Size Selection
When the requirements of the final products are not met, the Engineer may
require the Contractor to control the quality of the size selection.
809. PROCESSING
The Contractor shall use adequate processing equipment and methods to achieve
the characteristics and performance of the aggregates to be produced.
The processing methods may include successive steps such as primary crushing,
screening for elimination of fine and soft material, secondary crushing and
recycling, washing.
The Contractor shall carry out site trials in accordance with Clause 507 using the
Constructional Plant and methods proposed for selecting and processing the
materials to demonstrate their suitability to achieve the material requirements
specified in the Specifications.
(1) Crushing
The crushing process shall include all crushing stages, such as primary
crushing, secondary crushing or grinding (after primary screening) tertiary
grinding (after secondary screening), as necessary to meet the requirement
of the final product specified in the Specifications.
Quartzite & Sand Gyratory Crusher (for Cone Grinder or Cone Grinder
Production more than 1000T/h only) Gyratory Grinder (Gyradisc)
(2) Screening
The Contractor shall eliminate polluted or soft materials after the primary
crushing by screening the crushed materials through a 50 mm mesh screen.
The Engineer may instruct the Contractor to modify the above mentioned
size for the elimination of soft materials according to the results of the
laboratory trials.
In case of materials sensitive to crushing, the Engineer may instruct the
Contractor to carry out a secondary screening after the secondary crushing.
(4) Washing
Each type of final products shall be tested in accordance with the tests and
frequencies of testing as specified in the relevant Sections of these
Specifications.
(6) Records
All materials from rock quarries, quarries, alluvial deposits, borrow pits as
instructed by the Engineer shall only be used for permanent works shown on the
Drawing or instructed by the Engineer and any other use shall be subject to the
Engineer’s approval.
Where the Engineer has instructed that overburden or topsoil will be used in the
works, measurement and payment shall be in accordance with the relevant
Sections of these Specifications.