Build-Up Rate Calculation For 1M3 of Selected Concrete Grade Using Concrete Mixer
Build-Up Rate Calculation For 1M3 of Selected Concrete Grade Using Concrete Mixer
Item Rate
Cement (1440kg/ m3) RM 18/ 50 kg
Fine aggregate RM 87.40/ m3
Coarse aggregate RM 73.60/ m3
Rental rate of concrete mixer machine RM 63.33/ day
(This include the 5 set of concrete mixer machine)
Productivity of concrete mixer machine 4 m3/ hour
Concrete wastage. 5%
Worker salary (8 hours working/ day) RM 45/ day
Profit. 20%
1. Material cost
a) 1 metre cubic of cement
1 m3 x (1500kg/ m3) x RM18.00/ 50 kg RM540
b) 2 metre cubic of sand
2 m3 x RM 87.40/ m3 RM174.80
c) 4 metre cubic of coarse aggregates
4 m3 x RM 73.60/ m3 RM 294.40
Total material cost for 7 meter cubic of concrete: RM
1009.20
2. Labour cost
a) Given man-hour to produce one (1) metre cubic concrete is 3 hours.
b) Labour is paid RM60.00 daily.
3. Machine cost
a) Rental rate for concrete mixer including maintenance for one (1) day costs RM61.90.
Therefore, rate for one (1) hour is RM
7.74
b) Payment for one labour in handling the concrete mixer
RM 45/ 8 hours RM 5.63
Total mix concrete rental cost and
labour cost for handling the machine is: RM 13.37
0.5 m3 concrete mix is produced in an hour.
Thus, machine cost for one (1) meter cubic concrete.
RM 13.37/ 0.5m3 RM 26.74