Professional Documents
Culture Documents
Settlement of An Existing Structure Due To
Settlement of An Existing Structure Due To
Settlement of An Existing Structure Due To
1
4/27/2020
1. Conversion works
3. Change in use of a structure
Alteration, improvement, and renewal of old
To increase the load bearing capacity of a foundation, properties may be prompted by the need to
which may be required to enable an extra storey to be
added to the existing structure or if a change of use
preserve national assets of historical
would increase the imposed loading importance.
2. Protection works
4. Addition of a basement below an existing Protection work to structure when there is a
structure construction of new building in sufficiently
close proximity to existing buildings
5. Action of tree roots
3. Remedial works
Recent modern buildings which should have
6. The original foundation is simply not strong or continued to perform satisfactorily for some
stable enough; eg, decay of wooden piles. years have often suddenly undergone
movementd and displayed structural defects
which required immediate attention.
2
4/27/2020
3
4/27/2020
11. End of new foundation must have dowel bars 1. Length of wall to be support.
and toothed to produce strength and neat
connection between new foundation. 2. Width of existing foundation.
12. DPM can be install in underpinning works if 3. Condition of existing foundation.
required.
13. All excavation works must be filling back in 4. Load imposed to the existing foundation.
stages. 5. Estimated ability length for existing
14. It is recommended that parts of excavation works/ foundation.
working area to be underpinned must not more than
6 part. 6. Soil condition under existing foundation.
15. All part/ working area with the same No. can be
excavate in one time.
4
4/27/2020
This method can be used for strip and pad 5. When new foundation has matured, jack
foundation. hydraulic will be put on the top of the new
foundation.
It’s suitable for building which increase the 6. Then, precast concrete beam will be arrange on
load bearing capacity to the building. E.g. top of the jack.
increased storey from 5 to 10 storey. 7. Fast hardening concrete is laid between the
Subsoil in new excavation level will be precast concrete beam .
compact and compress to gave a 8. Before it has finally hardened, set the jack.
predetermined loads to the soil before 9. Precast concrete beam and half hardened
underpinning works done. concrete will be jack up to the existing
foundation. All pores between concrete will be
compacted and fill with half hardened concrete
5
4/27/2020
10.When concrete have matured, jack beam and 5. Can be use in as short as 1.80m depth
concrete one more time to the new level. It is working space
extended to give a predetermined load on the
new foundation, thus pretesting the soil
beneath. 6. Existing foundation supposed to be in good
11. Underpinning material such as engineering condition to receive piles. At the end it will
bricks, concrete blocks and steel beam will be act as a pile cap to the piles.
put in the hollow space as a support to precast
concrete beam before remove jack.
7. The condition and ability of the existing
12.Remove jack, and fill the hollow space with strip foundation will determine the spacing
underpinning material such as bricks or of the pile.
concretes.
1. This method is suitable for strip and pad 1. For strip foundation, excavation works is
foundation. done as per continuous underpinning.
Excavate bay by bay with 1.80m depth
2. Suitable for subsoil with deep bearing capacity working space.
which is not practical to use traditional
underpinning. 2. For pad foundation, excavation is done
under existing foundation.
3. Using jack in underpinning works can avoid deep 3. Hydraulic jack will be use to jacked precast
excavation. concrete pile into the suitable subsoil.
4. Short Precast concrete pile with pointed
4. No vibration and noise in using jack which will steel toe , size of 300x300x600mm will be
not disturb nearest building or environment.
jack as a first section (initial pile).
6
4/27/2020
7
4/27/2020
5. Excavate to suitable depth and arrange Needle and pile is use if the wall to be
reinforcement in the excavation pit. underpinned has a weak foundation that is
6. lastly, pour concrete to the pit and use a considered unsuitable for spanning over the
vibrator to release the air. heads of jack piles.
7. Steel casing will be bring out, one by one.
8. The best bored pile is the pile with toothing This method uses pairs of jacks or usually
around . It helps pile to bond strongly and
neatly with soil. bored piles in conjunction with an in-situ
reinforced concrete beam or needle place
9. It is better to make the lower part of the
bore pile bigger than usual to support the above the existing foundation.
pile.
8
4/27/2020
9
4/27/2020
This method is only suitable for strip 5. Removed formwork after concrete matured.
foundation. 6. Do final pinning with mortar ratio 1:3 where
It’s enable walls to be underpinned in necessary.
continuous runs without the use of needles
or raking shoring.
The procedure is to cut away portions of
brickwork, above the existing foundation to
enable precast concrete stool to be
inserted and pinned.
10