Verificaciones Ensayos de Recepción de Medidores - Es.en
Verificaciones Ensayos de Recepción de Medidores - Es.en
Inspections
1. Visual inspection
Selection of 5 meters for precision testing with balanced systems in the case of single-
phase meters.
6. Integration test. (5 kWh in the positive direction). See details in standard NMP: 021 2015.
Resolution must be sufficient to determine maximum deviations less than 0.2%.
7. Integration test. (5 kWh in reverse). See details in standard NMP: 021 2015. Resolution must
be sufficient to determine maximum deviations less than 0.2%.
1) Valid calibration certificates of the test benches used in the reception inspection.
2) Valid calibration certificates of the test benches used in the initial verification of
electronic meters.
3) Acceptance certificate at the end of the tests.
4) The meters that are sampled must be labeled with stickers that must self-destruct and
leave a trace on the body of the meter, if it is removed. The stickers will be supplied by
the performer of the service.
5) The final inspection report must necessarily include the code and certification date of
the standards used in the initial verification of the meters supplied.