Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 61

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF EDUCATION
DIVISION OF OZAMIZ CITY
Ozamiz City 7200

((School))

PROGRAM OF WORKS

Project Title: Budget Allocation:


Minimum Required Manpower:
Construction Foreman, Carpenter
Steelman/Welder,
Mason, Laborers
School: Minimum Required Equipment:
Source of Fund & Year: Welding Machine, Construction Tools
Completion Period: 30 CD
Item I.D. Item Description % of Total Unit Quantity Total Cost Remarks

I. DIRECT COST

1 Earthworks #DIV/0! cu.m


2 Concreting Works #DIV/0! cu.m
3 Rebar Works #DIV/0! pc
4 Formworks #DIV/0! bd.ft
5 Masonry Works #DIV/0! sq.m.
6 Doors & Windows #DIV/0! set
7 Steel Works #DIV/0! lot
8 Roofing Works #DIV/0! pc
9 Carpentry/Ceiling Works #DIV/0! sq.m.
10 Electrical Works #DIV/0! lot
11 Painting Works #DIV/0! sq.m.

Sub-Total 0.00
II. INDIRECT COST 9% of (I)
Overhead Expenses (5%) #DIV/0! 0.00
Contingencies (3%) #DIV/0! 0.00
Miscellaneous (1%) #DIV/0! 0.00
Sub-Total 0.00
III. TAX 5% of (I + II) #DIV/0! 0.00
IV. TOTAL CONSTRUCTION COST (I+II+III) 0.00
SAY

Prepared:

School Head

Reviewed by: Recommending Approval: Approved:

ERIC PAUL M. CATULONG SUSAN EPIFANIA B. CARPIO REBONFAMIL R. BAGUIO


Engineer - III Chief, SGOD Schools Division Superintendent
One Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT : PROPOSED ONE CLASSROOM 7 X 7 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. ITEM UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO NO. MATERIAL LABOR MATERIAL LABOR
A GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
and Services/Demobilization / Standard lot 1.00 2,149.73 1,433.15 2,149.73 1,433.15 3,582.88
Billboard
Sub-total 3,582.88
1.00 B Earthworks
1.01 Clearing and Grubbing sq.m 59.50 0.00 20.00 0.00 1,190.00 1,190.00
1.02 Structural Excavation cu.m 13.73 0.00 200.00 0.00 2,745.60 2,745.60
1.03 Backfilling and Compaction cu.m 9.47 0.00 45.00 0.00 426.06 426.06
1.04 Gravel Bedding G-1 cu.m 3.83 552.00 180.00 2,112.50 688.86 2,801.36
1.06 Select Fill cu.m 5.95 150.00 45.00 892.50 267.75 1,160.25
1.05 Soil Poisoning sq.m 65.45 15.00 4.50 981.75 294.53 1,276.28
Sub-total 9,599.55
2.00 C Concreting Works
Column Footing cu.m 1.46
2.01 Portland Cement bag 14.00 223.00 42.50 3,122.00 595.00 3,717.00
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Wall Footing cu.m 2.80
2.01 Portland Cement bag 26.00 223.00 42.50 5,798.00 1,105.00 6,903.00
2.05 Crushed Gravel 1" cu.m 3.00 552.00 150.00 1,656.00 450.00 2,106.00
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Column cu.m 2.14
2.01 Portland Cement bag 20.00 223.00 42.50 4,460.00 850.00 5,310.00
2.02 Crushed Gravel 3/4" cu.m 2.25 655.00 175.00 1,473.75 393.75 1,867.50
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Beams cu.m 2.21
2.01 Portland Cement bag 20.00 223.00 42.50 4,460.00 850.00 5,310.00
2.02 Crushed Gravel 3/4" cu.m 2.25 655.00 175.00 1,473.75 393.75 1,867.50
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Slab on Grade cu.m 7.65
2.01 Portland Cement bag 69.00 223.00 42.50 15,387.00 2,932.50 18,319.50
2.05 Crushed Gravel 1" cu.m 7.75 552.00 150.00 4,278.00 1,162.50 5,440.50
2.03 Washed Sand cu.m 4.00 435.00 150.00 1,740.00 600.00 2,340.00
Ramp on Fill cu.m 0.32
2.01 Portland Cement bag 3.00 223.00 42.50 669.00 127.50 796.50
2.05 Crushed Gravel 1" cu.m 0.50 552.00 150.00 276.00 75.00 351.00
2.03 Washed Sand cu.m 0.25 435.00 150.00 108.75 37.50 146.25
Sub-total 58,306.50
3.00 D Rebar Works
Footing kg 111.16
Wall Footing kg 81.50
Column kg 445.17
Beam kg 377.00
3.01 Deformed Round Bars, Grade 40 kg 1,014.83 39.97 7.63 40,562.57 7,746.86 48,309.43
3.02 G.I. Tie Wire kg 21.00 50.00 9.00 1,050.00 189.00 1,239.00
Sub-total 49,548.43
4.00 E Formworks
Column sq.m 37.41

1CL 7x7m Schoolbuilding 2 of 61


One Classroom

I.D. ITEM UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO NO. MATERIAL LABOR MATERIAL LABOR
4.01 Coco Lumber bd.ft 190.80 14.00 4.20 2,671.20 801.36 3,472.56
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 7.00 288.92 90.00 2,022.42 630.00 2,652.42
4.04 CWN, Assorted kg 3.00 60.00 18.00 180.00 54.00 234.00
Beams sq.m 35.70
4.01 Coco Lumber bd.ft 182.10 14.00 4.20 2,549.40 764.82 3,314.22
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 7.00 288.92 90.00 2,022.42 630.00 2,652.42
4.04 CWN, Assorted kg 3.00 60.00 18.00 180.00 54.00 234.00
Sub-total 12,559.61
5.00 F Masonry Works
Masonry Wall sq.m 84.78
5.04 CHB 4" thk pc 1,060.00 9.50 2.25 10,070.00 2,385.00 12,455.00
5.02 Portland Cement bag 28.00 223.00 51.00 6,244.00 1,428.00 7,672.00
5.03 Washed Sand cu.m 4.00 435.00 180.00 1,740.00 720.00 2,460.00
5.06 10mm x 6m RSB kg 113.00 39.97 9.03 4,516.61 1,020.39 5,537.00
5.07 G.I. Tie Wire kg 3.00 50.00 15.00 150.00 45.00 195.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 169.56
5.02 Portland Cement bag 56.00 223.00 51.00 12,488.00 2,856.00 15,344.00
5.03 Washed Sand cu.m 6.00 435.00 180.00 2,610.00 1,080.00 3,690.00
Sub-total 47,977.00
6.00 G Doors and Windows

D-1, Flush Door 0.90m x 2.10m on 100mm set 2.00 3,467.50 302.75 6,935.00 605.50 7,540.50
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 5,500.00 550.00 11,000.00 1,100.00 12,100.00
Casing and Fixed Clear Glass Transom on
50 x 100 mm Wooden Jamb complete with
6.35 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 2,750.00 275.00 5,500.00 550.00 6,050.00
Casing and Fixed Clear Glass Transom on
50 x 100 mm Wooden Jamb complete with
6.36 Accessories
Sub-total 25,690.50
7.00 H Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 342.72 41.19 12.48 14,116.64 4,276.11 18,392.75
7.03 LC 75 x 38 x 15 x 2.0mm kg 309.60 41.19 12.48 12,752.42 3,862.88 16,615.30
7.11 L 25 x 25 x 3mm kg 40.32 41.60 8.73 1,677.31 352.04 2,029.35
7.17 Flat Bar 1" x 1/4" kg 21.24 41.60 8.73 883.58 185.45 1,069.03
7.18 Plain Round Bar 10mmØ x 6m pc 6.00 107.00 32.10 642.00 192.60 834.60
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.25 9,300.00 2,790.00 2,325.00 697.50 3,022.50
Anchor Bolt with Nuts and Washer, 16mmØ pc 16.00 45.00 13.50 720.00 216.00 936.00
7.33 x 50mm x 300mm

Anchor Bolt with Nuts and Washer, 10mmØ pc 16.00 12.00 3.60 192.00 57.60 249.60
7.35 x 50mm x 200mm
7.46 Welding Rod kg 15.00 67.00 20.10 1,005.00 301.50 1,306.50
13.12 Primer, Zinc Chromate gal 2.00 537.00 161.10 1,074.00 322.20 1,396.20
Sub-total 45,851.84
8.00 I Roofing Works

Long-Span Roofing, Corrugated, Pre- m 83.20 360.00 72.00 29,952.00 5,990.40 35,942.40
8.16 Painted, 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 4.00 544.00 2,176.00 0.00 2,176.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 666.00 1.25 832.50 0.00 832.50
8.36 Roof Sealant L 1.00 239.80 239.80 0.00 239.80
Sub-total 44,630.70
9.00 J Carpentry Works
Interior ceiling sq.m 55.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 241.00 40.00 12.65 9,640.00 3,048.65 12,688.65
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 19.00 288.92 81.75 5,489.42 1,553.25 7,042.67

1CL 7x7m Schoolbuilding 3 of 61


One Classroom

I.D. ITEM UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO NO. MATERIAL LABOR MATERIAL LABOR
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00 325.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 10.00 352.50 105.75 3,525.00 1,057.50 4,582.50
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 25.00 245.00 73.50 6,125.00 1,837.50 7,962.50
Sub-total 33,953.32
10.00 K Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 20.00 50.00 15.00 1,000.00 300.00 1,300.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 6.00 15.00 4.50 90.00 27.00 117.00
10.17 Utility Box, 2" x 4" G.I. pc 4.00 30.00 4.28 120.00 17.10 137.10
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 180.00 23.97 7.02 4,315.38 1,263.60 5,578.98
10.28 Duplex C.O. with Plate pc 2.00 263.80 21.00 527.60 42.00 569.60
10.25 3-Gang Switch with Plate pc 1.00 208.00 29.59 208.00 29.59 237.59
10.23 Single Switch with Plate pc 1.00 97.68 13.46 97.68 13.46 111.14
10.20 FL 2 x 40W Industrial Type set 4.00 1,200.00 126.00 4,800.00 504.00 5,304.00
10.21 FL 1 x 40W Industrial Type set 1.00 700.00 73.50 700.00 73.50 773.50
10.46 Safety Switch 30A 2P set 1.00 603.25 90.49 603.25 90.49 693.74
10.58 Electrical Tape pc 1.00 37.50 5.63 37.50 5.63 43.13
Sub-total 15,242.03
13.00 L Painting Works
Concrete surfaces sq.m 169.56
13.18 Neutralizer gal 3.00 132.00 39.60 396.00 118.80 514.80
13.01 Latex, Flat gal 7.00 470.00 141.00 3,290.00 987.00 4,277.00
13.02 Latex, Semi Gloss gal 7.00 478.25 143.48 3,347.78 1,004.33 4,352.11
13.20 Acri Color qrt 2.00 165.00 49.50 330.00 99.00 429.00
Wood surfaces sq.m 63.40
13.04 Enamel, Flatwall gal 4.00 440.00 132.00 1,760.00 528.00 2,288.00
13.05 Enamel, Semi Gloss gal 4.00 460.00 138.00 1,840.00 552.00 2,392.00
13.16 Paint Thinner gal 2.00 260.00 78.00 520.00 156.00 676.00
Sub-total 14,928.91

I. DIRECT COST 361,871.27


II. INDIRECT COST 19% of (I) 68,755.54
III. TAX 12% of (I+II) 51,675.22
IV. TOTAL CONSTRUCTION COST (I+II+III) 482,302.03
V. ENGINEERING OVERHEAD 1% of (IV) 4,823.02
VI. TOTAL PROJECT COST (IV+V) Php487,125.05
Php488,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

1CL 7x7m Schoolbuilding 4 of 61


Two Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY TWO CLASSROOM 7 X 7 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 3,881.57 2,587.71 3,881.57 2,587.71 6,469.28
Services/Demobilization / Standard Billboard

Sub-total 6,469.28
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 119.00 0.00 20.00 0.00 2,380.00 2,380.00
1.02 Structural Excavation cu.m 23.88 0.00 200.00 0.00 4,776.00 4,776.00
1.03 Backfilling and Compaction cu.m 16.46 0.00 45.00 0.00 740.48 740.48
1.04 Gravel Bedding G-1 cu.m 7.44 552.00 180.00 4,104.12 1,338.30 5,442.42
1.06 Select Fill cu.m 11.90 150.00 45.00 1,785.00 535.50 2,320.50
1.05 Soil Poisoning sq.m 130.90 15.00 4.50 1,963.50 589.05 2,552.55
Sub-total 18,211.95
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 4.90
2.01 Portland Cement bag 45.00 223.00 42.50 10,035.00 1,912.50 11,947.50
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
2.03 Washed Sand cu.m 2.50 435.00 150.00 1,087.50 375.00 1,462.50
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 3.73
2.01 Portland Cement bag 34.00 223.00 42.50 7,582.00 1,445.00 9,027.00
2.02 Crushed Gravel 3/4" cu.m 3.75 655.00 175.00 2,456.25 656.25 3,112.50
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 106,034.50
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 145.25
Column kg 738.02
Beam kg 640.65
3.01 Deformed Round Bars, Grade 40 kg 1,708.98 39.97 7.63 68,307.94 13,045.83 81,353.77
3.02 G.I. Tie Wire kg 35.00 50.00 9.00 1,750.00 315.00 2,065.00
Sub-total 83,418.77
4.00 Formworks

2CL 7x14m Schoolbuilding 5 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 60.79
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 60.20
4.01 Coco Lumber bd.ft 307.20 14.00 4.20 4,300.80 1,290.24 5,591.04
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Sub-total 20,352.85
5.00 Masonry Works
Masonry Wall sq.m 143.18
5.04 CHB 4" thk pc 1,790.00 9.50 2.25 17,005.00 4,027.50 21,032.50
5.02 Portland Cement bag 47.00 223.00 51.00 10,481.00 2,397.00 12,878.00
5.03 Washed Sand cu.m 7.00 435.00 180.00 3,045.00 1,260.00 4,305.00
5.06 10mm x 6m RSB kg 190.00 39.97 9.03 7,594.30 1,715.70 9,310.00
5.07 G.I. Tie Wire kg 4.00 50.00 15.00 200.00 60.00 260.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 286.35
5.02 Portland Cement bag 95.00 223.00 51.00 21,185.00 4,845.00 26,030.00
5.03 Washed Sand cu.m 10.00 435.00 180.00 4,350.00 1,800.00 6,150.00
Sub-total 80,589.50
6.00 Doors and Windows
D-1, Flush Door 0.90m x 2.10m on 100mm set 4.00 3,467.50 302.75 13,870.00 1,211.00 15,081.00
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 4.00 5,500.00 550.00 22,000.00 2,200.00 24,200.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.35 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 4.00 2,750.00 275.00 11,000.00 1,100.00 12,100.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.36 Accessories
Sub-total 51,381.00
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 628.32 41.19 12.48 25,880.50 7,839.54 33,720.04
7.03 LC 75 x 38 x 15 x 2.0mm kg 619.20 41.19 12.48 25,504.85 7,725.75 33,230.60
7.11 L 25 x 25 x 3mm kg 80.64 41.60 8.73 3,354.62 704.08 4,058.71
7.17 Flat Bar 1" x 1/4" kg 28.32 41.60 8.73 1,178.11 247.27 1,425.38
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 24.00 12.00 3.60 288.00 86.40 374.40
7.35 50mm x 200mm
7.46 Welding Rod kg 28.00 67.00 20.10 1,876.00 562.80 2,438.80
13.12 Primer, Zinc Chromate gal 3.00 537.00 161.10 1,611.00 483.30 2,094.30
Sub-total 86,928.43
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m 156.00 360.00 72.00 56,160.00 11,232.00 67,392.00
8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 7.00 544.00 3,808.00 0.00 3,808.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,248.00 1.25 1,560.00 0.00 1,560.00
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 78,679.60
9.00 Carpentry Works
Interior ceiling sq.m 110.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 481.00 40.00 12.65 19,240.00 6,084.65 25,324.65
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 38.00 288.92 81.75 10,978.83 3,106.50 14,085.33

2CL 7x14m Schoolbuilding 6 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 9.00 50.00 15.00 450.00 135.00 585.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 14.00 352.50 105.75 4,935.00 1,480.50 6,415.50
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 37.00 245.00 73.50 9,065.00 2,719.50 11,784.50
Sub-total 60,807.98
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 48.00 50.00 15.00 2,400.00 720.00 3,120.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 12.00 15.00 4.50 180.00 54.00 234.00
10.17 Utility Box, 2" x 4" G.I. pc 8.00 30.00 4.28 240.00 34.20 274.20
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 432.00 23.97 7.02 10,356.92 3,032.64 13,389.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93 222.29
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 1.00 37.50 5.63 37.50 5.63 43.13
Sub-total 34,859.23
13.00 Painting Works
Concrete surfaces sq.m 286.35
13.18 Neutralizer gal 4.00 132.00 39.60 528.00 158.40 686.40
13.01 Latex, Flat gal 12.00 470.00 141.00 5,640.00 1,692.00 7,332.00
13.02 Latex, Semi Gloss gal 12.00 478.25 143.48 5,739.05 1,721.71 7,460.76
13.20 Acri Color qrt 3.00 165.00 49.50 495.00 148.50 643.50
Wood surfaces sq.m 126.80
13.04 Enamel, Flatwall gal 7.00 440.00 132.00 3,080.00 924.00 4,004.00
13.05 Enamel, Semi Gloss gal 7.00 460.00 138.00 3,220.00 966.00 4,186.00
13.16 Paint Thinner gal 4.00 260.00 78.00 1,040.00 312.00 1,352.00
Sub-total 25,664.66

I. DIRECT COST 653,397.75


II. INDIRECT COST 19% of (I) 124,145.57
III. TAX 12% of (I+II) 93,305.20
IV. TOTAL CONSTRUCTION COST (I+II+III) 870,848.52
V. ENGINEERING OVERHEAD 1% of (IV) 8,708.49
VI. TOTAL PROJECT COST (IV+V) Php879,557.01
Php880,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2CL 7x14m Schoolbuilding 7 of 61


Three Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY THREE CLASSROOM 7 X 7 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 5,696.37 3,797.58 5,696.37 3,797.58 9,493.95
Services/Demobilization / Standard Billboard

Sub-total 9,493.95
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 178.50 0.00 20.00 0.00 3,570.00 3,570.00
1.02 Structural Excavation cu.m 36.34 0.00 200.00 0.00 7,267.20 7,267.20
1.03 Backfilling and Compaction cu.m 25.27 0.00 45.00 0.00 1,136.97 1,136.97
1.04 Gravel Bedding G-1 cu.m 11.14 552.00 180.00 6,148.73 2,005.02 8,153.75
1.06 Select Fill cu.m 17.85 150.00 45.00 2,677.50 803.25 3,480.75
1.05 Soil Poisoning sq.m 196.35 15.00 4.50 2,945.25 883.58 3,828.83
Sub-total 27,437.49
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 7.00
2.01 Portland Cement bag 63.00 223.00 42.50 14,049.00 2,677.50 16,726.50
2.05 Crushed Gravel 1" cu.m 7.00 552.00 150.00 3,864.00 1,050.00 4,914.00
2.03 Washed Sand cu.m 3.50 435.00 150.00 1,522.50 525.00 2,047.50
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 5.25
2.01 Portland Cement bag 48.00 223.00 42.50 10,704.00 2,040.00 12,744.00
2.02 Crushed Gravel 3/4" cu.m 5.25 655.00 175.00 3,438.75 918.75 4,357.50
2.03 Washed Sand cu.m 2.75 435.00 150.00 1,196.25 412.50 1,608.75
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 156,833.50
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 205.31
Column kg 1,183.19
Beam kg 904.29
3.01 Deformed Round Bars, Grade 40 kg 2,591.54 39.97 7.63 103,583.98 19,783.04 123,367.02
3.02 G.I. Tie Wire kg 52.00 50.00 9.00 2,600.00 468.00 3,068.00
Sub-total 126,435.02
4.00 Formworks

3CL 7x21m Schoolbuilding 8 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 98.20
4.01 Coco Lumber bd.ft 501.00 14.00 4.20 7,014.00 2,104.20 9,118.20
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 17.00 288.92 90.00 4,911.58 1,530.00 6,441.58
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Beams sq.m 84.70
4.01 Coco Lumber bd.ft 432.00 14.00 4.20 6,048.00 1,814.40 7,862.40
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 15.00 288.92 90.00 4,333.75 1,350.00 5,683.75
4.04 CWN, Assorted kg 7.00 60.00 18.00 420.00 126.00 546.00
Sub-total 30,275.93
5.00 Masonry Works
Masonry Wall sq.m 201.57
5.04 CHB 4" thk pc 2,520.00 9.50 2.25 23,940.00 5,670.00 29,610.00
5.02 Portland Cement bag 67.00 223.00 51.00 14,941.00 3,417.00 18,358.00
5.03 Washed Sand cu.m 9.00 435.00 180.00 3,915.00 1,620.00 5,535.00
5.06 10mm x 6m RSB kg 267.00 39.97 9.03 10,671.99 2,411.01 13,083.00
5.07 G.I. Tie Wire kg 6.00 50.00 15.00 300.00 90.00 390.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 403.14
5.02 Portland Cement bag 134.00 223.00 51.00 29,882.00 6,834.00 36,716.00
5.03 Washed Sand cu.m 14.00 435.00 180.00 6,090.00 2,520.00 8,610.00
Sub-total 112,926.00
6.00 Doors and Windows
D-1, Flush Door 0.90m x 2.10m on 100mm set 6.00 3,467.50 302.75 20,805.00 1,816.50 22,621.50
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 6.00 5,500.00 550.00 33,000.00 3,300.00 36,300.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.35 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 6.00 2,750.00 275.00 16,500.00 1,650.00 18,150.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.36 Accessories
Sub-total 77,071.50
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 971.04 41.19 12.48 39,997.14 12,115.66 52,112.79
7.03 LC 75 x 38 x 15 x 2.0mm kg 928.80 41.19 12.48 38,257.27 11,588.63 49,845.90
7.11 L 25 x 25 x 3mm kg 120.96 41.60 8.73 5,031.94 1,056.13 6,088.06
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 18.00 107.00 32.10 1,926.00 577.80 2,503.80
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.75 9,300.00 2,790.00 6,975.00 2,092.50 9,067.50
Anchor Bolt with Nuts and Washer, 16mmØ x pc 48.00 45.00 13.50 2,160.00 648.00 2,808.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 32.00 12.00 3.60 384.00 115.20 499.20
7.35 50mm x 200mm
7.46 Welding Rod kg 42.00 67.00 20.10 2,814.00 844.20 3,658.20
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 131,157.58
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m 228.80 360.00 72.00 82,368.00 16,473.60 98,841.60
8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,831.00 1.25 2,288.75 0.00 2,288.75
8.36 Roof Sealant L 3.00 239.80 719.40 0.00 719.40
Sub-total 112,729.75
9.00 Carpentry Works
Interior ceiling sq.m 165.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 722.00 40.00 12.65 28,880.00 9,133.30 38,013.30
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 57.00 288.92 81.75 16,468.25 4,659.75 21,128.00

3CL 7x21m Schoolbuilding 9 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.22 Finishing Nails kg 4.00 70.00 21.00 280.00 84.00 364.00
9.23 Common Wire Nails kg 13.00 50.00 15.00 650.00 195.00 845.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00 3,510.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 18.00 352.50 105.75 6,345.00 1,903.50 8,248.50
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 49.00 245.00 73.50 12,005.00 3,601.50 15,606.50
Sub-total 87,715.30
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 72.00 50.00 15.00 3,600.00 1,080.00 4,680.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 18.00 15.00 4.50 270.00 81.00 351.00
10.17 Utility Box, 2" x 4" G.I. pc 12.00 30.00 4.28 360.00 51.30 411.30
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 648.00 23.97 7.02 15,535.38 4,548.96 20,084.34
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 6.00 263.80 21.00 1,582.80 126.00 1,708.80
10.25 3-Gang Switch with Plate pc 3.00 208.00 29.59 624.00 88.76 712.76
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39 333.43
10.20 FL 2 x 40W Industrial Type set 12.00 1,200.00 126.00 14,400.00 1,512.00 15,912.00
10.21 FL 1 x 40W Industrial Type set 3.00 700.00 73.50 2,100.00 220.50 2,320.50
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 1.00 37.50 5.63 37.50 5.63 43.13
Sub-total 50,363.94
13.00 Painting Works
Concrete surfaces sq.m 403.14
13.18 Neutralizer gal 6.00 132.00 39.60 792.00 237.60 1,029.60
13.01 Latex, Flat gal 17.00 470.00 141.00 7,990.00 2,397.00 10,387.00
13.02 Latex, Semi Gloss gal 17.00 478.25 143.48 8,130.32 2,439.10 10,569.42
13.20 Acri Color qrt 5.00 165.00 49.50 825.00 247.50 1,072.50
Wood surfaces sq.m 190.20
13.04 Enamel, Flatwall gal 10.00 440.00 132.00 4,400.00 1,320.00 5,720.00
13.05 Enamel, Semi Gloss gal 10.00 460.00 138.00 4,600.00 1,380.00 5,980.00
13.16 Paint Thinner gal 5.00 260.00 78.00 1,300.00 390.00 1,690.00
Sub-total 36,448.52

I. DIRECT COST 958,888.48


II. INDIRECT COST 19% of (I) 182,188.81
III. TAX 12% of (I+II) 136,929.28
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,278,006.57
V. ENGINEERING OVERHEAD 1% of (IV) 12,780.07
VI. TOTAL PROJECT COST (IV+V) Php1,290,786.64
Php1,291,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

3CL 7x21m Schoolbuilding 10 of 61


REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF EDUCATION
DIVISION OF OZAMIZ CITY
Ozamiz City 7200

PROGRAM OF WORKS

Project Title: Completion Period: 30 calendar days


Minimum Required Manpower:
1-Civil Engr., 1-Construction Foreman, 3-Steelman,
REPAIR/RENOVATION OF NEW SPORTS UNIT OFFICE
3-Steelman Helper, 2-Carpenter, 2-Carpenter Helper,
3-Mason, 3-Mason Helper, 1 Operator, 6-Laborers
Plan: Minimum Required Equipment:
Location: Old Building, Division of Ozamiz City 1-Stake Truck, 1-Bagger Mixer, 1-Concrete vibrator, 1-Bar Cutter,
1-Plate Compactor, and Construction Tools
Item I.D. Item Description % of Total Unit Quantity Total Cost Remarks

I. DIRECT COST
General Requirements lot
1 Earthworks lot
2 Concreting Works cu.m
3 Rebar Works kg
4 Formworks sq.m
5 Masonry Works sq.m
6 Doors and Windows set
7 Steel Works kg
8 Roofing Works m
9 Carpentry Works sq.m
10 Electrical Works outlet
13 Painting Works sq.m

Sub-Total
II. INDIRECT COST 19% of (I)
Overhead Expenses (5%)
Contingencies (3%)
Miscellaneous (1%)
Contractor's Profit (10%)
Sub-Total
III. TAX 12% of (I+II)
Sub-Total
IV. HAULING COST
V. TOTAL CONSTRUCTION COST (I+II+III+IV)

Prepared: Noted:

ERIC PAUL M. CATULONG, C.E. DANILO P. ARROYO


Project Engineer, PFSED Division PFC

Reviewed: Recommending Approval Approved:


by the authority of:
MARK JUN B. GOMESERIA RONALD E. BENITEZ, C.E. OLIVER R. HERNANDEZ, C.E.
Cost and Assessment Supervisor Regional Lead Engineer Chief, PFSED

ERWIN G. IGARTA, C.E.


Area Manager, PFSED
Two Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
DIVISION OF OZAMIZ CITY
Ozamiz City 7200

(SCHOOL)

PROJECT:

SCHOOL:

LOCATION:
SUBJECT: BILL OF MATERIALS

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR

1.00 Earthworks
1.01 Clearing and Grubbing sq.m
1.02 Structural Excavation cu.m
1.03 Backfilling and Compaction cu.m
1.04 Gravel Bedding G-1 cu.m
1.06 Select Fill cu.m
1.05 Soil Poisoning sq.m
Sub-total 0.00
2.00 Concreting Works
Column Footing cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Wall Footing cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Column cu.m
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4" cu.m
2.03 Washed Sand cu.m
Beams cu.m
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4" cu.m
2.03 Washed Sand cu.m
Slab on Grade cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Ramp on Fill cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Sub-total 0.00
3.00 Rebar Works
Footing kg
Wall Footing kg
Column kg
Beam kg
Slab on Grade kg
Ramp on Fill kg
3.01 Deformed Round Bars, Grade 40 kg
3.02 G.I. Tie Wire kg
Sub-total 0.00
4.00 Formworks
Column sq.m
4.01 Coco Lumber bd.ft
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc
4.04 CWN, Assorted kg
Beams sq.m
4.01 Coco Lumber bd.ft
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc
4.04 CWN, Assorted kg
Sub-total 0.00
5.00 Masonry Works

2CL 7x18m Schoolbuilding 12 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Masonry Wall sq.m
5.05 CHB 6" thk pc
5.02 Portland Cement bag
5.03 Washed Sand cu.m
5.06 10mm x 6m RSB kg
5.07 G.I. Tie Wire kg
5.08 Concrete Louver Blocks pc
Plastering sq.m
5.02 Portland Cement bag
5.03 Washed Sand cu.m
Sub-total 0.00
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm


Wooden Jamb complete with Accessories (lever set
6.03 type door knob)

W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear


Glass Blades on JalouPlus Type Silver Colored set
Frame and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.07 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear


Glass Blades on JalouPlus Type Silver Colored
set
Frame and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.45 Accessories
Sub-total 0.00
7.00 Steel Works
7.08 LC 150 x 65 x 20 x 3.0mm kg
7.04 LC 100 x 50 x 15 x 1.5mm kg
7.11 L 25 x 25 x 3mm kg
7.17 Flat Bar 1" x 1/4" kg
7.18 Plain Round Bar 10mmØ x 6m pc
7.25 Steel Plate 1.20m x 2.40m x 10mm pc
Anchor Bolt with Nuts and Washer, 16mmØ x pc
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x pc
7.35 50mm x 200mm
7.46 Welding Rod kg
Hanger
11.04 G.I. Pipe 1"Ø Sch.40 pc
7.17 Flat Bar 1.5" x 1/4" kg
13.12 Primer, Zinc Chromate gal
Sub-total 0.00
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m


8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc


8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc
8.36 Roof Sealant L
Sub-total 0.00
9.00 Carpentry Works
Interior ceiling sq.m
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc
9.22 Finishing Nails kg
9.23 Common Wire Nails kg
9.42 Wood Preservative, Brown L
Exterior Ceiling sq.m
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft
9.06 Plywood, Marine 1/4" x 4' x 8' pc
9.22 Finishing Nails kg
9.23 Common Wire Nails kg
9.42 Wood Preservative, Brown L
9.19 Fascia Board, Fiber Cement 10" x 12' pc
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc
Blackboards sq.m
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft
9.43 Lawanit, 1/4" thk pc
9.22 Finishing Nails kg
9.23 Common Wire Nails kg
9.24 Concrete Nails kg

2CL 7x18m Schoolbuilding 13 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Sub-total 0.00
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc
10.06 RSC 20mmØ pc
10.34 Entrance Cap 20mm dia. pc
10.16 Junction Box, 4" x 4" G.I. pc
10.17 Utility Box, 2" x 4" G.I. pc
10.37 Grounding Rod, 2.4m x 16mm dia. pc
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m
10.12 5.5 mm2 THW Wire, Stranded m
10.28 Duplex C.O. with Plate pc
10.25 3-Gang Switch with Plate pc
10.23 Single Switch with Plate pc
10.20 FL 2 x 40W Industrial Type set
10.21 FL 1 x 40W Industrial Type set
10.48 Panel Box, Flush Type, 4 Branches set
10.40 Circuit Breaker, 40A 2P set
10.38 Circuit Breaker, 20A 2P set
10.58 Electrical Tape pc
Sub-total 0.00
13.00 Painting Works
Concrete surfaces sq.m
13.18 Neutralizer gal
13.01 Latex, Flat gal
13.14 Masonry Putty gal
13.02 Latex, Semi Gloss gal
13.20 Acri Color qrt
Wood surfaces sq.m
13.04 Enamel, Flatwall gal
13.15 Glazing Putty gal
13.05 Enamel, Semi Gloss gal
13.16 Paint Thinner gal
Sub-total 0.00

I. DIRECT COST 0.00


II. INDIRECT COST 9% of (I) 0.00
III. TAX 5% of (I+II) 0.00
V. TOTAL CONSTRUCTION COST (I+II+III) 0.00

Prepared by:

School Head

Reviewed by: Recommending Approval: Approved:

ERIC PAUL M. CATULONG SUSAN EPIFANIA B. CARPIO REBONFAMIL R. BAGUIO


Engineer - III Chief, SGOD Schools Division Superintendent

2CL 7x18m Schoolbuilding 14 of 61


Two Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY TWO CLASSROOM 7 X 9 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 4,448.38 2,965.59 4,448.38 2,965.59 7,413.96
Services/Demobilization / Standard Billboard

Sub-total 7,413.96
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 111,073.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
3.01 Deformed Round Bars, Grade 40 kg 1,830.84 39.97 7.63 73,178.71 13,976.08 87,154.79
3.02 G.I. Tie Wire kg 37.00 50.00 9.00 1,850.00 333.00 2,183.00
Sub-total 89,337.79
4.00 Formworks

2CL 7x18m Schoolbuilding 15 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 60.79
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 71.70
4.01 Coco Lumber bd.ft 365.70 14.00 4.20 5,119.80 1,535.94 6,655.74
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 13.00 288.92 90.00 3,755.92 1,170.00 4,925.92
4.04 CWN, Assorted kg 6.00 60.00 18.00 360.00 108.00 468.00
Sub-total 22,253.38
5.00 Masonry Works
Masonry Wall sq.m 170.18
5.04 CHB 4" thk pc 2,128.00 9.50 2.25 20,216.00 4,788.00 25,004.00
5.02 Portland Cement bag 56.00 223.00 51.00 12,488.00 2,856.00 15,344.00
5.03 Washed Sand cu.m 8.00 435.00 180.00 3,480.00 1,440.00 4,920.00
5.06 10mm x 6m RSB kg 226.00 39.97 9.03 9,033.22 2,040.78 11,074.00
5.07 G.I. Tie Wire kg 5.00 50.00 15.00 250.00 75.00 325.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 340.35
5.02 Portland Cement bag 113.00 223.00 51.00 25,199.00 5,763.00 30,962.00
5.03 Washed Sand cu.m 12.00 435.00 180.00 5,220.00 2,160.00 7,380.00
Sub-total 95,633.00
6.00 Doors and Windows
D-1, Flush Door 0.90m x 2.10m on 100mm set 4.00 3,467.50 302.75 13,870.00 1,211.00 15,081.00
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 4.00 5,500.00 550.00 22,000.00 2,200.00 24,200.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.35 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 4.00 2,750.00 275.00 11,000.00 1,100.00 12,100.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.36 Accessories
Sub-total 51,381.00
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 628.32 41.19 12.48 25,880.50 7,839.54 33,720.04
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,007.68 41.19 12.48 41,506.34 12,572.81 54,079.15
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 24.00 12.00 3.60 288.00 86.40 374.40
7.35 50mm x 200mm
7.46 Welding Rod kg 37.00 67.00 20.10 2,479.00 743.70 3,222.70
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 112,140.75
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 9.00 544.00 4,896.00 0.00 4,896.00
8.17 2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,581.00 1.25 1,976.25 0.00 1,976.25
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 98,155.05
9.00 Carpentry Works
Interior ceiling sq.m 140.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 612.00 40.00 12.65 24,480.00 7,741.80 32,221.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 48.00 288.92 81.75 13,868.00 3,924.00 17,792.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00

2CL 7x18m Schoolbuilding 16 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.23 Common Wire Nails kg 12.00 50.00 15.00 600.00 180.00 780.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 16.00 352.50 105.75 5,640.00 1,692.00 7,332.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 44.00 245.00 73.50 10,780.00 3,234.00 14,014.00
Sub-total 74,752.80
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 48.00 50.00 15.00 2,400.00 720.00 3,120.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 12.00 15.00 4.50 180.00 54.00 234.00
10.17 Utility Box, 2" x 4" G.I. pc 8.00 30.00 4.28 240.00 34.20 274.20
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 432.00 23.97 7.02 10,356.92 3,032.64 13,389.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93 222.29
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 34,902.35
13.00 Painting Works
Concrete surfaces sq.m 340.35
13.18 Neutralizer gal 5.00 132.00 39.60 660.00 198.00 858.00
13.01 Latex, Flat gal 14.00 470.00 141.00 6,580.00 1,974.00 8,554.00
13.02 Latex, Semi Gloss gal 14.00 478.25 143.48 6,695.56 2,008.67 8,704.23
13.20 Acri Color qrt 4.00 165.00 49.50 660.00 198.00 858.00
Wood surfaces sq.m 156.80
13.04 Enamel, Flatwall gal 8.00 440.00 132.00 3,520.00 1,056.00 4,576.00
13.05 Enamel, Semi Gloss gal 8.00 460.00 138.00 3,680.00 1,104.00 4,784.00
13.16 Paint Thinner gal 4.00 260.00 78.00 1,040.00 312.00 1,352.00
Sub-total 29,686.23

I. DIRECT COST 748,810.22


II. INDIRECT COST 19% of (I) 142,273.94
III. TAX 12% of (I+II) 106,930.10
IV. TOTAL CONSTRUCTION COST (I+II+III) 998,014.27
V. ENGINEERING OVERHEAD 1% of (IV) 9,980.14
VI. TOTAL PROJECT COST (IV+V) Php1,007,994.41
Php1,008,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2CL 7x18m Schoolbuilding 17 of 61


Three Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY THREE CLASSROOM 7 X 9 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 6,528.80 4,352.54 6,528.80 4,352.54 10,881.34
Services/Demobilization / Standard Billboard

Sub-total 10,881.34
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 229.50 0.00 20.00 0.00 4,590.00 4,590.00
1.02 Structural Excavation cu.m 39.22 0.00 200.00 0.00 7,843.20 7,843.20
1.03 Backfilling and Compaction cu.m 26.95 0.00 45.00 0.00 1,212.57 1,212.57
1.04 Gravel Bedding G-1 cu.m 13.93 552.00 180.00 7,688.81 2,507.22 10,196.03
1.06 Select Fill cu.m 22.95 150.00 45.00 3,442.50 1,032.75 4,475.25
1.05 Soil Poisoning sq.m 252.45 15.00 4.50 3,786.75 1,136.03 4,922.78
Sub-total 33,239.82
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 8.20
2.01 Portland Cement bag 74.00 223.00 42.50 16,502.00 3,145.00 19,647.00
2.05 Crushed Gravel 1" cu.m 8.25 552.00 150.00 4,554.00 1,237.50 5,791.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 6.27
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.02 Crushed Gravel 3/4" cu.m 6.50 655.00 175.00 4,257.50 1,137.50 5,395.00
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 164,789.75
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 238.58
Column kg 1,183.19
Beam kg 1,049.69
3.01 Deformed Round Bars, Grade 40 kg 2,770.21 39.97 7.63 110,725.18 21,146.91 131,872.09
3.02 G.I. Tie Wire kg 56.00 50.00 9.00 2,800.00 504.00 3,304.00
Sub-total 135,176.09
4.00 Formworks

3CL 7x27m Schoolbuilding 18 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 98.20
4.01 Coco Lumber bd.ft 501.00 14.00 4.20 7,014.00 2,104.20 9,118.20
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 17.00 288.92 90.00 4,911.58 1,530.00 6,441.58
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Beams sq.m 101.30
4.01 Coco Lumber bd.ft 516.90 14.00 4.20 7,236.60 2,170.98 9,407.58
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 18.00 288.92 90.00 5,200.50 1,620.00 6,820.50
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Sub-total 33,035.86
5.00 Masonry Works
Masonry Wall sq.m 242.07
5.04 CHB 4" thk pc 3,026.00 9.50 2.25 28,747.00 6,808.50 35,555.50
5.02 Portland Cement bag 80.00 223.00 51.00 17,840.00 4,080.00 21,920.00
5.03 Washed Sand cu.m 11.00 435.00 180.00 4,785.00 1,980.00 6,765.00
5.06 10mm x 6m RSB kg 321.00 39.97 9.03 12,830.37 2,898.63 15,729.00
5.07 G.I. Tie Wire kg 7.00 50.00 15.00 350.00 105.00 455.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 484.14
5.02 Portland Cement bag 160.00 223.00 51.00 35,680.00 8,160.00 43,840.00
5.03 Washed Sand cu.m 16.00 435.00 180.00 6,960.00 2,880.00 9,840.00
Sub-total 134,728.50
6.00 Doors and Windows
D-1, Flush Door 0.90m x 2.10m on 100mm set 6.00 3,467.50 302.75 20,805.00 1,816.50 22,621.50
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 6.00 5,500.00 550.00 33,000.00 3,300.00 36,300.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.35 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 6.00 2,750.00 275.00 16,500.00 1,650.00 18,150.00
Casing and Fixed Clear Glass Transom on 50 x
100 mm Wooden Jamb complete with
6.36 Accessories
Sub-total 77,071.50
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 971.04 41.19 12.48 39,997.14 12,115.66 52,112.79
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,490.08 41.19 12.48 61,376.40 18,591.71 79,968.11
7.11 L 25 x 25 x 3mm kg 171.70 41.60 8.73 7,142.55 1,499.11 8,641.67
7.17 Flat Bar 1" x 1/4" kg 49.56 41.60 8.73 2,061.70 432.72 2,494.41
7.18 Plain Round Bar 10mmØ x 6m pc 18.00 107.00 32.10 1,926.00 577.80 2,503.80
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.75 9,300.00 2,790.00 6,975.00 2,092.50 9,067.50
Anchor Bolt with Nuts and Washer, 16mmØ x pc 48.00 45.00 13.50 2,160.00 648.00 2,808.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 32.00 12.00 3.60 384.00 115.20 499.20
7.35 50mm x 200mm
7.46 Welding Rod kg 54.00 67.00 20.10 3,618.00 1,085.40 4,703.40
13.12 Primer, Zinc Chromate gal 5.00 537.00 161.10 2,685.00 805.50 3,490.50
Sub-total 166,289.39
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m 291.20 360.00 72.00 104,832.00 20,966.40 125,798.40
8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 13.00 544.00 7,072.00 0.00 7,072.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 2,330.00 1.25 2,912.50 0.00 2,912.50
8.36 Roof Sealant L 3.00 239.80 719.40 0.00 719.40
Sub-total 141,942.30
9.00 Carpentry Works
Interior ceiling sq.m 210.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 918.00 40.00 12.65 36,720.00 11,612.70 48,332.70
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 72.00 288.92 81.75 20,802.00 5,886.00 26,688.00

3CL 7x27m Schoolbuilding 19 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.22 Finishing Nails kg 4.00 70.00 21.00 280.00 84.00 364.00
9.23 Common Wire Nails kg 17.00 50.00 15.00 850.00 255.00 1,105.00
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00 3,510.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 21.00 352.50 105.75 7,402.50 2,220.75 9,623.25
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 59.00 245.00 73.50 14,455.00 4,336.50 18,791.50
Sub-total 108,414.45
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 72.00 50.00 15.00 3,600.00 1,080.00 4,680.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 18.00 15.00 4.50 270.00 81.00 351.00
10.17 Utility Box, 2" x 4" G.I. pc 12.00 30.00 4.28 360.00 51.30 411.30
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 648.00 23.97 7.02 15,535.38 4,548.96 20,084.34
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 6.00 263.80 21.00 1,582.80 126.00 1,708.80
10.25 3-Gang Switch with Plate pc 3.00 208.00 29.59 624.00 88.76 712.76
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39 333.43
10.20 FL 2 x 40W Industrial Type set 12.00 1,200.00 126.00 14,400.00 1,512.00 15,912.00
10.21 FL 1 x 40W Industrial Type set 3.00 700.00 73.50 2,100.00 220.50 2,320.50
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 3.00 37.50 5.63 112.50 16.88 129.38
Sub-total 50,450.19
13.00 Painting Works
Concrete surfaces sq.m 484.14
13.18 Neutralizer gal 7.00 132.00 39.60 924.00 277.20 1,201.20
13.01 Latex, Flat gal 20.00 470.00 141.00 9,400.00 2,820.00 12,220.00
13.02 Latex, Semi Gloss gal 20.00 478.25 143.48 9,565.08 2,869.52 12,434.61
13.20 Acri Color qrt 5.00 165.00 49.50 825.00 247.50 1,072.50
Wood surfaces sq.m 235.20
13.04 Enamel, Flatwall gal 12.00 440.00 132.00 5,280.00 1,584.00 6,864.00
13.05 Enamel, Semi Gloss gal 12.00 460.00 138.00 5,520.00 1,656.00 7,176.00
13.16 Paint Thinner gal 6.00 260.00 78.00 1,560.00 468.00 2,028.00
Sub-total 42,996.31

I. DIRECT COST 1,099,015.50


II. INDIRECT COST 19% of (I) 208,812.95
III. TAX 12% of (I+II) 156,939.41
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,464,767.86
V. ENGINEERING OVERHEAD 1% of (IV) 14,647.68
VI. TOTAL PROJECT COST (IV+V) Php1,479,415.54
Php1,480,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

3CL 7x27m Schoolbuilding 20 of 61


Four Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY FOUR CLASSROOM 7 X 9 (MODIFIED)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 8,451.37 5,634.24 8,451.37 5,634.24 14,085.61
Services/Demobilization / Standard Billboard

Sub-total 14,085.61
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 306.00 0.00 20.00 0.00 6,120.00 6,120.00
1.02 Structural Excavation cu.m 48.84 0.00 200.00 0.00 9,768.00 9,768.00
1.03 Backfilling and Compaction cu.m 33.32 0.00 45.00 0.00 1,499.18 1,499.18
1.04 Gravel Bedding G-1 cu.m 18.41 552.00 180.00 10,159.56 3,312.90 13,472.46
1.06 Select Fill cu.m 30.60 150.00 45.00 4,590.00 1,377.00 5,967.00
1.05 Soil Poisoning sq.m 336.60 15.00 4.50 5,049.00 1,514.70 6,563.70
Sub-total 43,390.34
2.00 Concreting Works
Column Footing cu.m 4.83
2.01 Portland Cement bag 44.00 223.00 42.50 9,812.00 1,870.00 11,682.00
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
2.03 Washed Sand cu.m 2.50 435.00 150.00 1,087.50 375.00 1,462.50
Wall Footing cu.m 10.70
2.01 Portland Cement bag 97.00 223.00 42.50 21,631.00 4,122.50 25,753.50
2.05 Crushed Gravel 1" cu.m 10.75 552.00 150.00 5,934.00 1,612.50 7,546.50
2.03 Washed Sand cu.m 5.50 435.00 150.00 2,392.50 825.00 3,217.50
Column cu.m 6.15
2.01 Portland Cement bag 56.00 223.00 42.50 12,488.00 2,380.00 14,868.00
2.02 Crushed Gravel 3/4" cu.m 6.25 655.00 175.00 4,093.75 1,093.75 5,187.50
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Beams cu.m 8.11
2.01 Portland Cement bag 73.00 223.00 42.50 16,279.00 3,102.50 19,381.50
2.02 Crushed Gravel 3/4" cu.m 8.25 655.00 175.00 5,403.75 1,443.75 6,847.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Slab on Grade cu.m 30.60
2.01 Portland Cement bag 276.00 223.00 42.50 61,548.00 11,730.00 73,278.00
2.05 Crushed Gravel 1" cu.m 30.75 552.00 150.00 16,974.00 4,612.50 21,586.50
2.03 Washed Sand cu.m 15.50 435.00 150.00 6,742.50 2,325.00 9,067.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 210,188.00
3.00 Rebar Works
Footing kg 337.91
Wall Footing kg 313.33
Column kg 1,323.73
Beam kg 1,358.87
3.01 Deformed Round Bars, Grade 40 kg 3,333.84 39.97 7.63 133,253.46 25,449.48 158,702.94
3.02 G.I. Tie Wire kg 67.00 50.00 9.00 3,350.00 603.00 3,953.00
Sub-total 162,655.94
4.00 Formworks

4CL 7x36m Schoolbuilding 21 of 61


Four Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 107.55
4.01 Coco Lumber bd.ft 548.70 14.00 4.20 7,681.80 2,304.54 9,986.34
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 19.00 288.92 90.00 5,489.42 1,710.00 7,199.42
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Beams sq.m 130.90
4.01 Coco Lumber bd.ft 667.80 14.00 4.20 9,349.20 2,804.76 12,153.96
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 23.00 288.92 90.00 6,645.08 2,070.00 8,715.08
4.04 CWN, Assorted kg 10.00 60.00 18.00 600.00 180.00 780.00
Sub-total 39,458.80
5.00 Masonry Works
Masonry Wall sq.m 313.61
5.04 CHB 4" thk pc 3,921.00 9.50 2.25 37,249.50 8,822.25 46,071.75
5.02 Portland Cement bag 103.00 223.00 51.00 22,969.00 5,253.00 28,222.00
5.03 Washed Sand cu.m 14.00 435.00 180.00 6,090.00 2,520.00 8,610.00
5.06 10mm x 6m RSB kg 416.00 39.97 9.03 16,627.52 3,756.48 20,384.00
5.07 G.I. Tie Wire kg 9.00 50.00 15.00 450.00 135.00 585.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 627.21
5.02 Portland Cement bag 207.00 223.00 51.00 46,161.00 10,557.00 56,718.00
5.03 Washed Sand cu.m 21.00 435.00 180.00 9,135.00 3,780.00 12,915.00
Sub-total 174,129.75
6.00 Doors and Windows
D-1, Flush Door 0.90m x 2.10m on 100mm set 8.00 3,467.50 302.75 27,740.00 2,422.00 30,162.00
6.34 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Clear glass jalousie


window on standard aluminum housing with
set 8.00 5,500.00 550.00 44,000.00 4,400.00 48,400.00
fixed clear glass transom on 100mm yakal or
guijo wooden jamb.
6.35

W - 2, (1.3 x 1.6 m) Clear glass jalousie window


on standard aluminum housing with fixed clear
set 8.00 2,750.00 275.00 22,000.00 2,200.00 24,200.00
glass transom on 100mm yakal or guijo wooden
jamb.
6.36
Sub-total 102,762.00
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 1,370.88 41.19 12.48 56,466.55 17,104.46 73,571.00
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,972.48 41.19 12.48 81,246.45 24,610.61 105,857.06
7.11 L 25 x 25 x 3mm kg 212.58 41.60 8.73 8,843.16 1,856.05 10,699.21
7.17 Flat Bar 1" x 1/4" kg 63.72 41.60 8.73 2,650.75 556.35 3,207.10
7.18 Plain Round Bar 10mmØ x 6m pc 24.00 107.00 32.10 2,568.00 770.40 3,338.40
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 1.00 9,300.00 2,790.00 9,300.00 2,790.00 12,090.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 64.00 45.00 13.50 2,880.00 864.00 3,744.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 40.00 12.00 3.60 480.00 144.00 624.00
7.35 50mm x 200mm
7.46 Welding Rod kg 73.00 67.00 20.10 4,891.00 1,467.30 6,358.30
13.12 Primer, Zinc Chromate gal 7.00 537.00 161.10 3,759.00 1,127.70 4,886.70
Sub-total 224,375.78
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m 384.80 360.00 72.00 138,528.00 27,705.60 166,233.60
8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 17.00 544.00 9,248.00 0.00 9,248.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 3,079.00 1.25 3,848.75 0.00 3,848.75
8.36 Roof Sealant L 4.00 239.80 959.20 0.00 959.20
Sub-total 185,729.55
9.00 Carpentry Works
Interior ceiling sq.m 280.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 1,224.00 40.00 12.65 48,960.00 15,483.60 64,443.60
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 96.00 288.92 81.75 27,736.00 7,848.00 35,584.00
9.22 Finishing Nails kg 6.00 70.00 21.00 420.00 126.00 546.00
9.23 Common Wire Nails kg 23.00 50.00 15.00 1,150.00 345.00 1,495.00

4CL 7x36m Schoolbuilding 22 of 61


Four Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.42 Wood Preservative, Brown L 4.00 900.00 270.00 3,600.00 1,080.00 4,680.00
Others
9.19 Fascia Board, Fiber Cement 10" x 12' pc 26.00 352.50 105.75 9,165.00 2,749.50 11,914.50
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 74.00 245.00 73.50 18,130.00 5,439.00 23,569.00
Sub-total 142,232.10
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 96.00 50.00 15.00 4,800.00 1,440.00 6,240.00
10.07 RSC 25mmØ pc 1.00 175.00 52.50 175.00 52.50 227.50
10.36 Entrance Cap 25mm dia. pc 1.00 70.00 10.50 70.00 10.50 80.50
10.16 Junction Box, 4" x 4" G.I. pc 24.00 15.00 4.50 360.00 108.00 468.00
10.17 Utility Box, 2" x 4" G.I. pc 16.00 30.00 4.28 480.00 68.40 548.40
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 864.00 23.97 7.02 20,713.85 6,065.28 26,779.13
10.14 14.0 mm2 THW Wire, Stranded m 10.00 60.00 25.35 600.00 253.50 853.50
10.28 Duplex C.O. with Plate pc 8.00 263.80 21.00 2,110.40 168.00 2,278.40
10.25 3-Gang Switch with Plate pc 4.00 208.00 29.59 832.00 118.35 950.35
10.23 Single Switch with Plate pc 4.00 97.68 13.46 390.72 53.85 444.57
10.20 FL 2 x 40W Industrial Type set 16.00 1,200.00 126.00 19,200.00 2,016.00 21,216.00
10.21 FL 1 x 40W Industrial Type set 4.00 700.00 73.50 2,800.00 294.00 3,094.00
10.49 Panel Box, Flush Type, 8 Branches set 1.00 1,580.00 237.00 1,580.00 237.00 1,817.00
10.42 Circuit Breaker, 60A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 4.00 313.00 46.95 1,252.00 187.80 1,439.80
10.58 Electrical Tape pc 4.00 37.50 5.63 150.00 22.50 172.50
Sub-total 67,289.58
13.00 Painting Works
Concrete surfaces sq.m 627.21
13.18 Neutralizer gal 8.00 132.00 39.60 1,056.00 316.80 1,372.80
13.01 Latex, Flat gal 26.00 470.00 141.00 12,220.00 3,666.00 15,886.00
13.02 Latex, Semi Gloss gal 26.00 478.25 143.48 12,434.61 3,730.38 16,164.99
13.20 Acri Color qrt 7.00 165.00 49.50 1,155.00 346.50 1,501.50
Wood surfaces sq.m 313.60
13.04 Enamel, Flatwall gal 16.00 440.00 132.00 7,040.00 2,112.00 9,152.00
13.05 Enamel, Semi Gloss gal 16.00 460.00 138.00 7,360.00 2,208.00 9,568.00
13.16 Paint Thinner gal 8.00 260.00 78.00 2,080.00 624.00 2,704.00
Sub-total 56,349.29

I. DIRECT COST 1,422,646.74


II. INDIRECT COST 19% of (I) 270,302.88
III. TAX 12% of (I+II) 203,153.95
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,896,103.58
V. ENGINEERING OVERHEAD 1% of (IV) 18,961.04
VI. TOTAL PROJECT COST (IV+V) Php1,915,064.61
Php1,916,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

4CL 7x36m Schoolbuilding 23 of 61


One Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE CLASSROOM 7 X 9 (ORIGINAL)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 2,750.07 1,833.38 2,750.07 1,833.38 4,583.44
Services/Demobilization / Standard Billboard

Sub-total 4,583.44
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 76.50 0.00 20.00 0.00 1,530.00 1,530.00
1.02 Structural Excavation cu.m 14.69 0.00 200.00 0.00 2,937.60 2,937.60
1.03 Backfilling and Compaction cu.m 10.03 0.00 45.00 0.00 451.26 451.26
1.04 Gravel Bedding G-1 cu.m 4.76 552.00 180.00 2,625.86 856.26 3,482.12
1.06 Select Fill cu.m 7.65 150.00 45.00 1,147.50 344.25 1,491.75
1.05 Soil Poisoning sq.m 84.15 15.00 4.50 1,262.25 378.68 1,640.93
Sub-total 11,533.66
2.00 Concreting Works
Column Footing cu.m 1.46
2.01 Portland Cement bag 14.00 223.00 42.50 3,122.00 595.00 3,717.00
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Wall Footing cu.m 3.20
2.01 Portland Cement bag 29.00 223.00 42.50 6,467.00 1,232.50 7,699.50
2.05 Crushed Gravel 1" cu.m 3.25 552.00 150.00 1,794.00 487.50 2,281.50
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Column cu.m 2.14
2.01 Portland Cement bag 20.00 223.00 42.50 4,460.00 850.00 5,310.00
2.02 Crushed Gravel 3/4" cu.m 2.25 655.00 175.00 1,473.75 393.75 1,867.50
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Beams cu.m 2.60
2.01 Portland Cement bag 24.00 223.00 42.50 5,352.00 1,020.00 6,372.00
2.02 Crushed Gravel 3/4" cu.m 2.75 655.00 175.00 1,801.25 481.25 2,282.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Slab on Grade cu.m 7.65
2.01 Portland Cement bag 69.00 223.00 42.50 15,387.00 2,932.50 18,319.50
2.05 Crushed Gravel 1" cu.m 7.75 552.00 150.00 4,278.00 1,162.50 5,440.50
2.03 Washed Sand cu.m 4.00 435.00 150.00 1,740.00 600.00 2,340.00
Ramp on Fill cu.m 0.32
2.01 Portland Cement bag 3.00 223.00 42.50 669.00 127.50 796.50
2.05 Crushed Gravel 1" cu.m 0.50 552.00 150.00 276.00 75.00 351.00
2.03 Washed Sand cu.m 0.25 435.00 150.00 108.75 37.50 146.25
Sub-total 61,048.00
3.00 Rebar Works
Footing kg 111.16
Wall Footing kg 96.19
Column kg 445.17
Beam kg 431.34
Slab on Grade kg 201.22
Ramp on Fill kg 13.64
3.01 Deformed Round Bars, Grade 40 kg 1,298.71 39.97 7.63 51,909.48 9,913.96 61,823.44
3.02 G.I. Tie Wire kg 26.00 50.00 9.00 1,300.00 234.00 1,534.00
Sub-total 63,357.44
4.00 Formworks

1CL 7x9m Schoolbuilding 24 of 61


One Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 37.41
4.01 Coco Lumber bd.ft 190.80 14.00 4.20 2,671.20 801.36 3,472.56
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 7.00 288.92 90.00 2,022.42 630.00 2,652.42
4.04 CWN, Assorted kg 3.00 60.00 18.00 180.00 54.00 234.00
Beams sq.m 42.10
4.01 Coco Lumber bd.ft 214.80 14.00 4.20 3,007.20 902.16 3,909.36
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 8.00 288.92 90.00 2,311.33 720.00 3,031.33
4.04 CWN, Assorted kg 4.00 60.00 18.00 240.00 72.00 312.00
Sub-total 13,611.67
5.00 Masonry Works
Masonry Wall sq.m 98.28
5.05 CHB 6" thk pc 1,229.00 12.00 3.00 14,748.00 3,687.00 18,435.00
5.02 Portland Cement bag 50.00 223.00 51.00 11,150.00 2,550.00 13,700.00
5.03 Washed Sand cu.m 5.00 435.00 180.00 2,175.00 900.00 3,075.00
5.06 10mm x 6m RSB kg 131.00 39.97 9.03 5,236.07 1,182.93 6,419.00
5.07 G.I. Tie Wire kg 3.00 50.00 15.00 150.00 45.00 195.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 196.56
5.02 Portland Cement bag 65.00 223.00 51.00 14,495.00 3,315.00 17,810.00
5.03 Washed Sand cu.m 7.00 435.00 180.00 3,045.00 1,260.00 4,305.00
Sub-total 64,563.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 2.00 5,917.50 887.63 11,835.00 1,775.25 13,610.25
6.03 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 6,700.00 1,005.00 13,400.00 2,010.00 15,410.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.07 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 3,350.00 502.50 6,700.00 1,005.00 7,705.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.45 Accessories
Sub-total 36,725.25
7.00 Steel Works
7.08 LC 150 x 65 x 20 x 3.0mm kg 500.40 41.19 12.48 20,611.48 6,243.49 26,854.96
7.04 LC 100 x 50 x 15 x 1.5mm kg 395.14 41.19 12.48 16,275.65 4,930.11 21,205.76
7.11 L 25 x 25 x 3mm kg 98.11 41.60 8.73 4,081.46 856.64 4,938.10
7.17 Flat Bar 1" x 1/4" kg 21.24 41.60 8.73 883.58 185.45 1,069.03
7.18 Plain Round Bar 10mmØ x 6m pc 6.00 107.00 32.10 642.00 192.60 834.60
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.25 9,300.00 2,790.00 2,325.00 697.50 3,022.50
Anchor Bolt with Nuts and Washer, 16mmØ x pc 16.00 45.00 13.50 720.00 216.00 936.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 16.00 12.00 3.60 192.00 57.60 249.60
7.35 50mm x 200mm
7.46 Welding Rod kg 21.00 67.00 20.10 1,407.00 422.10 1,829.10
13.12 Primer, Zinc Chromate gal 2.00 537.00 161.10 1,074.00 322.20 1,396.20
Sub-total 62,335.85
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 104.00 360.00 72.00 37,440.00 7,488.00 44,928.00
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 5.00 544.00 2,720.00 0.00 2,720.00
8.17 2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 832.00 1.25 1,040.00 0.00 1,040.00
8.36 Roof Sealant L 1.00 239.80 239.80 0.00 239.80
Sub-total 54,367.80
9.00 Carpentry Works
Interior ceiling sq.m 70.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 306.00 40.00 12.65 12,240.00 3,870.90 16,110.90
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 24.00 288.92 81.75 6,934.00 1,962.00 8,896.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 6.00 50.00 15.00 300.00 90.00 390.00

1CL 7x9m Schoolbuilding 25 of 61


One Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
Exterior Ceiling sq.m 31.72
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 139.00 40.00 12.65 5,560.00 1,758.35 7,318.35
9.06 Plywood, Marine 1/4" x 4' x 8' pc 11.00 340.00 108.00 3,740.00 1,188.00 4,928.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 3.00 50.00 15.00 150.00 45.00 195.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 12.00 352.50 105.75 4,230.00 1,269.00 5,499.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 6.00 245.00 73.50 1,470.00 441.00 1,911.00
Blackboards sq.m 5.76
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 37.00 50.00 18.60 1,850.00 688.20 2,538.20
9.43 Lawanit, 1/4" thk pc 2.00 280.00 84.00 560.00 168.00 728.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 1.00 50.00 15.00 50.00 15.00 65.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 51,374.45
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 20.00 50.00 15.00 1,000.00 300.00 1,300.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 6.00 15.00 4.50 90.00 27.00 117.00
10.17 Utility Box, 2" x 4" G.I. pc 4.00 30.00 4.28 120.00 17.10 137.10
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 180.00 23.97 7.02 4,315.38 1,263.60 5,578.98
10.28 Duplex C.O. with Plate pc 2.00 263.80 21.00 527.60 42.00 569.60
10.25 3-Gang Switch with Plate pc 1.00 208.00 29.59 208.00 29.59 237.59
10.23 Single Switch with Plate pc 1.00 97.68 13.46 97.68 13.46 111.14
10.20 FL 2 x 40W Industrial Type set 4.00 1,200.00 126.00 4,800.00 504.00 5,304.00
10.21 FL 1 x 40W Industrial Type set 1.00 700.00 73.50 700.00 73.50 773.50
10.46 Safety Switch 30A 2P set 1.00 603.25 90.49 603.25 90.49 693.74
10.58 Electrical Tape pc 1.00 37.50 5.63 37.50 5.63 43.13
Sub-total 15,242.03
13.00 Painting Works
Concrete surfaces sq.m 196.56
13.18 Neutralizer gal 3.00 132.00 39.60 396.00 118.80 514.80
13.01 Latex, Flat gal 8.00 470.00 141.00 3,760.00 1,128.00 4,888.00
13.14 Masonry Putty gal 8.00 319.00 95.70 2,552.00 765.60 3,317.60
13.02 Latex, Semi Gloss gal 8.00 478.25 143.48 3,826.03 1,147.81 4,973.84
13.20 Acri Color qrt 2.00 165.00 49.50 330.00 99.00 429.00
Wood surfaces sq.m 84.16
13.04 Enamel, Flatwall gal 5.00 440.00 132.00 2,200.00 660.00 2,860.00
13.15 Glazing Putty gal 5.00 492.00 147.60 2,460.00 738.00 3,198.00
13.05 Enamel, Semi Gloss gal 5.00 460.00 138.00 2,300.00 690.00 2,990.00
13.16 Paint Thinner gal 3.00 260.00 78.00 780.00 234.00 1,014.00
Sub-total 24,185.24

I. DIRECT COST 462,927.84


II. INDIRECT COST 19% of (I) 87,956.29
III. TAX 12% of (I+II) 66,106.10
IV. TOTAL CONSTRUCTION COST (I+II+III) 616,990.22
V. ENGINEERING OVERHEAD 1% of (IV) 6,169.90
VI. TOTAL PROJECT COST (IV+V) Php623,160.13
Php624,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

1CL 7x9m Schoolbuilding 26 of 61


Two Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY TWO CLASSROOM 7 X 9 (ORIGINAL)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 5,002.00 3,334.67 5,002.00 3,334.67 8,336.67
Services/Demobilization / Standard Billboard

Sub-total 8,336.67
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 111,073.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
Slab on Grade kg 402.44
Ramp on Fill kg 27.27
3.01 Deformed Round Bars, Grade 40 kg 2,260.55 39.97 7.63 90,354.23 17,256.35 107,610.58
3.02 G.I. Tie Wire kg 46.00 50.00 9.00 2,300.00 414.00 2,714.00
Sub-total 110,324.58
4.00 Formworks
Column sq.m 60.79

2CL 7x18m Schoolbuilding 27 of 61


Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 71.70
4.01 Coco Lumber bd.ft 365.70 14.00 4.20 5,119.80 1,535.94 6,655.74
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 13.00 288.92 90.00 3,755.92 1,170.00 4,925.92
4.04 CWN, Assorted kg 6.00 60.00 18.00 360.00 108.00 468.00
Sub-total 22,253.38
5.00 Masonry Works
Masonry Wall sq.m 170.18
5.05 CHB 6" thk pc 2,128.00 12.00 3.00 25,536.00 6,384.00 31,920.00
5.02 Portland Cement bag 86.00 223.00 51.00 19,178.00 4,386.00 23,564.00
5.03 Washed Sand cu.m 8.00 435.00 180.00 3,480.00 1,440.00 4,920.00
5.06 10mm x 6m RSB kg 226.00 39.97 9.03 9,033.22 2,040.78 11,074.00
5.07 G.I. Tie Wire kg 5.00 50.00 15.00 250.00 75.00 325.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 340.35
5.02 Portland Cement bag 113.00 223.00 51.00 25,199.00 5,763.00 30,962.00
5.03 Washed Sand cu.m 12.00 435.00 180.00 5,220.00 2,160.00 7,380.00
Sub-total 110,769.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 4.00 5,917.50 887.63 23,670.00 3,550.50 27,220.50
6.03 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 4.00 6,700.00 1,005.00 26,800.00 4,020.00 30,820.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.07 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 4.00 3,350.00 502.50 13,400.00 2,010.00 15,410.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.45 Accessories
Sub-total 73,450.50
7.00 Steel Works
7.08 LC 150 x 65 x 20 x 3.0mm kg 917.40 41.19 12.48 37,787.71 11,446.39 49,234.10
7.04 LC 100 x 50 x 15 x 1.5mm kg 758.02 41.19 12.48 31,222.68 9,457.76 40,680.44
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 24.00 12.00 3.60 288.00 86.40 374.40
7.35 50mm x 200mm
7.46 Welding Rod kg 37.00 67.00 20.10 2,479.00 743.70 3,222.70
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 114,256.09
8.00 Roofing Works

Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk

Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 9.00 544.00 4,896.00 0.00 4,896.00
8.17 2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00


8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,581.00 1.25 1,976.25 0.00 1,976.25
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 98,155.05
9.00 Carpentry Works
Interior ceiling sq.m 140.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 612.00 40.00 12.65 24,480.00 7,741.80 32,221.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 48.00 288.92 81.75 13,868.00 3,924.00 17,792.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 12.00 50.00 15.00 600.00 180.00 780.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Exterior Ceiling sq.m 55.12
2CL 7x18m Schoolbuilding 28 of 61
Two Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 241.00 40.00 12.65 9,640.00 3,048.65 12,688.65
9.06 Plywood, Marine 1/4" x 4' x 8' pc 19.00 340.00 108.00 6,460.00 2,052.00 8,512.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00 325.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 16.00 352.50 105.75 5,640.00 1,692.00 7,332.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 10.00 245.00 73.50 2,450.00 735.00 3,185.00
Blackboards sq.m 11.52
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 74.00 50.00 18.60 3,700.00 1,376.40 5,076.40
9.43 Lawanit, 1/4" thk pc 4.00 280.00 84.00 1,120.00 336.00 1,456.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 2.00 50.00 15.00 100.00 30.00 130.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 93,645.85
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 48.00 50.00 15.00 2,400.00 720.00 3,120.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 12.00 15.00 4.50 180.00 54.00 234.00
10.17 Utility Box, 2" x 4" G.I. pc 8.00 30.00 4.28 240.00 34.20 274.20
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 432.00 23.97 7.02 10,356.92 3,032.64 13,389.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93 222.29
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 34,902.35
13.00 Painting Works
Concrete surfaces sq.m 340.35
13.18 Neutralizer gal 5.00 132.00 39.60 660.00 198.00 858.00
13.01 Latex, Flat gal 14.00 470.00 141.00 6,580.00 1,974.00 8,554.00
13.14 Masonry Putty gal 14.00 319.00 95.70 4,466.00 1,339.80 5,805.80
13.02 Latex, Semi Gloss gal 14.00 478.25 143.48 6,695.56 2,008.67 8,704.23
13.20 Acri Color qrt 4.00 165.00 49.50 660.00 198.00 858.00
Wood surfaces sq.m 168.32
13.04 Enamel, Flatwall gal 9.00 440.00 132.00 3,960.00 1,188.00 5,148.00
13.15 Glazing Putty gal 9.00 492.00 147.60 4,428.00 1,328.40 5,756.40
13.05 Enamel, Semi Gloss gal 9.00 460.00 138.00 4,140.00 1,242.00 5,382.00
13.16 Paint Thinner gal 5.00 260.00 78.00 1,300.00 390.00 1,690.00
Sub-total 42,756.43

I. DIRECT COST 842,003.81


II. INDIRECT COST 19% of (I) 159,980.72
III. TAX 12% of (I+II) 120,238.14
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,122,222.68
V. ENGINEERING OVERHEAD 1% of (IV) 11,222.23
VI. TOTAL PROJECT COST (IV+V) Php1,133,444.90
Php1,134,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

2CL 7x18m Schoolbuilding 29 of 61


Republic of the Philippines
DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY TWO CLASSROOM 7 X 9 (ORIGINAL)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 5,049.13 3,366.09 5,049.13 3,366.09 8,415.22
Services/Demobilization / Standard Billboard

Sub-total 8,415.22
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
0.1mm Thick Concrete Ledge cu.m 0.14
2.01 Portland Cement bag 2.00 223.00 42.50 446.00 85.00 531.00
2.05 Crushed Gravel 1" cu.m 0.25 552.00 150.00 138.00 37.50 175.50
2.03 Washed Sand cu.m 0.25 435.00 150.00 108.75 37.50 146.25
Sub-total 111,926.50
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
Slab on Grade kg 402.44
Ramp on Fill kg 27.27
0.1mm Thick Concrete Ledge kg 13.11
3.01 Deformed Round Bars, Grade 40 kg 2,273.66 39.97 7.63 90,878.17 17,356.42 108,234.59
3.02 G.I. Tie Wire kg 46.00 50.00 9.00 2,300.00 414.00 2,714.00
Sub-total 110,948.59
4.00 Formworks
Column sq.m 60.79
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 71.70
4.01 Coco Lumber bd.ft 365.70 14.00 4.20 5,119.80 1,535.94 6,655.74
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 13.00 288.92 90.00 3,755.92 1,170.00 4,925.92
4.04 CWN, Assorted kg 6.00 60.00 18.00 360.00 108.00 468.00
Sub-total 22,253.38
5.00 Masonry Works
Masonry Wall sq.m 170.18
5.05 CHB 6" thk pc 2,128.00 12.00 3.00 25,536.00 6,384.00 31,920.00
5.02 Portland Cement bag 86.00 223.00 51.00 19,178.00 4,386.00 23,564.00
5.03 Washed Sand cu.m 8.00 435.00 180.00 3,480.00 1,440.00 4,920.00
5.06 10mm x 6m RSB kg 226.00 39.97 9.03 9,033.22 2,040.78 11,074.00
5.07 G.I. Tie Wire kg 5.00 50.00 15.00 250.00 75.00 325.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 340.35
5.02 Portland Cement bag 113.00 223.00 51.00 25,199.00 5,763.00 30,962.00
5.03 Washed Sand cu.m 12.00 435.00 180.00 5,220.00 2,160.00 7,380.00
Sub-total 110,769.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 4.00 5,917.50 887.63 23,670.00 3,550.50 27,220.50
6.03 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 4.00 6,700.00 1,005.00 26,800.00 4,020.00 30,820.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.07 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 4.00 3,350.00 502.50 13,400.00 2,010.00 15,410.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.45 Accessories
Sub-total 73,450.50
7.00 Steel Works
7.08 LC 150 x 65 x 20 x 3.0mm kg 917.40 41.19 12.48 37,787.71 11,446.39 49,234.10
7.04 LC 100 x 50 x 15 x 1.5mm kg 758.02 41.19 12.48 31,222.68 9,457.76 40,680.44
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x
pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 24.00 12.00 3.60 288.00 86.40 374.40
7.35 50mm x 200mm
7.46 Welding Rod kg 37.00 67.00 20.10 2,479.00 743.70 3,222.70
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 114,256.09
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x
8.17 pc 9.00 544.00 4,896.00 0.00 4,896.00
2.440m x 0.4mm thk

Flashing, Pre-Painted, Ordinary, 0.610m x


8.19 pc 544.00 5,440.00 0.00 5,440.00
2.440m x 0.4mm thk 10.00
8.35 Teckscrew 2-1/2" pc 1,581.00 1.25 1,976.25 0.00 1,976.25
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 98,155.05
9.00 Carpentry Works
Interior ceiling sq.m 140.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 612.00 40.00 12.65 24,480.00 7,741.80 32,221.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 48.00 288.92 81.75 13,868.00 3,924.00 17,792.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 12.00 50.00 15.00 600.00 180.00 780.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Exterior Ceiling sq.m 55.12
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 241.00 40.00 12.65 9,640.00 3,048.65 12,688.65
9.06 Plywood, Marine 1/4" x 4' x 8' pc 19.00 340.00 108.00 6,460.00 2,052.00 8,512.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00 325.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 16.00 352.50 105.75 5,640.00 1,692.00 7,332.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen m 36.60 201.00 60.30 7,356.60 2,206.98 9,563.58
Blackboards sq.m 11.52
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 74.00 50.00 18.60 3,700.00 1,376.40 5,076.40
9.43 Lawanit, 1/4" thk pc 4.00 280.00 84.00 1,120.00 336.00 1,456.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 2.00 50.00 15.00 100.00 30.00 130.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 100,024.43
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 48.00 50.00 15.00 2,400.00 720.00 3,120.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 12.00 15.00 4.50 180.00 54.00 234.00
10.17 Utility Box, 2" x 4" G.I. pc 8.00 30.00 4.28 240.00 34.20 274.20
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 432.00 23.97 7.02 10,356.92 3,032.64 13,389.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93 222.29
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 34,902.35
13.00 Painting Works
Concrete surfaces sq.m 340.35
13.18 Neutralizer gal 5.00 132.00 39.60 660.00 198.00 858.00
13.01 Latex, Flat gal 14.00 470.00 141.00 6,580.00 1,974.00 8,554.00
13.14 Masonry Putty gal 14.00 319.00 95.70 4,466.00 1,339.80 5,805.80
13.02 Latex, Semi Gloss gal 14.00 478.25 143.48 6,695.56 2,008.67 8,704.23
13.20 Acri Color qrt 4.00 165.00 49.50 660.00 198.00 858.00
Wood surfaces sq.m 168.32
13.04 Enamel, Flatwall gal 9.00 440.00 132.00 3,960.00 1,188.00 5,148.00
13.15 Glazing Putty gal 9.00 492.00 147.60 4,428.00 1,328.40 5,756.40
13.05 Enamel, Semi Gloss gal 9.00 460.00 138.00 4,140.00 1,242.00 5,382.00
13.16 Paint Thinner gal 5.00 260.00 78.00 1,300.00 390.00 1,690.00
Sub-total 42,756.43

I. DIRECT COST 849,937.70


II. INDIRECT COST 19% of (I) 161,488.16
III. TAX 12% of (I+II) 121,371.10
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,132,796.97
V. ENGINEERING OVERHEAD 1% of (IV) 11,327.97
VI. TOTAL PROJECT COST (IV+V) Php1,144,124.94
Php1,145,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Three Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED ONE STOREY THREE CLASSROOM 7 X 9 (ORIGINAL)


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 7,341.37 4,894.24 7,341.37 4,894.24 12,235.61
Services/Demobilization / Standard Billboard

Sub-total 12,235.61
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 229.50 0.00 20.00 0.00 4,590.00 4,590.00
1.02 Structural Excavation cu.m 39.22 0.00 200.00 0.00 7,843.20 7,843.20
1.03 Backfilling and Compaction cu.m 26.95 0.00 45.00 0.00 1,212.57 1,212.57
1.04 Gravel Bedding G-1 cu.m 13.93 552.00 180.00 7,688.81 2,507.22 10,196.03
1.06 Select Fill cu.m 22.95 150.00 45.00 3,442.50 1,032.75 4,475.25
1.05 Soil Poisoning sq.m 252.45 15.00 4.50 3,786.75 1,136.03 4,922.78
Sub-total 33,239.82
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 8.20
2.01 Portland Cement bag 74.00 223.00 42.50 16,502.00 3,145.00 19,647.00
2.05 Crushed Gravel 1" cu.m 8.25 552.00 150.00 4,554.00 1,237.50 5,791.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 6.27
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.02 Crushed Gravel 3/4" cu.m 6.50 655.00 175.00 4,257.50 1,137.50 5,395.00
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 164,789.75
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 238.58
Column kg 1,183.19
Beam kg 1,049.69
Slab on Grade kg 603.66
Ramp on Fill kg 27.27
3.01 Deformed Round Bars, Grade 40 kg 3,401.14 39.97 7.63 135,943.44 25,963.23 161,906.67
3.02 G.I. Tie Wire kg 69.00 50.00 9.00 3,450.00 621.00 4,071.00
Sub-total 165,977.67
4.00 Formworks

3CL 7x27m Schoolbuilding 33 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Column sq.m 98.20
4.01 Coco Lumber bd.ft 501.00 14.00 4.20 7,014.00 2,104.20 9,118.20
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 17.00 288.92 90.00 4,911.58 1,530.00 6,441.58
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Beams sq.m 101.30
4.01 Coco Lumber bd.ft 516.90 14.00 4.20 7,236.60 2,170.98 9,407.58
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 18.00 288.92 90.00 5,200.50 1,620.00 6,820.50
4.04 CWN, Assorted kg 8.00 60.00 18.00 480.00 144.00 624.00
Sub-total 33,035.86
5.00 Masonry Works
Masonry Wall sq.m 242.07
5.05 CHB 6" thk pc 3,026.00 12.00 3.00 36,312.00 9,078.00 45,390.00
5.02 Portland Cement bag 122.00 223.00 51.00 27,206.00 6,222.00 33,428.00
5.03 Washed Sand cu.m 11.00 435.00 180.00 4,785.00 1,980.00 6,765.00
5.06 10mm x 6m RSB kg 321.00 39.97 9.03 12,830.37 2,898.63 15,729.00
5.07 G.I. Tie Wire kg 7.00 50.00 15.00 350.00 105.00 455.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 484.14
5.02 Portland Cement bag 160.00 223.00 51.00 35,680.00 8,160.00 43,840.00
5.03 Washed Sand cu.m 16.00 435.00 180.00 6,960.00 2,880.00 9,840.00
Sub-total 156,071.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 6.00 5,917.50 887.63 35,505.00 5,325.75 40,830.75
6.03 Wooden Jamb complete with Accessories

W - 1, ( 2.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 6.00 6,700.00 1,005.00 40,200.00 6,030.00 46,230.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.07 Accessories

W - 2, ( 1.3 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 6.00 3,350.00 502.50 20,100.00 3,015.00 23,115.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.45 Accessories
Sub-total 110,175.75
7.00 Steel Works
7.08 LC 150 x 65 x 20 x 3.0mm kg 1,417.80 41.19 12.48 58,399.18 17,689.88 76,089.06
7.04 LC 100 x 50 x 15 x 1.5mm kg 1,120.90 41.19 12.48 46,169.71 13,985.41 60,155.11
7.11 L 25 x 25 x 3mm kg 171.70 41.60 8.73 7,142.55 1,499.11 8,641.67
7.17 Flat Bar 1" x 1/4" kg 49.56 41.60 8.73 2,061.70 432.72 2,494.41
7.18 Plain Round Bar 10mmØ x 6m pc 18.00 107.00 32.10 1,926.00 577.80 2,503.80
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.75 9,300.00 2,790.00 6,975.00 2,092.50 9,067.50
Anchor Bolt with Nuts and Washer, 16mmØ x pc 48.00 45.00 13.50 2,160.00 648.00 2,808.00
7.33 50mm x 300mm
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 32.00 12.00 3.60 384.00 115.20 499.20
7.35 50mm x 200mm
7.46 Welding Rod kg 56.00 67.00 20.10 3,752.00 1,125.60 4,877.60
13.12 Primer, Zinc Chromate gal 5.00 537.00 161.10 2,685.00 805.50 3,490.50
Sub-total 170,626.86
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 291.20 360.00 72.00 104,832.00 20,966.40 125,798.40
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 13.00 544.00 7,072.00 0.00 7,072.00
8.17 2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 2,330.00 1.25 2,912.50 0.00 2,912.50
8.36 Roof Sealant L 3.00 239.80 719.40 0.00 719.40
Sub-total 141,942.30
9.00 Carpentry Works
Interior ceiling sq.m 210.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 918.00 40.00 12.65 36,720.00 11,612.70 48,332.70
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 72.00 288.92 81.75 20,802.00 5,886.00 26,688.00
9.22 Finishing Nails kg 4.00 70.00 21.00 280.00 84.00 364.00
9.23 Common Wire Nails kg 17.00 50.00 15.00 850.00 255.00 1,105.00

3CL 7x27m Schoolbuilding 34 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.42 Wood Preservative, Brown L 3.00 900.00 270.00 2,700.00 810.00 3,510.00
Exterior Ceiling sq.m 78.52
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 344.00 40.00 12.65 13,760.00 4,351.60 18,111.60
9.06 Plywood, Marine 1/4" x 4' x 8' pc 27.00 340.00 108.00 9,180.00 2,916.00 12,096.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 7.00 50.00 15.00 350.00 105.00 455.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 21.00 352.50 105.75 7,402.50 2,220.75 9,623.25
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 14.00 245.00 73.50 3,430.00 1,029.00 4,459.00
Blackboards sq.m 17.28
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 110.00 50.00 18.60 5,500.00 2,046.00 7,546.00
9.43 Lawanit, 1/4" thk pc 6.00 280.00 84.00 1,680.00 504.00 2,184.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 2.00 50.00 15.00 100.00 30.00 130.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 136,138.55
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 72.00 50.00 15.00 3,600.00 1,080.00 4,680.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 18.00 15.00 4.50 270.00 81.00 351.00
10.17 Utility Box, 2" x 4" G.I. pc 12.00 30.00 4.28 360.00 51.30 411.30
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 648.00 23.97 7.02 15,535.38 4,548.96 20,084.34
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 6.00 263.80 21.00 1,582.80 126.00 1,708.80
10.25 3-Gang Switch with Plate pc 3.00 208.00 29.59 624.00 88.76 712.76
10.23 Single Switch with Plate pc 3.00 97.68 13.46 293.04 40.39 333.43
10.20 FL 2 x 40W Industrial Type set 12.00 1,200.00 126.00 14,400.00 1,512.00 15,912.00
10.21 FL 1 x 40W Industrial Type set 3.00 700.00 73.50 2,100.00 220.50 2,320.50
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 3.00 37.50 5.63 112.50 16.88 129.38
Sub-total 50,450.19
13.00 Painting Works
Concrete surfaces sq.m 484.14
13.18 Neutralizer gal 7.00 132.00 39.60 924.00 277.20 1,201.20
13.01 Latex, Flat gal 20.00 470.00 141.00 9,400.00 2,820.00 12,220.00
13.14 Masonry Putty gal 20.00 319.00 95.70 6,380.00 1,914.00 8,294.00
13.02 Latex, Semi Gloss gal 20.00 478.25 143.48 9,565.08 2,869.52 12,434.61
13.20 Acri Color qrt 5.00 165.00 49.50 825.00 247.50 1,072.50
Wood surfaces sq.m 252.48
13.04 Enamel, Flatwall gal 13.00 440.00 132.00 5,720.00 1,716.00 7,436.00
13.15 Glazing Putty gal 13.00 492.00 147.60 6,396.00 1,918.80 8,314.80
13.05 Enamel, Semi Gloss gal 13.00 460.00 138.00 5,980.00 1,794.00 7,774.00
13.16 Paint Thinner gal 7.00 260.00 78.00 1,820.00 546.00 2,366.00
Sub-total 61,113.11

I. DIRECT COST 1,235,796.47


II. INDIRECT COST 19% of (I) 234,801.33
III. TAX 12% of (I+II) 176,471.74
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,647,069.53
V. ENGINEERING OVERHEAD 1% of (IV) 16,470.70
VI. TOTAL PROJECT COST (IV+V) Php1,663,540.22
Php1,664,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ

3CL 7x27m Schoolbuilding 35 of 61


Three Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

3CL 7x27m Schoolbuilding 36 of 61


Multipurpose Building

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED MULTIPURPOSE WORKSHOP BUILDING 7M X 18M


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 7,154.18 4,769.45 7,154.18 4,769.45 11,923.63
Services/Demobilization / Standard Billboard

Sub-total 11,923.63
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 26.81 0.00 200.00 0.00 5,361.60 5,361.60
1.03 Backfilling and Compaction cu.m 18.10 0.00 45.00 0.00 814.41 814.41
1.04 Gravel Bedding G-1 cu.m 9.39 552.00 180.00 5,184.38 1,690.56 6,874.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,376.30
2.00 Concreting Works
Column Footing cu.m 2.46
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.50 552.00 150.00 1,380.00 375.00 1,755.00
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Wall Footing cu.m 6.25
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.05 Crushed Gravel 1" cu.m 6.25 552.00 150.00 3,450.00 937.50 4,387.50
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Column cu.m 3.97
2.01 Portland Cement bag 36.00 223.00 42.50 8,028.00 1,530.00 9,558.00
2.02 Crushed Gravel 3/4" cu.m 4.00 655.00 175.00 2,620.00 700.00 3,320.00
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Beams cu.m 3.68
2.01 Portland Cement bag 34.00 223.00 42.50 7,582.00 1,445.00 9,027.00
2.02 Crushed Gravel 3/4" cu.m 3.75 655.00 175.00 2,456.25 656.25 3,112.50
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 1.40
2.01 Portland Cement bag 13.00 223.00 42.50 2,899.00 552.50 3,451.50
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Counter cu.m 0.79
2.01 Portland Cement bag 8.00 223.00 42.50 1,784.00 340.00 2,124.00
2.05 Crushed Gravel 1" cu.m 1.00 552.00 150.00 552.00 150.00 702.00
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 117,488.00
3.00 Rebar Works
Footing kg 174.32
Wall Footing kg 183.60
Column kg 762.53
Beam kg 618.35
Slab on Grade kg 402.44
Ramp on Fill kg 59.09

7x18m Multipurpose Building 37 of 61


Multipurpose Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Counter kg 41.43
3.01 Deformed Round Bars, Grade 40 kg 2,241.76 39.97 7.63 89,603.12 17,112.90 106,716.02
3.02 G.I. Tie Wire kg 45.00 50.00 9.00 2,250.00 405.00 2,655.00
Sub-total 109,371.02
4.00 Formworks
Column sq.m 56.11
4.01 Coco Lumber bd.ft 286.20 14.00 4.20 4,006.80 1,202.04 5,208.84
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 10.00 288.92 90.00 2,889.17 900.00 3,789.17
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 59.20
4.01 Coco Lumber bd.ft 302.10 14.00 4.20 4,229.40 1,268.82 5,498.22
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Sub-total 19,444.31
5.00 Masonry Works
Masonry Wall sq.m 188.10
5.05 CHB 6" thk pc 2,352.00 12.00 3.00 28,224.00 7,056.00 35,280.00
5.02 Portland Cement bag 95.00 223.00 51.00 21,185.00 4,845.00 26,030.00
5.03 Washed Sand cu.m 8.00 435.00 180.00 3,480.00 1,440.00 4,920.00
5.06 10mm x 6m RSB kg 250.00 39.97 9.03 9,992.50 2,257.50 12,250.00
5.07 G.I. Tie Wire kg 5.00 50.00 15.00 250.00 75.00 325.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 376.20
5.02 Portland Cement bag 125.00 223.00 51.00 27,875.00 6,375.00 34,250.00
5.03 Washed Sand cu.m 13.00 435.00 180.00 5,655.00 2,340.00 7,995.00
Sub-total 121,674.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 4.00 5,917.50 887.63 23,670.00 3,550.50 27,220.50
6.03 Wooden Jamb complete with Accessories
D-2 Flush Door 0.90m x 2.10m on 150mm set 1.00 3,967.50 529.13 3,967.50 529.13 4,496.63
6.04 Wooden Jamb complete with Accessories
D-3 Flush Door 0.70m x 2.10m on 150mm set 2.00 3,857.50 517.13 7,715.00 1,034.25 8,749.25
6.05 Wooden Jamb complete with Accessories

W - 1, ( 4.0 x 1.8 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 11,520.00 1,728.00 23,040.00 3,456.00 26,496.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.41 Accessories

W - 2, ( 2.1 x 1.8 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 5.00 6,048.00 907.20 30,240.00 4,536.00 34,776.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.42 Accessories

W - 3, ( 1.8 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 1.00 4,600.00 690.00 4,600.00 690.00 5,290.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.39 Accessories

W - 4, ( 0.6 x 0.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum
set 2.00 700.00 105.00 1,400.00 210.00 1,610.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.40 Accessories

9.50 Folding Door, Full Louver 450 x 1830mm set 16.00 1,435.00 430.50 22,960.00 6,888.00 29,848.00
Sub-total 138,486.38
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 685.44 41.19 12.48 28,233.27 8,552.23 36,785.50
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,007.68 41.19 12.48 41,506.34 12,572.81 54,079.15
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm

7x18m Multipurpose Building 38 of 61


Multipurpose Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 24.00 12.00 3.60 288.00 86.40 374.40
7.35 50mm x 200mm
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 12.00 960.56 338.00 11,526.75 4,056.00 15,582.75
7.46 Welding Rod kg 38.00 67.00 20.10 2,546.00 763.80 3,309.80
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 130,876.06
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 9.00 544.00 4,896.00 0.00 4,896.00
8.17 2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.19 2.440m x 0.4mm thk
Gutter, Pre-Painted, Ordinary, 0.915m x 2.440m pc 18.00 864.00 15,552.00 0.00 15,552.00
8.23 x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,581.00 1.25 1,976.25 0.00 1,976.25
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 113,707.05
9.00 Carpentry Works
Interior ceiling sq.m 140.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 612.00 40.00 12.65 24,480.00 7,741.80 32,221.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 48.00 288.92 81.75 13,868.00 3,924.00 17,792.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 12.00 50.00 15.00 600.00 180.00 780.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Exterior Ceiling sq.m 60.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 263.00 40.00 12.65 10,520.00 3,326.95 13,846.95
9.06 Plywood, Marine 1/4" x 4' x 8' pc 21.00 340.00 108.00 7,140.00 2,268.00 9,408.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00 325.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 16.00 352.50 105.75 5,640.00 1,692.00 7,332.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 6.00 245.00 73.50 1,470.00 441.00 1,911.00
Cabinets lot 1.00
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 147.26 50.00 18.60 7,363.20 2,739.11 10,102.31
9.08 Plywood, Marine 3/4" x 4' x 8' pc 16.00 1,050.00 315.00 16,800.00 5,040.00 21,840.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 7.00 340.00 108.00 2,380.00 756.00 3,136.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 4.00 50.00 15.00 200.00 60.00 260.00
9.24 Concrete Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.28 Wood Glue L 2.00 120.00 36.00 240.00 72.00 312.00
9.44 Concealed Hinges pc 76.00 30.00 9.00 2,280.00 684.00 2,964.00
9.45 S.S. Cabinet Handle pc 38.00 90.00 27.00 3,420.00 1,026.00 4,446.00
9.47 S.S. Tube 3/4"Ø m 1.00 420.00 126.00 420.00 126.00 546.00
9.48 S.S. Flange 3/4"Ø pa 1.00 75.00 22.50 75.00 22.50 97.50
9.49 Drawer Guide, Metal 20" Full Extension set 6.00 420.00 126.00 2,520.00 756.00 3,276.00
11.69 Mirror sq.ft 6.00 100.00 15.00 600.00 90.00 690.00
Blackboards sq.m 5.76
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 37.00 50.00 18.60 1,850.00 688.20 2,538.20
9.43 Lawanit, 1/4" thk pc 2.00 280.00 84.00 560.00 168.00 728.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 1.00 50.00 15.00 50.00 15.00 65.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 139,128.76
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 56.00 50.00 15.00 2,800.00 840.00 3,640.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 18.00 15.00 4.50 270.00 81.00 351.00
10.17 Utility Box, 2" x 4" G.I. pc 22.00 30.00 4.28 660.00 94.05 754.05
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 504.00 23.97 7.02 12,083.08 3,538.08 15,621.16

7x18m Multipurpose Building 39 of 61


Multipurpose Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 12.00 263.80 21.00 3,165.60 252.00 3,417.60
10.24 2-Gang Switch with Plate pc 4.00 153.00 21.53 612.00 86.10 698.10
10.23 Single Switch with Plate pc 6.00 97.68 13.46 586.08 80.78 666.86
10.20 FL 2 x 40W Industrial Type set 16.00 1,200.00 126.00 19,200.00 2,016.00 21,216.00
10.21 FL 1 x 40W Industrial Type set 4.00 700.00 73.50 2,800.00 294.00 3,094.00
10.47 Panel Box, Flush Type, 6 Branches set 1.00 1,400.00 210.00 1,400.00 210.00 1,610.00
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 5.00 313.00 46.95 1,565.00 234.75 1,799.75
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 54,298.43
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 1.00 5,500.00 825.00 5,500.00 825.00 6,325.00
11.64 Lavatory, Pedestal Type with Accessories set 1.00 3,150.00 472.50 3,150.00 472.50 3,622.50
11.72 S.S. Sink with Strainer and P-Trap set 2.00 3,000.00 450.00 6,000.00 900.00 6,900.00
11.70 Faucet, Lavatory set 1.00 800.00 120.00 800.00 120.00 920.00
11.71 Faucet, Sink set 2.00 1,250.00 187.50 2,500.00 375.00 2,875.00
11.75 Shower Set set 1.00 1,800.00 270.00 1,800.00 270.00 2,070.00
11.61 Water Closet Flange set 1.00 262.50 39.38 262.50 39.38 301.88
11.58 Angle Valve 3/8" x 1/2"Ø pc 4.00 150.00 45.00 600.00 180.00 780.00
11.05 G.I. Pipe 3/4"Ø Sch.40 pc 2.00 360.00 108.00 720.00 216.00 936.00
11.09 G.I. Coupling, 3/4"Ø pc 1.00 14.75 4.43 14.75 4.43 19.18
11.24 G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 1.00 40.00 12.00 40.00 12.00 52.00
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00 416.00
11.06 G.I. Pipe 1/2"Ø Sch.40 pc 3.00 260.00 78.00 780.00 234.00 1,014.00
11.21 G.I. Elbow 90o x 1/2"Ø pc 6.00 11.00 3.30 66.00 19.80 85.80
11.15 G.I. Tee, 1/2"Ø pc 5.00 17.75 5.33 88.75 26.63 115.38
11.44 Gate Valve, 1/2"Ø pc 3.00 250.00 75.00 750.00 225.00 975.00
11.65 S.S.Floor Drain 4' x 4" pc 4.00 97.50 14.63 390.00 58.50 448.50
11.68 S.S. Grab Rail 1-1/2"Ø pc 1.00 2,900.00 435.00 2,900.00 435.00 3,335.00
11.69 Mirror sq.ft 3.00 100.00 15.00 300.00 45.00 345.00
11.66 Teflon Tape roll 6.00 12.00 1.80 72.00 10.80 82.80
Sub-total 31,619.03
12.00 Sanitary Works
12.32 Septic Vault unit 1.00 27,893.87 12,117.88 27,893.87 12,117.88 40,011.75
12.01 Catch Basin unit 10.00 1,500.00 450.00 15,000.00 4,500.00 19,500.00
12.34 Waste Vault unit 1.00 4,620.00 1,386.00 4,620.00 1,386.00 6,006.00
12.02 Concrete Pipe 150mmØ pc 60.00 200.00 60.00 12,000.00 3,600.00 15,600.00
12.09 uPVC Sanitary Pipe 4"Ø pc 6.00 560.00 168.00 3,360.00 1,008.00 4,368.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50 214.50
12.13 uPVC Elbow 90o x 4"Ø pc 2.00 96.00 28.80 192.00 57.60 249.60
12.27 uPVC Wye 4" x 4" pc 2.00 165.00 49.50 330.00 99.00 429.00
12.21 uPVC Tee 4" x 4" pc 3.00 138.00 41.40 414.00 124.20 538.20
12.25 uPVC Wye 4" x 2" pc 2.00 97.00 29.10 194.00 58.20 252.20
12.29 Brass Cleanout 6" x 6" pc 1.00 675.00 202.50 675.00 202.50 877.50
12.28 Brass Cleanout 4" x 4" pc 3.00 350.00 105.00 1,050.00 315.00 1,365.00
12.11 uPVC Elbow 90o x 2"Ø pc 8.00 25.00 7.50 200.00 60.00 260.00
12.07 uPVC Sanitary Pipe 2"Ø pc 8.00 210.00 63.00 1,680.00 504.00 2,184.00
12.08 uPVC Sanitary Pipe 3"Ø pc 15.00 420.00 126.00 6,300.00 1,890.00 8,190.00
12.12 uPVC Elbow 90o x 3"Ø pc 30.00 53.00 15.90 1,590.00 477.00 2,067.00
12.22 uPVC Wye 2" x 2" pc 4.00 38.00 11.40 152.00 45.60 197.60
12.17 uPVC Tee 2" x 2" pc 2.00 36.00 10.80 72.00 21.60 93.60
12.30 uPVC P-Trap 2" pc 4.00 66.00 19.80 264.00 79.20 343.20
12.33 PVC Cement can 8.00 150.00 45.00 1,200.00 360.00 1,560.00
Sub-total 104,307.15
13.00 Painting Works
Concrete surfaces sq.m 376.20
13.18 Neutralizer gal 5.00 132.00 39.60 660.00 198.00 858.00
13.01 Latex, Flat gal 16.00 470.00 141.00 7,520.00 2,256.00 9,776.00
13.14 Masonry Putty gal 16.00 319.00 95.70 5,104.00 1,531.20 6,635.20
13.02 Latex, Semi Gloss gal 26.00 478.25 143.48 12,434.61 3,730.38 16,164.99
13.20 Acri Color qrt 7.00 165.00 49.50 1,155.00 346.50 1,501.50
Wood surfaces sq.m 243.15

7x18m Multipurpose Building 40 of 61


Multipurpose Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
13.04 Enamel, Flatwall gal 13.00 440.00 132.00 5,720.00 1,716.00 7,436.00
13.15 Glazing Putty gal 13.00 492.00 147.60 6,396.00 1,918.80 8,314.80
13.05 Enamel, Semi Gloss gal 20.00 460.00 138.00 9,200.00 2,760.00 11,960.00
13.16 Paint Thinner gal 9.00 260.00 78.00 2,340.00 702.00 3,042.00
Cabinets sq.m 112.32
13.27 Lacquer, Primer Surfacer gal 10.00 538.00 161.40 5,380.00 1,614.00 6,994.00
13.28 Lacquer, Spot Putty gal 8.00 521.00 156.30 4,168.00 1,250.40 5,418.40
13.35 Polytuff qrt 8.00 150.00 45.00 1,200.00 360.00 1,560.00
13.23 Lacquer, Automotive White gal 8.00 715.00 214.50 5,720.00 1,716.00 7,436.00
13.21 Tinting Color qrt 2.00 180.00 54.00 360.00 108.00 468.00
13.17 Lacquer Thinner gal 5.00 311.00 93.30 1,555.00 466.50 2,021.50
Sub-total 89,586.39
14.00 Tile Works
Wall sq.m 9.30
14.04 Glazed Wall Tiles 20cm x 20cm pc 240.00 14.00 4.20 3,360.00 1,008.00 4,368.00
14.16 Tile Adhesive 25 kg/bag bag 2.00 224.10 67.23 448.20 134.46 582.66
14.13 Tile Trim 6mm pc 5.00 97.75 29.33 488.75 146.63 635.38
14.15 Tile Grout 5 kg/bag bag 1.00 150.00 45.00 150.00 45.00 195.00
14.15 Flooring sq.m 3.00
14.01 Unglazed Floor Tiles 20cm x 20cm pc 78.00 12.00 3.60 936.00 280.80 1,216.80
14.16 Tile Adhesive 25 kg/bag bag 1.00 224.10 67.23 224.10 67.23 291.33
14.15 Tile Grout 5 kg/bag bag 1.00 150.00 45.00 150.00 45.00 195.00
Counter sq.m 6.00
14.04 Glazed Wall Tiles 20cm x 20cm pc 155.00 14.00 4.20 2,170.00 651.00 2,821.00
14.16 Tile Adhesive 25 kg/bag bag 2.00 224.10 67.23 448.20 134.46 582.66
14.13 Tile Trim 6mm pc 6.00 97.75 29.33 586.50 175.95 762.45
14.15 Tile Grout 5 kg/bag bag 1.00 150.00 45.00 150.00 45.00 195.00
Sub-total 11,845.28

I. DIRECT COST 1,216,131.78


II. INDIRECT COST 19% of (I) 231,065.04
III. TAX 12% of (I+II) 173,663.62
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,620,860.43
V. ENGINEERING OVERHEAD 1% of (IV) 16,208.60
VI. TOTAL PROJECT COST (IV+V) Php1,637,069.04
Php1,638,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

7x18m Multipurpose Building 41 of 61


Science Laboratory Building

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED SCIENCE LABORATORY BUILDING 7M X 18M


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS

Mobilization/Temporary Structures, Utilities and


lot 1.00 7,482.66 4,988.44 7,482.66 4,988.44 12,471.10
Services/Demobilization / Standard Billboard

Sub-total 12,471.10
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 17.28
2.01 Portland Cement bag 156.00 223.00 42.50 34,788.00 6,630.00 41,418.00
2.05 Crushed Gravel 1" cu.m 17.50 552.00 150.00 9,660.00 2,625.00 12,285.00
2.03 Washed Sand cu.m 8.75 435.00 150.00 3,806.25 1,312.50 5,118.75
Ramp on Fill cu.m 1.40
2.01 Portland Cement bag 13.00 223.00 42.50 2,899.00 552.50 3,451.50
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Counter and Working Tables cu.m 21.14
2.01 Portland Cement bag 191.00 223.00 42.50 42,593.00 8,117.50 50,710.50
2.05 Crushed Gravel 1" cu.m 21.25 552.00 150.00 11,730.00 3,187.50 14,917.50
2.03 Washed Sand cu.m 10.75 435.00 150.00 4,676.25 1,612.50 6,288.75
Sub-total 192,289.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 746.20
Beam kg 740.52
Ramp on Fill kg 29.54
Slab on Grade kg 454.52
Counter and Working Tables kg 556.15

7x18m Science Laboratory Building 42 of 61


Science Laboratory Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
3.01 Deformed Round Bars, Grade 40 kg 2,879.23 39.97 7.63 115,082.95 21,979.18 137,062.13
3.02 G.I. Tie Wire kg 58.00 50.00 9.00 2,900.00 522.00 3,422.00
Sub-total 140,484.13
4.00 Formworks
Column sq.m 60.79
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 71.70
4.01 Coco Lumber bd.ft 365.70 14.00 4.20 5,119.80 1,535.94 6,655.74
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 13.00 288.92 90.00 3,755.92 1,170.00 4,925.92
4.04 CWN, Assorted kg 6.00 60.00 18.00 360.00 108.00 468.00
Counter and Working Tables sq.m 56.28
4.01 Coco Lumber bd.ft 287.10 14.00 4.20 4,019.40 1,205.82 5,225.22
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 10.00 288.92 90.00 2,889.17 900.00 3,789.17
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Sub-total 31,657.77
5.00 Masonry Works
Masonry Wall sq.m 251.69
5.05 CHB 6" thk pc 3,147.00 12.00 3.00 37,764.00 9,441.00 47,205.00
5.02 Portland Cement bag 126.00 223.00 51.00 28,098.00 6,426.00 34,524.00
5.03 Washed Sand cu.m 11.00 435.00 180.00 4,785.00 1,980.00 6,765.00
5.06 10mm x 6m RSB kg 334.00 39.97 9.03 13,349.98 3,016.02 16,366.00
5.07 G.I. Tie Wire kg 7.00 50.00 15.00 350.00 105.00 455.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 503.37
5.02 Portland Cement bag 167.00 223.00 51.00 37,241.00 8,517.00 45,758.00
5.03 Washed Sand cu.m 17.00 435.00 180.00 7,395.00 3,060.00 10,455.00
Sub-total 162,152.00
6.00 Doors and Windows

D-1, Panel Door 0.90m x 2.10m on 150mm set 3.00 5,917.50 887.63 17,752.50 2,662.88 20,415.38
6.03 Wooden Jamb complete with Accessories
D-2 Flush Door 0.90m x 2.10m on 150mm set 1.00 3,967.50 529.13 3,967.50 529.13 4,496.63
6.04 Wooden Jamb complete with Accessories

D-3 Flush Door 0.70m x 2.10m on 150mm set 3.00 3,857.50 517.13 11,572.50 1,551.38 13,123.88
6.05 Wooden Jamb complete with Accessories

W - 1, ( 3.6 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 1.00 9,250.00 1,387.50 9,250.00 1,387.50 10,637.50
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.37 Accessories

W - 2, ( 3.6 x 1.2 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 6,950.00 1,042.50 13,900.00 2,085.00 15,985.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.38 Accessories

W - 3, ( 1.8 x 1.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 3.00 4,600.00 690.00 13,800.00 2,070.00 15,870.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.39 Accessories

W - 4, ( 0.6 x 0.6 m) Jalousie Window with


Clear Glass Blades on Standard Aluminum set 2.00 700.00 105.00 1,400.00 210.00 1,610.00
Casing and Fixed Clear Glass Transom on 50 x
150 mm Wooden Jamb complete with
6.40 Accessories
Sub-total 82,138.38
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 628.32 41.19 12.48 25,880.50 7,839.54 33,720.04
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,007.68 41.19 12.48 41,506.34 12,572.81 54,079.15
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm

7x18m Science Laboratory Building 43 of 61


Science Laboratory Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
Anchor Bolt with Nuts and Washer, 10mmØ x
pc 32.00 12.00 3.60 384.00 115.20 499.20
7.35 50mm x 200mm
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 12.00 960.56 338.00 11,526.75 4,056.00 15,582.75
7.46 Welding Rod kg 37.00 67.00 20.10 2,479.00 743.70 3,222.70
13.12 Primer, Zinc Chromate gal 4.00 537.00 161.10 2,148.00 644.40 2,792.40
Sub-total 127,848.30
8.00 Roofing Works
Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 9.00 544.00 4,896.00 0.00 4,896.00
8.17 2.440m x 0.4mm thk
Flashing, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.19 2.440m x 0.4mm thk
8.35 Teckscrew 2-1/2" pc 1,581.00 1.25 1,976.25 0.00 1,976.25
8.36 Roof Sealant L 2.00 239.80 479.60 0.00 479.60
Sub-total 98,155.05
9.00 Carpentry Works
Interior ceiling sq.m 140.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 612.00 40.00 12.65 24,480.00 7,741.80 32,221.80
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 48.00 288.92 81.75 13,868.00 3,924.00 17,792.00
9.22 Finishing Nails kg 3.00 70.00 21.00 210.00 63.00 273.00
9.23 Common Wire Nails kg 12.00 50.00 15.00 600.00 180.00 780.00
9.42 Wood Preservative, Brown L 2.00 900.00 270.00 1,800.00 540.00 2,340.00
Exterior Ceiling sq.m 60.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 263.00 40.00 12.65 10,520.00 3,326.95 13,846.95
9.06 Plywood, Marine 1/4" x 4' x 8' pc 21.00 340.00 108.00 7,140.00 2,268.00 9,408.00
9.22 Finishing Nails kg 2.00 70.00 21.00 140.00 42.00 182.00
9.23 Common Wire Nails kg 5.00 50.00 15.00 250.00 75.00 325.00
9.42 Wood Preservative, Brown L 1.00 900.00 270.00 900.00 270.00 1,170.00
9.19 Fascia Board, Fiber Cement 10" x 12' pc 16.00 352.50 105.75 5,640.00 1,692.00 7,332.00
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 6.00 245.00 73.50 1,470.00 441.00 1,911.00
Cabinets lot 1.00
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 132.00 50.00 18.60 6,600.00 2,455.20 9,055.20
9.08 Plywood, Marine 3/4" x 4' x 8' pc 14.00 1,050.00 315.00 14,700.00 4,410.00 19,110.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 4.00 50.00 15.00 200.00 60.00 260.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.28 Wood Glue L 2.00 120.00 36.00 240.00 72.00 312.00
9.44 Concealed Hinges pc 64.00 30.00 9.00 1,920.00 576.00 2,496.00
9.45 S.S. Cabinet Handle pc 40.00 90.00 27.00 3,600.00 1,080.00 4,680.00
9.46 6mm thk Clear Glass sq.ft 32.00 60.00 18.00 1,920.00 576.00 2,496.00
Blackboards sq.m 5.76
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 37.00 50.00 18.60 1,850.00 688.20 2,538.20
9.43 Lawanit, 1/4" thk pc 2.00 280.00 84.00 560.00 168.00 728.00
9.22 Finishing Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
9.23 Common Wire Nails kg 1.00 50.00 15.00 50.00 15.00 65.00
9.24 Concrete Nails kg 1.00 70.00 21.00 70.00 21.00 91.00
Sub-total 129,686.15
10.00 Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 48.00 50.00 15.00 2,400.00 720.00 3,120.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 12.00 15.00 4.50 180.00 54.00 234.00
10.17 Utility Box, 2" x 4" G.I. pc 8.00 30.00 4.28 240.00 34.20 274.20
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 432.00 23.97 7.02 10,356.92 3,032.64 13,389.56
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.23 Single Switch with Plate pc 2.00 97.68 13.46 195.36 26.93 222.29
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
7x18m Science Laboratory Building 44 of 61
Science Laboratory Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 34,902.35
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 2.00 5,500.00 825.00 11,000.00 1,650.00 12,650.00
11.63 Urinal 0.8gpf set 1.00 5,900.00 885.00 5,900.00 885.00 6,785.00
11.64 Lavatory, Pedestal Type with Accessories set 1.00 3,150.00 472.50 3,150.00 472.50 3,622.50
11.70 Faucet, Lavatory set 1.00 800.00 120.00 800.00 120.00 920.00
11.71 Faucet, Sink set 12.00 1,250.00 187.50 15,000.00 2,250.00 17,250.00
11.72 S.S. Sink with Strainer and P-Trap set 12.00 3,000.00 450.00 36,000.00 5,400.00 41,400.00
11.67 Tissue Holder pc 2.00 250.00 37.50 500.00 75.00 575.00
11.05 G.I. Pipe 3/4"Ø Sch.40 pc 3.00 360.00 108.00 1,080.00 324.00 1,404.00
11.09 G.I. Coupling, 3/4"Ø pc 2.00 14.75 4.43 29.50 8.85 38.35
11.22 G.I. Elbow 90o x 3/4"Ø pc 2.00 20.75 6.23 41.50 12.45 53.95
11.24 G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 40.00 12.00 80.00 24.00 104.00
11.06 G.I. Pipe 1/2"Ø Sch.40 pc 10.00 260.00 78.00 2,600.00 780.00 3,380.00
11.21 G.I. Elbow 90o x 1/2"Ø pc 16.00 11.00 3.30 176.00 52.80 228.80
11.08 G.I. Coupling, 1/2"Ø pc 4.00 10.75 3.23 43.00 12.90 55.90
11.15 G.I. Tee, 1/2"Ø pc 16.00 17.75 5.33 284.00 85.20 369.20
11.44 Gate Valve, 1/2"Ø pc 3.00 250.00 75.00 750.00 225.00 975.00
11.45 Gate Valve, 3/4"Ø pc 1.00 320.00 96.00 320.00 96.00 416.00
11.65 S.S.Floor Drain 4' x 4" pc 2.00 97.50 14.63 195.00 29.25 224.25
11.69 Mirror sq.ft 6.00 100.00 15.00 600.00 90.00 690.00
11.66 Teflon Tape roll 12.00 12.00 1.80 144.00 21.60 165.60
Sub-total 91,307.55
12.00 Sanitary Works
12.32 Septic Vault unit 1.00 27,893.87 12,117.88 27,893.87 12,117.88 40,011.75
12.09 uPVC Sanitary Pipe 4"Ø pc 4.00 560.00 168.00 2,240.00 672.00 2,912.00
12.16 uPVC Elbow 1/8 x 4"Ø pc 2.00 82.50 24.75 165.00 49.50 214.50
12.13 uPVC Elbow 90o x 4"Ø pc 5.00 96.00 28.80 480.00 144.00 624.00
12.27 uPVC Wye 4" x 4" pc 2.00 165.00 49.50 330.00 99.00 429.00
12.21 uPVC Tee 4" x 4" pc 2.00 138.00 41.40 276.00 82.80 358.80
12.25 uPVC Wye 4" x 2" pc 2.00 97.00 29.10 194.00 58.20 252.20
12.29 Brass Cleanout 6" x 6" pc 2.00 675.00 202.50 1,350.00 405.00 1,755.00
12.11 uPVC Elbow 90o x 2"Ø pc 8.00 25.00 7.50 200.00 60.00 260.00
12.07 uPVC Sanitary Pipe 2"Ø pc 8.00 210.00 63.00 1,680.00 504.00 2,184.00
12.22 uPVC Wye 2" x 2" pc 4.00 38.00 11.40 152.00 45.60 197.60
12.17 uPVC Tee 2" x 2" pc 6.00 36.00 10.80 216.00 64.80 280.80
12.33 PVC Cement can 2.00 150.00 45.00 300.00 90.00 390.00
Sub-total 49,869.65
13.00 Painting Works
Concrete surfaces sq.m 503.37
13.18 Neutralizer gal 7.00 132.00 39.60 924.00 277.20 1,201.20
13.01 Latex, Flat gal 21.00 470.00 141.00 9,870.00 2,961.00 12,831.00
13.02 Latex, Semi Gloss gal 21.00 478.25 143.48 10,043.34 3,013.00 13,056.34
13.20 Acri Color qrt 6.00 165.00 49.50 990.00 297.00 1,287.00
Wood surfaces sq.m 232.43
13.04 Enamel, Flatwall gal 12.00 440.00 132.00 5,280.00 1,584.00 6,864.00
13.06 Enamel, Quick Dry gal 12.00 526.00 157.80 6,311.99 1,893.60 8,205.58
13.16 Paint Thinner gal 6.00 260.00 78.00 1,560.00 468.00 2,028.00
Sub-total 45,473.12
14.00 Tile Works
Wall sq.m 17.40
14.04 Glazed Wall Tiles 20cm x 20cm pc 449.00 14.00 4.20 6,286.00 1,885.80 8,171.80
14.16 Tile Adhesive 25 kg/bag bag 4.00 224.10 67.23 896.40 268.92 1,165.32
14.13 Tile Trim 6mm pc 6.00 97.75 29.33 586.50 175.95 762.45
14.15 Tile Grout 5 kg/bag bag 2.00 150.00 45.00 300.00 90.00 390.00
14.15 Flooring sq.m 5.20
14.01 Unglazed Floor Tiles 20cm x 20cm pc 134.00 12.00 3.60 1,608.00 482.40 2,090.40
14.16 Tile Adhesive 25 kg/bag bag 1.00 224.10 67.23 224.10 67.23 291.33
14.15 Tile Grout 5 kg/bag bag 1.00 150.00 45.00 150.00 45.00 195.00
Counter and Working Tables sq.m 39.48
14.04 Glazed Wall Tiles 20cm x 20cm pc 1,017.00 14.00 4.20 14,238.00 4,271.40 18,509.40

7x18m Science Laboratory Building 45 of 61


Science Laboratory Building

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
14.16 Tile Adhesive 25 kg/bag bag 8.00 224.10 67.23 1,792.80 537.84 2,330.64
14.13 Tile Trim 6mm pc 36.00 97.75 29.33 3,519.00 1,055.70 4,574.70
14.15 Tile Grout 5 kg/bag bag 3.00 150.00 45.00 450.00 135.00 585.00
Sub-total 39,066.04

I. DIRECT COST 1,259,581.50


II. INDIRECT COST 19% of (I) 239,320.49
III. TAX 12% of (I+II) 179,868.24
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,678,770.23
V. ENGINEERING OVERHEAD 1% of (IV) 16,787.70
VI. TOTAL PROJECT COST (IV+V) Php1,695,557.93
Php1,696,000.00

Prepared by: Checked: Approved:

OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED

7x18m Science Laboratory Building 46 of 61


Republic of the Philippines
DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJE : TWO (2) CLASSROOMS TYPHOON RESISTANT SCHOOL BUILDING


SCHOO:
LOCAT :
OWNER: DEPARTMENT OF EDUCATION
SUBJE : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


ITEM DESCRIPTION UNIT QTY GRAND TOTAL
NO Material Labor Material Labor
I. GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities
lot 1.00 6,866.81 4,577.87 6,866.81 4,577.87 11,444.68
and Services/Demobilization
Sub-total 11,444.68
1.00 A Earthworks
1.01 Clearing and Grubbing sq.m 180.48 - 20.00 - 3,609.60 3,609.60
1.02 Structural Excavation cu.m 34.46 - 200.00 - 6,892.80 6,892.80
1.03 Backfilling and Compaction cu.m 19.83 - 45.00 - 892.31 892.31
1.04 Gravel Bedding G-1 cu.m 6.57 552.00 180.00 3,627.74 1,182.96 4,810.70
1.06 Select Fill cu.m 34.43 150.00 45.00 5,163.75 1,549.13 6,712.88
1.05 Soil Poisoning sq.m 189.50 15.00 4.50 2,842.56 852.77 3,695.33
Sub-total 26,613.61
2.00 B Concreting Works
Column Footing cu.m 4.36
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
2.05 Crushed Gravel 1" cu.m 4.00 552.00 150.00 2,208.00 600.00 2,808.00
Tie beams cu.m 5.68
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
Wall Footing cu.m 4.56
2.01 Portland Cement bag 42.00 223.00 42.50 9,366.00 1,785.00 11,151.00
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
Columns cu.m 9.56
2.01 Portland Cement bag 86.00 223.00 42.50 19,178.00 3,655.00 22,833.00
2.03 Washed Sand cu.m 5.00 435.00 150.00 2,175.00 750.00 2,925.00
2.05 Crushed Gravel 1" cu.m 9.00 552.00 150.00 4,968.00 1,350.00 6,318.00
Beams and Girders cu.m 13.33
2.01 Portland Cement bag 120.00 223.00 42.50 26,760.00 5,100.00 31,860.00
2.03 Washed Sand cu.m 6.00 435.00 150.00 2,610.00 900.00 3,510.00
2.05 Crushed Gravel 1" cu.m 12.00 552.00 150.00 6,624.00 1,800.00 8,424.00
Roof Deck (with waterproofing) cu.m 18.05
2.01 Portland Cement bag 163.00 223.00 42.50 36,349.00 6,927.50 43,276.50
Waterproofing Compund bag 163.00 35.00 10.50 5,705.00 1,711.50 7,416.50
2.03 Washed Sand cu.m 8.00 435.00 150.00 3,480.00 1,200.00 4,680.00
2.05 Crushed Gravel 1" cu.m 16.00 552.00 150.00 8,832.00 2,400.00 11,232.00
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.03 Washed Sand cu.m 7.00 435.00 150.00 3,045.00 1,050.00 4,095.00
2.05 Crushed Gravel 1" cu.m 14.00 552.00 150.00 7,728.00 2,100.00 9,828.00
Ramp on Fill cu.m 1.50
2.01 Portland Cement bag 14.00 223.00 42.50 3,122.00 595.00 3,717.00
2.03 Washed Sand cu.m 1.00 435.00 150.00 435.00 150.00 585.00
2.05 Crushed Gravel 1" cu.m 2.00 552.00 150.00 1,104.00 300.00 1,404.00
Sub-total 248,828.00
3.00 C Rebar Works
Column Footing
3.01 Deformed Round Bars, Grade 40 kg 271.13 39.97 7.63 10,836.99 2,069.71 12,906.69
3.02 G.I. Tie Wire kg 6.00 50.00 9.00 300.00 54.00 354.00
Tie beams
3.01 Deformed Round Bars, Grade 40 kg 694.22 39.97 7.63 27,747.81 5,299.43 33,047.24
3.02 G.I. Tie Wire kg 14.00 50.00 9.00 700.00 126.00 826.00
Wall Footing
3.01 Deformed Round Bars, Grade 40 kg 152.64 39.97 7.63 6,101.21 1,165.24 7,266.46
3.02 G.I. Tie Wire kg 4.00 50.00 9.00 200.00 36.00 236.00
Columns
3.01 Deformed Round Bars, Grade 40 kg 1,165.63 39.97 7.63 46,590.31 8,898.08 55,488.39
3.02 G.I. Tie Wire kg 24.00 50.00 9.00 1,200.00 216.00 1,416.00
Beams and Girders
3.01 Deformed Round Bars, Grade 40 kg 2,195.19 39.97 7.63 87,741.82 16,757.42 104,499.24
3.02 G.I. Tie Wire kg 44.00 50.00 9.00 2,200.00 396.00 2,596.00
Suspended Slab
3.01 Deformed Round Bars, Grade 40 kg 969.58 39.97 7.63 38,754.27 7,401.51 46,155.78
3.02 G.I. Tie Wire kg 20.00 50.00 9.00 1,000.00 180.00 1,180.00
Slab on Grade
3.01 Deformed Round Bars, Grade 40 kg 484.79 39.97 7.63 19,377.14 3,700.75 23,077.89
3.02 G.I. Tie Wire kg 10.00 50.00 9.00 500.00 90.00 590.00
Ramp on Fill
3.01 Deformed Round Bars, Grade 40 kg 19.10 39.97 7.63 763.27 145.77 909.04
3.02 G.I. Tie Wire kg 1.00 50.00 9.00 50.00 9.00 59.00
Sub-total 290,607.73
4.00 D Formworks .
Tie beams sq.m 56.80
4.01 Coco Lumber bd.ft 323.00 14.00 4.20 4,522.00 1,356.60 5,878.60
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 10.00 288.92 90.00 2,889.17 900.00 3,789.17
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Columns sq.m 109.20
4.01 Coco Lumber bd.ft 929.00 14.00 4.20 13,006.00 3,901.80 16,907.80
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 19.00 288.92 90.00 5,489.42 1,710.00 7,199.42
4.04 CWN, Assorted kg 14.00 60.00 18.00 840.00 252.00 1,092.00
Beams and Girders sq.m 166.60
4.01 Coco Lumber bd.ft 1,416.50 14.00 4.20 19,831.00 5,949.30 25,780.30
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 29.00 288.92 90.00 8,378.58 2,610.00 10,988.58
4.04 CWN, Assorted kg 20.00 60.00 18.00 1,200.00 360.00 1,560.00
Suspended Slab (Roof Deck) sq.m 180.48
4.01 Coco Lumber bd.ft 3,069.00 14.00 4.20 42,966.00 12,889.80 55,855.80
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 31.00 288.92 90.00 8,956.42 2,790.00 11,746.42
4.04 CWN, Assorted kg 43.00 60.00 18.00 2,580.00 774.00 3,354.00
Sub-total 144,542.08
5.00 E Masonry Works
6" thk Masonry Wall sq.m 315.54
5.05 CHB 6" thk pc 3,945.00 12.00 3.00 47,340.00 11,835.00 59,175.00
5.02 Portland Cement bag 158.00 223.00 51.00 35,234.00 8,058.00 43,292.00
5.03 Washed Sand cu.m 14.00 435.00 180.00 6,090.00 2,520.00 8,610.00
5.06 10mm x 6m RSB kg 418.00 39.97 9.03 16,707.46 3,774.54 20,482.00
5.07 G.I. Tie Wire kg 9.00 50.00 15.00 450.00 135.00 585.00
Plastering sq.m 665.16
5.02 Portland Cement bag 220.00 223.00 51.00 49,060.00 11,220.00 60,280.00
5.03 Washed Sand cu.m 22.00 435.00 180.00 9,570.00 3,960.00 13,530.00
5.09 Plaster Moulding lm 134.40 125.00 62.50 16,800.00 8,400.00 25,200.00
Sub-total 231,154.00
6.00 F Doors and Windows
6.47 D-1, (0.90 x 2.10) Steel Door and Jamb set 4.00 6,000.00 1,800.00 24,000.00 7,200.00 31,200.00
6.51 W - 1, ( 2.4 x 1.5 m) Steel Casement Wi set 4.00 5,750.00 2,012.50 23,000.00 8,050.00 31,050.00
6.52 W - 2, ( 1.8 x 1.5 m) Steel Casement Wi set 4.00 4,350.00 1,522.50 17,400.00 6,090.00 23,490.00
Sub-total 85,740.00
10.00 I Electrical Works
Roughing-ins
10.01 Electrical Conduit uPVC, 15mmØ pc 54.00 50.00 15.00 2,700.00 810.00 3,510.00
10.06 RSC 20mmØ pc 1.00 112.50 33.75 112.50 33.75 146.25
10.34 Entrance Cap 20mm dia. pc 1.00 50.00 7.50 50.00 7.50 57.50
10.16 Junction Box, 4" x 4" G.I. pc 22.00 15.00 4.50 330.00 99.00 429.00
10.17 Utility Box, 2" x 4" G.I. pc 16.00 30.00 4.28 480.00 68.40 548.40
10.37 Grounding Rod, 2.4m x 16mm dia. pc 1.00 150.00 22.50 150.00 22.50 172.50
Wires & Fixtures
10.11 3.5 mm2 THW Wire, Stranded m 486.00 23.97 7.02 11,651.54 3,411.72 15,063.26
10.12 5.5 mm2 THW Wire, Stranded m 10.00 35.86 10.14 358.58 101.40 459.98
10.28 Duplex C.O. with Plate pc 4.00 263.80 21.00 1,055.20 84.00 1,139.20
10.24 2-Gang Switch with Plate pc 2.00 153.00 21.53 306.00 43.05 349.05
10.25 3-Gang Switch with Plate pc 2.00 208.00 29.59 416.00 59.18 475.18
10.20 FL 2 x 40W Industrial Type set 8.00 1,200.00 126.00 9,600.00 1,008.00 10,608.00
10.21 FL 1 x 40W Industrial Type set 2.00 700.00 73.50 1,400.00 147.00 1,547.00
10.33 Ceiling Receptacle 3-1/2"Ø pc 2.00 25.00 3.75 50.00 7.50 57.50
10.53 Incandescent Bulb 50W set 2.00 35.00 5.25 70.00 10.50 80.50
10.48 Panel Box, Flush Type, 4 Branches set 1.00 1,202.75 180.41 1,202.75 180.41 1,383.16
10.40 Circuit Breaker, 40A 2P set 1.00 441.25 66.19 441.25 66.19 507.44
10.38 Circuit Breaker, 20A 2P set 3.00 313.00 46.95 939.00 140.85 1,079.85
10.58 Electrical Tape pc 2.00 37.50 5.63 75.00 11.25 86.25
Sub-total 37,700.01
13.00 L Painting Works
Concrete surfaces sq.m 1,121.44
13.18 Neutralizer gal 15.00 132.00 39.60 1,980.00 594.00 2,574.00
13.01 Latex, Flat gal 45.00 470.00 141.00 21,150.00 6,345.00 27,495.00
13.14 Masonry Putty gal 45.00 319.00 95.70 14,355.00 4,306.50 18,661.50
13.02 Latex, Semi Gloss gal 45.00 478.25 143.48 21,521.44 6,456.43 27,977.87
13.20 Acri Color qrt 12.00 165.00 49.50 1,980.00 594.00 2,574.00
Sub-total 79,282.37

I. DIRECT COST 1,155,912.49


II. INDIRECT COST 19% of (I) 219,623.37
III. TAX 12% of (I+II) 165,064.30
IV. TOTAL CONSTRUCTION COST (I+II+III) 1,540,600.16
V. ENGINEERING OVERHEAD 1% of (IV) 15,406.00
VI. TOTAL PROJECT COST (IV+V) 1,556,006.16
Php 1,557,000.00

Prepared by: Noted:

Project Engineer, PFSED School Principal Division PFC

Checked: Reviewed: Approved:

OLIVER R. HERNANDEZ
Area Supervisor, PFSED Cost and Assessment Supervisor Chief, PFSED
One Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
DIVISION OF OZAMIZ CITY
Ozamiz City

PROJECT: REPAIR/RENOVATION OF NEW SPORTS UNIT OFFICE


Old Building, Division Office
LOCATION :
OWNER Division of Ozamiz City
:
SUBJECT : APPROVED AGENCY ESTIMATE

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
9.00 Carpentry Works
Partition sq.m
2”x3”x10’ S4S Lumber, Coco bd.ft 120.00 18.00 5.40 2,160.00 648.00 2,808.00
2”x2”x10’ S4S Lumber, Coco bd.ft 150.00 18.00 5.40 2,700.00 810.00 3,510.00
¼”x4’x8’ Ordinary Plywood sheet 30.00 330.00 99.00 9,900.00 2,970.00 12,870.00
Common wire nails kg 13.00 55.00 16.50 715.00 214.50 929.50
Finishing nails kg 10.00 75.00 22.50 750.00 225.00 975.00
Sub-total 21,092.50
11.00 Plumbing Works
11.62 Water Closet 1.6gpf with Accessories set 1.00 5,500.00 825.00 5,500.00 825.00 6,325.00
11.64 Lavatory, Pedestal Type with Accessories set 1.00 3,150.00 472.50 3,150.00 472.50 3,622.50
11.60 Faucet, Hose Bibb, Brass 1/2"Ø pc 2.00 160.00 24.00 320.00 48.00 368.00
11.67 Tissue Holder pc 1.00 250.00 37.50 250.00 37.50 287.50
11.05 G.I. Pipe 3/4"Ø Sch.40 pc 3.00 360.00 108.00 1,080.00 324.00 1,404.00
11.09 G.I. Coupling, 3/4"Ø pc 2.00 14.75 4.43 29.50 8.85 38.35
11.24 G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 2.00 40.00 12.00 80.00 24.00 104.00
11.06 G.I. Pipe 1/2"Ø Sch.40 pc 3.00 260.00 78.00 780.00 234.00 1,014.00
11.21 G.I. Elbow 90o x 1/2"Ø pc 5.00 11.00 3.30 55.00 16.50 71.50
11.08 G.I. Coupling, 1/2"Ø pc 2.00 10.75 3.23 21.50 6.45 27.95
11.15 G.I. Tee, 1/2"Ø pc 4.00 17.75 5.33 71.00 21.30 92.30
11.65 S.S.Floor Drain 4' x 4" pc 1.00 97.50 14.63 97.50 14.63 112.13
11.66 Teflon Tape roll 3.00 12.00 1.80 36.00 5.40 41.40
11.69 Mirror sq.ft 1.00 100.00 15.00 100.00 15.00 115.00
Sub-total 13,623.63
13.00 Painting Works
Concrete surfaces sq.m
13.18 Neutralizer gal 3.00 132.00 39.60 396.00 118.80 514.80
13.01 Latex, Flat gal 3.00 470.00 141.00 1,410.00 423.00 1,833.00
13.02 Latex, Semi Gloss gal 3.00 478.25 143.48 1,434.76 430.43 1,865.19
13.20 Acri Color qrt 1.00 165.00 49.50 165.00 49.50 214.50
Wood surfaces sq.m
13.04 Enamel, Flatwall gal 4.00 440.00 132.00 1,760.00 528.00 2,288.00
13.05 Enamel, Semi Gloss gal 4.00 460.00 138.00 1,840.00 552.00 2,392.00
13.16 Paint Thinner gal 2.00 260.00 78.00 520.00 156.00 676.00
Sub-total 9,783.49
14.00 Tile Works
14.15 Flooring sq.m
14.01 Unglazed Floor Tiles 40x40cm pc 200.00 57.50 3.60 11,500.00 720.00 12,220.00
14.16 Tile Adhesive 25 kg/bag bag 4.00 224.10 67.23 896.40 268.92 1,165.32
14.15 Tile Grout 5 kg/bag bag 4.00 150.00 45.00 600.00 180.00 780.00
Sub-total 14,165.32

I. DIRECT COST 58,664.94


II. INDIRECT COST 5% of (I) 11,146.34
V. TOTAL CONSTRUCTION COST (I+II+III+IV) 69,811.27
VI. TOTAL PROJECT COST (IV+V) Php69,811.27
Php70,000.00

Prepared: Noted:

ERIC PAUL M. CATULONG, C.E. DANILO P. ARROYO


Project Engineer, PFSED Division PFC

Reviewed: Recommending Approval Approved:


by the authority of:
MARK JUN B. GOMESERIA RONALD E. BENITEZ, C.E. OLIVER R. HERNANDEZ, C.E.
Cost and Assessment Coordinator Regional Lead Engineer Chief, PFSED

1CL 7x9m Schoolbuilding 50 of 61


One Classroom

I.D. UNIT COST TOTAL COST


DESCRIPTION UNIT QTY GRAND TOTAL
NO MATERIAL LABOR MATERIAL LABOR
ERWIN G. IGARTA, C.E.
Area Manager, PFSED

1CL 7x9m Schoolbuilding 51 of 61


e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
1.00 Earthworks e
###
e
1.01 Clearing and Grubbing sq.m - 20.00 l
m
1.02 Structural Excavation cu.m - 200.00
a
1.03 Backfilling and Compaction cu.m - 45.00 n
/
1.04 Gravel Bedding G-1 cu.m 552.00 180.00 T
1.05 Soil Poisoning sq.m 15.00 4.50 i
n
1.06 Select Fill cu.m 150.00 45.00 s
2.00 Concreting Works - - m
i
2.01 Portland Cement bag 223.00 42.50 t
h
2.02 Crushed Gravel 3/4" cu.m 655.00 175.00
2.03 Washed Sand cu.m 435.00 150.00
2.04 Demolition of reinforced concrete cu.m - 500.00
2.05 Crushed Gravel 1" cu.m 552.00 150.00
3.00 Rebar Works - -
3.01 Deformed Round Bars, Grade 40 kg 39.97 7.63
3.02 G.I. Tie Wire kg 50.00 9.00
3.03 G.I. Tie Wire roll 1,750.00 262.50
4.00 Formworks - -
4.01 Coco Lumber bd.ft 14.00 4.20
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 288.92 90.00
4.03 Plywood Ordinary, 1/2" x 4' x 8' pc 490.33 162.00
4.04 CWN, Assorted kg 60.00 18.00
5.00 Masonry Works - -
5.01 Demolition of Masonry Wall sq.m - 360.00
5.02 Portland Cement bag 223.00 51.00
5.03 Washed Sand cu.m 435.00 180.00
5.04 CHB 4" thk pc 9.50 2.25
5.05 CHB 6" thk pc 12.00 3.00
5.06 10mm x 6m RSB kg 39.97 9.03
5.07 G.I. Tie Wire kg 50.00 15.00
5.08 Concrete Louver Blocks pc 30.00 9.00
5.09 Plaster Moulding lm 125.00 62.50
6.00 Doors and Windows - -
6.01 Removal of Door with Jamb set - 88.76
6.02 Removal of Window with Jamb sq.m - 24.16
D-1, Panel Door 0.90m x 2.10m on 150mm Wooden Jamb complete with
6.03 set 5,917.50 887.63
###
Accessories
D-2 Flush Door 0.90m x 2.10m on 150mm Wooden Jamb complete with
6.04 set 3,967.50 529.13
Accessories
D-3 Flush Door 0.70m x 2.10m on 150mm Wooden Jamb complete with
6.05 set 3,857.50 517.13
Accessories
D-4 Cubicle Door 0.60m x 1.20m on 150mm Wooden Jamb complete with
6.06 set 2,958.75 443.81
Accessories
W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.07 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 6,700.00 1,005.00
###
mm Wooden Jamb complete with Accessories
W - 2, ( 1.5 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.08 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,800.00 570.00
###
mm Wooden Jamb complete with Accessories
W - 3, ( 0.7 x 2.6 m) Jalousie Window with Clear Glass Blades on
6.09 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,500.00 525.00
mm Wooden Jamb complete with Accessories

Page 52 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
6.10 Panel Door 0.90m x 2.10m pc 4,602.80 - e
e
6.11 Panel Door 0.80m x 2.10m pc 3,400.00 - l
m
6.12 Panel Door 0.70m x 2.10m pc 3,100.00 -
a
6.13 Panel Door 0.60m x 2.10m pc 3,100.00 - n
/
6.14 Flush Door 0.90m x 2.10m pc 2,088.00 - T
6.15 Flush Door 0.80m x 2.10m pc 1,740.00 - i
n
6.16 Flush Door 0.70m x 2.10m pc 1,690.00 - s
6.17 Flush Door 0.60m x 2.10m pc 1,640.00 - m
i
6.18 Steel Door 0.70m x 2.10m pc 4,375.00 - t
h
6.19 Steel Door 0.80m x 2.10m pc 4,500.00 -
6.20 Steel Door 0.90m x 2.10m pc 4,600.00 -
6.21 PVC Door 0.60m x 2.10m pc 1,550.00 -
6.22 Door Jamb 45mm x 100mm set 1,050.00 -
6.23 Door Jamb 45mm x 125mm set 1,450.00 -
6.24 Door Jamb 45mm x 150mm set 1,550.00 -
6.25 Steel Encased Clear Glass Window with Grilles sq.ft 125.00 56.25
6.26 Security Grilles sq.ft 90.00 40.50
6.27 Entrance, Lockset Standard set 467.50 -
6.28 Entrance, Handleset set 7,760.00 -
6.29 Entrance, Cylindrical Lockset set 1,640.00 -
6.30 Entrance, Lever Lockset set 2,820.00 -
6.31 Bathroom, Lockset Keyless set 1,080.00 -
6.32 Hinges, Standard 3-1/2" x 3-1/2" pa 75.00 -
6.33 Hinges, Ball Bearing 3-1/2" x 3-1/2" pa 680.00 -
D-1, Flush Door 0.90m x 2.10m on 100mm Wooden Jamb complete with
6.34 set 3,467.50 302.75
###
Accessories
W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.35 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 set 5,500.00 550.00
###
mm Wooden Jamb complete with Accessories
W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.36 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 set 2,750.00 275.00
###
mm Wooden Jamb complete with Accessories
W - 1, ( 3.6 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.37 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 9,250.00 1,387.50
###
mm Wooden Jamb complete with Accessories
W - 2, ( 3.6 x 1.2 m) Jalousie Window with Clear Glass Blades on
6.38 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 6,950.00 1,042.50
###
mm Wooden Jamb complete with Accessories

W - 3, ( 1.8 x 1.6 m) Jalousie Window with Clear Glass Blades on


6.39 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 4,600.00 690.00
###
mm Wooden Jamb complete with Accessories
W - 4, ( 0.6 x 0.95 m) Jalousie Window with Clear Glass Blades on
6.39a Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 910.42 182.40
mm Wooden Jamb complete with Accessories
W - 4, ( 0.6 x 0.6 m) Jalousie Window with Clear Glass Blades on
6.40 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 700.00 105.00
###
mm Wooden Jamb complete with Accessories

W - 1, ( 4.0 x 1.8 m) Jalousie Window with Clear Glass Blades on


6.41 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 11,520.00 1,728.00
###
mm Wooden Jamb complete with Accessories
W - 2, ( 2.1 x 1.8 m) Jalousie Window with Clear Glass Blades on
6.42 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 6,048.00 907.20
###
mm Wooden Jamb complete with Accessories

Page 53 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
e
W - 3, ( 1.3 x 1.8 m) Jalousie Window with Clear Glass Blades on
e
6.43 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,744.00 561.60
###
l
mm Wooden Jamb complete with Accessories
m
W - 4, ( 1.2 x 0.7 m) Jalousie Window with Clear Glass Blades on a
6.44 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 1,344.00 201.60
### n
mm Wooden Jamb complete with Accessories /
T
W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on i
6.45 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,350.00 502.50
### n
mm Wooden Jamb complete with Accessories s
m
D-3 Flush Door 0.60m x 2.10m on 150mm Wooden Jamb complete with i
6.46 set 3,657.50 487.13
Accessories t
D-1, (0.90 x 2.10) Steel Door and Jamb with Fixed Glass Transom h
6.47 set 6,000.00 1,800.00
complete with Accessories
D-2, (0.80 x 2.10) Steel Door and Jamb with Fixed Glass Transom
6.48 set 5,800.00 1,740.00
complete with Accessories
D-3, (0.90 x 2.10) Steel Door and Jamb with Steel Grilles Transom and
6.49 set 6,500.00 1,800.00
Stainless Kick Plate complete with Accessories
D-4, (0.70 x 2.10) Steel Door and Jamb with Fixed Glass Transom
6.50 set 5,500.00 1,650.00
complete with Accessories

W - 1, ( 2.4 x 1.5 m) Steel Casement Window with Grilles, Semi French


6.51 set 5,750.00 2,012.50
###
Type with 1/4 thk Clear Glass Panes complete with Accessories

W - 2, ( 1.8 x 1.5 m) Steel Casement Window with Grilles, Semi French


6.52 set 4,350.00 1,522.50
###
Type with 1/4 thk Clear Glass Panes complete with Accessories

W - 3, ( 1.8 x 1.2 m) Steel Casement Window with Grilles, Semi French


6.53 set 3,500.00 1,225.00
###
Type with 1/4 thk Clear Glass Panes complete with Accessories

W - 4, ( 0.6 x 0.6 m) Steel Awning Window with Grilles with 1/4 thk Clear
6.54 set 750.00 262.50
###
Glass Panes complete with Accessories
7.00 Steel Works - -
7.01 C 6 x 10.5 kg 54.73 19.61
7.02 C 6 x 8.2 kg 54.73 19.61
7.03 LC 75 x 38 x 15 x 2.0mm kg 41.19 12.48
7.04 LC 100 x 50 x 15 x 1.5mm kg 41.19 12.48
7.05 LC 100 x 50 x 15 x 2.0mm kg 41.19 12.48
7.06 LC 100 x 50 x 15 x 3.0mm kg 41.19 12.48
7.07 LC 150 x 65 x 20 x 2.0mm kg 41.19 12.48
7.08 LC 150 x 65 x 20 x 3.0mm kg 41.19 12.48
7.09 LC 120 x 50 x 20 x 2.0mm kg 41.19 12.48
7.10 LC 120 x 50 x 20 x 3.0mm kg 41.19 12.48
7.11 L 25 x 25 x 3mm kg 41.60 8.73
7.12 L 30 x 30 x 6mm kg 41.60 8.73
7.13 L 50 x 50 x 5mm kg 41.60 8.73
7.14 L 50 x 50 x 6mm kg 41.60 8.73
7.15 Flat Bar 1" x 1/8" kg 41.60 8.73
7.16 Flat Bar 1" x 3/16" kg 41.60 8.73
7.17 Flat Bar 1" x 1/4" kg 41.60 8.73
7.18 Plain Round Bar 10mmØ x 6m pc 107.00 32.10
7.19 Plain Round Bar 12mmØ x 6m pc 185.00 55.50
7.20 Plain Round Bar 16mmØ x 6m pc 286.00 85.80
7.21 Square Bar 12mm□ x 6m pc 141.00 42.30
7.22 Square Bar 16mm□ x 6m pc 218.00 65.40
7.23 Square Bar 19mm□ x 6m pc 412.00 123.60

Page 54 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
7.24 Steel Plate 1.20m x 2.40m x 12mm pc 10,500.00 3,150.00 e
e
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 9,300.00 2,790.00 l
m
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 8,635.00 2,590.50
a
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5,390.00 1,617.00 n
/
7.28 Tubular 50mm x 150mm x 2.0mm pc 2,640.00 792.00 T
7.29 Tubular 50mm x 100mm x 1.5mm pc 1,085.00 325.50 i
n
7.30 Turn Buckle 12 mmØ pc 60.00 18.00 s
7.31 Turn Buckle 16 mmØ pc 80.00 24.00 m
i
7.32 Anchor Bolt with Nuts and Washer, 20mmØ x 50mm x 300mm pc 65.00 19.50 t
h
7.33 Anchor Bolt with Nuts and Washer, 16mmØ x 50mm x 300mm pc 45.00 13.50
7.34 Anchor Bolt with Nuts and Washer, 12mmØ x 50mm x 300mm pc 27.00 8.10
7.35 Anchor Bolt with Nuts and Washer, 10mmØ x 50mm x 200mm pc 12.00 3.60
7.36 B.I. Pipe 100mmØ Sch.40 pc 2,262.00 678.60
7.37 B.I. Pipe 75mmØ Sch.40 pc 1,658.00 497.40
7.38 B.I. Pipe 50mmØ Sch.40 pc 880.00 264.00
7.39 B.I. Pipe 38mmØ Sch.40 pc 632.00 189.60
7.40 B.I. Pipe 32mmØ Sch.40 pc 537.00 161.10
7.41 B.I. Pipe 50mmØ Sch.20 pc 691.00 207.30
7.42 B.I. Pipe 38mmØ Sch.20 pc 499.00 149.70
7.43 B.I. Pipe 32mmØ Sch.20 pc 435.00 130.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 960.56 338.00
7.45 G.I. Pipe 2"Ø Sch.40 pc 1,489.38 502.00
7.46 Welding Rod kg 67.00 20.10
8.00 Roofing Works - -
8.01 Removal of Roofing Sheets sq.m - 7.50
8.02 Removal of Ridge Roll pc - 15.00
8.03 Removal of Flashing pc - 15.00
8.04 Removal of Gutter pc - 15.00
8.05 Removal of Fascia Board pc - 23.50
8.06 Corrugated G.I. Sheet Ga.26, 36" x 8' pc 218.83 43.77
8.07 Corrugated G.I. Sheet Ga.26, 36" x 9' pc 246.54 49.31
8.08 Corrugated G.I. Sheet Ga.26, 36" x 10' pc 273.93 54.79
8.09 Corrugated G.I. Sheet Ga.26, 36" x 12' pc 327.14 65.43
8.10 Plain G.I. Sheet Ga.26, 4' x 8' pc 400.00 80.00
8.11 Plain G.I. Sheet Ga.26, 3' x 8' pc 228.50 45.70
8.12 Gutter Ga.26, 24" x 8' pc 150.00 30.00
8.13 Flashing Ga.26, 24"x 8' pc 302.50 60.50
8.14 Ridge Roll Ga.26, 24"x 8' pc 302.50 60.50
8.15 Long-Span Roofing, Rib-Type, Pre-Painted, 1220mm x 0.4mm thk m 360.00 72.00
8.16 Long-Span Roofing, Corrugated, Pre-Painted, 1220mm x 0.4mm thk m 360.00 72.00
8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.18 Ridge Roll, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.19 Flashing, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.20 Flashing, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.21 Flashing, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk pc 767.00 153.40
8.22 Gutter, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.23 Gutter, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.24 Gutter, Stainless, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 767.00 153.40

Page 55 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
8.25 Gutter, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk m 68.00 13.60 e
e
8.26 Polyethylene Foam with One Side Aluminum 10mm thk m 105.00 21.00 l
m
8.27 Polyethylene Foam with One Side Aluminum 15mm thk m 142.00 28.40
a
8.28 Polyethylene Foam with One Side Aluminum 20mm thk m 179.50 35.90 n
/
8.29 Polyethylene Foam with One Side Aluminum 25mm thk m 216.50 43.30 T
8.30 Polyethylene Foam with Two Side Aluminum 5mm thk m 103.50 20.70 i
n
8.31 Polyethylene Foam with Two Side Aluminum 10mm thk m 141.00 28.20 s
8.32 Polyethylene Foam with Two Side Aluminum 15mm thk m 178.00 35.60 m
i
8.33 Polyethylene Foam with Two Side Aluminum 20mm thk m 215.00 43.00 t
h
8.34 Polyethylene Foam with Two Side Aluminum 25mm thk m 252.00 50.40
8.35 Teckscrew 2-1/2" pc 1.25 0.25
8.36 Roof Sealant L 239.80 47.96
8.37 Blind Rivets pc 0.50 0.10
8.38 Umbrella Nails kg 60.00 12.00
9.00 Carpentry Works - -
9.01 Removal of Ceiling sq.m - 8.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 288.92 81.75
9.03 Plywood, Ordinary 3/8" x 4' x 8' pc 520.00 156.00
9.04 Plywood, Ordinary 1/2" x 4' x 8' pc 490.33 144.00
9.05 Plywood, Ordinary 3/4" x 4' x 8' pc 850.00 255.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 340.00 108.00
9.07 Plywood, Marine 1/2" x 4' x 8' pc 650.00 195.00
9.08 Plywood, Marine 3/4" x 4' x 8' pc 1,050.00 315.00
9.09 Fiber Cement Board, 1/4" x 4' x 8' pc 540.00 162.00
9.10 Fiber Cement Board, 3/16" x 4' x 8' pc 390.00 117.00
9.11 Rough Lumber, Sun Dried, Yakal bd.ft 120.00 36.00
9.12 Rough Lumber, Sun Dried, Guijo bd.ft 120.00 36.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 40.00 12.65
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 50.00 18.60
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 245.00 73.50
9.16 Fascia Board, Wooden bd.ft 36.00 10.80
9.17 Fascia Board, Fiber Cement 10" x 8' pc 279.00 83.70
9.18 Fascia Board, Fiber Cement 12" x 8' pc 325.00 97.50
9.19 Fascia Board, Fiber Cement 10" x 12' pc 352.50 105.75
9.20 Fascia Board, Fiber Cement 12" x 12' pc 405.00 121.50
9.21 Ficem Board Nails kg 90.00 27.00
9.22 Finishing Nails kg 70.00 21.00
9.23 Common Wire Nails kg 50.00 15.00
9.24 Concrete Nails kg 70.00 21.00
9.25 Removal of T&G bd.ft - 5.00
9.26 T&G 3/4" x 4" ft 20.00 6.00
9.27 T&G 3/4" x 6" ft 32.50 9.75
9.28 Wood Glue L 120.00 36.00
9.29 Acoustic Board 2' x 4' pc 320.00 96.00
9.30 Main Tee Runner 1" x 1" x 10' pc 98.85 29.66
9.31 Cross Tee 1" x 1" x 10' pc 90.00 27.00
9.32 Wall Angle 1" x 1" x 10' pc 90.00 27.00
9.33 Suspension Rod #8 kg 145.00 43.50

Page 56 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
9.34 Removal of Wooden Truss bd.ft - 4.00 e
e
9.35 Removal of Purlins bd.ft - 4.00 l
m
9.36 Removal of Partition sq.m - 8.00
a
9.37 Machine Bolts with Std. Nuts and Washers, 5/8" x 7" pc 18.00 5.40 n
/
9.38 Machine Bolts with Std. Nuts and Washers, 5/8" x 8" pc 20.00 6.00 T
9.39 Machine Bolts with Std. Nuts and Washers, 5/8" x 10" pc 25.00 7.50 i
n
9.40 Machine Bolts with Std. Nuts and Washers, 1/2" x 7" pc 12.00 3.60 s
9.41 Machine Bolts with Std. Nuts and Washers, 1/2" x 8" pc 15.00 4.50 m
i
9.42 Wood Preservative, Brown L 900.00 270.00 t
h
9.43 Lawanit, 1/4" thk pc 280.00 84.00
9.44 Concealed Hinges pc 30.00 9.00
9.45 S.S. Cabinet Handle pc 90.00 27.00
9.46 6mm thk Clear Glass sq.ft 60.00 18.00
9.47 S.S. Tube 3/4"Ø m 420.00 126.00
9.48 S.S. Flange 3/4"Ø pa 75.00 22.50
9.49 Drawer Guide, Metal 20" Full Extension set 420.00 126.00
9.50 Folding Door, Full Louver 450 x 1830mm set 1,435.00 430.50
9.51 Heavy Duty Steel Track with Roller m - 495.00
10.00 Electrical Works - -
10.01 Electrical Conduit uPVC, 15mmØ pc 50.00 15.00
10.02 Electrical Conduit uPVC, 20mmØ pc 69.75 20.93
10.03 Electrical Conduit uPVC, 32mmØ pc 137.50 41.25
10.04 Electrical Conduit uPVC, 40mmØ pc 192.50 57.75
10.05 Electrical Conduit uPVC, 50mmØ pc 214.75 64.43
10.06 RSC 20mmØ pc 112.50 33.75
10.07 RSC 25mmØ pc 175.00 52.50
10.08 RSC 32mmØ pc 339.00 101.70
10.09 RSC 38mmØ pc 430.50 129.15
10.10 30.0 mm2 THW Wire, Stranded m 126.00 54.00
10.11 3.5 mm THW Wire, Stranded
2
m 23.97 7.02
10.12 5.5 mm THW Wire, Stranded
2
m 35.86 10.14
10.13 8.0 mm2 THW Wire, Stranded m 54.98 16.38
10.14 14.0 mm THW Wire, Stranded
2
m 60.00 25.35
10.15 22.0 mm2 THW Wire, Stranded m 94.00 40.17
10.16 Junction Box, 4" x 4" G.I. pc 15.00 4.50
10.17 Utility Box, 2" x 4" G.I. pc 30.00 4.28
10.18 FL 2 x 40W Recessed Type with Luminare 24" x 48" set 2,600.00 390.00
10.19 FL 1 x 40W Recessed Type with Luminare 6" x 48" set 1,184.50 177.68
10.20 FL 2 x 40W Industrial Type set 1,200.00 126.00
10.21 FL 1 x 40W Industrial Type set 700.00 73.50
10.22 FL 1 x 20W Industrial Type set 630.00 66.00
10.23 Single Switch with Plate pc 97.68 13.46
10.24 2-Gang Switch with Plate pc 153.00 21.53
10.25 3-Gang Switch with Plate pc 208.00 29.59
10.26 3-Way Switch with Plate pc 251.00 37.65
10.27 Single C.O. with Plate pc 88.00 13.20
10.28 Duplex C.O. with Plate pc 263.80 21.00
10.29 Duplex C.O. Weatherproof pc 756.50 76.50

Page 57 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
10.30 Aircon Outlet with Plate pc 282.75 42.41 e
e
10.31 TV Terminal Outlet with Plate pc 322.50 48.38 l
m
10.32 Telephone Outlet with Plate pc 251.00 37.65
a
10.33 Ceiling Receptacle 3-1/2"Ø pc 25.00 3.75 n
/
10.34 Entrance Cap 20mm dia. pc 50.00 7.50 T
10.35 Entrance Cap 32mm dia. pc 75.00 11.25 i
n
10.36 Entrance Cap 25mm dia. pc 70.00 10.50 s
10.37 Grounding Rod, 2.4m x 16mm dia. pc 150.00 22.50 m
i
10.38 Circuit Breaker, 20A 2P set 313.00 46.95 t
h
10.39 Circuit Breaker, 30A 2P set 313.00 46.95
10.40 Circuit Breaker, 40A 2P set 441.25 66.19
10.41 Circuit Breaker, 50A 2P set 441.25 66.19
10.42 Circuit Breaker, 60A 2P set 441.25 66.19
10.43 Circuit Breaker, 100A 2P set 650.00 97.50
10.44 Circuit Breaker, 175A 2P set - -
10.45 Safety Switch 100A 2P set 2,224.75 333.71
10.46 Safety Switch 30A 2P set 603.25 90.49
10.47 Panel Box, Flush Type, 6 Branches set 1,400.00 210.00
10.48 Panel Box, Flush Type, 4 Branches set 1,202.75 180.41
10.49 Panel Box, Flush Type, 8 Branches set 1,580.00 237.00
10.50 Panel Box, Flush Type, 12 Branches set 2,530.75 379.61
10.51 Panel Box, Flush Type, 10 Branches set 1,850.00 277.50
10.52 Flourescent Tube 40W set - -
10.53 Incandescent Bulb 50W set 35.00 5.25
10.54 Vibrating Bell 8" set 1,500.00 225.00
10.55 Fire Alarm Bell, Vibrating Type set 2,000.00 300.00
10.56 Fire Alarm Station, Manual Single Action set 1,750.00 262.50
10.57 Fire Alarm Control Panel, One Zone set 5,500.00 825.00
10.58 Electrical Tape pc 37.50 5.63
10.59 Rubber Tape roll 100.00 15.00
11.00 Plumbing Works - -
11.01 uPVC Water Line 1/2"Ø pc 55.00 16.50
11.02 uPVC Water Line 3/4"Ø pc 85.00 25.50
11.03 uPVC Water Line 1"Ø pc 112.00 33.60
11.04 G.I. Pipe 1"Ø Sch.40 pc 460.00 138.00
11.05 G.I. Pipe 3/4"Ø Sch.40 pc 360.00 108.00
11.06 G.I. Pipe 1/2"Ø Sch.40 pc 260.00 78.00
11.07 G.I. Coupling, 3/8"Ø pc 11.00 3.30
11.08 G.I. Coupling, 1/2"Ø pc 10.75 3.23
11.09 G.I. Coupling, 3/4"Ø pc 14.75 4.43
11.10 G.I. Coupling, 1"Ø pc 23.75 7.13
11.11 G.I. Coupling, 1-1/2"Ø pc 35.00 10.50
11.12 G.I. Coupling, 2"Ø pc 45.00 13.50
11.13 G.I. Coupling, 3"Ø pc 150.00 45.00
11.14 G.I. Tee, 3/8"Ø pc 19.75 5.93
11.15 G.I. Tee, 1/2"Ø pc 17.75 5.33
11.16 G.I. Tee, 3/4"Ø pc 21.25 6.38
11.17 G.I. Tee, 1"Ø pc 42.75 12.83

Page 58 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
11.18 G.I. Tee, 3/8" x 1/2"Ø pc 23.75 7.13 e
e
11.19 G.I. Tee, 3/4" x 1/2"Ø pc 41.25 12.38 l
m
11.20 G.I. Tee, 1" x 1/2"Ø pc 41.25 12.38
a
11.21 G.I. Elbow 90o x 1/2"Ø pc 11.00 3.30 n
/
11.22 G.I. Elbow 90 x 3/4"Ø
o
pc 20.75 6.23 T
11.23 G.I. Elbow 90o x 1"Ø pc 33.75 10.13 i
n
11.24 G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 40.00 12.00 s
11.25 G.I. Coupling Reducer, 1-1/2" x 1/2"Ø pc 40.00 12.00 m
i
11.26 G.I. Coupling Reducer, 2" x 1"Ø pc 58.25 17.48 t
h
11.27 G.I. Plug, 1/2"Ø pc 9.75 2.93
11.28 G.I. Plug, 3/4"Ø pc 12.50 3.75
11.29 G.I. Plug, 1"Ø pc 20.50 6.15
11.30 G.I. Plug, 1-1/2"Ø pc 30.75 9.23
11.31 G.I. Plug, 2"Ø pc 42.50 12.75
11.32 S.S. Elbow 90o x 1/2"Ø pc 90.00 27.00
11.33 S.S. Elbow 90 x 3/4"Ø
o
pc 146.00 43.80
11.34 S.S. Elbow 90o x 1"Ø pc 230.00 69.00
11.35 S.S. Coupling, 3/4"Ø pc 130.00 39.00
11.36 S.S. Coupling, 1"Ø pc 200.00 60.00
11.37 S.S. Tee, 1/2"Ø pc 130.00 39.00
11.38 S.S. Tee, 3/4"Ø pc 200.00 60.00
11.39 S.S. Tee, 1"Ø pc 330.00 99.00
11.40 S.S. Union Patente, 1/2"Ø pc 300.00 90.00
11.41 S.S. Union Patente, 3/4"Ø pc 400.00 120.00

Page 59 of 61
One Classroom

Republic of the Philippines


DEPARTMENT OF EDUCATION
PHYSICAL FACILITIES AND SCHOOLS ENGINEERING DIVISION
Pasig City

PROJECT: PROPOSED REINFORCED SEPTIC VAULT 2.30 X 3.45 X 2.15M


SCHOOL :
LOCATION :
OWNER : DEPARTMENT OF EDUCATION
SUBJECT : APPROVED AGENCY ESTIMATE

UNIT COST TOTAL COST


ITEM/DESCRIPTION UNIT QTY
MATERIAL LABOR MATERIAL LABOR
GENERAL REQUIREMENTS
Mobilization/Temporary Structures, Utilities and
lot 1.00 314.28 209.52 314.28 209.52
Services/Demobilization
Sub-total
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 8.00 0.00 20.00 0.00 160.00
1.02 Structural Excavation cu.m 12.50 0.00 200.00 0.00 2,500.00
1.03 Backfilling and Compaction cu.m 12.50 0.00 45.00 0.00 562.50
1.04 Gravel Bedding G-1 cu.m 1.00 552.00 180.00 552.00 180.00
Sub-total
2.00 Concreting Works
Septic Vault cu.m 5.30
2.01 Portland Cement bag 48.00 223.00 42.50 10,704.00 2,040.00
2.05 Crushed Gravel 1" cu.m 5.50 552.00 150.00 3,036.00 825.00
2.03 Washed Sand cu.m 2.75 435.00 150.00 1,196.25 412.50
Sub-total
3.00 Rebar Works
Septic Vault kg 389.82
3.01 Deformed Round Bars, Grade 40 kg 389.82 39.97 7.63 15,581.20 2,975.78
3.02 G.I. Tie Wire kg 8.00 50.00 9.00 400.00 72.00
Sub-total
4.00 Formworks
Septic Vault sq.m 67.28
4.01 Coco Lumber bd.ft 343.20 14.00 4.20 4,804.80 1,441.44
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 12.00 288.92 90.00 3,467.00 1,080.00
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00
Sub-total

I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)

40041.25 12339.22
Prepared by: Noted:

60 of 61
One Classroom

epublic of the Philippines


RTMENT OF EDUCATION
S AND SCHOOLS ENGINEERING DIVISION
Pasig City

X 3.45 X 2.15M

GRAND TOTAL

523.80

523.80

160.00
2,500.00
562.50
732.00
3,954.50

12,744.00
3,861.00
1,608.75
18,213.75

18,556.99
472.00
19,028.99

6,246.24
4,547.00
390.00
11,183.24

52,904.28
10,051.81
7,554.73
70,510.82
705.11
Php71,215.93
Php72,000.00

61 of 61

You might also like