Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

CBDG Design Guide

Prestressed Concrete Design


When prestressing was first introduced into bridgeworks in the 1930’s it revolutionised concrete bridges. Prestressing made
longer spans and slender decks possible. It is used during the construction and erection of the bridge as well as in the
 permanent structure,
structure, increasing the load carrying
carrying capacity and durability of the concrete.
concrete.
Today, prestressed concrete is used for simple supported spans a few meters long to cable-stayed bridges with spans of 500m.
It has become the material of choice for medium and long-span bridges and viaducts around the world.
The following sections describe the features of prestressed concrete bridges. The advantages and disadvantages are
highlighted, and key design issues discussed while the list of references includes the essential reading for any designer of
 prestressed concrete
concrete bridges.

Introduction
Prestressed concrete is different from ordinary (non-prestressed) reinforced concrete because the tendons apply loads to the
concrete as a result of their prestress force, whilst in reinforced concrete the stresses in the reinforcement result from the loads
applied to the structure. A proportion of the external loads is therefore resisted by applying a load in the opposite sense through
the prestressing whilst the balance has to be resisted by ordinary reinforcement.
Prestressing tendons may be internal, i.e. within the concrete either bonded to the concrete or unbonded, or external, i.e.
outside the concrete but (generally) inside the envelope of the member, see Fig. 1. It i s possible for external tendons to be
outside the concrete envelope; as their eccentricity to the centroid of the concrete section increases, the section behaves more
as an extradosed cable-stayed structure than a prestressed concrete member and different design rules are appropriate.

Prestressed members
members can be either pretensioned, i.e. the tendons are stressed before the concrete is cast around them and the
force transferred to the concrete when it has obtained sufficient strength, or post-tensioned, i.e. sheathing is cast into the
concrete to form ducts through which the tendons are threaded and then stressed after the concrete has gained sufficient
strength. Table 1 compares the advantages and disadvantages of pre- and post-tensioning.

Prestressed Concrete Design Page 1


CBDG Design Guide

Precast members will generally be pretensioned with tendons bonded to the concrete, or used in segmental construction where
members are formed from precast segments, which are subsequently stressed together. Precast segmental structures in the UK
have to use external tendons because of doubt s over the efficacy of the duct joints between segments. In situ members will be
 post-tensioned with either bonded or unbonded tendons. Table 2 lists factors affecting the choice of bonded or unbonded
tendons.
When a concrete member is prestressed it will deflect and shorten. If the tendon profile is such that th e deflected shape of the
isolated member is compatible with the restraints acting on the member, the profile is said to be concordant. This will always
 be the case for a statically determinate member. However, tendon profiles in statically indeterminate members will not
generally be concordant.

Table 1 Comparison of pre- and post-tensioning


Type of  Ad van tag es Dis adv ant ages
construction

Pretensioned no need for anchorages heavy stressing bed required


tendons protected by concrete without the more difficult to incorporate deflected
need for grouting or other protection tendons
prestress is generally better distributed in
transmission zones

Post-tensioned no external stressing bed required tendons require a protective system


more flexibility in tendon layout and profile large concentrated forces in end blocks
draped tendons can be used easily

When the tendon profile is concordant, the only forces induced at any point in the member by the action of prestressing are an
axial compression equal to the prestressing force and a moment equal to the product of the prestressing force and its
eccentricity relative to the neutral axis of the member. These are the primary prestressing forces.

Table 2 Comparison o f bonded and unbonded const ruction


Type of  Ad van tag es Dis adv ant ages
construction

Bonded tendons are more effective at the ultimate tendons cannot be inspected or replaced
limit state tendons cannot be re-stressed once grouted
does not depend on the anchorage after
grouting
localises the effect of damage

Unbonded tendons can be removed for inspection and less efficient at ultimate limit state
are replaceable if corroded relies on the integrity of the anchorages and
reduced friction losses deviators
generally faster construction effects of any damage are more widespread
tendons can be re-stressed less efficient in controlling cracking
thinner webs

When the tendon profile is non-concordant, additional forces and moments will be induced in the member during prestressing
 by the restraints acting on it. These are known as the secondary or parasitic effects.
Other common nomenclature associated with prestressed concrete is defined in Fig. 2.

Prestressed Concrete Design Page 2


CBDG Design Guide

Concrete is stronger in compression than in tension. Prestress is introduced to pre-compress the areas of concrete, which would
otherwise be in tension under service loads. The concrete section is therefore stronger and behaves more as a homogeneous
section, allowing elastic methods of analysis to be used, although the concrete compressive stresses can be high. When the
tendons are bonded to the concrete, their high ultimate strength can be mobilised, which generally means that the ultimate
flexural capacity of a prestressed concrete member is much greater than the applied ultimate design moment. Therefore,
limiting the maximum compressive stresses and crack widths under service loads is generally critical in the d esign of
 prestressed concrete members, although this may not be the case for members with unbonded tendons or members with bonded
tendons and large allowable crack widths. Therefore, flexural design is normally carried out at the serviceability limit state and
then checked at the ultimate limit state. Shear design is carried out at the ultimate limit state.
The prestressing force applied to the concrete immediately after tensioning and anchoring (post-tensioning) or after transfer
(pretensioning) will be less than the jacking load due to one or more of the following:
• elastic deformation of the concrete;
• losses due to friction, and
• wedge slip in the anchorages.
The value of the prestressing force will continue to reduce with time due to:
• relaxation of prestressing steel;
• creep of the concrete
• shrinkage of the concrete.
It is normal to check the flexural stresses in a prestressed concrete member both when the prestress force is initially transferred
to the concrete (at transfer), taking account of the initial losses, and in service, after all losses have occurred.
Prestress can be considered as a load or as a resistance. At the serviceability limit state, it i s normally considered as a load
whilst, at the limit state, it is considered as a combination of a load and a resistance.
When considered as a load, the effects of prestress can be determined by analysing the structure under a system of equivalent
loads representing the forces from the prestressing tendons acting on the concrete. Such an analysis automatically takes
account of both primary and secondary effects.
When prestress has been considered as a load, the contribution of prestressing tendons to the resistance of a section is limited
to their additional strength beyond prestressing. This can be calculated by assuming that the origin of the stress-strain
relationship of the tendons is displaced by the effects of prestressing.
For bonded tendons, this is illustrated in Fig. 3. The o rigin of the stress-strain relationship is taken as being at point A,
corresponding to a prestress force, Pt, and the contribution of the tendons to the resistance of the section is ∆f  pA p. When the
whole of the prestress is considered as a resistance, the origin is taken as point B.

Prestressed Concrete Design Page 3


CBDG Design Guide

For unbonded and external tendons, the additional strain in the tendons, ∆ε p, is determined taking into account the
deformations of the concrete member

Pt =  prestressing force at time t


E p = Young's Modulus of tendons
A p = area of tendons
ε p0 = the mean strain in the tendons at the time they are bonded to the concrete, (i.e. the initial strain in the tendon,
allowing only for losses due to friction and draw, + ∆ε p0)
∆ε p0 = 0, for pretensioned members;
= the strain in the concrete due to stressing the tendon (or to stressing the first tendon when a number of tendons are
stressed successively), for post-tensioned members
∆ε p = the additional strain in the tendons (i.e. the tensile strain in the concrete at the centroid of the tendons).
∆f 
 p = the additional stress in the tendons
f  p = the total stress in the tendons
[Insert a paragraph describing partial prestressing with a table listing the advantages and disadvantages]
The design of prestressed concrete bridges is described in a number of standard texts, some of which are listed at the end of
this chapter of the Design Guide. The following sections give advice and information on particular aspects of the design of
 prestressed concrete bridges.

Prestressin g wi th External Tendons


[Section to be written giving advice of details /materials for sheathing, grouting, strategies for replacement of tendons]
[Photograph of bridge deck with external tendons]

Segmental Constructi on
[Section to be written describing the issues to be considered in prestressed concrete segmental bridge design, e.g. design
methods for glued and dry joints, continuity of sheathing across joints between segments, commonly used methods of erection,
staged transfer of dead load from falsework to prestressed section (see also ref 3 below)].
[Include photograph of segmental bridge and diagrams as appropriate]

Precast Beams
[Section dealing with stability issues during transport, erection & casting of deck concrete – what loads should be allowed for,
etc.]

End Block Design


[Section explaining the principles of end block design using “strut-and-tie” models and bending theory. When each methods is
appropriate. Particularly good references should be reviewed and included in the list of references at the end of this chapter.]
[Include photographs of good and (if possible) bad end block detailing]

Prestressed Concrete Design Page 4


CBDG Design Guide

Precast Shells and Composi te Action


[Section discussing appropriate design rules for the design of precast shells filled with insitu concrete and prestressed so that
it behaves as a single composite section]
[Photograph of Taney Bridge under construction – KRW to provide]

The Designers Perspective


For the bridge designer, prestressed concrete provides one of the most versatile materials to design and construct with. Unusual
shapes and structural arrangements may be readily adopted with either insitu or precast constructions, while using prestressed
concrete allows the designer to adopt more slender and longer spans than would be possible with just reinforced concrete
construction.
Prestressing is used in many different way in bridgeworks. It can be in the form of longitudinal tendons to cater for the
longitudinal moments and shears in a deck or column, or as transverse tendons prestressing the top slab of a deck to cater for
the local wheel loads. Occasionally it is also used as vertical prestress to enhance the deck web shear capacity or to distribute
forces with-in the deck diaphragms. Often contactors will use the prestressing in the temporary condition to support the bridge
during the construction stages. For the innovative designer its uses are endless, although it must be said that in general the
British designers do not use prestressing as often as French and other continental designers.
The concept of prestressing is simple in that it is just an external load applied to a section to balance the tensile stresses that
occur. However, in practice the design is more complex than for simple reinforced concrete and the interaction between the
structural behaviour, the concrete properties and the prestressing tendons has to be carefully considered by the designer. The
 prestressing force causes the concrete to creep while the creep and shrinkage in the concrete reduces the force in the prestress.
The prestress secondary moments, sometimes referred to as parasitic moments, may also be redistributed by creep within the
concrete and the designer has to combine all these effects into the design.
With prestressed concrete bridges, the designer must always take into account the construction sequence and the way the
 bridge is going to be built. This quite often has more influence on the prestress tendon arrangement and profile than do the
forces and moments applied to the sections. With balanced cantilever construction the prestress tendons are arranged in groups
of cantilever and continuity tendons. With span-by-span construction the prestress tendons are usually anchored on the
construction joints and often have couplers to extend them into the next span cast. If a bridge deck is fully cast before the
 prestress is applied then the prestress may consist of single tendons extending from one abutment to the other.
When choosing which type of prestressing to use, whether it be strand, wires, bars, internal or external, the designers decision
is usually based on economics, ease of construction and maintenance. Strands are usually the cheapest type of prestressing
tendon when considered in terms of £ per kN o f force, while prestressing bars can be simpler to install, especially for short
lengths. External tendons can simplify concreting and reinforcement fixing as well as future inspection and maintenance, but
internal tendons are usually less expensive and offer a greater level of protection against accidental damage.
The design process that the designer uses for concrete bridges depends on the type of prestressing used. For internal tendons,
the design of the prestress is usually g overned by the SLS conditions. The prestress quantity and layout needs to ensure that the
stresses within the structure are within the acceptable limits. In this case, the ultimate moment capacity is not usually critical
while the shear design is usually a case of having sufficient concrete width and depth, and adequate reinforcement. With
external tendons the longitudinal design may be governed by the ULS condition. The amount of prestress needed at any section
is dictated by the Ultimate Moments applied with the SLS stresses usually less critical.
Designers have a range of software available to them for the analysis of prestressed concrete bridges. To fully analysis all the
aspects of prestressed concrete the software package must be able to handle the stage-by-stage construction that inevitable
occurs with this type of construction. Creep and shrinkage of the concrete and friction, draw-in and other prestress losses
should also be modelled within the analysis. Software programmes that combine all of these aspects include ADAPT,
RM2004, Sofistik, LARSA and Midas. Other software is also available and as the power of computers increase, even the most
complex of structures can be analysed in a short time. The designer should always be aware that all of these programmes have
limitations and a certain amount of interpretation and approximation is still needed to end up with the right answers!
As with all forms of bridgeworks, prestressed concrete has its own set of detailing rules that need to be carefully followed.
Space within the concrete is needed for the anchorages and couplers and the extra reinforcement associated with these areas.
The required duct spacing and cover is dependent on the force in the tendon and the tendon radius. The structure must also
 provide sufficient room to locate the jack and stress the tendons. Ducts clashing with reinforcement can challenge both the
detailer and site team. There is usually a need to draw up the prestressing tendons and reinforcement in detail to ensure that it
all fits within the concrete section, and there is still enough room to get the concrete in!
The designer should not forget the need for future inspection and maintenance of the prestressing tendons. Where external
tendons are employed, there should be good access for inspection and for moving the equipment for restressing and grouting
around.

Prestressed Concrete Design Page 5


CBDG Design Guide

One of the main advantages of prestressing is the improved long-term durability of the structure by reducing or eliminating
cracking within the concrete and a designer can make use of this in vulnerable parts of the bridge.
Where a project warrants the use of precast concrete, prestressing often simplifies the construction details across the
connections. By prestressing the connection the need for insitu connections and complex reinforcing details can be minimised,
or eliminated.
The longest free span in the world for a concrete box girder is currently Stolma Bridge in Norway with a main span of 301m
although the Shibanpe Bridge in China currently under construction will have a main span o f 330m. This shows that
 prestressed concrete can rival steel and arch construction for spans up to this length, while with cable-stayed bridges it is
common to find prestressed concrete being the material of choice for the deck with spans up to 450m.

Recomm ended Sources of Reference for Prestressed Concr ete Bridge Design

 A Gui de t o t he Desig n o f Anc ho r B lo cks for Post-t ens io ned Prestr essed Co ncret e, Gui de No . 1, CIRIA, London
1976. John L Clarke
Provides guidance on the flow of forces and the calculation of reinforcement in end blocks of post-tensioned construction.

Prestressed Concrete Bridges, Birkhäuser, Christian Menn


General text on prestressed concrete bridge design. Section 4.6.4 discusses detailing to resist local forces from curved tendons
(in curved or straight bridges). Chapter 7 is devoted to the design and construction of special bridges and section 7.6 is
 particularly helpful in covering the design of curved prestressed concrete girders.

Standard Method of Detailing Structural Concrete, The Institution of Structural Engineers & The Concrete Society, 1989
Chapter 7 deals with prestressed concrete and discusses succinctly a number of issues which should be considered when
designing and detailing prestressed concrete bridges.

Concrete Box Girder Bridges, Jorg Schlaich & Harmut Scheef.


This book contains good practical examples which are linked with theory.

FIP Handbook o n Practical Design .


This book gives practical examples of the design procedures for a variety of prestressed concrete bridges

Design of Bridges with External Prestressing, A.F.Daly & P.Jackson


[commentary still to be written]

Collection of papers on external prestressing, M.Virlogeux


[precise references and commentary to be provided]

Concrete Bridge Construction (?), W.Podlony


This book is very helpful in discussing important construction details which the designer should take into account when
developing his designs.

Prestressed Concrete Design Page 6

You might also like