Professional Documents
Culture Documents
POW BOQ Format
POW BOQ Format
DEPARTMENT OF EDUCATION
DIVISION OF OZAMIZ CITY
Ozamiz City 7200
((School))
PROGRAM OF WORKS
I. DIRECT COST
Sub-Total 0.00
II. INDIRECT COST 9% of (I)
Overhead Expenses (5%) #DIV/0! 0.00
Contingencies (3%) #DIV/0! 0.00
Miscellaneous (1%) #DIV/0! 0.00
Sub-Total 0.00
III. TAX 5% of (I + II) #DIV/0! 0.00
IV. TOTAL CONSTRUCTION COST (I+II+III) 0.00
SAY
Prepared:
School Head
D-1, Flush Door 0.90m x 2.10m on 100mm set 2.00 3,467.50 302.75 6,935.00 605.50 7,540.50
6.34 Wooden Jamb complete with Accessories
Anchor Bolt with Nuts and Washer, 10mmØ pc 16.00 12.00 3.60 192.00 57.60 249.60
7.35 x 50mm x 200mm
7.46 Welding Rod kg 15.00 67.00 20.10 1,005.00 301.50 1,306.50
13.12 Primer, Zinc Chromate gal 2.00 537.00 161.10 1,074.00 322.20 1,396.20
Sub-total 45,851.84
8.00 I Roofing Works
Long-Span Roofing, Corrugated, Pre- m 83.20 360.00 72.00 29,952.00 5,990.40 35,942.40
8.16 Painted, 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 4.00 544.00 2,176.00 0.00 2,176.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 6,469.28
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 119.00 0.00 20.00 0.00 2,380.00 2,380.00
1.02 Structural Excavation cu.m 23.88 0.00 200.00 0.00 4,776.00 4,776.00
1.03 Backfilling and Compaction cu.m 16.46 0.00 45.00 0.00 740.48 740.48
1.04 Gravel Bedding G-1 cu.m 7.44 552.00 180.00 4,104.12 1,338.30 5,442.42
1.06 Select Fill cu.m 11.90 150.00 45.00 1,785.00 535.50 2,320.50
1.05 Soil Poisoning sq.m 130.90 15.00 4.50 1,963.50 589.05 2,552.55
Sub-total 18,211.95
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 4.90
2.01 Portland Cement bag 45.00 223.00 42.50 10,035.00 1,912.50 11,947.50
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
2.03 Washed Sand cu.m 2.50 435.00 150.00 1,087.50 375.00 1,462.50
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 3.73
2.01 Portland Cement bag 34.00 223.00 42.50 7,582.00 1,445.00 9,027.00
2.02 Crushed Gravel 3/4" cu.m 3.75 655.00 175.00 2,456.25 656.25 3,112.50
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 106,034.50
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 145.25
Column kg 738.02
Beam kg 640.65
3.01 Deformed Round Bars, Grade 40 kg 1,708.98 39.97 7.63 68,307.94 13,045.83 81,353.77
3.02 G.I. Tie Wire kg 35.00 50.00 9.00 1,750.00 315.00 2,065.00
Sub-total 83,418.77
4.00 Formworks
Long-Span Roofing, Corrugated, Pre-Painted, m 156.00 360.00 72.00 56,160.00 11,232.00 67,392.00
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 7.00 544.00 3,808.00 0.00 3,808.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 9,493.95
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 178.50 0.00 20.00 0.00 3,570.00 3,570.00
1.02 Structural Excavation cu.m 36.34 0.00 200.00 0.00 7,267.20 7,267.20
1.03 Backfilling and Compaction cu.m 25.27 0.00 45.00 0.00 1,136.97 1,136.97
1.04 Gravel Bedding G-1 cu.m 11.14 552.00 180.00 6,148.73 2,005.02 8,153.75
1.06 Select Fill cu.m 17.85 150.00 45.00 2,677.50 803.25 3,480.75
1.05 Soil Poisoning sq.m 196.35 15.00 4.50 2,945.25 883.58 3,828.83
Sub-total 27,437.49
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 7.00
2.01 Portland Cement bag 63.00 223.00 42.50 14,049.00 2,677.50 16,726.50
2.05 Crushed Gravel 1" cu.m 7.00 552.00 150.00 3,864.00 1,050.00 4,914.00
2.03 Washed Sand cu.m 3.50 435.00 150.00 1,522.50 525.00 2,047.50
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 5.25
2.01 Portland Cement bag 48.00 223.00 42.50 10,704.00 2,040.00 12,744.00
2.02 Crushed Gravel 3/4" cu.m 5.25 655.00 175.00 3,438.75 918.75 4,357.50
2.03 Washed Sand cu.m 2.75 435.00 150.00 1,196.25 412.50 1,608.75
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 156,833.50
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 205.31
Column kg 1,183.19
Beam kg 904.29
3.01 Deformed Round Bars, Grade 40 kg 2,591.54 39.97 7.63 103,583.98 19,783.04 123,367.02
3.02 G.I. Tie Wire kg 52.00 50.00 9.00 2,600.00 468.00 3,068.00
Sub-total 126,435.02
4.00 Formworks
Long-Span Roofing, Corrugated, Pre-Painted, m 228.80 360.00 72.00 82,368.00 16,473.60 98,841.60
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 10.00 544.00 5,440.00 0.00 5,440.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
PROGRAM OF WORKS
I. DIRECT COST
General Requirements lot
1 Earthworks lot
2 Concreting Works cu.m
3 Rebar Works kg
4 Formworks sq.m
5 Masonry Works sq.m
6 Doors and Windows set
7 Steel Works kg
8 Roofing Works m
9 Carpentry Works sq.m
10 Electrical Works outlet
13 Painting Works sq.m
Sub-Total
II. INDIRECT COST 19% of (I)
Overhead Expenses (5%)
Contingencies (3%)
Miscellaneous (1%)
Contractor's Profit (10%)
Sub-Total
III. TAX 12% of (I+II)
Sub-Total
IV. HAULING COST
V. TOTAL CONSTRUCTION COST (I+II+III+IV)
Prepared: Noted:
(SCHOOL)
PROJECT:
SCHOOL:
LOCATION:
SUBJECT: BILL OF MATERIALS
1.00 Earthworks
1.01 Clearing and Grubbing sq.m
1.02 Structural Excavation cu.m
1.03 Backfilling and Compaction cu.m
1.04 Gravel Bedding G-1 cu.m
1.06 Select Fill cu.m
1.05 Soil Poisoning sq.m
Sub-total 0.00
2.00 Concreting Works
Column Footing cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Wall Footing cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Column cu.m
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4" cu.m
2.03 Washed Sand cu.m
Beams cu.m
2.01 Portland Cement bag
2.02 Crushed Gravel 3/4" cu.m
2.03 Washed Sand cu.m
Slab on Grade cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Ramp on Fill cu.m
2.01 Portland Cement bag
2.05 Crushed Gravel 1" cu.m
2.03 Washed Sand cu.m
Sub-total 0.00
3.00 Rebar Works
Footing kg
Wall Footing kg
Column kg
Beam kg
Slab on Grade kg
Ramp on Fill kg
3.01 Deformed Round Bars, Grade 40 kg
3.02 G.I. Tie Wire kg
Sub-total 0.00
4.00 Formworks
Column sq.m
4.01 Coco Lumber bd.ft
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc
4.04 CWN, Assorted kg
Beams sq.m
4.01 Coco Lumber bd.ft
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc
4.04 CWN, Assorted kg
Sub-total 0.00
5.00 Masonry Works
Prepared by:
School Head
Sub-total 7,413.96
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 111,073.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
3.01 Deformed Round Bars, Grade 40 kg 1,830.84 39.97 7.63 73,178.71 13,976.08 87,154.79
3.02 G.I. Tie Wire kg 37.00 50.00 9.00 1,850.00 333.00 2,183.00
Sub-total 89,337.79
4.00 Formworks
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 10,881.34
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 229.50 0.00 20.00 0.00 4,590.00 4,590.00
1.02 Structural Excavation cu.m 39.22 0.00 200.00 0.00 7,843.20 7,843.20
1.03 Backfilling and Compaction cu.m 26.95 0.00 45.00 0.00 1,212.57 1,212.57
1.04 Gravel Bedding G-1 cu.m 13.93 552.00 180.00 7,688.81 2,507.22 10,196.03
1.06 Select Fill cu.m 22.95 150.00 45.00 3,442.50 1,032.75 4,475.25
1.05 Soil Poisoning sq.m 252.45 15.00 4.50 3,786.75 1,136.03 4,922.78
Sub-total 33,239.82
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 8.20
2.01 Portland Cement bag 74.00 223.00 42.50 16,502.00 3,145.00 19,647.00
2.05 Crushed Gravel 1" cu.m 8.25 552.00 150.00 4,554.00 1,237.50 5,791.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 6.27
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.02 Crushed Gravel 3/4" cu.m 6.50 655.00 175.00 4,257.50 1,137.50 5,395.00
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 164,789.75
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 238.58
Column kg 1,183.19
Beam kg 1,049.69
3.01 Deformed Round Bars, Grade 40 kg 2,770.21 39.97 7.63 110,725.18 21,146.91 131,872.09
3.02 G.I. Tie Wire kg 56.00 50.00 9.00 2,800.00 504.00 3,304.00
Sub-total 135,176.09
4.00 Formworks
Long-Span Roofing, Corrugated, Pre-Painted, m 291.20 360.00 72.00 104,832.00 20,966.40 125,798.40
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 13.00 544.00 7,072.00 0.00 7,072.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 14,085.61
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 306.00 0.00 20.00 0.00 6,120.00 6,120.00
1.02 Structural Excavation cu.m 48.84 0.00 200.00 0.00 9,768.00 9,768.00
1.03 Backfilling and Compaction cu.m 33.32 0.00 45.00 0.00 1,499.18 1,499.18
1.04 Gravel Bedding G-1 cu.m 18.41 552.00 180.00 10,159.56 3,312.90 13,472.46
1.06 Select Fill cu.m 30.60 150.00 45.00 4,590.00 1,377.00 5,967.00
1.05 Soil Poisoning sq.m 336.60 15.00 4.50 5,049.00 1,514.70 6,563.70
Sub-total 43,390.34
2.00 Concreting Works
Column Footing cu.m 4.83
2.01 Portland Cement bag 44.00 223.00 42.50 9,812.00 1,870.00 11,682.00
2.05 Crushed Gravel 1" cu.m 5.00 552.00 150.00 2,760.00 750.00 3,510.00
2.03 Washed Sand cu.m 2.50 435.00 150.00 1,087.50 375.00 1,462.50
Wall Footing cu.m 10.70
2.01 Portland Cement bag 97.00 223.00 42.50 21,631.00 4,122.50 25,753.50
2.05 Crushed Gravel 1" cu.m 10.75 552.00 150.00 5,934.00 1,612.50 7,546.50
2.03 Washed Sand cu.m 5.50 435.00 150.00 2,392.50 825.00 3,217.50
Column cu.m 6.15
2.01 Portland Cement bag 56.00 223.00 42.50 12,488.00 2,380.00 14,868.00
2.02 Crushed Gravel 3/4" cu.m 6.25 655.00 175.00 4,093.75 1,093.75 5,187.50
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Beams cu.m 8.11
2.01 Portland Cement bag 73.00 223.00 42.50 16,279.00 3,102.50 19,381.50
2.02 Crushed Gravel 3/4" cu.m 8.25 655.00 175.00 5,403.75 1,443.75 6,847.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Slab on Grade cu.m 30.60
2.01 Portland Cement bag 276.00 223.00 42.50 61,548.00 11,730.00 73,278.00
2.05 Crushed Gravel 1" cu.m 30.75 552.00 150.00 16,974.00 4,612.50 21,586.50
2.03 Washed Sand cu.m 15.50 435.00 150.00 6,742.50 2,325.00 9,067.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 210,188.00
3.00 Rebar Works
Footing kg 337.91
Wall Footing kg 313.33
Column kg 1,323.73
Beam kg 1,358.87
3.01 Deformed Round Bars, Grade 40 kg 3,333.84 39.97 7.63 133,253.46 25,449.48 158,702.94
3.02 G.I. Tie Wire kg 67.00 50.00 9.00 3,350.00 603.00 3,953.00
Sub-total 162,655.94
4.00 Formworks
Long-Span Roofing, Corrugated, Pre-Painted, m 384.80 360.00 72.00 138,528.00 27,705.60 166,233.60
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 17.00 544.00 9,248.00 0.00 9,248.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 4,583.44
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 76.50 0.00 20.00 0.00 1,530.00 1,530.00
1.02 Structural Excavation cu.m 14.69 0.00 200.00 0.00 2,937.60 2,937.60
1.03 Backfilling and Compaction cu.m 10.03 0.00 45.00 0.00 451.26 451.26
1.04 Gravel Bedding G-1 cu.m 4.76 552.00 180.00 2,625.86 856.26 3,482.12
1.06 Select Fill cu.m 7.65 150.00 45.00 1,147.50 344.25 1,491.75
1.05 Soil Poisoning sq.m 84.15 15.00 4.50 1,262.25 378.68 1,640.93
Sub-total 11,533.66
2.00 Concreting Works
Column Footing cu.m 1.46
2.01 Portland Cement bag 14.00 223.00 42.50 3,122.00 595.00 3,717.00
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Wall Footing cu.m 3.20
2.01 Portland Cement bag 29.00 223.00 42.50 6,467.00 1,232.50 7,699.50
2.05 Crushed Gravel 1" cu.m 3.25 552.00 150.00 1,794.00 487.50 2,281.50
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Column cu.m 2.14
2.01 Portland Cement bag 20.00 223.00 42.50 4,460.00 850.00 5,310.00
2.02 Crushed Gravel 3/4" cu.m 2.25 655.00 175.00 1,473.75 393.75 1,867.50
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Beams cu.m 2.60
2.01 Portland Cement bag 24.00 223.00 42.50 5,352.00 1,020.00 6,372.00
2.02 Crushed Gravel 3/4" cu.m 2.75 655.00 175.00 1,801.25 481.25 2,282.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Slab on Grade cu.m 7.65
2.01 Portland Cement bag 69.00 223.00 42.50 15,387.00 2,932.50 18,319.50
2.05 Crushed Gravel 1" cu.m 7.75 552.00 150.00 4,278.00 1,162.50 5,440.50
2.03 Washed Sand cu.m 4.00 435.00 150.00 1,740.00 600.00 2,340.00
Ramp on Fill cu.m 0.32
2.01 Portland Cement bag 3.00 223.00 42.50 669.00 127.50 796.50
2.05 Crushed Gravel 1" cu.m 0.50 552.00 150.00 276.00 75.00 351.00
2.03 Washed Sand cu.m 0.25 435.00 150.00 108.75 37.50 146.25
Sub-total 61,048.00
3.00 Rebar Works
Footing kg 111.16
Wall Footing kg 96.19
Column kg 445.17
Beam kg 431.34
Slab on Grade kg 201.22
Ramp on Fill kg 13.64
3.01 Deformed Round Bars, Grade 40 kg 1,298.71 39.97 7.63 51,909.48 9,913.96 61,823.44
3.02 G.I. Tie Wire kg 26.00 50.00 9.00 1,300.00 234.00 1,534.00
Sub-total 63,357.44
4.00 Formworks
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 8,336.67
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 111,073.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
Slab on Grade kg 402.44
Ramp on Fill kg 27.27
3.01 Deformed Round Bars, Grade 40 kg 2,260.55 39.97 7.63 90,354.23 17,256.35 107,610.58
3.02 G.I. Tie Wire kg 46.00 50.00 9.00 2,300.00 414.00 2,714.00
Sub-total 110,324.58
4.00 Formworks
Column sq.m 60.79
Long-Span Roofing, Corrugated, Pre-Painted, m 197.60 360.00 72.00 71,136.00 14,227.20 85,363.20
8.16 1220mm x 0.4mm thk
Ridge Roll, Pre-Painted, Ordinary, 0.610m x pc 9.00 544.00 4,896.00 0.00 4,896.00
8.17 2.440m x 0.4mm thk
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 8,415.22
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
0.1mm Thick Concrete Ledge cu.m 0.14
2.01 Portland Cement bag 2.00 223.00 42.50 446.00 85.00 531.00
2.05 Crushed Gravel 1" cu.m 0.25 552.00 150.00 138.00 37.50 175.50
2.03 Washed Sand cu.m 0.25 435.00 150.00 108.75 37.50 146.25
Sub-total 111,926.50
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 738.02
Beam kg 740.52
Slab on Grade kg 402.44
Ramp on Fill kg 27.27
0.1mm Thick Concrete Ledge kg 13.11
3.01 Deformed Round Bars, Grade 40 kg 2,273.66 39.97 7.63 90,878.17 17,356.42 108,234.59
3.02 G.I. Tie Wire kg 46.00 50.00 9.00 2,300.00 414.00 2,714.00
Sub-total 110,948.59
4.00 Formworks
Column sq.m 60.79
4.01 Coco Lumber bd.ft 310.20 14.00 4.20 4,342.80 1,302.84 5,645.64
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 11.00 288.92 90.00 3,178.08 990.00 4,168.08
4.04 CWN, Assorted kg 5.00 60.00 18.00 300.00 90.00 390.00
Beams sq.m 71.70
4.01 Coco Lumber bd.ft 365.70 14.00 4.20 5,119.80 1,535.94 6,655.74
4.02 Plywood Ordinary, 1/4" x 4' x 8' pc 13.00 288.92 90.00 3,755.92 1,170.00 4,925.92
4.04 CWN, Assorted kg 6.00 60.00 18.00 360.00 108.00 468.00
Sub-total 22,253.38
5.00 Masonry Works
Masonry Wall sq.m 170.18
5.05 CHB 6" thk pc 2,128.00 12.00 3.00 25,536.00 6,384.00 31,920.00
5.02 Portland Cement bag 86.00 223.00 51.00 19,178.00 4,386.00 23,564.00
5.03 Washed Sand cu.m 8.00 435.00 180.00 3,480.00 1,440.00 4,920.00
5.06 10mm x 6m RSB kg 226.00 39.97 9.03 9,033.22 2,040.78 11,074.00
5.07 G.I. Tie Wire kg 5.00 50.00 15.00 250.00 75.00 325.00
5.08 Concrete Louver Blocks pc 16.00 30.00 9.00 480.00 144.00 624.00
Plastering sq.m 340.35
5.02 Portland Cement bag 113.00 223.00 51.00 25,199.00 5,763.00 30,962.00
5.03 Washed Sand cu.m 12.00 435.00 180.00 5,220.00 2,160.00 7,380.00
Sub-total 110,769.00
6.00 Doors and Windows
D-1, Panel Door 0.90m x 2.10m on 150mm set 4.00 5,917.50 887.63 23,670.00 3,550.50 27,220.50
6.03 Wooden Jamb complete with Accessories
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Three Classroom
Sub-total 12,235.61
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 229.50 0.00 20.00 0.00 4,590.00 4,590.00
1.02 Structural Excavation cu.m 39.22 0.00 200.00 0.00 7,843.20 7,843.20
1.03 Backfilling and Compaction cu.m 26.95 0.00 45.00 0.00 1,212.57 1,212.57
1.04 Gravel Bedding G-1 cu.m 13.93 552.00 180.00 7,688.81 2,507.22 10,196.03
1.06 Select Fill cu.m 22.95 150.00 45.00 3,442.50 1,032.75 4,475.25
1.05 Soil Poisoning sq.m 252.45 15.00 4.50 3,786.75 1,136.03 4,922.78
Sub-total 33,239.82
2.00 Concreting Works
Column Footing cu.m 4.07
2.01 Portland Cement bag 37.00 223.00 42.50 8,251.00 1,572.50 9,823.50
2.05 Crushed Gravel 1" cu.m 4.25 552.00 150.00 2,346.00 637.50 2,983.50
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Wall Footing cu.m 8.20
2.01 Portland Cement bag 74.00 223.00 42.50 16,502.00 3,145.00 19,647.00
2.05 Crushed Gravel 1" cu.m 8.25 552.00 150.00 4,554.00 1,237.50 5,791.50
2.03 Washed Sand cu.m 4.25 435.00 150.00 1,848.75 637.50 2,486.25
Column cu.m 5.61
2.01 Portland Cement bag 51.00 223.00 42.50 11,373.00 2,167.50 13,540.50
2.02 Crushed Gravel 3/4" cu.m 5.75 655.00 175.00 3,766.25 1,006.25 4,772.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Beams cu.m 6.27
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.02 Crushed Gravel 3/4" cu.m 6.50 655.00 175.00 4,257.50 1,137.50 5,395.00
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Slab on Grade cu.m 22.95
2.01 Portland Cement bag 207.00 223.00 42.50 46,161.00 8,797.50 54,958.50
2.05 Crushed Gravel 1" cu.m 23.00 552.00 150.00 12,696.00 3,450.00 16,146.00
2.03 Washed Sand cu.m 11.50 435.00 150.00 5,002.50 1,725.00 6,727.50
Ramp on Fill cu.m 0.65
2.01 Portland Cement bag 6.00 223.00 42.50 1,338.00 255.00 1,593.00
2.05 Crushed Gravel 1" cu.m 0.75 552.00 150.00 414.00 112.50 526.50
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 164,789.75
3.00 Rebar Works
Footing kg 298.75
Wall Footing kg 238.58
Column kg 1,183.19
Beam kg 1,049.69
Slab on Grade kg 603.66
Ramp on Fill kg 27.27
3.01 Deformed Round Bars, Grade 40 kg 3,401.14 39.97 7.63 135,943.44 25,963.23 161,906.67
3.02 G.I. Tie Wire kg 69.00 50.00 9.00 3,450.00 621.00 4,071.00
Sub-total 165,977.67
4.00 Formworks
OLIVER R. HERNANDEZ
Sub-total 11,923.63
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 26.81 0.00 200.00 0.00 5,361.60 5,361.60
1.03 Backfilling and Compaction cu.m 18.10 0.00 45.00 0.00 814.41 814.41
1.04 Gravel Bedding G-1 cu.m 9.39 552.00 180.00 5,184.38 1,690.56 6,874.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,376.30
2.00 Concreting Works
Column Footing cu.m 2.46
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.50 552.00 150.00 1,380.00 375.00 1,755.00
2.03 Washed Sand cu.m 1.25 435.00 150.00 543.75 187.50 731.25
Wall Footing cu.m 6.25
2.01 Portland Cement bag 57.00 223.00 42.50 12,711.00 2,422.50 15,133.50
2.05 Crushed Gravel 1" cu.m 6.25 552.00 150.00 3,450.00 937.50 4,387.50
2.03 Washed Sand cu.m 3.25 435.00 150.00 1,413.75 487.50 1,901.25
Column cu.m 3.97
2.01 Portland Cement bag 36.00 223.00 42.50 8,028.00 1,530.00 9,558.00
2.02 Crushed Gravel 3/4" cu.m 4.00 655.00 175.00 2,620.00 700.00 3,320.00
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Beams cu.m 3.68
2.01 Portland Cement bag 34.00 223.00 42.50 7,582.00 1,445.00 9,027.00
2.02 Crushed Gravel 3/4" cu.m 3.75 655.00 175.00 2,456.25 656.25 3,112.50
2.03 Washed Sand cu.m 2.00 435.00 150.00 870.00 300.00 1,170.00
Slab on Grade cu.m 15.30
2.01 Portland Cement bag 138.00 223.00 42.50 30,774.00 5,865.00 36,639.00
2.05 Crushed Gravel 1" cu.m 15.50 552.00 150.00 8,556.00 2,325.00 10,881.00
2.03 Washed Sand cu.m 7.75 435.00 150.00 3,371.25 1,162.50 4,533.75
Ramp on Fill cu.m 1.40
2.01 Portland Cement bag 13.00 223.00 42.50 2,899.00 552.50 3,451.50
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Counter cu.m 0.79
2.01 Portland Cement bag 8.00 223.00 42.50 1,784.00 340.00 2,124.00
2.05 Crushed Gravel 1" cu.m 1.00 552.00 150.00 552.00 150.00 702.00
2.03 Washed Sand cu.m 0.50 435.00 150.00 217.50 75.00 292.50
Sub-total 117,488.00
3.00 Rebar Works
Footing kg 174.32
Wall Footing kg 183.60
Column kg 762.53
Beam kg 618.35
Slab on Grade kg 402.44
Ramp on Fill kg 59.09
9.50 Folding Door, Full Louver 450 x 1830mm set 16.00 1,435.00 430.50 22,960.00 6,888.00 29,848.00
Sub-total 138,486.38
7.00 Steel Works
7.07 LC 150 x 65 x 20 x 2.0mm kg 685.44 41.19 12.48 28,233.27 8,552.23 36,785.50
7.05 LC 100 x 50 x 15 x 2.0mm kg 1,007.68 41.19 12.48 41,506.34 12,572.81 54,079.15
7.11 L 25 x 25 x 3mm kg 130.82 41.60 8.73 5,441.95 1,142.18 6,584.13
7.17 Flat Bar 1" x 1/4" kg 35.40 41.60 8.73 1,472.64 309.08 1,781.72
7.18 Plain Round Bar 10mmØ x 6m pc 12.00 107.00 32.10 1,284.00 385.20 1,669.20
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 0.50 9,300.00 2,790.00 4,650.00 1,395.00 6,045.00
Anchor Bolt with Nuts and Washer, 16mmØ x pc 32.00 45.00 13.50 1,440.00 432.00 1,872.00
7.33 50mm x 300mm
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
Sub-total 12,471.10
1.00 Earthworks
1.01 Clearing and Grubbing sq.m 153.00 0.00 20.00 0.00 3,060.00 3,060.00
1.02 Structural Excavation cu.m 25.80 0.00 200.00 0.00 5,160.00 5,160.00
1.03 Backfilling and Compaction cu.m 17.58 0.00 45.00 0.00 790.88 790.88
1.04 Gravel Bedding G-1 cu.m 9.30 552.00 180.00 5,130.84 1,673.10 6,803.94
1.06 Select Fill cu.m 15.30 150.00 45.00 2,295.00 688.50 2,983.50
1.05 Soil Poisoning sq.m 168.30 15.00 4.50 2,524.50 757.35 3,281.85
Sub-total 22,080.17
2.00 Concreting Works
Column Footing cu.m 2.53
2.01 Portland Cement bag 23.00 223.00 42.50 5,129.00 977.50 6,106.50
2.05 Crushed Gravel 1" cu.m 2.75 552.00 150.00 1,518.00 412.50 1,930.50
2.03 Washed Sand cu.m 1.50 435.00 150.00 652.50 225.00 877.50
Wall Footing cu.m 5.70
2.01 Portland Cement bag 52.00 223.00 42.50 11,596.00 2,210.00 13,806.00
2.05 Crushed Gravel 1" cu.m 5.75 552.00 150.00 3,174.00 862.50 4,036.50
2.03 Washed Sand cu.m 3.00 435.00 150.00 1,305.00 450.00 1,755.00
Column cu.m 3.47
2.01 Portland Cement bag 32.00 223.00 42.50 7,136.00 1,360.00 8,496.00
2.02 Crushed Gravel 3/4" cu.m 3.50 655.00 175.00 2,292.50 612.50 2,905.00
2.03 Washed Sand cu.m 1.75 435.00 150.00 761.25 262.50 1,023.75
Beams cu.m 4.43
2.01 Portland Cement bag 40.00 223.00 42.50 8,920.00 1,700.00 10,620.00
2.02 Crushed Gravel 3/4" cu.m 4.50 655.00 175.00 2,947.50 787.50 3,735.00
2.03 Washed Sand cu.m 2.25 435.00 150.00 978.75 337.50 1,316.25
Slab on Grade cu.m 17.28
2.01 Portland Cement bag 156.00 223.00 42.50 34,788.00 6,630.00 41,418.00
2.05 Crushed Gravel 1" cu.m 17.50 552.00 150.00 9,660.00 2,625.00 12,285.00
2.03 Washed Sand cu.m 8.75 435.00 150.00 3,806.25 1,312.50 5,118.75
Ramp on Fill cu.m 1.40
2.01 Portland Cement bag 13.00 223.00 42.50 2,899.00 552.50 3,451.50
2.05 Crushed Gravel 1" cu.m 1.50 552.00 150.00 828.00 225.00 1,053.00
2.03 Washed Sand cu.m 0.75 435.00 150.00 326.25 112.50 438.75
Counter and Working Tables cu.m 21.14
2.01 Portland Cement bag 191.00 223.00 42.50 42,593.00 8,117.50 50,710.50
2.05 Crushed Gravel 1" cu.m 21.25 552.00 150.00 11,730.00 3,187.50 14,917.50
2.03 Washed Sand cu.m 10.75 435.00 150.00 4,676.25 1,612.50 6,288.75
Sub-total 192,289.75
3.00 Rebar Works
Footing kg 185.06
Wall Footing kg 167.24
Column kg 746.20
Beam kg 740.52
Ramp on Fill kg 29.54
Slab on Grade kg 454.52
Counter and Working Tables kg 556.15
D-1, Panel Door 0.90m x 2.10m on 150mm set 3.00 5,917.50 887.63 17,752.50 2,662.88 20,415.38
6.03 Wooden Jamb complete with Accessories
D-2 Flush Door 0.90m x 2.10m on 150mm set 1.00 3,967.50 529.13 3,967.50 529.13 4,496.63
6.04 Wooden Jamb complete with Accessories
D-3 Flush Door 0.70m x 2.10m on 150mm set 3.00 3,857.50 517.13 11,572.50 1,551.38 13,123.88
6.05 Wooden Jamb complete with Accessories
OLIVER R. HERNANDEZ
Project Engineer, PFSED Area Supervisor, PFSED Chief, PFSED
OLIVER R. HERNANDEZ
Area Supervisor, PFSED Cost and Assessment Supervisor Chief, PFSED
One Classroom
Prepared: Noted:
Page 52 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
6.10 Panel Door 0.90m x 2.10m pc 4,602.80 - e
e
6.11 Panel Door 0.80m x 2.10m pc 3,400.00 - l
m
6.12 Panel Door 0.70m x 2.10m pc 3,100.00 -
a
6.13 Panel Door 0.60m x 2.10m pc 3,100.00 - n
/
6.14 Flush Door 0.90m x 2.10m pc 2,088.00 - T
6.15 Flush Door 0.80m x 2.10m pc 1,740.00 - i
n
6.16 Flush Door 0.70m x 2.10m pc 1,690.00 - s
6.17 Flush Door 0.60m x 2.10m pc 1,640.00 - m
i
6.18 Steel Door 0.70m x 2.10m pc 4,375.00 - t
h
6.19 Steel Door 0.80m x 2.10m pc 4,500.00 -
6.20 Steel Door 0.90m x 2.10m pc 4,600.00 -
6.21 PVC Door 0.60m x 2.10m pc 1,550.00 -
6.22 Door Jamb 45mm x 100mm set 1,050.00 -
6.23 Door Jamb 45mm x 125mm set 1,450.00 -
6.24 Door Jamb 45mm x 150mm set 1,550.00 -
6.25 Steel Encased Clear Glass Window with Grilles sq.ft 125.00 56.25
6.26 Security Grilles sq.ft 90.00 40.50
6.27 Entrance, Lockset Standard set 467.50 -
6.28 Entrance, Handleset set 7,760.00 -
6.29 Entrance, Cylindrical Lockset set 1,640.00 -
6.30 Entrance, Lever Lockset set 2,820.00 -
6.31 Bathroom, Lockset Keyless set 1,080.00 -
6.32 Hinges, Standard 3-1/2" x 3-1/2" pa 75.00 -
6.33 Hinges, Ball Bearing 3-1/2" x 3-1/2" pa 680.00 -
D-1, Flush Door 0.90m x 2.10m on 100mm Wooden Jamb complete with
6.34 set 3,467.50 302.75
###
Accessories
W - 1, ( 2.6 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.35 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 set 5,500.00 550.00
###
mm Wooden Jamb complete with Accessories
W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.36 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 100 set 2,750.00 275.00
###
mm Wooden Jamb complete with Accessories
W - 1, ( 3.6 x 1.6 m) Jalousie Window with Clear Glass Blades on
6.37 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 9,250.00 1,387.50
###
mm Wooden Jamb complete with Accessories
W - 2, ( 3.6 x 1.2 m) Jalousie Window with Clear Glass Blades on
6.38 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 6,950.00 1,042.50
###
mm Wooden Jamb complete with Accessories
Page 53 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
e
W - 3, ( 1.3 x 1.8 m) Jalousie Window with Clear Glass Blades on
e
6.43 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,744.00 561.60
###
l
mm Wooden Jamb complete with Accessories
m
W - 4, ( 1.2 x 0.7 m) Jalousie Window with Clear Glass Blades on a
6.44 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 1,344.00 201.60
### n
mm Wooden Jamb complete with Accessories /
T
W - 2, ( 1.3 x 1.6 m) Jalousie Window with Clear Glass Blades on i
6.45 Standard Aluminum Casing and Fixed Clear Glass Transom on 50 x 150 set 3,350.00 502.50
### n
mm Wooden Jamb complete with Accessories s
m
D-3 Flush Door 0.60m x 2.10m on 150mm Wooden Jamb complete with i
6.46 set 3,657.50 487.13
Accessories t
D-1, (0.90 x 2.10) Steel Door and Jamb with Fixed Glass Transom h
6.47 set 6,000.00 1,800.00
complete with Accessories
D-2, (0.80 x 2.10) Steel Door and Jamb with Fixed Glass Transom
6.48 set 5,800.00 1,740.00
complete with Accessories
D-3, (0.90 x 2.10) Steel Door and Jamb with Steel Grilles Transom and
6.49 set 6,500.00 1,800.00
Stainless Kick Plate complete with Accessories
D-4, (0.70 x 2.10) Steel Door and Jamb with Fixed Glass Transom
6.50 set 5,500.00 1,650.00
complete with Accessories
W - 4, ( 0.6 x 0.6 m) Steel Awning Window with Grilles with 1/4 thk Clear
6.54 set 750.00 262.50
###
Glass Panes complete with Accessories
7.00 Steel Works - -
7.01 C 6 x 10.5 kg 54.73 19.61
7.02 C 6 x 8.2 kg 54.73 19.61
7.03 LC 75 x 38 x 15 x 2.0mm kg 41.19 12.48
7.04 LC 100 x 50 x 15 x 1.5mm kg 41.19 12.48
7.05 LC 100 x 50 x 15 x 2.0mm kg 41.19 12.48
7.06 LC 100 x 50 x 15 x 3.0mm kg 41.19 12.48
7.07 LC 150 x 65 x 20 x 2.0mm kg 41.19 12.48
7.08 LC 150 x 65 x 20 x 3.0mm kg 41.19 12.48
7.09 LC 120 x 50 x 20 x 2.0mm kg 41.19 12.48
7.10 LC 120 x 50 x 20 x 3.0mm kg 41.19 12.48
7.11 L 25 x 25 x 3mm kg 41.60 8.73
7.12 L 30 x 30 x 6mm kg 41.60 8.73
7.13 L 50 x 50 x 5mm kg 41.60 8.73
7.14 L 50 x 50 x 6mm kg 41.60 8.73
7.15 Flat Bar 1" x 1/8" kg 41.60 8.73
7.16 Flat Bar 1" x 3/16" kg 41.60 8.73
7.17 Flat Bar 1" x 1/4" kg 41.60 8.73
7.18 Plain Round Bar 10mmØ x 6m pc 107.00 32.10
7.19 Plain Round Bar 12mmØ x 6m pc 185.00 55.50
7.20 Plain Round Bar 16mmØ x 6m pc 286.00 85.80
7.21 Square Bar 12mm□ x 6m pc 141.00 42.30
7.22 Square Bar 16mm□ x 6m pc 218.00 65.40
7.23 Square Bar 19mm□ x 6m pc 412.00 123.60
Page 54 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
7.24 Steel Plate 1.20m x 2.40m x 12mm pc 10,500.00 3,150.00 e
e
7.25 Steel Plate 1.20m x 2.40m x 10mm pc 9,300.00 2,790.00 l
m
7.26 Steel Plate 1.20m x 2.40m x 9mm pc 8,635.00 2,590.50
a
7.27 Steel Plate 1.20m x 2.40m x 6mm pc 5,390.00 1,617.00 n
/
7.28 Tubular 50mm x 150mm x 2.0mm pc 2,640.00 792.00 T
7.29 Tubular 50mm x 100mm x 1.5mm pc 1,085.00 325.50 i
n
7.30 Turn Buckle 12 mmØ pc 60.00 18.00 s
7.31 Turn Buckle 16 mmØ pc 80.00 24.00 m
i
7.32 Anchor Bolt with Nuts and Washer, 20mmØ x 50mm x 300mm pc 65.00 19.50 t
h
7.33 Anchor Bolt with Nuts and Washer, 16mmØ x 50mm x 300mm pc 45.00 13.50
7.34 Anchor Bolt with Nuts and Washer, 12mmØ x 50mm x 300mm pc 27.00 8.10
7.35 Anchor Bolt with Nuts and Washer, 10mmØ x 50mm x 200mm pc 12.00 3.60
7.36 B.I. Pipe 100mmØ Sch.40 pc 2,262.00 678.60
7.37 B.I. Pipe 75mmØ Sch.40 pc 1,658.00 497.40
7.38 B.I. Pipe 50mmØ Sch.40 pc 880.00 264.00
7.39 B.I. Pipe 38mmØ Sch.40 pc 632.00 189.60
7.40 B.I. Pipe 32mmØ Sch.40 pc 537.00 161.10
7.41 B.I. Pipe 50mmØ Sch.20 pc 691.00 207.30
7.42 B.I. Pipe 38mmØ Sch.20 pc 499.00 149.70
7.43 B.I. Pipe 32mmØ Sch.20 pc 435.00 130.50
7.44 G.I. Pipe 1-1/4"Ø Sch.40 pc 960.56 338.00
7.45 G.I. Pipe 2"Ø Sch.40 pc 1,489.38 502.00
7.46 Welding Rod kg 67.00 20.10
8.00 Roofing Works - -
8.01 Removal of Roofing Sheets sq.m - 7.50
8.02 Removal of Ridge Roll pc - 15.00
8.03 Removal of Flashing pc - 15.00
8.04 Removal of Gutter pc - 15.00
8.05 Removal of Fascia Board pc - 23.50
8.06 Corrugated G.I. Sheet Ga.26, 36" x 8' pc 218.83 43.77
8.07 Corrugated G.I. Sheet Ga.26, 36" x 9' pc 246.54 49.31
8.08 Corrugated G.I. Sheet Ga.26, 36" x 10' pc 273.93 54.79
8.09 Corrugated G.I. Sheet Ga.26, 36" x 12' pc 327.14 65.43
8.10 Plain G.I. Sheet Ga.26, 4' x 8' pc 400.00 80.00
8.11 Plain G.I. Sheet Ga.26, 3' x 8' pc 228.50 45.70
8.12 Gutter Ga.26, 24" x 8' pc 150.00 30.00
8.13 Flashing Ga.26, 24"x 8' pc 302.50 60.50
8.14 Ridge Roll Ga.26, 24"x 8' pc 302.50 60.50
8.15 Long-Span Roofing, Rib-Type, Pre-Painted, 1220mm x 0.4mm thk m 360.00 72.00
8.16 Long-Span Roofing, Corrugated, Pre-Painted, 1220mm x 0.4mm thk m 360.00 72.00
8.17 Ridge Roll, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.18 Ridge Roll, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.19 Flashing, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.20 Flashing, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.21 Flashing, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk pc 767.00 153.40
8.22 Gutter, Pre-Painted, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 544.00 108.80
8.23 Gutter, Pre-Painted, Ordinary, 0.915m x 2.440m x 0.4mm thk pc 864.00 172.80
8.24 Gutter, Stainless, Ordinary, 0.610m x 2.440m x 0.4mm thk pc 767.00 153.40
Page 55 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
8.25 Gutter, Pre-Painted, Spanish, 0.610m x 2.440m x 0.4mm thk m 68.00 13.60 e
e
8.26 Polyethylene Foam with One Side Aluminum 10mm thk m 105.00 21.00 l
m
8.27 Polyethylene Foam with One Side Aluminum 15mm thk m 142.00 28.40
a
8.28 Polyethylene Foam with One Side Aluminum 20mm thk m 179.50 35.90 n
/
8.29 Polyethylene Foam with One Side Aluminum 25mm thk m 216.50 43.30 T
8.30 Polyethylene Foam with Two Side Aluminum 5mm thk m 103.50 20.70 i
n
8.31 Polyethylene Foam with Two Side Aluminum 10mm thk m 141.00 28.20 s
8.32 Polyethylene Foam with Two Side Aluminum 15mm thk m 178.00 35.60 m
i
8.33 Polyethylene Foam with Two Side Aluminum 20mm thk m 215.00 43.00 t
h
8.34 Polyethylene Foam with Two Side Aluminum 25mm thk m 252.00 50.40
8.35 Teckscrew 2-1/2" pc 1.25 0.25
8.36 Roof Sealant L 239.80 47.96
8.37 Blind Rivets pc 0.50 0.10
8.38 Umbrella Nails kg 60.00 12.00
9.00 Carpentry Works - -
9.01 Removal of Ceiling sq.m - 8.00
9.02 Plywood, Ordinary 1/4" x 4' x 8' pc 288.92 81.75
9.03 Plywood, Ordinary 3/8" x 4' x 8' pc 520.00 156.00
9.04 Plywood, Ordinary 1/2" x 4' x 8' pc 490.33 144.00
9.05 Plywood, Ordinary 3/4" x 4' x 8' pc 850.00 255.00
9.06 Plywood, Marine 1/4" x 4' x 8' pc 340.00 108.00
9.07 Plywood, Marine 1/2" x 4' x 8' pc 650.00 195.00
9.08 Plywood, Marine 3/4" x 4' x 8' pc 1,050.00 315.00
9.09 Fiber Cement Board, 1/4" x 4' x 8' pc 540.00 162.00
9.10 Fiber Cement Board, 3/16" x 4' x 8' pc 390.00 117.00
9.11 Rough Lumber, Sun Dried, Yakal bd.ft 120.00 36.00
9.12 Rough Lumber, Sun Dried, Guijo bd.ft 120.00 36.00
9.13 Rough Lumber, Sun Dried, Tanguile bd.ft 40.00 12.65
9.14 S4S Lumber, Kiln Dried, Tanguile bd.ft 50.00 18.60
9.15 Ceiling Vent 1" x 12" x 4' with Screen pc 245.00 73.50
9.16 Fascia Board, Wooden bd.ft 36.00 10.80
9.17 Fascia Board, Fiber Cement 10" x 8' pc 279.00 83.70
9.18 Fascia Board, Fiber Cement 12" x 8' pc 325.00 97.50
9.19 Fascia Board, Fiber Cement 10" x 12' pc 352.50 105.75
9.20 Fascia Board, Fiber Cement 12" x 12' pc 405.00 121.50
9.21 Ficem Board Nails kg 90.00 27.00
9.22 Finishing Nails kg 70.00 21.00
9.23 Common Wire Nails kg 50.00 15.00
9.24 Concrete Nails kg 70.00 21.00
9.25 Removal of T&G bd.ft - 5.00
9.26 T&G 3/4" x 4" ft 20.00 6.00
9.27 T&G 3/4" x 6" ft 32.50 9.75
9.28 Wood Glue L 120.00 36.00
9.29 Acoustic Board 2' x 4' pc 320.00 96.00
9.30 Main Tee Runner 1" x 1" x 10' pc 98.85 29.66
9.31 Cross Tee 1" x 1" x 10' pc 90.00 27.00
9.32 Wall Angle 1" x 1" x 10' pc 90.00 27.00
9.33 Suspension Rod #8 kg 145.00 43.50
Page 56 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
9.34 Removal of Wooden Truss bd.ft - 4.00 e
e
9.35 Removal of Purlins bd.ft - 4.00 l
m
9.36 Removal of Partition sq.m - 8.00
a
9.37 Machine Bolts with Std. Nuts and Washers, 5/8" x 7" pc 18.00 5.40 n
/
9.38 Machine Bolts with Std. Nuts and Washers, 5/8" x 8" pc 20.00 6.00 T
9.39 Machine Bolts with Std. Nuts and Washers, 5/8" x 10" pc 25.00 7.50 i
n
9.40 Machine Bolts with Std. Nuts and Washers, 1/2" x 7" pc 12.00 3.60 s
9.41 Machine Bolts with Std. Nuts and Washers, 1/2" x 8" pc 15.00 4.50 m
i
9.42 Wood Preservative, Brown L 900.00 270.00 t
h
9.43 Lawanit, 1/4" thk pc 280.00 84.00
9.44 Concealed Hinges pc 30.00 9.00
9.45 S.S. Cabinet Handle pc 90.00 27.00
9.46 6mm thk Clear Glass sq.ft 60.00 18.00
9.47 S.S. Tube 3/4"Ø m 420.00 126.00
9.48 S.S. Flange 3/4"Ø pa 75.00 22.50
9.49 Drawer Guide, Metal 20" Full Extension set 420.00 126.00
9.50 Folding Door, Full Louver 450 x 1830mm set 1,435.00 430.50
9.51 Heavy Duty Steel Track with Roller m - 495.00
10.00 Electrical Works - -
10.01 Electrical Conduit uPVC, 15mmØ pc 50.00 15.00
10.02 Electrical Conduit uPVC, 20mmØ pc 69.75 20.93
10.03 Electrical Conduit uPVC, 32mmØ pc 137.50 41.25
10.04 Electrical Conduit uPVC, 40mmØ pc 192.50 57.75
10.05 Electrical Conduit uPVC, 50mmØ pc 214.75 64.43
10.06 RSC 20mmØ pc 112.50 33.75
10.07 RSC 25mmØ pc 175.00 52.50
10.08 RSC 32mmØ pc 339.00 101.70
10.09 RSC 38mmØ pc 430.50 129.15
10.10 30.0 mm2 THW Wire, Stranded m 126.00 54.00
10.11 3.5 mm THW Wire, Stranded
2
m 23.97 7.02
10.12 5.5 mm THW Wire, Stranded
2
m 35.86 10.14
10.13 8.0 mm2 THW Wire, Stranded m 54.98 16.38
10.14 14.0 mm THW Wire, Stranded
2
m 60.00 25.35
10.15 22.0 mm2 THW Wire, Stranded m 94.00 40.17
10.16 Junction Box, 4" x 4" G.I. pc 15.00 4.50
10.17 Utility Box, 2" x 4" G.I. pc 30.00 4.28
10.18 FL 2 x 40W Recessed Type with Luminare 24" x 48" set 2,600.00 390.00
10.19 FL 1 x 40W Recessed Type with Luminare 6" x 48" set 1,184.50 177.68
10.20 FL 2 x 40W Industrial Type set 1,200.00 126.00
10.21 FL 1 x 40W Industrial Type set 700.00 73.50
10.22 FL 1 x 20W Industrial Type set 630.00 66.00
10.23 Single Switch with Plate pc 97.68 13.46
10.24 2-Gang Switch with Plate pc 153.00 21.53
10.25 3-Gang Switch with Plate pc 208.00 29.59
10.26 3-Way Switch with Plate pc 251.00 37.65
10.27 Single C.O. with Plate pc 88.00 13.20
10.28 Duplex C.O. with Plate pc 263.80 21.00
10.29 Duplex C.O. Weatherproof pc 756.50 76.50
Page 57 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
10.30 Aircon Outlet with Plate pc 282.75 42.41 e
e
10.31 TV Terminal Outlet with Plate pc 322.50 48.38 l
m
10.32 Telephone Outlet with Plate pc 251.00 37.65
a
10.33 Ceiling Receptacle 3-1/2"Ø pc 25.00 3.75 n
/
10.34 Entrance Cap 20mm dia. pc 50.00 7.50 T
10.35 Entrance Cap 32mm dia. pc 75.00 11.25 i
n
10.36 Entrance Cap 25mm dia. pc 70.00 10.50 s
10.37 Grounding Rod, 2.4m x 16mm dia. pc 150.00 22.50 m
i
10.38 Circuit Breaker, 20A 2P set 313.00 46.95 t
h
10.39 Circuit Breaker, 30A 2P set 313.00 46.95
10.40 Circuit Breaker, 40A 2P set 441.25 66.19
10.41 Circuit Breaker, 50A 2P set 441.25 66.19
10.42 Circuit Breaker, 60A 2P set 441.25 66.19
10.43 Circuit Breaker, 100A 2P set 650.00 97.50
10.44 Circuit Breaker, 175A 2P set - -
10.45 Safety Switch 100A 2P set 2,224.75 333.71
10.46 Safety Switch 30A 2P set 603.25 90.49
10.47 Panel Box, Flush Type, 6 Branches set 1,400.00 210.00
10.48 Panel Box, Flush Type, 4 Branches set 1,202.75 180.41
10.49 Panel Box, Flush Type, 8 Branches set 1,580.00 237.00
10.50 Panel Box, Flush Type, 12 Branches set 2,530.75 379.61
10.51 Panel Box, Flush Type, 10 Branches set 1,850.00 277.50
10.52 Flourescent Tube 40W set - -
10.53 Incandescent Bulb 50W set 35.00 5.25
10.54 Vibrating Bell 8" set 1,500.00 225.00
10.55 Fire Alarm Bell, Vibrating Type set 2,000.00 300.00
10.56 Fire Alarm Station, Manual Single Action set 1,750.00 262.50
10.57 Fire Alarm Control Panel, One Zone set 5,500.00 825.00
10.58 Electrical Tape pc 37.50 5.63
10.59 Rubber Tape roll 100.00 15.00
11.00 Plumbing Works - -
11.01 uPVC Water Line 1/2"Ø pc 55.00 16.50
11.02 uPVC Water Line 3/4"Ø pc 85.00 25.50
11.03 uPVC Water Line 1"Ø pc 112.00 33.60
11.04 G.I. Pipe 1"Ø Sch.40 pc 460.00 138.00
11.05 G.I. Pipe 3/4"Ø Sch.40 pc 360.00 108.00
11.06 G.I. Pipe 1/2"Ø Sch.40 pc 260.00 78.00
11.07 G.I. Coupling, 3/8"Ø pc 11.00 3.30
11.08 G.I. Coupling, 1/2"Ø pc 10.75 3.23
11.09 G.I. Coupling, 3/4"Ø pc 14.75 4.43
11.10 G.I. Coupling, 1"Ø pc 23.75 7.13
11.11 G.I. Coupling, 1-1/2"Ø pc 35.00 10.50
11.12 G.I. Coupling, 2"Ø pc 45.00 13.50
11.13 G.I. Coupling, 3"Ø pc 150.00 45.00
11.14 G.I. Tee, 3/8"Ø pc 19.75 5.93
11.15 G.I. Tee, 1/2"Ø pc 17.75 5.33
11.16 G.I. Tee, 3/4"Ø pc 21.25 6.38
11.17 G.I. Tee, 1"Ø pc 42.75 12.83
Page 58 of 61
e
r
/
database.xls M
a
Unit Cost of Labor & Materials s
o
n
Material Labor /
Item
Item Description Unit S
No. Unit Cost t
11.18 G.I. Tee, 3/8" x 1/2"Ø pc 23.75 7.13 e
e
11.19 G.I. Tee, 3/4" x 1/2"Ø pc 41.25 12.38 l
m
11.20 G.I. Tee, 1" x 1/2"Ø pc 41.25 12.38
a
11.21 G.I. Elbow 90o x 1/2"Ø pc 11.00 3.30 n
/
11.22 G.I. Elbow 90 x 3/4"Ø
o
pc 20.75 6.23 T
11.23 G.I. Elbow 90o x 1"Ø pc 33.75 10.13 i
n
11.24 G.I. Coupling Reducer, 1/2" x 3/4"Ø pc 40.00 12.00 s
11.25 G.I. Coupling Reducer, 1-1/2" x 1/2"Ø pc 40.00 12.00 m
i
11.26 G.I. Coupling Reducer, 2" x 1"Ø pc 58.25 17.48 t
h
11.27 G.I. Plug, 1/2"Ø pc 9.75 2.93
11.28 G.I. Plug, 3/4"Ø pc 12.50 3.75
11.29 G.I. Plug, 1"Ø pc 20.50 6.15
11.30 G.I. Plug, 1-1/2"Ø pc 30.75 9.23
11.31 G.I. Plug, 2"Ø pc 42.50 12.75
11.32 S.S. Elbow 90o x 1/2"Ø pc 90.00 27.00
11.33 S.S. Elbow 90 x 3/4"Ø
o
pc 146.00 43.80
11.34 S.S. Elbow 90o x 1"Ø pc 230.00 69.00
11.35 S.S. Coupling, 3/4"Ø pc 130.00 39.00
11.36 S.S. Coupling, 1"Ø pc 200.00 60.00
11.37 S.S. Tee, 1/2"Ø pc 130.00 39.00
11.38 S.S. Tee, 3/4"Ø pc 200.00 60.00
11.39 S.S. Tee, 1"Ø pc 330.00 99.00
11.40 S.S. Union Patente, 1/2"Ø pc 300.00 90.00
11.41 S.S. Union Patente, 3/4"Ø pc 400.00 120.00
Page 59 of 61
One Classroom
I. DIRECT COST
II. INDIRECT COST 19% of (I)
III. TAX 12% of (I+II)
IV. TOTAL CONSTRUCTION COST (I+II+III)
V. ENGINEERING OVERHEAD 1% of (IV)
VI. TOTAL PROJECT COST (IV+V)
40041.25 12339.22
Prepared by: Noted:
60 of 61
One Classroom
X 3.45 X 2.15M
GRAND TOTAL
523.80
523.80
160.00
2,500.00
562.50
732.00
3,954.50
12,744.00
3,861.00
1,608.75
18,213.75
18,556.99
472.00
19,028.99
6,246.24
4,547.00
390.00
11,183.24
52,904.28
10,051.81
7,554.73
70,510.82
705.11
Php71,215.93
Php72,000.00
61 of 61