Professional Documents
Culture Documents
Tongo Assosa - Completion Report (Draft)
Tongo Assosa - Completion Report (Draft)
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
TABLE OF CONTENTS
1.INTRODUCTION…………………………………………………………………………………………………….1
Pure Consulting Engineers PLC in Sub-Consultancy with Sound Engineering Solutions PLC
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
3.2 Manuals used........................................................................................................................................15
4. PROJECT CASH FLOW………………………………………………………………………………………….17
Pure Consulting Engineers PLC in Sub-Consultancy with Sound Engineering Solutions PLC
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
List of Tables
Table 1- 1: Contract Data.................................................................................................................................3
Table 1- 2: Project Description.......................................................................................................................5Y
Table 2- 1: Staff inputs until the project completion..........................................................................................9
Table 2- 2: Deliverables and responsible professionals from both sides.........................................................1
Table 4- 1: Payment schedule........................................................................................................................17
Table 4- 2: Invoice Schedule.........................................................................................................................19
List of Figures
Figure 1- 1: Project Location..........................................................................................................................6Y
Figure 2- 1: Project Implementation Structure................................................................................................12
Pure Consulting Engineers PLC in Sub-Consultancy with Sound Engineering Solutions PLC
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
1. INTRODUCTION
1.1 Introduction and purpose
The Federal Democratic Republic of Ethiopia has launched Road Sector Development Program (RSDP) to enhance
development objectives and the living standard of the population all over the country. Accordingly, Ethiopian Roads
Authority, on behalf of the Federal Democratic Republic of Ethiopia (FDRE) is implementing various road projects
including new road construction, rehabilitation or upgrading of main trunk, link and rural roads to expand the Roads
Network all over the country.
The Government of Federal Democratic Republic of Ethiopia (FDRE) represented by the Ethiopian Roads Authority
(ERA) has allocated funds towards the Consultancy Services to carry out Concept Design, Feasibility and EIA, RAP,
and Tender Document Preparation & Engineering Cost Estimate of Tongo Assosa road project.
The Ethiopian Roads Authority (ERA) of the Federal Democratic Republic of Ethiopia (the Employer) signed an
Agreement with Pure Consulting Engineers PLC in Sub-Consultancy with Sound Engineering Solutions PLC for
Consultancy Service for the Concept Design, Feasibility, EIA, RAP, Risk Assessment and Tender Document
Preparation & Engineering Cost Estimate of Tongo Assosa Road Project.
The Ethiopian Roads Authority (ERA) has been entrusted the responsibility of implementing this road project. ERA,
on the behalf of the Federal Democratic Republic of Ethiopia, intends to utilize part of its budgetary allocation to
finance the Consultancy services for the project under reference. The provision of this service is procured through
National Competitive Bidding (NCB).
The preparation of Works tender documents on Design and Build basis dictates the application of the highest
possible Engineering and Contract standard so that the implementation of the construction project can be realized
without undue imbalance of risk between the contracting parties. Therefore, based on this premise the Consultant
carries out such services with utmost care, diligence and expertise.
The Consultant shall perform all necessary services and activities to fulfill the stated objectives whether or not a
specific activity is stated in the Scope of Services in the Terms of Reference.
The purpose of this concept design document is to present findings on sensitive areas such as landslide area,
swampy areas, high embankment stability, flood plains; and identified Environmental and Social problems and
together with their corresponding recommendations for mitigation measures given as Engineering solutions. The
findings on identified Environmental and Social problems shall include but not limited to:
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
ROW issue such as identification of spoil areas, resettlement/land use demand of the design, reinstatement
Effects of deep cuts and high fills on the livelihood of local residents
Traffic management issues in town sections, difficult terrains
Health and safety on site
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
1.2 Contract Data
Table 1- 1: Contract Data
Project Name : Bule Hora – Shakiso – Kibremengist Road Project, Lot 1:
Kibremengist-Bule Kero & Tongo-Assosa Road Project And Bule Hora
– Shakiso – Kibremengist Road Project, Lot 1: Tongo Assosa Road
Project
Lot : Tongo Assosa Design and Build Road Project
Project No. : S/01/NCB/RFP/GOE/2012 EFY
Funding : The government of Federal Democratic Republic of Ethiopia (FDRE)
Consultant : Pure Consulting Engineers PLC in Sub-Consultancy with Sound
Engineering Solutions PLC
Type of Services : Concept Design, Tender Documents and Engineering Cost Estimate
Project Period : Six (6) Months
Consultancy Contract
Signed on: : January 3, 2020
Commencement Date : 14 January 2020 (ERA’s letter dated 14 January 2020 with reference
No. AA19/26/10-155
Planned Duration : Six (6) Months
Project Cost : Ethiopian Birr 15,458,875 (Ethiopian Birr Fifteen Million Four Hundred
Fifty Eight Thousand Eight Hundred Seventy Five Only) inclusive of
15%VAT and local taxes.
Concept design of Lot 1 and Phase : Ethiopian Birr 4,098,071.00 (Ethiopian Birr Four Million Ninety Eight
I of Detailed engineering Design of Thousand Seventy One Only) inclusive of 15%VAT and local taxes.
the first section/Lot
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
1.3 Project Deliverables
The deliverables produced under this project include :
Detailed site investigation works that include Survey works & Route selection
Feasibility study, Environmental impact assessment, Risk Assessment, detailed Engineering Estimation of
the proposed route to guide the employer towards knowledge based decision
Concept design of the proposed route, so that can be used as crude guide for the tenderer during
procurement stage
Tender document including the Employer`s requirement that can be employed during the whole life of the
project from tendering to final close out stage forming a binding contract between the employer and the
successful tenderer
Shift work
Reduction of working hours
Re-scheduling site visits
Providing service
Providing protective equipment
Even though, we had been doing with our utter most care some delays had been inevitable as a result of the
aforementioned force majeure.
Thus, our company will finalize and submit all the final reports as practicable as possible after the employer review
the draft submissions , in case there is any, or else the draft submissions will be finalized and submitted to the
employer by the end of July,2020.
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
1.5 Project Description
The Tongo – Asosa Design and Build Road Project is located entirely in Benishangul Gumuz National Regional
State, and is having a total length of about 130 km. The starting point of the project i.e. Asosa Town is located at
about 665km from Addis Ababa. The project starts at Asosa town which is located in the Benishangul Gumuz
Regional State: Asosa zone. The approximate coordinates in ADINDAN projection for the starting point are
(E=671392.065, N=1115410.685) (UTM: ADINDAN, Zone 36). The project traverses through Asosa Town
Administration, Megele 32, Megele 33, Abrehamo, Sherkole-Engi, Sherkole-ofendi, Kushmagan, Budur Kebeles,
Fufur Kebele, Banga kebele, Baldegis kebele, Shoshor kebele, Mimi kebele and ends at Tongo town with
approximate ending point coordinates of (E=659537.007, N=1035295.758).
Project Name Construction Works of Tongo – Asosa Design and Build Road Project
Traffic Volume vpd For Assosa town AADT is 5434, for the remaining section AADT is 945
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
Project Location
The project team has been organized in such a way that attribute for the timely accomplishment of tasks in a
standard quality and to the requirements set by the TOR. The team consist of the following professional personnel’s :
Pavement/Material Engineer
Structural Engineer
Senior Surveyor
Hydrologist
Contract Engineer
The project team leader put a maximum effort towards the coordination works and towards a timely implementation
of the project.
Data collection is being undertaken, both in Addis Ababa and from the project site, and data collected to date
includes the following:
Maps at 1:50,000 scale covering all of the project area (hard copy and digital files from Ethiopian Mapping
Agency);
ERA Design Manuals
ERA Quality Manuals
Metrological Data
Land use map of the area
Soil Map
DEM 30X30m grid, DEM 90x90m grid
Socio economic profile and maps of the Weredas and Zones
Master plans of Town Administrations and Woredas
Geological Maps at 1:250,000 and at 2,000,000 from the Geological Survey of Ethiopia
Based on the findings during site visit and data collection the consultant had submitted a project inception report on
March 2020 and the final version was submitted after incorporating comments given by the client on April 2020.
In addition to the onsite engineering study of the proposed route a detailed public consultation had been conducted
with different stake holders.
Using these consultation as a supportive and indicative information in consideration of the engineering and other
technical aspects of the proposed route the consultant had conducted the route selection of the proposed project.
Furthermore, the data collected during site visit used as a forefront for all the reports and deliverables that the
consultant produce and submitted during the project commencement period.
2.2.2 Implementation structures and deliverables
Both the lead consultant and sub consultant giving a lieu attention towards the implementation of the consultancy
services had delivered the following deliverables listed in Tale 2-1 below, as per the proposed time schedule on the
TOR.
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
Table 2- 2: Deliverables and responsible professionals from both sides
List of Deliverable Delivery Date Status of the work
Final Inception Report April 02,2020 Completed and the Final version submitted to the
client
Final Concept Engineering Design Report June 20,2020 Completed and the Final version submitted to the
client
Final Concept Design Drawing June ,2020 Completed and the Final version submitted to the
client
Final EIA for Concept Design July,2020 Completed and the Final version submitted to the
client
Final Tender Document, June 10,2020 Completed and the Final version submitted to the
client
Risk Assessment Report June 19,2020 Completed and there was no comment given on the
draft submission hence, it is assumed that the client
accepted the submission
Engineering Estimates May, 2020 Completed and the Final version submitted to the
client
Feasibility report of concept design and June ,2020 Completed and there was no comment given on the
RAP Report draft submission hence, it is assumed that the client
accepted the submission
Consultancy Completion Report Under Will be submitted by July 24,2020
preparation
Concept Engineering
Design Report (CAD)
Inputs
The main items of works of the project and narrative description of individual tasks are as described in the forth
coming sub sections.
Staff mobilization
The Design Team that comprised of the Team Leader and Highway Engineer, the Hydrologist, the Structural
Engineer, the Geotechnical Engineer, the Pavement Engineer and the Environmentalist has been formed for the site
investigation of the Project Area and to undertake the Inception and Reconnaissance Site Visit from February 28,
2020 to March 9, 2020.
3.1.2 DATA COLLECTION AND RECONNAISSANCE SURVEY
The data collection and reconnaissance survey was the fundamental source and primary source of data for the
overall concept design and reporting activities.
Site Reconnaissance
Having organized and reviewed secondary data, the Consultant carried out the site reconnaissance activity in the
month of February 28, 2020 with a participation of all key project professionals. The site reconnaissance was carried
out by the Consultant to get familiarized with the project corridor and to gain firsthand information of site conditions.
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
During the site reconnaissance survey the pavement, structure and geometric condition of the existing roads, soil
characteristics, land use/land cover, geology, hydrology, construction materials, ROW, Environmental and other
related issues have been investigated.
Furthermore, the Consultant staff was introduced to various organizations for the purpose of data collection and
partnership.
Visiting all stretch of the project to assess and observe the existing drainage condition;
Defining the catchment areas of major existing and new drainage structures of the project road using
the topographic map of the project area.
Perform the hydrological and hydraulic study.
Propose drainage facilities.
3.1.5 Geometric Design
The geometric design of the road was carried out based on the field investigation results and detailed topographic
survey data’s in accordance to ERA Geometric Design Manual requirement. This was done to design the horizontal
as well as vertical alignment design and the other components such as super-elevation and widening requirements.
Appropriate safety design items and road furniture was specified and typical detail drawings were produced based on
project design standards and guidelines.
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
3.1.6 EIA for the Concept Design
Detailed EIA has been undertaken after assessment of the conditions of the project road and its vicinities.
The tender document was evaluated by the client, commented and forwarded to the consultant. Based on the
comments forwarded from the client the consultant corrected the tendering requirements and the final document was
submitted to the client within soft and hard copy.
The Planned and Actual accomplishment based on monthly cash flow distribution will be presented here under with
the following Figure-1 below:
However, after a lot of discussion with parties and the client the project was combined into one and the starting point
was changed to Assosa Town and the end point to Tongo.
Thus the scope of the project was totally changed from the one provided on the TOR and RFP. The project end result
i.e. the concept design was prepared for the changed route in which the client and all other stake holders agreed up
on.
Even though the project loting and the start and end point were changed all the deliverables were prepared as per
the deliverable schedule stated in the TOR.
The overall performance of the project as can be seen from Figure 4-1 under Section 4, during the first three months
the performance of the project was below the plan. However after March 2020, the consultant had managed to
accelerate the works and finalize the tasks as per the plan by July 2020.
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
The lessons learned on commencing this project can be generalized and grouped in to two categories thus are:
Technical lessons
Management and leadership lessons
Security issue: Another challenge that is related to the project implementation is the security issue. The
location of the project creates favorable conditions for bandits to live inside the deep forest and naturally
undisturbed area. Hence, a special attention was given and police officers were requested form the
Consultancy services for the Route Selection and Survey, Feasibility and Environmental Impact,
Assessment (EIA) Studies, Concept Engineering Design, Resettlement Action Plan (RAP) and Ethiopian Roads Authority
Tender Document Preparation for Tongo - Asosa DB Road Project. July, 2020
Consultancy Completion Report (Draft)
administration and the design crew was braced by the security officers. Thus, it was realized that in every
activity of the project commencement life particularly during data collection for the design purpose and
during construction phase a lieu attention must be given for the issue to facilitate the smooth progress of the
project work and to maintain safe working environment for the design builder personnel.
During site visit it was observed that, because of absence of properly designed and constructed road that connect the
woredas and towns around Ethio- South Sudanese border most of the community who lived there preferred to go to
South Sudanese towns for marketing purpose rather than to neighborhood towns. In this regard, proper and timely
implementation of the project not only respond socio- economic issues but also to political issues.