Download as pdf or txt
Download as pdf or txt
You are on page 1of 101

Managing the Level Crossing Removal Program

Victorian Auditor -General’s Office



Level 31 / 35 Collins Street
Melbourne Vic 3000

T 03 8601 7000
enquiries@audit.vic.gov.au
www.audit.vic.gov.au

Managing the
Level Crossing
Removal Program
December 2017

December 2017
2017–18:10

Victorian Auditor-General’s Report


2017–18:10

10557 VAGO_Managing the Level Crossing Removal Program_Cover.pdf | Page 1 of 1 10557 VAGO_Managing the Level Crossing Removal Program_Cover.pdf | Page 1 of 1
 

Managing the 
Level Crossing 
Removal Program 

 
 
Ordered to be published  
VICTORIAN GOVERNMENT PRINTER 
December 2017 
PP No 358, Session 2014–17 
 

This report is printed on Monza Recycled paper. Monza Recycled is certified Carbon Neutral by The Carbon Reduction Institute 
(CRI) in accordance with the global Greenhouse Gas Protocol and ISO 14040 framework. The Lifecycle Analysis for Monza 
Recycled is cradle to grave including Scopes 1, 2 and 3. It has FSC Mix Certification combined with 55% recycled content. 

ISBN 978 1 925678 09 3 
 
 
 
The Hon Bruce Atkinson MLC  The Hon Colin Brooks MP 
President  Speaker 
Legislative Council  Legislative Assembly 
Parliament House  Parliament House 
Melbourne  Melbourne 
 
 
Dear Presiding Officers 
 
Under the provisions of section 16AB of the Audit Act 1994, I transmit my report 
Managing the Level Crossing Removal Program.  
 
Yours faithfully 
 
 
 
Andrew Greaves 
Auditor-General 
14 December 2017 
 
   
 
 
Contents 
Audit overview ............................................................................................................. 7 
Conclusion .................................................................................................................................. 7 
Findings ...................................................................................................................................... 8 
Recommendations ................................................................................................................... 15 
Responses to recommendations .............................................................................................. 16 

1  Audit context ......................................................................................................... 17 
  Background ..................................................................................................................... 17 
  Options for level crossing removals ................................................................................ 19 
  Level Crossing Removal Program .................................................................................... 20 
  Status of the Level Crossing Removal Program ............................................................... 23 
  Integration with other transport projects ....................................................................... 24 
  Governance framework ................................................................................................... 24 
  Agency roles .................................................................................................................... 27 
  Relevant legislation ......................................................................................................... 29 
  Why this audit is important ............................................................................................. 29 
  What this audit examined and how ................................................................................ 29 
  Report structure .............................................................................................................. 30 

2  Level crossing selection and cost ........................................................................... 31 
  Conclusion ....................................................................................................................... 31 
  Site prioritisation and selection ...................................................................................... 31 
  Options assessment ........................................................................................................ 35 
  Program cost ................................................................................................................... 41 
  Strategic planning for future prioritisation ..................................................................... 45 

3  Procurement and delivery ..................................................................................... 47 
  Conclusion ....................................................................................................................... 47 
  Delivery models ............................................................................................................... 47 
  Contract structure ........................................................................................................... 50 
  Management of procurement risks ................................................................................. 51 
  Packaging and sequencing of works ................................................................................ 54 
  Rail occupations .............................................................................................................. 59 

4  Intended benefits .................................................................................................. 61 
  Conclusion ....................................................................................................................... 61 
  Benefits management framework ................................................................................... 61 
  Maximising value-capture opportunities ........................................................................ 64 

5  Network integration and integrity ......................................................................... 67 
  Conclusion ....................................................................................................................... 67 
  Oversight of public transport network integrity.............................................................. 67 
  Cost implications of poor network integrity .................................................................... 71 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  5 


Appendix A. Audit Act 1994 section 16—submissions and comments ..................... 75 

Appendix B. List of crossings for removal .................................................................. 85 

Appendix C. ALCAM 2008 metropolitan crossings list ............................................... 87 

Appendix D. VicRoads 2013 priority list ..................................................................... 89 

Appendix E. Core quantifiable benefits...................................................................... 93 

Appendix F. Contract models ..................................................................................... 95 

Appendix G. Benefits framework ............................................................................... 97 
 

Acronyms 
ALCAM  Australian Level Crossing Assessment Model 
ARO  Accredited rail operators 
BCR  Benefit–cost ratio 
CBA  Cost–benefit analysis  
CPLU  Cranbourne Pakenham Line Upgrade 
CTD  Caulfield to Dandenong 
DEDJTR  Department of Economic Development, Jobs, Transport and Resources 
DPC  Department of Premier and Cabinet 
DTF  Department of Treasury and Finance 
HCMT  High Capacity Metropolitan Train 
HVHR  High Value High Risk 
IDO  Integrated development opportunity 
KPI    Key performance indicator 
LXRA  Level Crossing Removal Authority 
LXRP  Level Crossing Removal Program 
MTIP  Major Transport Infrastructure Program  
MTM  Metro Trains Melbourne 
MTP  Metro Tunnel Project 
NACG  National Alliance Contracting Guidelines 
NOP  Non-owner participants  
PTV  Public Transport Victoria 
TfV  Transport for Victoria 
VAGO  Victorian Auditor-General’s Office 
 
   

6  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Audit overview 
Melbourne is facing unprecedented population growth in the coming decades, 
which will result in an increase in travel demands. Plan Melbourne 2014 stated 
that, by 2050, Melbourne’s road and rail network will need to accommodate an 
additional 10.7 million daily trips, on top of the 14.2 million daily trips recorded 
in 2014.  
The Level Crossing Removal Program (LXRP) is one of the Victorian 
Government’s key transport infrastructure projects. Part of an overarching 
policy to improve Melbourne’s transport network, its stated aim is to remove 
50 of the most dangerous and congested level crossings. 
Following its election in 2014, the government upheld its pre-election 
commitment to remove 50 crossings by 2022. The May 2015 Budget included an 
additional commitment to remove 20 crossings by 2018. Since the LXRP’s 
announcement, the government has identified an additional two level crossings 
for removal, bringing the total to 52.  
Established in 2015, the Level Crossing Removal Authority (LXRA) took over 
responsibility for managing the program from VicRoads. At September 2017: 
 10 level crossings had been removed 
 16 were in design and construction stages 
 11 had a contract awarded 
 nine were in the tender stage 
 six were in early planning stages. 
As the LXRP is only two years into an eight-year program, our assessment at this 
time serves to identify risks, lessons and opportunities for improvement for 
future works. 
We have examined whether the LXRP is cost-effective in terms of whether it has 
improved, or is expected to improve, the safety and efficiency of the state’s road 
and rail network. 
Our audit focused on the role of the Department of Economic Development, 
Jobs, Transport and Resources (DEDJTR), LXRA, Public Transport Victoria (PTV), 
and Transport for Victoria (TfV) in providing oversight and strategic focus for 
the LXRP. 

Contrary to publicly stated objectives, not all of the 50 level crossings selected 
Conclusion  for removal are the most dangerous and congested. In this sense, the LXRP is 
not fully effective when compared to the stated objective. 
The delivery of the program is ahead of schedule, and LXRA expects to surpass 
its target of removing 20 crossings by 2018. However, this pace presents risks to 
achieving value for money. These risks are compounded by an inadequate and 
delayed business case, and poor indicators to measure program benefits. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  7 


While LXRA is managing some aspects of the program well, including rail 
occupations and monitoring integrated development opportunities (IDO), 
opportunities remain to improve the LXRP—in particular, the rigour applied 
to and transparency of site selection and prioritisation, site packaging and 
procurement, benefits management, and integration of various rail projects. 
Addressing these concerns will provide greater assurance that the program will 
both improve the safety and efficiency of the state’s road and rail network, and 
maximise value for money. 
Gaps in rail network integrity have had significant consequences for the 
Network integrity refers 
to a functionally effective,  integration of the LXRP and other concurrent rail projects, including the Metro 
reliable, maintainable,  Tunnel Project (MTP) and the Cranbourne Pakenham Line Upgrade (CPLU).  
secure, safe and 
environmentally  Now that TfV is responsible for setting the state’s strategic transport direction, 
compatible public  it needs to address the gaps in rail network planning and requirements, so that 
transport network.   future network requirements appropriately inform planning for major rail 
transport projects. TfV’s development of transport planning frameworks has 
the potential to improve rail network planning. 

Program business case 
Findings 
The LXRP business case was finalised in April 2017, almost two years after the 
program had commenced.  
Weaknesses in the business case undermine its purpose and its value as a basis 
for the government’s decision to commit to the investment. This situation needs 
to be remedied in future advice to government about investment decisions for 
crossing removals, if these decisions are to be based on a sound understanding 
of the costs, benefits and options of the investment.  

Site selection and prioritisation 
The LXRP business case is not consistent with the stated objective of the LXRP—
to remove 50 of the most dangerous and congested level crossings—in that it 
omits the word ‘most’. 
This important difference arises in part because DEDJTR did not assess the 
merits of the 50 level crossing sites identified for removal, which were part of 
an election commitment in 2014. 
As a result, the April 2017 approved business case does not include any analysis 
or rationale for why the 50 level crossings were selected as higher priority—or 
demonstrate that they were more dangerous and congested—than other level 
crossings across Melbourne. The 50 selected level crossing sites include a 
number of sites that have not been identified as dangerous and congested. 
This means that the business case was necessarily limited in its function to fully 
inform the incoming government about available options and whether the 
selected sites provided the best approach for it to achieve its desired policy 
objectives. 

8  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Options assessment for grade separation 
LXRA and VicRoads completed their options assessments for grade 
separations—separating the level of rail and road—of 20 crossings before the 
business case was completed. 
LXRA’s options assessments for the remaining 30 crossings—developed as part 
of the business case—differed in approach and in the level of detail to the first 
20. The options assessment framework for these 30 crossing sites included a 
multi-criteria analysis tool to guide the selection of grade separation types. 
This framework aims to ensure that the chosen options are cost-effective and 
defensible, and the process is comprehensive, transparent and consistent. 
The options assessment framework does not weight criteria to indicate the 
relative importance of each criterion. While this allows for flexible  
decision-making, it also means options assessments can be inconsistent and 
that the selection of the preferred option lacks transparency. 
LXRA refers all preferred grade separation options, including supporting options 
analysis, to the Minister for Public Transport (the Minister) for approval. 
The Minister has discretion to approve the option or, where it is likely to be 
contentious with key stakeholders, refer it to government for endorsement. 
LXRA’s identification of contentious sites is subjective, with no clearly 
documented rationale, and offers limited transparency around how decisions 
were made. 
In advising government on options for the Frankston line sites, LXRA used 
different assessment criteria than it used for the other sites. LXRA advised that 
it did this to accommodate additional information gathered about the sites 
through more detailed analysis and community consultation. However, the 
existing option assessment framework is designed to incorporate additional 
information as site investigation proceeds.  
There are important differences between the two sets of criteria. In particular, 
the criteria used for the Southern package of crossing removals focus on aspects 
like impact on adjacent properties whereas the original criteria focus on project 
alignment and outcomes. While the modified criteria produced similar results to 
the original assessments in this instance, the decision to use different criteria 
indicates that LXRA is not consistently or transparently applying the options 
assessment framework. 

Program cost 
The cumulative cost of the program has increased by more than 38 per cent—
based on the initial estimate of $5–6 billion in 2015—to $8.3 billion at July 2017. 
DEDJTR did not follow the High Value High Risk (HVHR) guidelines to update the 
business case to reflect ongoing changes to program cost estimates arising from 
scope changes, including the addition of two more sites. The identification of 
future network requirements also did not result in updates to the program costs 
in the business case. The change in cost, with no assumed benefit increase, 
would result in a reduced benefit–cost ratio (BCR).  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  9 


The business case was set up on the assumption of like-for-like replacement of 
existing infrastructure, but this was not realistic. For example, as the program 
progresses, works at level crossing removal sites along the Frankston and 
Cranbourne/Pakenham lines—such as required traction power upgrades and 
High Capacity Metropolitan Train (HCMT) requirements—are being identified. 
These requirements were known at the time of the business case development.  
The business case provides for future proofing works—for example increasing 
station platform length, extending the width of the rail corridor, or building 
wider road bridges—for 16 crossings. LXRA has made provision of $148 million 
for this work, which is less than 2 per cent of the $7.6 billion identified in the 
business case. 

Procurement and delivery 
The 52 level crossing removal sites are divided into packages for delivery—
eight packages contain between two and nine level crossings and two packages 
have one crossing each. There are six crossings that LXRA has not yet allocated 
to a package.  
The LXRP is being delivered using a mix of contract types: 
 Competitive alliance contracts—two or more shortlisted parties develop 
competing project costs (26 sites). 
 Partial price competitive alliance contracts—shortlisted parties develop 
pricing for some elements of the total project cost. The sole successful party 
then prices the remaining elements alongside the owner of the project 
(24 sites). 
 Design and construct contracts—the client develops a limited design and 
invites potential suppliers to tender on the basis of completing and 
constructing the design. This contract typically allocates construction and 
design risk to the suppliers (two sites). 

Partial price competition 
While LXRA and VicRoads procured the initial 20 sites through competitive price 
competition, LXRA will only apply full price competition to a quarter of the 
remaining 32 sites, procuring the rest through partial price competition. In one 
instance, for the North Eastern package, LXRA procured the proponent for all 
four level crossings in the package using partial price competition. The main 
consideration for this decision was to fast track procurement so that LXRA could 
meet the government’s committed time frame for the LXRP and the duplication 
of the Hurstbridge line.  
While partial price competition can streamline the tendering process—as LXRA 
does not need to compare two fully priced proposals—it also removes an 
element of competitive tension. Victorian policy permits the use of partial price 
competition in some circumstances—for example where the community needs 
works to commence immediately. However, LXRA’s rationale for selecting this 
method for its North Eastern Package—to fast-track the package to meet a 
government commitment—is not in itself a sufficient justification.  

10  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Contract structure 
Under its contract structure for the North Eastern, North Western, Western 
and Southern packages, parties bid competitively for the initial sites. If LXRA is 
satisfied with the alliance’s performance on those sites, it asks the alliance to 
develop a formal proposal for the additional sites in the package. This means 
the additional sites will not be subject to full price competition.  
LXRA advises that there are benefits to this structure. For example, according to 
LXRA, the structure allows for stable engagement with the private sector and 
locks in key resources prior to significant construction activity across Australia in 
2019–22. However there are some inherent risks in the procurement process, 
primarily due to reduced price and design competition. These risks are 
compounded in the North Eastern package, where LXRA did not use full price 
competition to procure a proponent for the initial sites.  

Managing procurement risks  
To manage its procurement risks, LXRA is using benchmarking and the 
commercial frameworks of its alliance agreements.  
LXRA’s benchmarking framework includes a tool for comparing price and 
productivity efficiencies across the LXRP alliances. The tool allows LXRA to 
monitor whether it is achieving value for money in delivery of the program. 
To date, LXRA has only applied the benchmarking tool to the North Eastern 
package.  
When awarding initial works packages, LXRA locks in overhead and profit for all 
remaining sites in that package. This introduces an element of competition into 
awarding the remaining sites. However, there is a risk that parties can bid low 
on overheads and profit with the expectation of increased direct job costs on 
later sites. To date, overhead and profit as a percentage of direct job costs has 
been lower for packages using the deferred pricing model than for the initial 
four alliances that did not use this model. This reinforces the need for LXRA to 
continue to develop its benchmarking tool to assess proposals effectively and 
identify potential under- or overpricing. It is important that LXRA continues to 
improve its framework and embed it into future procurements.  
LXRA is also using a risk and reward regime for each alliance, which compares 
actual and target performance in both cost and non-cost areas. The non-cost 
elements of LXRA’s risk and reward regimes are in line with national guidance 
and include clear methods for calculating performance. However, LXRA has 
capped the amount that its contractors pay in the event of a cost overrun. This 
means there is a risk that if the cost overrun for a package exceeds the cap, the 
state will effectively bear all additional project risk.  
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  11 


Packaging and sequencing 
The LXRP business case considered two options for packaging the remaining 
30 level crossing removals: 
 a corridor approach—in which crossing sites along rail corridors are 
packaged together 
 a discipline-based approach—where similar work types are packaged 
together (such as stations, power, signalling and rail track).  
LXRA’s evaluation of these two options emphasised that time, management 
of disruptions, and risk management were important considerations. LXRA 
ultimately determined that the corridor approach better matched the LXRP’s 
cost and timeliness procurement objectives. 
LXRA did not analyse which of the crossings had the highest priority for removal 
from a safety or rail efficiency perspective, to inform the sequencing of crossing 
removals. Of the 50 level crossings, LXRA has prioritised those that had greater 
preparatory work completed and that had a less complex design solution. This 
has brought forward some crossing removals, and LXRA expects to exceed the 
government target of 20 crossing removals by 2018.  
The remaining crossings are more complex and more challenging to complete 
within the allocated time frame and budget. However, it is too early to tell the 
impact of the current packaging and sequencing regime on the overall program.  
LXRA is using 10 packages across the whole program. However, it did not 
package the following crossings using the corridor approach: 
 Abbotts Road, Dandenong South—part of the Western package instead of 
the Caulfield to Dandenong (CTD) package 
 Skye Road, Frankston—part of the North Western package instead of 
Southern package.  
The level crossing at Skye Road was initially part of the Southern package. 
However, following a decision to accelerate the removal of this level crossing, 
LXRA moved Skye Road into the North Western package.  
LXRA estimated that this cost an additional $11 million, due to a reduction in 
planned program efficiencies. While $11 million is not material in the context 
of the whole LXRP program, accelerating its removal by moving responsibility 
to the North Western Alliance helps LXRA to meet the government’s committed 
target of removing 20 level crossing by 2018.  

Rail occupation management 
Removing level crossings involves the temporary closure of the rail line and its 
occupation to enable construction works. LXRA and alliance members have 
processes in place to manage rail occupations appropriately and have managed 
them well. However, more than half of the planned occupations are yet to 
occur.  

12  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Planning for major occupations commences at least six months before the 
proposed occupation because contractors usually work 24 hours a day, 
seven days a week during the occupation. 
As at July 2017, only three of the 48 completed major occupations were late. 
Two of these delays were less than one hour, and the third was one day late. 
This is a good result and evidence of sound occupation planning and project 
management during the occupations. 

Intended benefits 
As completion of the LXRP is not due until 2022, there is insufficient data at 
present to make an informed judgement on how well the program is achieving 
intended outcomes.  
DEDJTR has developed a benefits management framework in accordance 
with Department of Treasury and Finance (DTF) requirements. This includes 
development of an investment logic map, benefit map and benefit management 
plan. However, current monitoring and reporting of outcomes is not meaningful 
due to the lack of comprehensive key performance indicators (KPI) and targets. 

Key performance indicators and targets 
KPI targets specified in the benefit management plan only require performance 
improvement without defining what constitutes the improvement. Examples 
of such targets are, ‘100 per cent of sites with road based public transport will 
have improved punctuality’ or ‘100 per cent of sites will improve access to jobs, 
education, and services’. LXRA advised that this is deliberate because factors 
other than the crossing removal can affect outcomes. Given this, the KPIs 
themselves are unlikely to be suitable measures.  

At March 2017, LXRA had prepared four individual draft benefit reports for the 
removed level crossings. These reports do not provide meaningful information 
about the extent of improvement and whether the progress results are in line 
with expectations. 

Value capture 
LXRA has developed a comprehensive plan aimed at maximising value capture 
opportunities through the LXRP. For the LXRP, value capture is limited to IDOs—
surplus railway land from a grade separation that can be sold to the private 
sector to develop. IDOs can include broader social benefits, such as social 
housing, community services and open spaces. 
LXRA developed an IDO strategy in December 2015, providing guidance on 
identifying IDOs and their potential benefits and how these benefits can be 
realised.  
LXRA’s ongoing monitoring of identified IDO projects is timely and 
comprehensive. Monthly IDO dashboard reports provide a comprehensive 
summary of the status of each level crossing site against project milestones. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  13 


Network integrity 
One of PTV’s key functions, since September 2016, is to ensure the integrity of 
the public transport network, to make sure it is functionally effective, reliable, 
maintainable, secure, safe and environmentally compatible. As part of this role, 
PTV is responsible for establishing:  
 network technical requirements—high-level technical requirements for a 
transport corridor or geographic area 
 network technical standards—derived from network technical requirements 
to inform and direct the development of system requirements and 
specifications, and accredited rail operators (ARO) engineering standards.  
PTV does not have adequate resources to be effective in its network integrity 
role. This has had undesirable cost and scope consequences for the integration 
of the LXRP and other concurrent rail projects into the rail network. PTV, with 
support from TfV—which is now responsible for strategic future transport 
planning—will need to ensure that actions to address this shortcoming are 
effective.  

Application of standards to the LXRP 
LXRA sets project system requirements that contractors delivering the LXRP 
must comply with. These requirements translate PTV and Metro Trains 
Melbourne (MTM) requirements, as well as other standards and specifications. 
However, during the translation process, there is scope for variations which can, 
in turn, have cost implications for projects. For example, approval to not comply 
or partially comply may reduce project costs and time lines. MTM manages the 
approval processes for changes to MTM engineering standards and their 
interpretation using a standard waiver or design practice note.  
However, as MTM has limited insight into network-level requirements and 
planned developments, there is a risk that these decisions can impact other or 
future transport projects. Furthermore, as MTM is also a member of all of the 
LXRP alliances, a perceived conflict of interest exists—MTM is both part of the 
project development team applying for a standard waiver and part of the 
organisation making decisions on variation requests. 

Controls for network integrity risks 
PTV has established a number of arrangements to improve oversight of and 
accountability over its network integrity function. These include a network 
integrity governance framework and a formalised standards governance process 
in the new agreement with MTM, beginning 30 November 2017.  
PTV’s additional controls to improve its network integrity function are 
happening in parallel with the delivery of a number of important transport 
projects. It is important for PTV and TfV to closely monitor the effectiveness of 
these new arrangements, particularly for programs such as the LXRP which is 
well underway.  

14  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


We recommend that the Department of Economic Development, Jobs, 
Recommendations  Transport and Resources: 
1. follow High Value High Risk guidelines in developing a business case as the 
basis for government’s investment decisions, including timing of approval, 
presenting a range of project options and updating the business case with 
any significant changes (see Section 2.2) 
2. in conjunction with the Level Crossing Removal Authority, develop a 
transparent selection and prioritisation process for targeted removal of 
level crossings beyond current commitments made by government 
(see Sections 2.2 and 2.5) 
3. develop comprehensive key performance indicators and targets to 
meaningfully measure achievement of intended benefits (see Section 4.2)  
4. in conjunction with the Level Crossing Removal Authority, progressively 
monitor the progress of achievement of Level Crossing Removal Program 
outcomes to facilitate timely insight into how the program is progressing 
towards benefits realisation (see Section 4.2) 
5. in conjunction with Public Transport Victoria, develop contemporary 
network rail standards, so that agencies delivering rail projects have an 
understanding of network requirements and what is required to assure 
projects meet engineering, network integration and safety requirements 
(see Section 5.2)  
6. in conjunction with Public Transport Victoria, monitor the effectiveness of 
Public Transport Victoria’s controls to improve its network integrity function 
(see Section 5.2).  
We recommend that the Level Crossing Removal Authority: 
7. apply options assessments transparently and consistently (see Section 2.3) 
8. commission an independent evaluation and report on whether the deferred 
pricing contract structure is cost-effective and has delivered its intended 
benefits (see Section 3.3) 
9. embed its benchmarking tool into the procurement process before using it 
to award additional works sites (see Section 3.4) 
10. in conjunction with Transport for Victoria, evaluate its packaging approach 
and incorporate lessons learned into future level crossing removals (see 
Section 3.5). 

   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  15 


We have consulted with DEDJTR, PTV, VicRoads and VicTrack, and we considered 
Responses to  their views when reaching our audit conclusions. As required by section 16(3) of 
recommendations  the Audit Act 1994, we gave a draft copy of this report to those agencies and 
asked for their submissions or comments. We also provided a copy of the report 
to the Department of Premier and Cabinet (DPC). 
The following is a summary of those responses. The full responses are included 
in Appendix A.  
DEDJTR accepted the recommendations, noting its intention to improve the 
delivery of the balance of the LXRP, and provided an action plan to address 
them.    
PTV accepted the recommendations and provided an action plan on how it will 
implement them. 
Although there were no recommendations directed toward VicRoads and 
VicTrack, both agencies provided a response. VicTrack advised it will continue its 
collaboration with LXRA and other agencies as required.  
  
 
 
 
 
   
 

16  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Audit context
Melbourne has an extensive transport network, which includes rail, roads, 
Background  cycle paths and footpaths. The challenge is to ensure these components work 
together as an integrated transport system so that people and goods can move 
efficiently in and around Melbourne.  

Melbourne is facing unprecedented population growth. In the next 30 years, 
Victoria’s population is expected to increase by up to 60 per cent to 9.5 million. 
As the population grows, travel demands also increase, with public transport 
use growing at a faster rate than the population. Plan Melbourne 2014 indicates 
that, by 2050, Melbourne’s road and rail network will need to accommodate an 
additional 10.7 million daily trips, on top of the 14.2 million daily trips recorded 
in 2014. 
Managing increasing demand on road and rail infrastructure is a key task for 
government, and central to maintaining Melbourne’s liveability. 

Level crossing removals in Melbourne 
A level crossing—also known as a grade crossing—is an intersection where a 
railway line crosses a road or path at the same level, as opposed to crossing 
over or under using a bridge or tunnel.  
Separating the level of the road and rail is a grade separation. Grade separations 
can enhance road and rail network performance through the removal of the 
conflict at a crossing, improved station design, improved station access, and the 
integration of stations into the surrounding area. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  17 


Reasons for removing level crossings  
Governments remove level crossings for a range of reasons, including to 
facilitate an increase in the frequency of train services, to extend rail lines 
through developed areas or to improve safety and traffic flow. In the past, 
some of these removals were part of a larger project—for example, the grade 
separations in the extension of the Hurstbridge-South Morang lines—however, 
most were done on an ad hoc basis. 
Between 2005 and 2015, there were more than 149 collisions between a 
The rail corridor is the 
land on which the railway  train and a vehicle or pedestrian along a rail corridor across metropolitan 
is built. It comprises all  Melbourne—including the 178 level crossings on the electrified rail network. 
property typically  Of these, 38 resulted in fatalities and 22 in serious injuries. Boom gate closure 
bounded from fence line  times and traffic volumes across sites vary significantly and, in some locations, 
to fence line or, if not 
fenced, everywhere 
extended boom gate closures can contribute to road traffic congestion. 
15 metres either side of 
the outermost parts of 
Large number of crossings in metropolitan Melbourne 
the track, unless 
otherwise indicated. The number of road level crossings remaining on Melbourne’s metropolitan 
electrified train network is high compared to other Australian cities—see 
Figure 1A.  

 
National comparison of metropolitan rail level crossings  

Number of level crossings 
City  at September 2017 
Adelaide  84 
Brisbane  47 
Melbourne  178(a) 
Perth   29 
Sydney  3 
(a) Figure for Melbourne is prior to the LXRP. 
Canberra, Darwin and Hobart do not have metropolitan train services. 
VAGO. 

A level crossing removal program managed by VicRoads, Metro Level Crossing


Blitz, commenced under the previous government in 2011, with business cases 
finalised in 2013 and 2014.  
The current government announced a level crossing removal program while 
still in opposition. This program formed part of its Project 10 000 election 
commitment which identified 40 level crossings for removal. Ten further 
crossings were added before the election. 
These crossings formed part of the 2015–22 LXRP. In 2015, LXRA was 
established and took over responsibility for managing the program from 
VicRoads. 

18  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


 
There are four main types of road-rail grade separations—see Figure 1B. 
Options for 
level crossing   
removals   Main types of road-rail grade separations 
Rail over road—the road remains at its 
existing level and a rail bridge is built 
over it. Modifications to train stations 
may be required, at least to the platform 
levels, to suit the new rail level. 
Elevating the rail line provides 
opportunities for increased connectivity 
across the rail corridor. 

Rail under road—the rail line is 
lowered to go beneath the existing 
road. A bridge is built to maintain the 
road at its existing level. Where there 
are nearby train stations, these need 
to be modified or rebuilt to suit the 
new rail level. Additional pedestrian or 
cycling bridges may be used to 
improve access across the lowered railway. 

Road over rail—the rail line remains at 
its existing level and a road bridge is 
constructed over it. Local road and 
pedestrian accessibility is maintained 
with local service roads or by providing 
alternative access. This does not 
generally require any modifications to 
rail platforms because the level of the 
rail does not change. Where there are nearby train stations, access to them 
needs to be maintained. 

Road under rail—the road is lowered 
to go beneath the rail line. A rail bridge 
is built to allow the rail to remain at its 
existing level. Local road and pedestrian 
accessibility is maintained with local 
service roads or by providing 
alternative access. Where there are 
nearby train stations, access to them 
needs to be maintained. 

VAGO, based on information provided by LXRA. Photographs courtesy of LXRA. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  19 


Other options for grade separations include: 
 hybrid options—involve raising or lowering both road and rail instead of only 
one 
 closure—closing the level crossing. This option provides no new alternative 
crossing of the rail corridor and road traffic must find an alternate route.  
 
The LXRP is one of the Victorian Government’s key transport infrastructure 
Level Crossing  projects. Its stated aim is to remove 50 of the most dangerous and congested 
Removal Program  level crossings by 2022. In May 2015, as part of the Budget, government 
announced an interim target of 20 removals by 2018.  
Since LXRP’s announcement, the LXRA has identified two additional level 
crossings for removal, bringing the total to 52—see Appendix B for a full list. 
Figure 1C shows the location of these crossings.  

 
Locations of the level crossings to be removed under the LXRP 

 
VAGO, based on information provided by LXRA. 

20  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


The stated benefits of the LXRP are diverse. They include to deliver significant 
safety improvements for drivers and pedestrians, improve travel around 
Melbourne and enable more trains to run more often and on time. 

Level crossing removal packages 
Level crossings will be removed along most Metropolitan train lines. The 
Cranbourne-Pakenham line will have the most removals, however, these will 
only amount to 52 per cent of the level crossings on that line—see Figure 1D. 

 
Level crossing removal by metropolitan train line 
Level crossings
35
43%
30
52%
25 13%

20 11%
13%
15 43%
0%
30%
10 38%
17% 29% 33%
5 50%
0% 0%
0

Train line

Level crossings remaining Level crossings to be removed by LXRP
  
VAGO, based on information provided by LXRA. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  21 


Individual level crossing removal sites are grouped into delivery packages—see 
Figure 1E. 

 
Level crossing removal packages 

Package  Level crossings included 
Package 1  North Road, Ormond; McKinnon Road, 
McKinnon; Centre Road, Bentleigh; Burke Road, 
Glen Iris 
Package 2  Main Road and Furlong Road, St Albans; 
Blackburn Road, Blackburn; Heatherdale Road, 
Mitcham 
Package 3 (CTD)  Grange Road and Koornang Road, Carnegie; 
Murrumbeena Road, Murrumbeena; Poath 
Road, Hughesdale; Clayton Road and Centre 
Road, Clayton; Corrigan Road, Heatherton Road 
and Chandler Road, Noble Park 
Package 4  Scoresby Road and Mountain Highway, 
Bayswater 
Melton Highway  Melton Highway, Sydenham 
Thompsons Road  Thompsons Road, Lyndhurst 
North Eastern Package  Lower Plenty Road, Rosanna; Grange Road, 
Alphington; Bell Street, Preston; High Street, 
Reservoir 
North Western Package  Bell Street, Coburg; Buckley Street, Essendon; 
Camp Road, Campbellfield; Glenroy Road, 
Glenroy; Moreland Road, Brunswick; Skye Road, 
Frankston 
Western Package  Abbotts Road, Dandenong South; Aviation Road, 
Laverton; Cherry Street and Werribee Street, 
Werribee; Ferguson Street, Williamstown; 
Kororoit Creek Road, Williamstown North 
Southern Package  Balcombe Road, Mentone; Charman Road and 
Park Road, Cheltenham; Edithvale Road, 
Edithvale; Eel Race Road and Station Street, 
Carrum; Seaford Road, Seaford; Bondi Road and 
Mascot Avenue, Bonbeach 
Unallocated level  Clyde Road, Berwick; Hallam Road, Hallam; 
crossings  Manchester Road, Mooroolbark; Maroondah 
Highway, Lilydale; South Gippsland Highway, 
Dandenong; Toorak Road, Kooyong 
VAGO, based on information provided by LXRA. 
   

22  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Each package has its own governance arrangements that include: 
 a project director  
 a project team, consisting of senior project managers, project managers, 
senior project/design engineers, and project control/support officers. 
The project director reports to the LXRA Chief Operating Officer, who reports to 
the Chief Executive Officer. 
The project teams are supported by functional teams that include 
communications and stakeholder relations staff, safety staff, cost controllers and 
commercial managers. 

VicRoads had commenced work on the procurement and construction of 
Status of the  10 level crossing removals prior to the establishment of LXRA. The LXRP 
Level Crossing  incorporated these crossings. The status of those crossings was: 
Removal Program   four sites had already completed full business cases—Blackburn Road, Main 
Road, Burke Road and North Road 
 four sites had prepared project proposals—McKinnon Road, Centre Road 
(Bentleigh), Furlong Road and Heatherdale Road 
 two sites had completed preliminary planning and a business case—
Mountain Highway and Scoresby Road. 
All 52 level crossings are planned to be removed by 2022. While an interim 
target of removing 20 crossings by 2018 was set in 2015, LXRA is now intending 
to complete up to 28 by 2018. The 2017–18 State Budget brought forward 
additional funding to achieve this outcome.  
By September 2017, LXRA had removed 10 crossings, with another 16 in the 
design and construction stage—see Figure 1F. 

 
LXRP status as at September 2017 
Early planning 
6 crossings
12%
Removed
10 crossings
19%

In tender
9 crossings
17%

Design and 
construction
Contract awarded  16 crossings
11 crossings 31%
21%

 
‘Contract awarded’ includes additional works packages.  
VAGO, based on information on LXRA’s website. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  23 


Some level crossing removals are part of the government’s program of major rail 
Integration  network upgrades. This includes the removal of nine level crossings on the 
with other  Caulfield-Dandenong corridor and three level crossings on the Sunbury corridor 
to allow for the rail service increases planned as part of the CPLU and MTP.  
transport projects 
Coordination between the LXRP and other major transport projects is important 
for the development of Melbourne’s future transport network.  

Project governance is about guiding and monitoring the delivery of intended 
Governance  benefits and outcomes. The DTF project governance guidelines state that there 
framework  are four key principles for effective project governance: 
 establish a single point of overall accountability  
 service delivery ownership determines project ownership  
 project decision-making is separate to stakeholder management  
 distinction between project governance and organisational structures.  
HVHR investments require greater scrutiny and support from central agencies. 

Major transport infrastructure program 
The LXRP is part of DEDJTR’s Major Transport Infrastructure Program (MTIP) 
governance framework. Figure 1G outlines this framework. 
As government has approved key decisions for the LXRP (including the scope, 
budget and procurement approach), the governance focus is now on project 
delivery.  
Ultimately, the government is required to approve the LXRP business case, 
project proposals or works packages, and funding for project delivery. 
 
 

24  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


 
Governance for the MTIP 

DEDJTR DPC
Secretary Secretary

TfV
Project client

Coordinator-General  Infrastructure Coordination 
(MTIP) Committee
Provides a forum for discussing 
Oversees the delivery of the 
project matters and informing 
LXRP as part of a suite of 
departments heads. 
transport infrastructure projects  Transport Infrastructure 
that includes the MTP, the  Policy, Planning and 
Mernda Rail Extension, the West  Delivery Committee 
Gate Tunnel and North East Link. 
 

Major Projects 
Steering Committee
LXRA
Key forum for project decisions. 
Its role is to ensure that major 
transport projects are developed 
in accordance with strategic 
directions set by the Transport 
Infrastructure Policy, Planning 
and Delivery Committee. 
Includes representation from 
DEDJTR, portfolio agencies—
Chief Executive Officer including PTV and VicRoads—as 
well as from DPC and DTF.
 
VAGO, based on information provided by LXRA. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  25 


Project delivery 
Figure 1H shows the framework for the delivery stage of the LXRP. 

 
LXRP project delivery governance framework 

Minister for Public Transport

DEDJTR Secretary

Coordinator-General—MTIP Board

LXRA Chief Executive Officer

Project Steering Committee

LXRA PTV MTM VicRoads V/Line VicTrack TfV

LXRA project teams
 
VAGO, based on information provided by TfV. 

The Major Transport Infrastructure Board advises the Coordinator-General of 
the MTIP on the delivery of the program. It includes independent members, 
industry experts and the Coordinator-General. LXRA reports monthly to the 
MTIP Board on the progress of the LXRP, including delivery, safety and finance 
issues, and key risks.  
   

26  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


LXRA established a Project Steering Committee to: 
 oversee the progress and implementation of the LXRP 
 consider operational impacts on the rail and road network and franchise 
arrangements 
 approve plans for level crossing site occupations 
 endorse the scope and technical requirements for the project, including 
agreeing on standards and requirements  
 discuss, but not determine, any change to the project scope or time lines 
 ensure that objectives and key deliverables are met 
 ensure that all stakeholders are kept informed about the progress and status  
 resolve disputes arising between the parties 
 note monthly reports provided by LXRA, PTV or MTM. 
LXRA’s Chief Operating Officer chairs the Project Steering Committee which 
comprises senior representation from PTV, VicRoads, V/Line, VicTrack, MTM and 
TfV. 

Governance prior to LXRA 
DEDJTR, PTV and VicRoads were accountable for the finalisation of the project 
development stage, including the business cases and project proposals prior to 
LXRA. This audit does not focus on the project prior to LXRA’s establishment. 

Level Crossing Removal Authority 
Agency roles 
The government established LXRA in March 2015 as an administrative office 
within DEDJTR to manage the delivery of the LXRP, the Mernda Rail Extension 
and any other project as required. As stated in the LXRP business case, LXRA will 
oversee the LXRP’s implementation and delivery of expected benefits. 

Department of Economic Development, Jobs, Transport 
and Resources 
DEDJTR is responsible for the integration of transport projects into the overall 
transport network. The Coordinator-General sits within DEDJTR and has 
responsibility for overseeing the MTIP.  
The Coordinator-General provides strategic advice on progress towards 
achieving the intended project benefits to the Premier, the Minister for 
Public Transport and the Minister for Roads and Road Safety, as well as the 
Secretary of DEDJTR and the Head of TfV. The Coordinator-General also provides 
assurance regarding the planning, procurement and delivery of the projects.  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  27 


Transport for Victoria 
Formally established in April 2017, TfV is the state’s lead transport agency. 
TfV’s objective is to bring together the planning and coordination of Victoria’s 
transport system and agencies, including VicRoads and PTV, and to integrate 
Victoria’s transport system to connect people, places and opportunities.  

VicRoads 
VicRoads’ purpose is to deliver social, economic and environmental benefits to 
communities throughout Victoria by managing the state’s arterial road network 
and its use as an integral part of the overall transport system. 

Public Transport Victoria 
PTV was established in April 2012. In September 2016, PTV received a 
ministerial direction to undertake a network integrity and assurance role, 
to ensure:  
 the public transport network remains functionally effective, reliable, 
maintainable, secure, safe and environmentally compatible as it evolves 
through future investment 
 capital programs are aligned to network requirements and standards 
 the readiness of the operating environment to implement investments into 
the transport network. 
Prior to the establishment of TfV, PTV was also responsible for detailed public 
transport network and service planning.  

VicTrack 
Created in 1997, VicTrack is a state-owned business operating under the 
Transport Integration Act 2010. It owns Victoria’s railway land, infrastructure 
and assets. Through a subsidiary—the Rolling Stock Holdings group of 
companies—it also owns much of the state’s rolling stock (trains and trams). 
VicTrack leases train and tram infrastructure and assets to PTV, which then 
sub-leases the infrastructure and assets to the metropolitan train and tram 
operators and V/Line. VicTrack also has a role in providing telecommunications 
services to operators.  

   

28  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


The Transport Integration Act 2010 requires that all decisions affecting the
Relevant transport system are made within the same decision-making framework, to
legislation support the provision of an integrated and sustainable transport system. The
Act:
 encourages transport agencies to work together toward the common goal of
an integrated and sustainable transport system
 makes it clear that the transport system needs to be sustainable
economically, environmentally and socially
 provides a framework for integrated transport policy and operations
 recognises that the transport system should be thought of as a single system
performing multiple tasks rather than separate or competing transport
modes
 integrates land use and transport planning and decision-making by
extending the policy framework to land use agencies which significantly
impact the transport system
 establishes transport bodies with consistent charters to deliver outcomes
aligned to the overall vision and objectives of the Act.

The LXRP faces a number of challenges including its large scale, engineering
Why this audit complexity, short delivery time frame and budget pressures. Elements of the
is important project have attracted criticism, particularly grade separation options.
The LXRP is designed to contribute to longer-term improvements to the road
and rail network by easing transport congestion and delivering a safer and more
efficient road network. This audit, at this point in time, serves to identify the
risks, lessons and opportunities for improvement for future works.

This audit examined whether the LXRP has been cost-effective in improving,
What this or potentially improving, the safety and efficiency of the state’s road and rail
audit examined network. Our audit focused on DEDJTR’s role, LXRA’s role in program delivery
and how and benefits monitoring, and TfV’s role in providing oversight and strategic
focus for the LXRP.
Other agencies in the scope of this audit are PTV, VicRoads and VicTrack.
The audit methods included:
 interviews with agency and departmental staff, and site visits
 review of strategies, program delivery documents, business case, and
Cabinet material
 analysis of datasets relating to road and level crossing safety, traffic
congestion and rail services.
We conducted this audit in accordance with section 15 of the Audit Act 1994
and the Australian Auditing and Assurance Standards. The cost of the audit was
$530 000.

Victorian Auditor-General’s Report  Managing the Level Crossing Removal Program 29


The rest of this report is structured as follows:  
Report   Part 2 examines the basis for program investment and decision-making 
structure   Part 3 analyses program procurement, packaging and sequencing of works 
 Part 4 looks at the intended program benefits 
 Part 5 examines network integration and integrity.  
   

30  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Level crossing
selection and cost
A comprehensive business case is important for large investments and should 
be prepared prior to making an investment decision. It provides confidence to 
decision-makers that the:  
 strategic justification for the investment is valid 
 right investment option is selected 
 government can deliver the investment as planned.  
DTF’s HVHR guidance states that the business case should consider the whole 
investment life cycle and that its role changes from one stage to another. In later 
stages, government uses it to ensure that it is delivering the investment as 
planned. If there are any changes, agencies should update the business case and 
assess the ongoing business justification in light of the new details. 
The LXRP business case was completed prior to the addition of the two extra 
crossings, and covers only 50. 

Weaknesses in the LXRP business case undermine its value and ability to 
Conclusion  provide a sound basis for the government’s decision to commit to the 
investment. The government’s election commitment was the basis for the 
selection of sites for the LXRP.  
Not all of the selected level crossings are among the 50 most dangerous and 
congested. However, post-election advice to government did not test the 
validity of the selected sites against other site options. 

The government has consistently stated that the main objective of the LXRP is 
Site  to remove 50 of the most dangerous and congested level crossings. This is not 
prioritisation and  consistent with the LXRP business case, as it omits the word ‘most’. 
selection  As the sites identified for removal were part of an election commitment, 
DEDJTR decided not to assess the merits of their selection. As a result, there is 
no analysis or rationale in the business case or other documentation about why 
the 50 level crossings selected were given priority. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  31 


The role of the public service to provide full and frank advice was not realised in 
this case. DEDJTR should have advised the incoming government that an 
analysis was needed of the selected sites against the stated program objective 
of removing 50 of the most dangerous and congested level crossings. A 2015 
DTF gateway review of the business case identified these issues.  
There was a range of guidance, summarised in Figure 2A, available to inform the 
prioritisation of level crossings for removal. DEDJTR could have used this to 
validate or test the merits of the sites chosen. 
In the absence of program-specific analysis, aligning site-specific conditions to 
criteria linked to the expected benefits of the LXRP, government cannot be 
assured that its investment in the removal of 50 level crossings is targeted 
appropriately. 

 
Guidance for prioritising level crossing removals 

Australian Level Crossing Assessment Model (ALCAM) 
ALCAM is a tool for identifying key potential risks or deficiencies at level crossings and for prioritising 
crossings for upgrades. It has three components: 
 infrastructure factor—which considers how the physical properties at each site will affect human 
behaviour 
 exposure factor—which considers the baseline likelihood of an accident at a level crossing, excluding 
site-specific conditions that are captured in the infrastructure factor 
 consequence factor—which considers the seriousness of a collision at a crossing in terms of fatalities 
and injuries.  
When combined, these three components produce a unique risk score for each level crossing. 
Level crossing surveys are used to update the risk profiles for each crossing. A survey of level crossings occurs 
approximately every five years. A Victorian list was last publicly released in 2008, by the then Department of 
Transport.  
VicRoads strategic framework 
VicRoads created a strategic framework to provide guidance on the prioritisation of level crossings for 
removal in metropolitan Melbourne. Completed in June 2014, the framework used 2013 data and was 
publicly available in October 2015. 
VicRoads assessed each level crossing against the following weighted criteria to determine priority: 
 the crossing’s strategic fit in the transport network (60 per cent) 
 potential environmental and economic benefits (25 per cent)  
 safety (15 per cent). 
The framework rated crossings as either high, medium, lower or no priority. VicRoads developed two priority 
lists of level crossing sites for removal—a 2013 priority list and a 2022 forecast priority list. 
Royal Automobile Club of Victoria (RACV) prioritisation list 
In February 2013, the RACV published a priority list of 31 level crossings for removal. Project 10 000 cites the 
RACV prioritisation list as a source for the government’s removal program.  
VAGO. 

32  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Our analysis of the 50 LXRP sites in the business case compared to the publicly
available ALCAM list for 2008 shows around 62 per cent of the LXRP crossings
(31 sites) are in the top 50 metropolitan crossings on this list—see Figure 2B.
Appendix C contains the ALCAM 2008 list excluding crossings removed before
LXRP.

 
LXRP crossings compared to ALCAM 2008 list 

Key:  Level crossings for removal under the LXRP;  the 50 highest-risk level crossings according to ALCAM 2008 as per
Appendix C; level crossings that are both listed for removal under the LXRP and among the 50 highest-risk level crossings
according to ALCAM 2008.
This map shows only the original 50 sites of the LXRP.
VAGO.

Our analysis shows that LXRP will remove 16 of the 20 crossings (80 per cent)
that VicRoads rated as high priority in its 2013 list, and five of the nine crossings
(56 per cent) rated medium priority—see Figure 2C. However, VicRoads rated
29 crossings in the LXRP lower or no priority—see Appendix D.

Victorian Auditor-General’s Report  Managing the Level Crossing Removal Program 33


 
LXRP crossings compared to VicRoads 2013 list 

 
   
Key:  level crossings for removal under the LXRP;  level crossings identified in the VicRoads 2013 list;  
 level crossings that are both listed for removal under the LXRP and VicRoads in 2013. 
This map shows only the original 50 sites of the LXRP. 
VAGO. 

Some of the sites in the LXRP are not highly ranked on either the VicRoads or 
ALCAM lists. For example, VicRoads rated the following sites as no priority and 
they also received relatively low priority on the full ALCAM 2008 list: 
 Camp Road, Campbellfield (ALCAM rank 144)  
 Kororoit Creek Road, Williamstown North (ALCAM rank 139) 
 Abbotts Road, Dandenong South (ALCAM rank 132) 
 Manchester Road, Mooroolbark (ALCAM rank 130). 
In contrast, the following sites are not included in the LXRP, despite being high 
priority on the VicRoads list, with one site in the top 50 of the ALCAM list: 
 Union Road, Surrey Hills (ALCAM rank 13)  
 Glenferrie Road, Kooyong (ALCAM rank 67) 
 Glen Huntly Road, Glen Huntly (ALCAM rank 71) 
 Madden Grove, Burnley (ALCAM rank 72). 

34  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


This shows that the LXRP is not meeting its stated objective of removing 50 of 
the most dangerous crossings in Melbourne. 

Options assessment is used to identify the most appropriate grade separation 
Options  option for each site. LXRA and VicRoads completed options assessments 
assessment  for 20 crossings before the business case was completed. LXRA’s options 
assessments for the remaining 30 crossings, developed as part of the business 
case, differ in approach and level of detail to the first 20.  
The remainder of Section 2.3 focuses on options assessments for the remaining 
30 sites. 

Options assessment framework 
DEDJTR developed a framework to assess and shortlist grade separation 
options at each of the 30 sites. Application of this framework aims to ensure 
that the chosen options are cost-effective and defensible, and the process is 
comprehensive, transparent and consistent. The framework is detailed in 
Figure 2D. 

  
Options assessment framework 

Assessment 
Stage  phase  Description 
Business case  Initial feasibility  Identifies options that are not 
assessment  technically feasible to implement. This 
results in a shorter list of options for 
assessment in the next phase.  
  Rapid  Identifies options for further 
assessment  development—around four to five. 
It is a qualitative assessment of the 
performance of options against the 
project objectives and outcomes.  
  Detailed  A detailed evaluation of the 
assessment  performance and impacts of the 
remaining options, to identify between 
one and three options to take forward 
to the next phase. 
Project/works  Final  A further detailed assessment of the 
package  assessment  remaining options using more 
proposals  developed design documentation to 
inform the scope of the recommended 
reference solution.  
Procurement  Market-based  An assessment of proposals put forward 
assessment  by bidders during the procurement stage 
to ensure that the proposed solution still 
meets project objectives.  
VAGO, based on information provided by LXRA. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  35 


The options assessment framework includes a multi-criteria analysis tool to 
select reference options for inclusion in the business case and the preferred 
solution to present to government. As LXRA completes further technical 
investigation and consultation for each site, it reapplies the tool using the 
updated information.  
LXRA does not directly assess primary criteria. It rates an option’s performance 
as either strong, average or poor against each secondary criterion. While there 
is guidance on what constitutes strong, average or poor performance, the 
criteria are not weighted. This means that there is no indication of the relative 
importance of each criterion. 

Changes to the multi-criteria analysis tool  
Under the options assessment framework—see Figure 2D—LXRA should reapply 
the multi-criteria analysis tool to options once it has gathered more detailed site 
information. In the final assessment phase for sites in the Southern package, 
LXRA used a different set of criteria. 
Figure 2E lists the criteria applied to the Southern sites and those applied to all 
other sites to date.  
LXRA advised that it did this to accommodate additional information gathered 
about the Southern package sites through more detailed analysis and 
community consultation. However, the existing option assessment framework is 
designed to incorporate additional information as site investigation proceeds.  
 
   

36  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


 
Assessment criteria 

Southern sites    All other sites (business case) 
Category  Secondary criteria    Primary criteria  Secondary criteria 
Adjacent properties  Property acquisition Alignment with  More reliable and efficient
Voluntary Purchase Scheme program  transport networks
Permanent land use changes benefits  Better connected, liveable
Noise communities
Visual impact/views Safer communities
Overshadowing Project  Capital cost
Overlooking outcomes  Whole-of-life cost
Community and  Cross-corridor connectivity Value-capture opportunities
stakeholders  Shared user paths Time frame
Linear/parks/landscaping Delivery risks
IDOs Protection of future assets
Environment and  Environment impact Project  Land acquisition impacts
sustainability  Heritage impact impacts  Land use impacts
Flooding risk Environment impacts
Contaminated soil Temporary impacts
Construction   Utility service impact
impact  Rail closures
Road closures
Station closures
Car park closures
Delivery risk
Cost  Capital cost
VAGO, based on information provided by LXRA.

There are important differences between the two sets of criteria. In particular,
the Southern sites’ criteria place more emphasis on adjacent properties and do
not consider whole-of-life cost. LXRA’s assessment using the modified criteria
produced similar results to the original assessments in this instance. However,
the decision to change the criteria indicates that LXRA has not consistently or
transparently applied the options assessment framework.

Approval of options
LXRA refers all preferred options to the Minister for Public Transport (the
Minister) for approval. The Minister may approve the option or, where it is likely
to be contentious with key stakeholders, refer the site to government for
endorsement.
How LXRA identifies sites as contentious is not clear. LXRA advises that the
decision to refer a site to Cabinet is determined by the Minister. LXRA does not
document this decision.

Victorian Auditor-General’s Report  Managing the Level Crossing Removal Program 37


Community consultation during options assessment  
LXRA’s community consultation during the options assessment process differs 
between packages. LXRA relied on the market to create innovative design 
solutions in one of the largest packages of works—CTD. The community 
consultation for this site happened concurrently with the tender process. This 
limited the role that community views could play in the options assessment 
process, as shown in the case study in Figure 2F.  

 
Case study: Consultation for the CTD package  

Community consultation for the CTD package occurred at the same time as 
the tender process. LXRA advised that, as a result, probity and commercial 
confidentiality requirements limited the information that it was able to 
share with the public.  
LXRA started raising public awareness of the project in May 2015 and 
gathered initial community input on design in July 2015. At the same time, it 
released the request for proposal to two shortlisted parties.  
During the request for proposal period, LXRA’s community consultation 
efforts included briefings, workshops and feedback sessions aimed at 
allowing community members to view design concepts. It also included a 
Community Tender Advisory Panel that consisted of representatives from 
the community and stakeholder groups. The panel served as a proxy for 
wider community consultation by giving feedback on design solutions at key 
points during the tender process.  
As the request for proposal was occurring concurrently, the panel was 
bound by confidentiality provisions. LXRA advised that this panel allowed it 
to gather community feedback on the design without breaching 
confidentiality and probity arrangements. In February 2016, LXRA 
announced a preferred party and the preferred design solution. Throughout 
February and March 2016, LXRA sought community feedback about the 
preferred rail-over-road solution.  
The feedback indicated that there was significant opposition from adjacent 
residents and traders due to concerns over amenity and noise. In advice to 
government, LXRA defended the rail-over-road solution as performing 
substantially better than other options. It also cautioned that a complete 
redesign prior to awarding the contract could have serious probity and legal 
implications, resulting in a need to re-tender the project.  
LXRA introduced a range of measures to mitigate the impact of elevated rail 
on the community, including open spaces, landscaping and a voluntary 
purchase scheme for properties abutting the corridor. The combined cost of 
these measures was $49.6 million⁽ᵃ⁾. 

(a) Voluntary purchase scheme accounts for $17.26 million of $49.6 million. 
VAGO, based on information provided by LXRA. 
   

38  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


In contrast, Figure 2G provides an example of LXRA integrating community 
consultation into the options assessment process. 

 
Case study: Southern package consultation time line 

Community consultation for sites on the Frankston line commenced well 
before procurement for the package in January 2017. In September and 
October 2016, LXRA sought feedback from the community on possible 
design solutions for the sites. The consultation findings showed community 
opposition to rail-over-road solutions. 
In December 2016, LXRA presented these findings to government, along 
with a detailed options analysis for each site. Although LXRA’s options 
analysis showed that rail-over-road solutions generally performed better, 
government elected to change five sites to rail under road. LXRA advised 
that as it had not yet released tender documentation, there were no probity 
or legal concerns about changing design solutions. 

VAGO, based on information provided by LXRA.  

These examples demonstrate that the timing of consultation has a big impact on 
the role community views can play in options assessment. LXRA used the 
lessons learned from CTD, and applied them to the Southern package. By 
consulting with the community on design options prior to commencing 
procurement for the Southern package, LXRA was able to better understand and 
integrate community views into its advice to government and options 
assessment process.  

Cost estimates for reference options 
As part of the detailed assessment phase of the options assessment framework, 
LXRA produced cost estimates for each shortlisted grade separation option. The 
LXRP business case, however, does not present this range of cost estimates for 
grade separation options. 
Although LXRA completed cost estimates for one to four grade separation 
options, the business case only included the cost of one reference option.  
These options represented a point-in-time view—for February 2016—of the 
estimated cost of how LXRA could deliver the program. The business case did 
not include the potential maximum and minimum costs of other options, as 
shown in Figure 2H. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  39 


 
Comparative cost estimates for the remaining 30 sites 

$ billion
7

6 6.49

4 4.44

3 3.57

0
Minimum Reference options Maximum
   
Reference options cost does not include packaging savings. 
VAGO, based on information from LXRA project option reports. 

As LXRA developed the reference options with limited stakeholder and 
community consultation, there was a significant risk that the proposed 
reference option could change and impact on program costs.  
This risk has subsequently materialised. There have been multiple changes from 
reference options, resulting in increases to the total program cost.  

Changes from reference options 
LXRA is undertaking further investigation and public consultation at individual 
sites as the LXRP rolls out. As a result, LXRA is recommending different design 
solutions from the reference options—as shown in Figure 2I. LXRA submits 
proposed new solutions, together with additional funding requirements, to 
government for approval. 

40  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


 
Changes from reference options for the remaining 30 sites 

Relocated 5
(crossing on adjacent site) 7

Rail over road hybrid 4
(road lowered) 3

1
Road under rail
1

10
Rail over road
14

2
Road over rail
2

8
Rail under road
3

Current solution Reference option
 
Status at July 2017. 
VAGO, based on information provided by LXRA. 

The most significant changes are the five additional rail-under-road solutions 
and four fewer rail-over-road solutions. Based on advice LXRA provided to 
government, changing a site from rail-over-road to a rail-under-road solution 
could increase the cost of that removal by an average of $18 million, and up to 
$100 million for more complex sites, such as those on the Frankston line. 

The business case did not adhere to the HVHR guidelines in a number of ways, 
Program cost  including by: 
 not providing cost estimates for more than one option per site—the HVHR 
guidelines expect project options to be thoroughly analysed in the business 
case, including expressing a cost range 
 basing business case costings on a like-for-like replacement of existing 
infrastructure  
 not considering operational or maintenance costs, or other rail programs 
impacting the LXRP 
 not updating the business case to reflect ongoing changes to program cost 
estimates—these changes include the addition of two level crossing removal 
sites and changes to preferred reference options.  
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  41 


The cumulative cost of the program has increased since the initial funding 
announcement in 2015, as shown in Figure 2J.  

 
LXRP cost 

$ billion
9 8.3
7.6 7.8
8
7
6.0
6
5
4
3
2
1
0
2014–15 2015–16 2016–17 2017–18
 
The $6.0 billion in 2014–15 represents the $5–6 billion range quoted as part of 
government’s election commitment. 
The $7.6 billion in 2015–16 represents the program cost identified in the business case.  
VAGO from information provided by LXRA. 

The business case provides a total program cost estimate of $7.6 billion—made 
LXRP associated network 
up of $6.6 billion for level crossings and $1.0 billion in associated network 
improvements are 
additional works  improvements. An HVHR gateway review of this business case highlighted that 
delivered with level  the program cost in the business case is greater than the $5–6 billion election 
crossing removals, such  commitment.  
as new train stations and 
improved public transport  The cost of the program as at July 2017 is $8.3 billion. This represents an 
access.   increase of more than 38 per cent—based on the initial estimate of $5–6 billion. 
The cost increase is mostly due to changes in the recommended options, 
particularly for the sites along the Frankston line. 

Cost of works packages 
The cost of packages is included in the total program cost. As at July 2017, 
the program’s forecast final cost is $306.3 million over the approved 
individual work package budgets, excluding program risk. The majority of 
the budget overrun is from the CTD package—$302.9 million. This is due to 
a number of factors including the complexity of the construction method, 
poorer-than-expected site conditions and additional scope in response to 
stakeholder and community feedback. 

42  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Other costs 
Futureproofing works 
The business case provides for the construction of futureproofing works for 
13 of the 16 crossings identified as requiring such works. These works include: 
 increasing station platform length 
 widening the rail corridor 
 building wider road bridges. 
LXRA will make provisions for the remaining three crossings—for example, by 
setting aside the required land—but will not construct the works as part of the 
current program. 
The business case estimates the cost of futureproofing works at all 16 sites 
to be $148 million. This is less than 2 per cent of the $7.6 billion project cost 
identified in the business case. As LXRA does not track spend on futureproofing 
items, we are unable to confirm the additional costs of the works undertaken to 
date. 

Power upgrades 
Additional works such as upgrades to the traction power network or signal 
power at a number of crossings were not included in the business case. 
Figure 2K demonstrates the implications of changing network electrical 
standards.  

 
Case study: Implications of changing a network electrical standard 

MTM and PTV have an agreed electrical network standard requiring a 
minimum 1 300 volts under normal conditions and 1 150 volts for first-order 
traction power failure conditions. The standard allows for changes to the 
service plan including the integration of HCMT rolling stock and proposed 
service level changes. The majority of the traction power network does not 
comply with the new standard. 
The LXRP business case is based on maintaining existing network capacity. 
LXRP provides for the removal and replacement of overhead systems and 
associated infrastructure only where the removal requires new track.  
New substations for future traction power requirements were specifically 
excluded from the business case cost estimates, as the LXRP is not a network 
upgrade project. 

VAGO, based on information provided by LXRA. 

MTM electrical standards—for traction power and signal power—have been in 
place since January 2015 and should have been considered when the business 
case was being developed. As the business case did not consider this electrical 
standard, unplanned scope and design changes have been necessary.  
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  43 


Cost–benefit analysis 
Although a cost–benefit analysis (CBA) is the key metric for evaluating the 
quantitative economic merit of the program, government decided to fund the 
LXRP prior to the completion of the business case.  
The LXRP’s CBA conforms to the HVHR guidelines and applies the recommended 
discount rate of 7 per cent for this type of project. Sensitivity testing which 
includes the application of a 10 per cent discount rate was also completed. 
In its appraisal, DEDJTR has quantified core benefits using an approach that 
The Victorian Integrated 
Transport Model is the  primarily relies on the Victorian Integrated Transport Model. See Appendix E for 
state’s main strategic  a summary of the core quantifiable benefits in its program appraisal. 
transport model that 
predicts changes in  Benefit–cost ratio 
overall transport demand 
and mode choice.   BCR attempts to identify the relationship between the costs and benefits of a 
project. If a project’s BCR is: 
 greater than one, it indicates that project benefits outweigh the cost  
 less than one, the project’s costs outweigh the benefits.  
Figure 2L provides a CBA summary for the three appraisal scenarios included in 
the business case.  

 
CBA summary 

7 per cent 
Scenario  Benefits  discount rate (real)  BCR 
LXRP (reference case)  Core transport system benefits  $4.7 billion  0.78 
LXRP (reference case including  Additional and wider economic  $0.7 billion  0.9 
additional and wider economic  benefits 
benefits) 
Combined appraisal (LXRA, MTP  Core transport system benefits  $14 billion  1.2 
and CPLU) 
City-shaping benefits  $3 billion   
Productivity benefits  $4 billion   
VAGO, based on information provided by LXRA. 

As shown in Figure 2L, the LXRP reference case does not achieve a positive BCR 
using the standard discount rate of 7 per cent. If the BCR was updated to 
account for current program cost, assuming there are no further increases in 
benefits, this would result in a reduced BCR.  
Further, sensitivity testing identifies that if costs increase by 20 per cent, this 
will result in a BCR of only 0.65 at this discount rate.  
The cost at July 2017 stands at $8.3 billion, a 9 per cent increase on the 
$7.6 billion in the business case. Given the LXRP has only removed 10 crossings 
to date, with five years still remaining and more complex crossings to remove, 
there is a real risk of further cost increases.  

44  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


A BCR of 0.9 is achieved when wider economic benefits are included with the 
reference case. However, DTF guidelines recommend excluding wider economic 
benefits from the BCR calculation while appraising projects. 
A positive BCR is only achieved for the combined appraisal, which includes the 
total sum of benefits from all major rail projects—CPLU and the MTP—not just 
the LXRP.  
DEDJTR’s rationale for using this approach is that these projects are 
interdependent, and the CPLU and MTP assume delivery of the LXRP. Therefore, 
the projects were combined to look at the city-shaping benefits. This is a 
reasonable approach as these are not mutually exclusive projects.  
DEDJTR engaged a third party to peer review the economic evaluation of the 
LXRP business case. A report was prepared which concluded that, overall, the 
approaches as described in the economic evaluation appear appropriate for the 
economic assessment of the LXRP.  

TfV and LXRA should develop a robust selection and prioritisation process for 
Strategic  future level crossing removals so that the rationale for selecting sites is 
planning for future  transparent.  
prioritisation  Infrastructure Victoria’s 30-year infrastructure strategy recommends that the 
government develop a transparent prioritisation process within five years for 
the targeted removal of level crossings beyond its current commitments. It also 
recommends that this process should build on work already completed by 
VicRoads and consider desired land use outcomes, including supporting major 
employment centres. 

Activity to date 
TfV is leading a planning study to identify potential future level crossing 
removals as part of it network planning function. This study will: 
 identify a list of initial priority sites for government to consider for early 
removal in conjunction with the current committed program  
 provide program options for government to identify future level crossing 
removals. 
The study will also consider the links to other planned network investments and 
how these may offer opportunities to package them with the level crossing 
removals. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  45 


Figure 2M shows the criteria TfV has developed to identify initial potential sites.  

 
Criteria for identifying initial sites 

Adjacency  The site is adjacent to, and affects, an existing LXRP 
site. 

Major need  The site will have very significant impacts on 
congestion or safety, taking into consideration rail 
service increases that have been enabled by other 
projects that are being implemented. 

Efficiency  There may be significant cost efficiencies that could 
opportunity  be realised by delivering the level crossing removal in 
conjunction with an existing LXRP site. 
VAGO, based on information provided by TfV. 

Potential sites must satisfy the criteria in Figure 2M before moving to the 
program options assessment phase. TfV has also developed criteria for this 
phase as shown in Figure 2N. 

 
Criteria for identifying program options 

Movement  Amount of traffic (current and future), level crossing 
boom gate closure times, the type of movements and 
traffic using each crossing, train frequencies (current 
and future) and strategic network considerations. 

Safety  Safety risk ratings (ALCAM) and incident records 
(fatalities, serious injuries, near misses). 

Place  Activity areas, urban renewal and growth precincts, 
community services and facilities, station access, 
pedestrians, cyclists and emergency services. 

Deliverability  Cost, risk and packaging (considering rail occupations, 
site adjacency, disruption and likely procurement 
efficiencies). 
VAGO, based on information provided by TfV. 

While initial planning demonstrates TfV is working towards developing 
criteria and a methodology to test sites, it is not evident if there will be a 
criteria weighting system so that site assessment is objective and transparent. 
Nor is it clear how TfV plans to determine which sites to test.  
   

46  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Procurement and delivery
Infrastructure project delivery should balance the control of project cost and 
risk against achieving objectives and outcomes. It also requires agencies to 
consider which delivery methods are available and best suited to achieve 
economic and efficient delivery. 

The need for LXRA to meet the government’s committed time frame for the 
Conclusion  LXRP has had an impact on procurement, packaging and sequencing. Although 
the use of partial price competition saves time, it removes competitive tension 
and, if not adequately managed, the LXRP is at risk of not maximising value for 
money. It is too early to tell if LXRA is successfully mitigating this risk because 
not all of its risk mitigation tools are fully developed.  
LXRA has prioritised the removal of level crossings that had greater preparatory 
work completed and less complex design solutions. This has brought forward 
some removals, and LXRA now intends to exceed the target of 20 removals by 
2018. The remaining crossings are more complex and potentially more 
challenging to complete within the allocated time frame and budget. 

LXRP sites are grouped into packages for tender. Traditional design and 
Delivery  construct contracts are being used to procure two sites and alliance contracts 
models  for all others. 

Alliance contracting 
The alliance contracting model involves a state agency (the owner) working 
collaboratively with private sector parties, or non-owner participants (NOP), to 
deliver a project. It requires parties to work together in good faith, act with 
integrity and make decisions that are best for the project as a collaborative 
team.  
The key difference between a traditional contract model and an alliance 
contract model is the allocation of risk. In traditional contract arrangements, 
parties allocate risk to the party best able to deal with it. In contrast, parties to 
an alliance contract share responsibility for managing all project risks.  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  47 


Alliance contracting is useful when a project has risks that owners cannot 
adequately define prior to commencement. The flexibility of the alliance model 
allows parties to deal with new risks as they arise, rather than seek contract 
variations.  
There are three main approaches to pricing in alliance contracts: 
 Competitive alliances (or full price competition)—where two or more 
A target outturn cost is 
shortlisted parties develop competing target outturn costs. According to the 
the estimated actual cost 
of designing, constructing  National Alliance Contracting Guidelines (NACG)—which Victoria has 
and delivering the project.  adopted as its alliance contracting policy—owners should consider full price 
competition as the default pricing position for any alliance. 
 Partial price competition—where shortlisted parties only develop pricing for 
some elements of the target outturn cost. The sole successful party then 
prices the remaining target outturn cost elements alongside the owner.  
 Non-price competition—where owners select private sector parties using 
non-price selection criteria only, such as team capability and experience. 
Figure 3A shows the contract and pricing models used by LXRA and VicRoads for 
each package. 

 
Contract and pricing model for LXRP delivery 

Package   Sites    Contractual and pricing model   Awarded by 


Package 1   4    Competitive alliance for all sites  VicRoads 
Package 2   4    Competitive alliance for all sites  VicRoads 
Package 3—CTD   9    Competitive alliance for all sites  LXRA 
Package 4   2    Competitive alliance for all sites  VicRoads 
Melton Highway  1    Design and construct   LXRA 
Thompsons Road   1    Design and construct as part of VicRoads duplication of  VicRoads 
Thompsons Road 
North Eastern package   4    Partial price competition alliance for all sites  LXRA 
North Western package   6    Competitive alliance for initial two sites; partial price  LXRA 
competition for additional four sites 
Western package   6    Competitive alliance for initial one site; partial price  LXRA 
competition for additional five sites 
Southern package   9    Competitive alliance for initial four sites; partial price  LXRA 
competition for additional five sites 
Unallocated level crossings   6    LXRA to award these sites using partial price competition  LXRA 
to existing alliances dependent on performance 
VAGO, based on information provided by LXRA. 

48  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Partial price competition  
Partial price competition contracts remove an element of competitive tension 
from the tendering process. This can restrict an agency’s ability to achieve value 
for money and can limit innovation in design and construction solutions.  
To date, LXRA has used partial price competition to award two sites, both in the 
North Eastern package. At the completion of the LXRP, LXRA will have used 
partial price competition for 24 of the 52 level crossings. 
Despite the NACG preferring competition as a default condition for alliances, 
they permit the use of partial price competition in alliances in some 
circumstances. However, the guidelines also state that agencies should seek an 
exemption before proceeding with a non-competitive or partially competitive 
alliance.  

LXRA advised that exemptions were unnecessary as government approved each 
procurement strategy and, in compliance with this approval, LXRA put in place 
performance and benchmarking frameworks for comparing price and 
productivity efficiencies.  
North Eastern package  
The North Eastern package is the only package where LXRA will use only partial 
price competition. 
The rationale for this decision was the need to fast track procurement for the 
North Eastern package to meet the government’s commitments to remove 
20 level crossings and duplicate the Hurstbridge line by 2018.  
This is not consistent with the NACG. The need to accelerate procurement—in 
most situations—does not justify using partial price competition. The exception 
is a rare situation where the community needs construction to commence 
immediately. LXRA has not argued that there is a need for immediate 
commencement of the North Eastern package.  
LXRA’s view is that the NACG does not apply as the LXRP time frame came from 
a government direction. However, LXRA is ultimately responsible for advising 
the government on the appropriateness of procurement strategies, including 
whether they align with state policy.  
In addition to meeting committed time frames, LXRA advised that partial price 
competition presents other benefits to the project as it: 
 secures resources prior to a market activity peak across Australia in  
2019–22 
 enables concurrent stakeholder consultation and constructor involvement 
in options assessment. 
However, these benefits also apply to other alliances where LXRA procured the 
initial sites using full price competition. Over the life of the package, LXRA 
should monitor, report on and commission an independent evaluation on 
whether partial price competition has achieved value for money and delivered 
on the benefits stated above.  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  49 


LXRA devised a contract structure that allows it to defer pricing on some 
Contract  crossing removal sites for the North Eastern, North Western, Western and 
structure  Southern packages.  
Parties competitively bid for the initial work package, which can include one to 
four sites. If LXRA is satisfied with the alliance’s performance in delivering the 
first site’s works, it will then ask the alliance to develop a formal proposal for the 
additional sites in that package.  
LXRA may approach other alliances or the wider market to deliver the additional 
works if it is not satisfied with the alliance’s performance or proposal.  
Appendix F shows the initial and additional works for each package. There are at 
least two sites in each package that LXRA will allocate to an alliance without full 
price competition. 

Benefits of the contract structure  
LXRA chose this contract structure based on lessons learned during VicRoads’ 
extended procurement process for early LXRP packages as well as its own 
procurement of the CTD package. According to LXRA, one benefit of the 
structure is that it keeps project teams together, resulting in productivity 
improvements through the retention of staff and key knowledge and skills 
throughout the whole process. 
LXRA has identified other advantages with this contract structure, in terms of 
engagement with the private sector—particularly, that it: 
 allows LXRA to leverage contractor involvement in development and 
communications processes 
 enables contractors to lock in key resources that may be lost to other 
infrastructure projects 
 ensures stable engagement with the private sector  
 reduces tendering costs and ensures focus is on the actual delivery of works  
 allows the majority of procurement activity to be completed prior to peak 
market activity in 2019–22.  
As LXRA is yet to allocate any of the additional works to an alliance, it has not 
tested the effectiveness of its contract structure. LXRA should monitor this 
throughout the program.  

Risks of the contract structure 
LXRA’s contract structure introduces a number of risks to achieving value for 
money and on-time project delivery, primarily due to the reduced price and 
design competition. Parties may also engage in loss-leading behaviours in initial 
tendering in order to secure the larger package of works. 
   

50  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


DTF and DPC advice to government also identified potential risks:  
 the selected party for the initial sites may have an incumbency advantage 
when seeking the additional sites, due to existing knowledge, experience 
and stakeholder relationships  
 LXRA may need to return to the market if the selected proponent performs 
poorly on the initial site(s), leading to significant program delay—this is 
particularly the case with the Western program alliance which has only one 
site in the initial works package. 
These risks are compounded in the North Eastern package, where LXRA did not 
use full price competition to procure a proponent for the initial sites. 
Acknowledging these risks, LXRA is developing mitigation tools, as outlined in 
Section 3.4. 

LXRA is using benchmarking and commercial frameworks to manage the risks of 
Management  partial price competition and the contract structure.  
of procurement 
risks  Benchmarking framework 
LXRA’s benchmarking framework includes a tool for comparing price and 
productivity efficiencies across the program alliances and allows LXRA to 
consider whether a proposal achieves value for money.  
The benchmarking tool contains a detailed breakdown of costs for each level 
crossing removal in the program, as well as for some previously completed 
removals. Where a project has not been completed or awarded, LXRA bases the 
data on the business case cost estimate for that site. Data compiled in the tool 
includes direct job costs such as signalling and landscaping, as well as design 
and occupation costs.  
LXRA also collates cost data according to grade separation type—for example, 
rail under road—which enables it to develop and compare cost profiles for each 
type of grade separation. This is an essential step as the type of grade 
separation is a strong factor in determining the overall cost of a removal.  
When LXRA awards contracts or completes level crossing removals, it replaces 
estimates in the tool with contracted or actual costs. Therefore, as the program 
continues, the tool will become more accurate and will provide a more 
adequate control for procurement cost risks. 
LXRA also uses an independent estimator to confirm that proponents have 
priced their target outturn costs competitively and that they adequately reflect 
the scope of work.  
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  51 


Limited application of benchmarking tool 
To date, LXRA has only applied the benchmarking tool for the North Eastern 
Program Alliance.  
Government approved the procurement strategy for this package in May 2016, 
subject to the Treasurer’s approval of a strong performance and benchmarking 
regime. LXRA selected the preferred party for this package in August 2016. The 
Treasurer only formally approved the benchmarking framework in 
December 2016, shortly before approving the award of the contract in 
January 2017. The short time frame between approval of the tool and the award 
of the contract indicates that LXRA relied on the tool to mitigate procurement 
risks prior to its formal approval. LXRA advised that DTF had viewed the tool and 
informally approved its use prior to the Treasurer’s formal approval. 
LXRA has advised that it will use the benchmarking tool when assessing future 
proposals for additional works as a way to overcome the risks of a 
non-competitive process. It is therefore important that LXRA continues to 
update the tool with actual cost data as it becomes available and integrate it 
into future procurements.  
While the benchmarking tool has the potential to allow LXRA to monitor value 
for money, it cannot, on its own, drive innovation in design and construction 
solutions. LXRA uses the commercial frameworks of its alliances to motivate 
NOPs to find innovative construction and design solutions. 

Commercial frameworks 
LXRA is using the commercial framework of its alliance agreements to mitigate 
the risks of its procurement strategy. The commercial framework sets out the 
structure and principles that govern remuneration for the project. It includes 
the following three main elements: 
 reimbursable costs—NOPs’ actual direct project costs 
 corporate overhead and profit 
 a risk and reward regime.  

Direct costs, corporate overhead and profit 
LXRA sets some financial elements for all of its alliances using full price 
competition. This is what makes LXRA’s alliances—excluding CTD—partially 
competitive rather than non-competitive. These elements serve as a control for 
the risks of LXRA’s deferred pricing contract structure. The largest element set 
this way is corporate overhead and profit.  
When awarding the initial works packages, LXRA locks in overhead and profit for 
all remaining sites in the package. Overhead and profit as a percentage of direct 
job costs is lower for awarded packages using the deferred pricing model than 
for the initial four alliances that did not use this model.  

52  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


This could demonstrate that LXRA’s model is effectively engaging the market, 
ensuring a steady pipeline of work that allows proponents to lower 
procurement costs. However, there is a risk that parties have bid low on 
overhead and profit with the expectation of increased direct job costs on later 
sites. This highlights the need for LXRA to continue to update and apply the 
benchmarking tool to effectively assess its proposals. 

Risk and reward regimes 
A risk and reward regime sets out the owner and NOPs’ share of the ‘pain or 
gain’ outcome of the project. This involves comparing actual and target 
performance in both cost and non-cost areas.  
In terms of cost, parties essentially share in the cost underrun (gain share) or 
overrun (pain share) of a project.  
All of LXRA’s alliance contracts cap NOP pain share—the amount the NOP would 
have to pay in the event of a cost overrun. This is standard practice in alliance 
contracting. However, the NACG notes that owners should be cautious of such 
caps. When the overrun exceeds the cap, the state effectively bears all project 
risk beyond a certain point. This unequal risk exposure can put pressure on 
collaborative alliance principles such as best-for-project decision-making.  
NACG recommends that owners consider placing a reciprocal cap on the 
amount NOPs can receive for a cost underrun. This helps to alleviate concerns 
about the potential for NOPs to earn large profits.  
LXRA applied a cap on pain share to three of its works packages. However, there 
is no reciprocal cap on gain share for CTD. Packages 1, 2 and 4, awarded by 
VicRoads, also do not have a cap on gain share. 

For non-cost areas, the regime includes financial incentives for strong 
performance and penalties for poor performance. A risk and reward regime is a 
key element of the collaborative nature of alliances.  
LXRA’s risk and reward regimes are generally in line with NACG. Although the 
regime is slightly different for each package of works, each one includes a clear 
method of calculating performance. LXRA uses its risk and reward regimes to 
motivate strong performance in areas such as safety, minimising passenger 
disruptions, continuous improvement and stakeholder management. This 
mitigates the risks introduced by partial price competition.  
LXRA intends to use its risk and reward regimes to measure alliance 
performance during project delivery. In particular, LXRA intends to apply a ‘track 
record’ test to determine whether an alliance has performed well enough to 
merit allocation of additional sites within the package. The track record test 
assesses alliance performance against KPIs, package cost risk or reward regime, 
and any other measures LXRA deems necessary to assess performance.  
If LXRA applies this consistently, it will mitigate the risk of parties having an 
incumbency advantage when seeking further sites. 

   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  53 


Packaging 
Packaging and 
sequencing  Dividing the LXRP into packages of work is beneficial for LXRA as it can match 
level crossing removals to rail capacity investments, road projects or other 
of works 
works. Packaging also provides a more predictable pipeline of work for industry.  
LXRA estimated that packaging level crossing removals, as opposed to 
individually removing them, would save approximately $400 million across the 
program.  

Packaging options 
The LXRP business case considered two options for packaging the remaining 
301 level crossing removals, namely: 
 a corridor approach—in which crossing sites along rail corridors are 
packaged together 
 a discipline-based approach—where similar work types are packaged 
together (such as stations, power, signalling, and rail track).  
LXRA’s evaluation of these two options emphasised that time, management of 
disruptions and risk management were important considerations. LXRA 
ultimately determined that the corridor approach better matched the LXRP’s 
objectives.  
The business case also considered the number of crossings in work packages. 
Analysis of previous procurement processes found larger package sizes could 
result in savings as they provide efficiencies with staff, site facilities, design, 
occupation and direct costs. LXRA balanced these potential savings from larger 
package sizes with market participation and capacity limitations to facilitate 
competition for packages.  

Packages of work 
Of the 52 level crossing removal sites, eight packages contain between two 
and nine level crossings and two packages have one crossing each. There are 
six crossings that LXRA has not yet allocated to a package.  
Figure 3B shows that the LXRP has packaged the majority of crossings according 
to their rail corridor location. 

                                                                 
1 The business case was completed prior to the addition of the two extra crossings. 

54  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


 
Level crossing removal packages 

Key:  Melton Highway,  North Eastern,  North Western,  Southern,  Western,  Package 1,  Package 2,  Package 3,
 Package 4,  Thompsons Road,  Unallocated.
Source: VAGO, based on information provided by LXRA.

LXRA has not packaged three crossings within the relevant corridor:
 Abbotts Road, Dandenong South—Western package
 Toorak Road, Kooyong—unallocated ‘package’, yet in close proximity to, and
on the same line as, Burke Road, Glen Iris (Package 1)
 Skye Road, Frankston—North Western package.
The level crossing at Skye Road was initially part of the Frankston package,
consistent with the corridor approach. However, following a decision to
accelerate the removal of this level crossing, LXRA moved it to another
alliance—North Western package—as described in Figure 3C.

Victorian Auditor-General’s Report  Managing the Level Crossing Removal Program 55


 
Case study: Acceleration of Skye Road crossing removal 

Skye Road is the most southern crossing on the Frankston line in the LXRP. 
While it was in the top 50 most dangerous metropolitan crossings on the 
ALCAM 2008 list, VicRoads rated it as no priority in its 2013 list and it was 
not on RACV’s 2013 priority list.  
LXRA initially listed this crossing as part of the Frankston package—later 
renamed the Southern package—as additional work.  
In December 2016, LXRA provided advice to government on accelerating the 
removal of the Skye Road crossing by moving it to the North Western 
package, as initial work. Advice to government emphasised the benefits of 
acceleration, and stated that the change would achieve a value-for-money 
outcome for the state. However, it did not include the expected acceleration 
cost, relative priority for removal, or disadvantages of accelerating the 
removal. 
LXRA advised that the main benefit achieved would be to bring forward the 
commencement of the removal by one year, from mid-2018 to mid-2017. 
LXRA also advised the benefits would include saving escalation costs and 
assisting delivery of its most difficult and complex package. 
Both the Southern package and the North Western package are using a 
competitive alliance for the initial sites, with additional sites dependent on 
the alliance’s performance.  
DTF initially advised government against accelerating the removal of 
Skye Road. It considered the acceleration was rushed and warned that it 
may increase the cost and complexity of the North Western package. At 
DTF’s request, LXRA provided documentation showing the capacity of the 
North Western package to undertake the additional work. DTF subsequently 
approved the acceleration. 
Prior to receipt of this documentation, government decided to proceed and 
moved responsibility to the North Western Alliance. In March 2017, LXRA 
estimated that this cost an additional $11 million, due to a reduction in 
anticipated program efficiencies. 

VAGO, based on information provided by LXRA. 

Compared with other crossings in the Southern package, Skye Road is the 
easiest to progress as the community supports the reference option in the 
business case. While $11 million in additional costs is not material in the context 
of the whole LXRP, accelerating its removal by moving responsibility to the 
North Western Alliance helps LXRA to meet the government’s committed target 
of removing 20 level crossings by 2018.  
Inclusion of additional level crossing sites 
The pre-determined selection of level crossings affects packaging. As stated 
previously, the government added two level crossings to the LXRP, due to their 
adjacency to other LXRP works. This indicates that the LXRP could have gained 
efficiencies by considering level crossings that are outside the 50 selected.  

56  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Figures 3D and 3E present alternative packaging options for the Frankston and 
Craigieburn lines.  
In the 7.5-kilometre stretch of the Frankston rail line between Edithvale Road 
and Station Street, Seaford, there are 10 level crossings. The LXRP will remove 
five of these, leaving five in place. 
Also on the Frankston line—in the 1.9-kilometre stretch between Neerim Road 
and North Road—there are three level crossings. The LXRP has removed 
North Road. Glen Huntly Road level crossing is 1.6 kilometres from North Road 
and the Neerim Road level crossing is less than 300 metres away. Neither of 
these are part of the LXRP. 

 
Alternative packaging options—Frankston line 

 
Distances listed are from the first to last crossing. 
VAGO, based on research by Stone and Woodcock.  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  57 


On the Craigieburn line, LXRA will remove Buckley Street as part of the LXRP. 
However, two level crossings in close proximity are not part of the program for 
removal. The Park Street level crossing is 550 metres away and Puckle Street is 
1.1 kilometres away, as shown in Figure 3E. 

 
Alternative packaging options—Craigieburn line 

 
The distance shown is between the Buckley Street and Puckle Street crossings. 
VAGO, based on information provided by TfV. 

TfV is currently leading the development of the methodology for selecting 
further level crossings for removal, so neither LXRA nor TfV could advise us of 
whether or how crossings such as those listed above will be incorporated in 
future removal packages. 

Sequencing 
Sequencing refers to the order in which removals occur, both within packages 
and across the whole LXRP.  
Sequencing of all transport infrastructure projects currently underway—
including the LXRP—needs effective management to ensure expertise and 
resources are available, and to minimise the impact on the community.  

Sequencing of LXRP works 
Meeting the government’s commitment to deliver 20 crossing removals by  
mid-2018 is a determining factor in the sequencing of crossing removals. 
When planning the delivery of crossing removals, LXRA also considered: 
 the large volume of rail projects in Victoria and New South Wales between 
2016 and 2025, including MTP, CPLU, Sydney metro expansions and 
New South Wales light rail projects 
 maintaining flexibility in the procurement and delivery of crossings 
 government announcements about the timing of individual crossing 
removals 
 the extent of preparatory works that were complete for each crossing 
 whether the design solution was known, and its complexity. 

58  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


LXRA did not analyse which crossings had the highest priority for removal, from 
a safety or rail efficiency perspective, to inform the sequencing of crossing 
removals. LXRA advised that instead, the packaging of works drove sequencing 
decisions. This meant that crossings that were already progressed enough to be 
put to tender became the initial works within a package and were removed first. 
LXRA implemented the sequencing of works through the request for proposal of 
each package. This outlined a proposed delivery order and time frame, however, 
alliances were able to propose alternative sequencing within the package to 
optimise value for money.  

Removing level crossings involves the temporary closure of the rail line and its 
Rail  occupation to enable construction works. Minimising the impact to the 
occupations  travelling public has been an important consideration for LXRA and alliance 
members.  

Types of occupations 
There have been two types of rail track occupations:  
 major works—longer track occupations which result in larger disruptions 
and often require alternative transport services for the travelling public  
 minor works—short-term use of the track, with less disruption, where 
occupations usually happen after the last train has run and before the first 
train the following morning, or single weekend day works.  
At July 2017, there were 95 major and 257 minor occupations planned, of which 
around 51 per cent and 56 per cent respectively have been completed, as 
shown in Figure 3F. 

 
Occupations 

Minor
143 114 257
occupations

Major
48 47 95
occupations

0 50 100 150 200 250 300


Occupations
Completed occupations Planned occupations
 
VAGO, based on information provided by LXRA. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  59 


At September 2017, the longest major occupation was 42 days and the longest 
planned occupation is 83 days.  

Planning for occupations 
During the request for proposal stage, alliances are responsible for proposing 
the number, type and length of occupations that will best deliver their program 
of works. If LXRA deems that the proposed occupation schedule is not 
acceptable, it seeks to resolve its concerns with the appointed alliance. 
Planning for major occupations commences at least six months before the 
proposed occupation. As the rail line operator, MTM is the ultimate approver of 
rail occupations. If planning documents do not meet its requirements, or the 
occupation is not likely to cease on the agreed day and time, MTM may 
postpone or cancel the planned occupation.  
At July 2017, the alliances did not complete around 3 per cent—three 
occupations—of total major occupations as planned. Two of these delays were 
less than one hour, and the third was one day late. The small number of late 
completions is a good result, and evidence of sound occupation planning and 
management. 
Alternative transport provision 
The majority of major occupations, and some minor occupations, require 
alternative transport, usually through bus replacements.  
PTV, LXRA, MTM and VicRoads notify public transport users of planned service 
disruptions and bus replacement services well in advance through public 
transport websites, social media and notifications at train stations and tram 
stops.  
 
 
   

60  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Intended benefits
The intended benefits of the LXRP are diverse and include those generally 
recognised for transport projects—specifically, improvements to safety and 
travel, stimulating economic growth, revitalising local communities, and 
facilitating more trains running more often. 

As completion of the LXRP is not due until 2022—with only 10 of 52 crossings 
Conclusion 
removed—there is insufficient data at present to make an informed judgement 
on the extent to which it is achieving intended outcomes. Additionally, while 
LXRA has developed KPIs and targets, some of these are not meaningful. 
Without these, LXRA cannot assess the extent to which the program is achieving 
intended outcomes.  

DEDJTR has developed a benefits management framework in accordance with 
Benefits  DTF requirements.  
management  The framework includes an investment logic map, benefit map and benefit 
framework  management plan. These were developed from a series of workshops, which 
included consideration of the problem and benefits, and knowledge from 
previous level crossing removal projects and other related programs.  
DEDJTR circulated the investment logic map, benefit map and benefit 
management plan to stakeholders from various government departments for 
comment. 
The following high-level benefits have been identified for the LXRP: 
 Improved productivity from more reliable and efficient transport 
networks—addressing the congestion and delays caused by level crossings 
will improve the efficiency of Melbourne’s transport networks. 
 Better connected, liveable and thriving communities—removal of level 
crossings will reduce delays and increase the attractiveness of living and 
investing in areas surrounding the crossings. 
 Safer communities—removing rail and road intersections will eliminate the 
conflict points between trains and road users, and trains and pedestrians, 
reducing the number of crashes.  

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  61 


DEDJTR developed KPIs and targets to measure the delivery of these benefits. 
LXRA is responsible for monitoring the achievement of performance targets and 
for actions required to improve any area where the target is not achieved. 
LXRP’s benefits framework has limited outcomes reporting—due to the lack of 
comprehensive indicators and targets—and needs improvement. The benefits 
framework is outlined in Appendix G.  

KPIs, targets and reporting 
KPIs and targets specified in the benefit management plan are not 
comprehensive, in that they only require an ‘improvement’—for example:  
 100 per cent of sites with road based public transport will have improved 
punctuality 
 100 per cent of sites will have improved access to local activity centres and 
major services. 
These targets would be realised with any level crossing removal. 
LXRA advised us that it deliberately set targets in this way because factors other 
than the crossing removal can affect outcomes. Given this, the KPIs themselves 
are unlikely to be suitable measures. 
LXRA should still monitor its performance against intended benefits so that it 
can meaningfully report on the contribution the LXRP is making in achieving 
outcomes.  
The business case indicates that the principal transport benefits from the LXRP 
are changes in journey times for private, business and freight vehicles across 
Melbourne’s road network.  
The business case indicates that LXRA will measure and report for the whole 
program, although it will collect some measures and KPIs for individual 
packages. For the CTD rail corridor project, LXRA will prepare a benefits 
management plan for the entire corridor rather than for individual crossings.  
LXRA advised that when the removal program is completed, it intends to  
‘roll up’ individual benefits reports into a holistic program report. In doing so, 
LXRA will have limited timely insight into how LXRP as a whole is progressing 
towards benefits realisation.  
LXRA has quantified journey times as travel time savings, included in its CBA as a 
core benefit. LXRA should use these and other CBA core quantified benefits as 
KPIs, and measure and report on these core transport benefits consistent with 
the business case. See Appendix E for the value of core quantifiable benefits.  

Progress towards benefit realisation  
LXRA prepared draft benefit reports for four sites that show the impact of 
crossing removals as at March 2017—Burke Road, Centre Road, McKinnon Road 
and North Road. Three sites, excluding McKinnon Road, have seven KPIs with 
available data. Data is available for only one KPI for McKinnon Road. None of the 
sites have met all seven KPIs.  

62  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


LXRA acknowledges that the draft benefit reports do not provide meaningful 
information about the extent of improvement and whether the progress results 
are in line with expectations.  
LXRA makes a judgement on KPI data it compiles such as travel times, vehicle 
speeds, physical pedestrian counts, cyclists and community surveys. Where the 
data indicates benefits are not tracking as expected, LXRA considers whether it 
should take corrective action. However, LXRA does not document its assessment 
of the data. 
Benefit reports would be more meaningful if they included commentary to 
interpret the results. For example, if travel time in the morning peak reduced by 
1.9 minutes, commentary on whether these results are positive or otherwise 
should be included.  
Figure 4A provides examples of KPI targets that level crossing removals have 
met or not met. 

 
Examples of KPI targets 

Target   Result  
Average travel time   Met for Burke Road, Centre Road and 
reduced   North Road 
 Not met for McKinnon Road 
Vehicle throughput   Met for Burke Road, Centre Road and 
increased  North Road  
 Partly met for McKinnon Road 
Travel time reliability   Met for Centre Road and North Road  
improved   Partly met for Burke Road 
 Not met for McKinnon Road 
No new safety incidents   No data available 
VAGO, based on information provided by LXRA. 

Data is not yet available for a number of KPIs. These include: 
 community satisfaction with local amenity following crossing removal  
 IDOs 
 public transport intermodal connectivity  
 reduced number of safety incidents and improved ALCAM risk score.  
Overall, the reports for the four crossings indicate that benefits realised to date 
are below expectations. Further, without specific targets, it is not known if the 
extent of improvement, where achieved, is in line with expected outcomes. 

 
 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  63 


LXRA has developed a comprehensive plan aimed at maximising value-capture 
Maximising  opportunities through the LXRP. 
value-capture  Value capture is the act of collecting a portion of the benefits from public 
opportunities  infrastructure investments that flow to the value of land. Government can then 
use that value to pay for a portion of the corresponding infrastructure 
investment.  
For the LXRP, value capture is limited to IDOs. For example, railway land that 
An integrated 
becomes surplus to requirements through a grade separation may, with some 
development 
opportunity (IDO) refers  enabling works by LXRA, be suitable for sale to the private sector to develop. 
to the value created  IDOs can also include broader social benefits such as social housing, community 
through infrastructure  services and open spaces. 
and land development 
that occurs when  LXRA released an IDO strategy in December 2015. It provides guidance on 
removing the level  identifying IDOs, potential benefits and how benefits can be realised.  
crossing.  
Implementing the strategy involves the following key activities: 
 establishing an experienced multidisciplinary team to optimise value capture 
 developing an appropriate planning approval process focused on project 
planning and design, to increase certainty and improve value-capture 
opportunities 
 identifying entrepreneurial commercial and development opportunities that 
are scoped against market appetite for investment and risk taking—the 
identification of development opportunities is done using project proposals 
and the procurement process, rather than through program-level planning.  

Monitoring IDOs 
LXRA’s ongoing monitoring of IDO projects is timely and comprehensive. It 
produces monthly IDO dashboard reports that provide a high-level 
comprehensive summary of the status of each level crossing site against project 
milestones. The report includes:  
 gross and net revenue forecasts for the state from the sale of developed 
land 
 costs incurred by the state to facilitate IDOs 
 the type and number of residential and commercial properties proposed to 
be developed.  
At March 2017, LXRA had identified 26 possible IDO sites estimated to provide a 
net return to the state of $153 million. This includes $271 million from property 
sales less $118 million for development enabling works, such as site preparation 
works.  
   

64  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


The Coordinator-General has signed the development contract for one site, 
24 sites are under consideration and one site is not proceeding. LXRA expects 
completion of the first IDO site in March 2021 and the last in September 2027. 
While LXRA aims to recover the enabling costs it incurs at each site, it does not 
have a specific net revenue return target. 
LXRA’s inability to get stakeholders to reach agreement on property 
developments is delaying the timely realisation of IDOs, particularly on more 
contentious developments, such as high-rise apartments or office towers.  
This lack of agreement delays government approval of the development scope 
and subsequent property development agreement. This means that despite the 
alliance completing the level crossing removal and enabling works for the IDO, 
construction cannot start even though LXRA has engaged a developer. 
LXRA also acknowledges the estimated return to the state may reduce if there is 
significant community opposition to the proposed development or the cost of 
enabling works becomes excessive.  

Maintenance of open space 
Responsibility for maintenance of community open space, such as parklands, 
created through an IDO project is yet to be resolved.  
Although LXRA meets the cost of developing the land into open space, its 
crossing removal budget does not extend to meeting the ongoing maintenance 
costs. LXRA has advised that VicTrack—the owner of the railway land—and the 
local councils—whose municipality the open space belongs to—have not yet 
reached agreement for the ongoing maintenance of the area. VicTrack advised 
that it could manage this activity if funding was provided to do so.  
In April 2016, LXRA put forward a proposal to government for a $15 million 
open space maintenance account created through the CTD project. DPC and DTF 
questioned the establishment, management and maintenance of the account. 
As at October 2017, the proposal is still under consideration. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  65 


 

Network integration 
and integrity
The LXRP is occurring in parallel with a range of other major transport projects 
including the MTP, CPLU and HCMT projects. 
Integration between the LXRP and other major rail projects is important for 
ensuring the efficient and effective development of Melbourne’s future 
transport network—now overseen by TfV. PTV also has a major role in ensuring 
integration of all rail projects into the network.  

PTV does not have adequate resources to effectively perform its network 
Conclusion  integrity role. This has undesirable cost and scope consequences for the 
integration of the LXRP and other concurrent rail projects into the rail network. 
PTV, with support from TfV, which is now responsible for transport planning, 
will need to ensure that actions to address shortcomings are effective.  

One of PTV’s key functions, since September 2016, is to ensure network 
Oversight of  integrity—a functionally effective, reliable, maintainable, secure, safe and 
public transport  environmentally compatible public transport network. Among other things, 
network integrity  this requires PTV to: 
 understand the network’s future performance requirements 
 establish network requirements and standards 
 understand the current condition of rail assets.  
This function is particularly important for the effective delivery of the LXRP as 
part of a series of other city-changing rail projects. Specifically, PTV and TfV 
need to make sure all concurrent rail projects properly integrate with the 
existing train network and that their expected project benefits can be realised.  
PTV has not performed this role due to a lack of capability, and by not 
establishing standards or controlling risks. 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  67 


Capability gaps 
PTV commissioned an independent review in May 2016 (the May 2016 review), 
which identified that PTV had insufficient capability to perform its network 
integrity function: 
‘the network integrity role was not performed to an adequate level 
having limited resources, a focus on discrete individual projects rather 
than a “whole of network” public transport system perspective and 
insufficient governance during delivery.’ 
The May 2016 review also found a number of capability gaps existed within PTV, 
including engineering, technical safety and asset management. The review 
noted that if PTV does not address these gaps, network integrity is at significant 
risk. PTV would then not be able to demonstrate that it is effectively managing 
its portfolio of transport assets and providing long-term value for money.  

Absence of contemporary rail standards 
As part of its network integrity and assurance role, PTV is responsible for 
establishing: 
 network technical requirements—high-level technical requirements for a 
transport corridor or geographic area 
 network technical standards—derived from network technical requirements 
and used to inform and direct the development of system requirements and 
specifications, and engineering standards that AROs are required to develop.  
Neither network technical requirements nor network technical standards have 
been established—instead, Victoria operates under the industry-derived 
Victorian Rail Industry Operators Group standards. 
The May 2016 review also found that no entity has responsibility for reviewing 
the Victorian Rail Industry Operators Group standards adopted by the AROs. The 
process of updating and challenging standards to achieve a best-for-Victoria 
performance standard has not progressed effectively in recent times. 
The May 2016 review emphasised that without contemporary standards, 
agencies delivering rail projects are proceeding with varying levels of 
understanding of network requirements and of their duties to assure projects 
meet engineering, network integration and technical safety requirements.  
This poses significant risks of the new systems not being integrated into the 
current network.  
PTV has acknowledged that while it has relied on Victorian Rail Industry 
Operators Group standards, a modern public transport network requires a more 
robust and formally managed set of technical standards, including the 
establishment of appropriately controlled engineering standards.  
   

68  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


PTV has initiated action aimed at establishing appropriate engineering 
standards, with a view to replacing the Victorian Rail Industry Operators Group 
standards with the network technical standards by July 2018.  

Application of standards to the LXRP 
LXRA set project system requirements that contractors delivering the LXRP are 
required to comply with. These project system requirements are a translation of 
PTV and MTM requirements, as well as other standards and specifications. 
However, during the project system requirements process, there is scope for 
variations which, in turn, can have cost implications for projects—for example, 
an approval to not comply or partially comply may reduce project costs and 
time lines.  
MTM, the ARO in the metropolitan area, manages the approval processes for 
changes to its engineering standards and their interpretation. This can occur 
using either a:  
 standard waiver—a mechanism to assess, document and approve any 
deviation from current endorsed standards applicable to maintain, upgrade, 
renew, build and commission MTM assets 
 design practice note—an instruction issued by MTM on how to interpret, or 
to clarify a standard or practice, which is then applicable to that standard 
for the entire network.  
However, PTV agrees that as MTM has limited insight into network‐level 
requirements, including future developments, there is a risk that these 
decisions can affect other transport projects.  
Furthermore, as MTM is also a member of all of the LXRP alliances, there is a 
perceived conflict of interest. MTM is both part of the project development 
team applying for a standard waiver and part of the organisation making 
decisions on variation requests. 
LXRA and PTV have both advised that MTM’s standard waiver process mitigates 
the risk of the perceived conflict occurring, as the process is managed through a 
different part of the organisation than the one that is involved with the project. 
The Office of the National Rail Safety Regulator is also an important control. 
MTM is accountable to the Office of the National Rail Safety Regulator, requiring 
it to conform to correct processes in granting waivers; otherwise, its 
accreditation is at risk. 
While the Office of the National Rail Safety Regulator would consider processes 
for granting standard waivers, it would not necessarily look at the process of 
developing design practice notes. To mitigate this and other network integrity 
risks, PTV has introduced a number of controls. 
   

Victorian Auditor‐General’s Report  Managing the Level Crossing Removal Program  69 


Controls for network integrity risks 
PTV has established a number of arrangements to improve oversight of and 
accountability over how it manages network integrity risks. These include a 
network integrity governance framework, as shown in Figure 5A.  

 
Network integrity governance framework 
 

Network Asset Configuration 
and Assurance Committee 

Network Integrity  Network Operations 
Working Group  Working Group

 Network technical standards   Network performance requirements
 Current network configuration   Network concept of operations
 Client requirement document  Operational modelling governance
 
VAGO, based on information provided by PTV. 

In November 2016, PTV established the Network Asset Configuration and 
Assurance Committee to provide: 
 integrated advice on network planning and development 
 assurance that the capital program is aligned to network technical 
requirements and network technical standards 
 assurance that the existing network is ready to receive planned investments. 
The Network Asset Configuration and Assurance Committee also approves any 
proposed changes to network performance requirements. 
Two working groups support the Network Asset Configuration and Assurance 
Committee: 
 The Network Integrity Working Group—established in February 2017, 
includes representatives from PTV, MTM, TfV, VicTrack, V/Line and Yarra 
Trams. It is accountable for the technical integrity of the public transport 
network system and assets, including: 
 approving interpretation of network standards 
 approving all standard waivers specific to a project  
 reviewing risks, assumptions, issues and opportunities that will have an 
impact on the integrity of the network, including future proofing.  
 The Network Operations Working Group—provides advice on public 
transport network capability and performance. 
   

70  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


In addition to these internal governance arrangements, PTV also added a 
formalised standards governance process in the new franchise agreement with 
MTM, beginning on 30 November 2017. This includes the planned 
establishment, in January 2018, of a standards governance group comprising 
senior representatives from PTV and MTM that will review and approve:  
 any proposed changes to network standards 
 any proposed new standards  
 any processes to be adopted relating to the assessment or acceptance of any 
MTM noncompliance with a standard. 
PTV’s introduction of these additional controls to improve its network integrity 
function is happening in parallel with the delivery of a number of important 
transport projects. It is therefore important for PTV, and TfV, to closely monitor 
the effectiveness of these new arrangements, particularly for programs such as 
the LXRP, which is well underway.  
Network development plan 
PTV developed a network development plan for metropolitan rail in 2012, which 
sets out the future state of the rail network. PTV has not revised this plan. 
TfV has indicated that it is developing a rail network development plan to 
replace PTV’s 2012 plan. The LXRP business case refers to PTV’s plan. 
LXRA’s report to the MTIP board in April 2017 stated that:  
‘TfV currently does not have an agreed baseline for the performance 
of the metropolitan rail network (e.g. trains per hour, power 
requirements), no comprehensive assessment of the condition of rail 
assets and no agreed plan for the future state of the network.’  
Until TfV develops and approves an updated plan, there is a risk that LXRA may 
need to vary or redo works associated with the current crossing removals.  

Poor network integrity has already contributed to cost increases for some rail 
Cost  projects, such as those along the Cranbourne Pakenham rail corridor that 
implications of  include the HCMT, CTD and the MTP.  
poor network  In March 2017, PTV predicted that the long lead times of projects in the CPLU 
integrity  program would necessitate parallel development and delivery to meet key 
delivery dates. However, detailed consideration of the appropriate network 
requirements, and their subsequent application to the projects currently in 
delivery, highlighted some scope gaps and interface management issues that 
need to be resolved.  
An indicative cost estimate for addressing these issues was $381.3 million—
$158.6 million for additional work required in 2017–18 and a provision to cover 
associated risks of $222.7 million. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  71 


The successful completion of the CTD project, as well as other major transport 
projects, is critical for the successful future operation of the MTP. As PTV 
predicted, parallel development and delivery of these projects has been 
necessary to meet key delivery dates. 
As part of DTF’s HVHR project requirements, a due-diligence review on the 
interface and integration risks associated with the MTP and associated 
inter-related projects on the Sunbury to Dandenong rail corridor was 
commissioned in September 2016.  
The review noted that the LXRA, together with the Melbourne Metro Rail 
Authority, had developed interface control documents for the CTD and HCMT 
projects—including for additional works that LXRA could deliver while 
completing grade separations that would be beneficial for the HCMT.  
The review also acknowledged that while a number of issues with the 
inconsistency of network standards existed, these are dealt with through the 
MTM Engineering Standards Committee. LXRA, MTM, PTV and the Melbourne 
Metro Rail Authority attend this committee. LXRA has established a process to 
evaluate the inconsistencies against current approved project baselines. The 
outcomes are reported back to MTM and PTV. 
The April 2017 Infrastructure Coordination Committee report also stated that 
the absence of an agreed network performance plan is resulting in the 
uncoordinated inclusion of additional scope to accommodate some future 
requirements, including: 
 Camp Road futureproofing of the Somerton rail connection and future 
Campbellfield Station  
 Kororoit Creek Road power upgrade to 1 300kV  
 Aviation Road/Cherry Street upgrade to include two additional tracks on the 
Werribee Line. 
The April 2017 Infrastructure Coordination Committee report also identified 
that the uncoordinated changes to rail standards related to existing LXRA 
projects have impacts on scope, cost and time lines.  
In response, LXRA has started discussions across the MTIP and with TfV aimed at 
developing future rail standards and an interim change management control 
arrangement to enable the scope of LXRA projects to be controlled. 

Change management process 
The LXRP project steering committee, comprising LXRA, PTV, MTM, VicRoads, 
VicTrack and TfV, manages information gaps such as network performance, 
asset condition and future network requirements. 
For example, if PTV requests LXRA undertake additional works to accommodate 
possible future changes to the network, PTV needs to justify the request, 
including the cost. If the committee considers the request is not justified, it does 
not proceed. If the committee cannot reach a decision, it puts the request to 
TfV. The steering committee can make decisions on additional works’ ability to 
comply with any updated or new standards.  

72  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Without additional funding, LXRA is reluctant to approve requests for additional 
works.  
Now that TfV is responsible for setting the strategic transport direction, it 
should capture lessons from the LXRP to provide sector-wide leadership to 
transport agencies, so that future network requirements underpin planning for 
all future major transport projects.  
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  73 


Appendix A  
Audit Act 1994 section 16—
submissions and comments 
We have consulted with the DEDJTR, PTV, VicRoads and VicTrack, and we 
considered their views when reaching our audit conclusions. As required by 
section 16(3) of the Audit Act 1994, we gave a draft copy of this report to those 
agencies and asked for their submissions and comments. We also provided a 
copy of the report to DPC. 
Responsibility for the accuracy, fairness and balance of those comments rests 
solely with the agency head. 
Responses were received as follows: 
DEDJTR ................................................................................................................. 76 
PTV ....................................................................................................................... 80 
VicRoads .............................................................................................................. 83 
VicTrack ................................................................................................................ 84 
 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  75 


RESPONSE provided by the Secretary, DEDJTR 

     

76  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


RESPONSE provided by the Secretary, DEDJTR—continued 

   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  77 


RESPONSE provided by the Secretary, DEDJTR—continued  

   

78  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


RESPONSE provided by the Secretary, DEDJTR—continued 

   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  79 


RESPONSE provided by the Acting Chief Executive Officer, PTV 

   

80  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


RESPONSE provided by the Acting Chief Executive Officer, PTV—continued 

   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  81 


RESPONSE provided by the Acting Chief Executive Officer, PTV—continued 

     

82  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


RESPONSE provided by the Chief Executive Officer, VicRoads 

     

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  83 


RESPONSE provided by the Acting Chief Executive, VicTrack 

84  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Appendix B  
List of crossings for 
removal  
Figure B1 provides the list of LXRP level crossing removals. 

Figure B1  
Level crossings part of the LXRP 

1  Burke Road, Glen Iris  27 Camp Road, Campbellfield 
2  Centre Road, Bentleigh  28 Buckley Street, Essendon 
3  McKinnon Road, McKinnon  29 Glenroy Road, Glenroy 
4  North Road, Ormond  30 Bell Street, Coburg 
5  Furlong Road, St Albans  31 Moreland Road, Brunswick 
6  Main Road, St Albans  32 Kororoit Creek Road, Williamstown North 
7  Blackburn Road, Blackburn  33 Abbotts Road, Dandenong South 
8  Heatherdale Road, Mitcham  34 Aviation Road, Laverton 
9  Chandler Road, Noble Park  35 Ferguson Street, Williamstown 
10  Corrigan Road, Noble Park  36 Cherry Street, Werribee 
11  Grange Road, Carnegie  37 Werribee Street, Werribee 
12  Heatherton Road, Noble Park  38 Eel Race Road, Carrum 
13  Koornang Road, Carnegie  39 Seaford Road, Seaford 
14  Murrumbeena Road, Murrumbeena  40 Station Street, Carrum 
15  Poath Road, Hughesdale  41 Balcombe Road, Mentone 
16  Centre Road, Clayton  42 Charman Road, Cheltenham 
17  Clayton Road, Clayton  43 Edithvale Road, Edithvale 
18  Mountain Highway, Bayswater  44 Station St/Bondi Road, Bonbeach 
19  Scoresby Road, Bayswater  45 Manchester Road, Mooroolbark 
20  Thompsons Road, Lyndhurst  46 Maroondah Highway, Lilydale 
21  Melton Highway, Sydenham  47 Clyde Road, Berwick 
22  Grange Road, Alphington  48 Hallam Road, Hallam 
23  Lower Plenty Road, Rosanna  49 South Gippsland Highway, Dandenong 
24  Bell Street, Preston  50 Toorak Road, Kooyong 
25  High Street, Reservoir  51 Park Road, Cheltenham⁽ᵃ⁾  
26  Skye Road, Frankston  52 Mascot Avenue/Station Street, Bonbeach⁽ᵃ⁾ 
(a) Additional level crossings identified for removal. 
VAGO, based on information provided by LXRA. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  85 


Appendix C
ALCAM 2008 metropolitan
crossings list
Figure C1 is the ALCAM 2008 list of 50 metropolitan level crossing ranked from
highest to lower risk.

Figure C1  
ALCAM 2008 metropolitan crossings rank 

1 Main Road, St Albans 26 Heatherton Road, Noble Park


2 Furlong Road, St Albans 27 Charman Road, Cheltenham
3 Bell Street, Coburg 28 Clyde Road, Berwick
4 Clayton Road, Clayton 29 Toorak Road, Kooyong
5 Macaulay Road, Kensington 30 Hallam Road, Hallam
6 Bell Street, Preston 31 Swanpool Avenue, Chelsea
7 Glenroy Road, Glenroy 32 Racecourse Road, Pakenham
8 Grange Road, Carnegie 33 Koornang Road, Carnegie
9 Cherry Street, Werribee 34 Webster Street, Dandenong
10 Union Road, Surrey Hills 35 Tooronga Road, Malvern
11 North Road, Ormond 36 Chandler Road, Noble Park
12 Aviation Road, Laverton 37 Station Street, Bonbeach(a)
13 Blackburn Road, Blackburn 38 Skye Road, Frankston
14 Buckley Street, Essendon 39 Keon Parade, Keon Park
15 Old Geelong Road, Hoppers Crossing 40 Gaffney Street, Coburg North
16 Mc Gregor Road, Pakenham 41 South Gippsland Highway, Dandenong
17 Riversdale Road, Camberwell 42 Maidstone Street, Altona
18 Ferguson Street, Williamstown 43 Scoresby Road, Bayswater
19 Lower Plenty Road, Rosanna 44 Webb Street, Narre Warren
20 Station Street, Fairfield 45 South Road, Brighton
21 Murray Road, Preston 46 Main Street, Pakenham
22 Station Street, Carrum 47 High Street, Glen Iris
23 Centre Road, Clayton 48 Grange Road, Alphington
24 Seaford Road, Seaford 49 Corrigan Road, Noble Park
25 Moreland Road, Brunswick 50 Maroondah Highway, Lilydale
(a) This site is one of the additional two sites and is not included in our analysis.
Springvale Road, Nunawading; Springvale Road, Springvale; Mitcham Road, Mitcham and Kororoit Creek Road, Altona were
removed prior to the LXRP and are not included in this list or in our analysis. Those highlighted in light blue are part of the LXRP.
VAGO.

Victorian Auditor-General’s Report  Managing the Level Crossing Removal Program 87


Appendix D  
VicRoads 2013 priority list 
Figure D1 is VicRoads’ 2013 priority list of individual metropolitan crossing sites. 

Figure D1  
VicRoads’ 2013 priority list 

VicRoads 2013 high priority  VicRoads 2013 medium  VicRoads 2013 lower priority 


crossings  priority crossings  crossings 
Balcombe Road, Mentone  Buckley Street, Essendon  Anderson Road, Yarraville 
Blackburn Road, Blackburn  Edithvale Road, Edithvale  Aviation Road, Laverton 
Burke Road, Glen Iris  Gaffney Street, Pascoe Vale  Bear Street, Mordialloc 
Centre Road, Bentleigh  Glenroy Road, Glenroy  Bondi Road, Bonbeach 
Centre Road, Clayton  Grange Road, Caulfield East  Champion Road, Williamstown 
Chandler Road, Noble Park  Heatherdale Road, Mitcham  Chelsea Road, Chelsea 
Charman Road, Cheltenham  Neerim Road, Caulfield East  Corrigan Road, Noble Park 
(a)
Cherry Street, Werribee  Park Road, Cheltenham   Highett Road, Highett 
Clayton Road, Clayton  Westgarth Street, Northcote  Hudsons Road, Spotswood 
Glen Huntly Road, Glen Huntly    Lincoln Parade, Aspendale 
Glenferrie Road, Kooyong    Lochiel Avenue, Edithvale 
Heatherton Road, Noble Park    Maddox Road, Williamstown 
Koornang Road, Carnegie    McDonald Street, Mordialloc 
Madden Grove, Richmond    McKinnon Road, McKinnon 
Main Road, St Albans    Mont Albert Road, Canterbury 
Melton Highway, Sydenham    Parkers Road, Parkdale 
Murrumbeena Road,    Puckle Street, Moonee Ponds 
Murrumbeena 
North Road, Ormond     Ramsden Street, Clifton Hill 
Poath Road, Hughesdale    Seaford Road, Seaford 
Union Road, Surrey Hills    Station Street, Carrum 
     Station Street, Fairfield 
     Station Street, Seaford 
     Webster Street, Dandenong  
     Wickham Road, Moorabbin 
 
 
 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  89 


Figure D1 
VicRoads’ 2013 priority list—continued 

VicRoads 2013 no priority crossings 
Abbott Street, Sandringham  Charles Street, Northcote  Greens Road, Dandenong South 
Abbotts Road, Lyndhurst  Childs Road, Epping  Greville Street, Prahran 
Albert Street, Brunswick  Church Street, Brighton  Grieve Parade, Altona 
Albion Street, Brunswick  Civic Parade, Seaholme  Hallam South Road, Hallam 
Allendale Road, Eltham  Clarendon Street, Frankston  Hampton Street, Hampton 
Alpine Street, Ferntree Gully  Clyde Road, Berwick  Heyington Avenue, Thomastown 
Arden Street, North Melbourne  Coolstore Road, Croydon  High Street, Glen Iris 
Argyle Avenue, Chelsea  Cramer Street, Preston  High Street, Reservoir 
Armstrongs Road, Seaford  Dawson Street, Brunswick  Hillcrest Road, Frankston 
Arthurton Road, Northcote  Devon Road, Pascoe Vale  Holden Road, Diggers Rest 
Ascot Vale, Road Flemington  Diamond Street, Eltham  Hope Street, Brunswick 
Bakers Road, Coburg North  Donnybrook Road,  Hopkins Road, Rockbank 
Donnybrook 
Barry Road, Campbellfield  Dublin Road, Ringwood East  Hutton Street, Thornbury 
Bay Street, Brighton  Eel Race Road, Carrum  Keon Parade, Reservoir 
Beavers Road, Thornbury  Evans Road, Lyndhurst  Kororoit Creek Road, Altona 
Bedford Road, Ringwood  Exford Road, Melton South  Latrobe Street, Cheltenham 
Bell Street, Coburg  Fawkner Cemetery  Leakes Road, Rockbank 
Entrance, Hadfield 
Bell Street, Preston  Ferguson Street,  Linacre Road, Hampton 
Williamstown 
Beveridge Road, Beveridge  Ferris Road, Melton South  Lower Grange Road, Alphington 
Boundary Road, Hadfield  Fitzgerald Road, Sunshine  Lower Plenty Road, Rosanna 
West/Ardeer 
Box Forest Road, Hadfield  Furlong Road, St Albans  Macaulay Road, Kensington 
Brunswick Road, Brunswick  Gaffney Street, Coburg  Macaulay Road, North 
Melbourne 
Brunt Road, Officer  Galvin Road, Werribee  Maidstone Street, Altona 
Calder Park Drive, Calder Park  Giffard Street, Williamstown  Maidstone Street, Altona 
Camms Road, Cranbourne  Glen Eira Road, Ripponlea  Main Hurstbridge, Rd Diamond 
Creek 
Camp Road, Campbellfield  Golf Links Road, Baxter  Main Street, Pakenham 
Cardinia Road, Pakenham  Grange Road, Alphington   Manchester Road, Mooroolbark 
  
   

90  Managing the Level Crossing Removal Program  Victorian Auditor‐General’s Report 


Figure D1 
VicRoads’ 2013 priority list—continued 

VicRoads 2013 no priority crossings 
Maroondah Hwy, Lilydale  Park Street, Parkville  Station Street (Mascot 
Avenue), Bonbeach(a) 
Marshall Street, Ivanhoe  Paschke Crescent, Lalor  Station Street, Lalor 
McGregor Road, Pakenham  Paynes Road, Rockbank  Sth Gippsland Hwy, 
Dandenong South 
Melba Avenue, Lilydale  Pier Street, Altona  Summerhill Road, Wollert 
Millers Road, Seaholme  Poplar Road, Parkville  Swanpool Avenue, Chelsea 
Moorooduc Hwy, Frankston  Progress Street, Dandenong  Thompsons Road, Cranbourne 
South  West 
Moreland Road, Brunswick  Prospect Hill Road,  Toorak Road, Kooyong 
Camberwell 
Mountain Highway, Bayswater  Racecourse Road, Pakenham  Tooronga Road, Malvern 
Mt Cottrell Road, Melton  Railway Avenue, Ferntree  Troups Road, Rockbank 
South  Gully 
Mt Derrimut Road, Deer Park  Railway Road, Eltham  Union Street, Brunswick 
Munro Street, Coburg  Regent Street, Reservoir  Union Street, Windsor 
Murray Road, Preston  Reynard Street, Coburg  Victoria Road, Northcote 
New Street, Hampton  Riversdale Road,  Victoria Street, Brunswick 
Camberwell 
New Street/Dendy Street,  Robinsons Road, Deer Park  Warrigal Road, Parkdale 
Brighton 
Normanby Avenue, Thornbury  Robinsons Road, Frankston  Watsons Rd, Diggers Rest 
Oakover Road, Preston  Ruthven Street, Macleod  Wattletree Road, Eltham 
West 
Officer South Road, Officer  Scoresby Road, Bayswater  Webb Street, Narre 
O’Hea Street, Coburg  Settlement Road,  Werribee Street, Werribee 
Thomastown 
Old Calder Hwy, Diggers Rest  South Road, Brighton  Wilson Road, Wattle Glen  
Old Geelong Road, Hoppers  Station Street, Sunbury  Woolton Avenue, Thornbury 
Crossing  
Overton Road, Seaford  Station Street, Aspendale  Yarralea Street, Alphington 
Park Street, Moonee Ponds  Station Street, Beaconsfield   
(a) Additional level crossing removals. 
Level crossing sites included in the LXRP are highlighted blue. 
VAGO, based on data provided by VicRoads’ strategic framework for the prioritisation of metropolitan level 
crossings. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  91 


Appendix E  
Core quantifiable benefits  
Figure E1 describes the quantifiable benefits and net present value (NPV), 
collectively referred to as the core cost–benefit analysis approach.  

Figure E1  
Benefits summary 

Core quantifiable  2016 NPV $million 
benefits  Description  (7 per cent discount rate) 
Travel time  Includes changes in the journey times for  1 898 
savings  private, business and freight vehicles across 
Melbourne’s road network. 
 
Vehicle operating  Total VOCs include all running costs of the  362 
cost (VOC) savings  vehicle—depreciation, fuel, repairs and 
maintenance. 
Road travel  The removal of level crossings may have an  546 
reliability savings   impact on travel time reliability for road users 
by eliminated unpredictability of boom gates. 
Public transport  A reduction in road congestion will improve  899(a) 
user benefits  travel times and reliability for bus passengers, 
as well as potentially causing some rail users to 
drive instead, and therefore alleviate crowding 
on trains. A number of new train stations will 
be built, or existing ones upgraded. 
Accident cost  The removal of level crossings will eliminate a  134(b) 
savings  number of dangerous locations from the road 
network and may reduce the likelihood of  
risk-taking behaviour along these roads. 
Resource cost  RCCs are the difference between the overall  751 
corrections (RCC)  social and user-perceived costs of travel. For 
savings  example, motorists perceive some of the costs 
of operating a vehicle, such as fuel, but do not 
necessarily perceive other expenses like 
depreciation. 
Cost of pollution  Different transport modes result in different  0.03 
production of environmental emissions, such as 
air pollution and greenhouse gas emissions, 
changes in travel patterns may cause changes 
in network-wide emissions. 

 
 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  93 


Figure E1 
Benefits summary—continued 

Core quantifiable  2016 NPV $million 
benefits  Description  (7 per cent discount rate) 
Residual value— Benefits are based on a 50-year evaluation  128 
replacement cost  period. Beyond this LXRP assets will still 
provide services to transport users. The 
residual value of the benefits to be derived 
from level crossing removals at the end of the 
50-year evaluation period has been estimated 
as the discounted value of the assets at the end 
of the period. 
Construction  During construction, there will be times  -57(c) 
disruption cost  requiring road and rail line closures. Road 
diversions and/or provision of replacement bus 
services but this may mean that journey times 
are longer. At other times, roads or rail lines 
may operate with reduced levels of service. 
Wider economic  Wider economic benefits are productivity  554(d) 
benefits   impacts that a standard CBA does not 
adequately cover. Analysis of wider economic 
impacts attempts to capture the broader 
impacts of a project including the effects of 
connectivity, land development and business 
logistics improvement on productivity and 
output. 
(a) Public transport user benefits is made up of public transport user benefits ($141 million), 
station improvement benefits ($466 million) and interchange improvement benefits 
($292 million). 
(b) Accident cost savings is made up of direct level crossing relating collision reduction 
($145 million) offset by an estimated increase in other road incidents due to higher 
vehicle kilometres travelled (-$11 million). 
(c) Construction disruption disbenefit comprises disruption to rail passengers ($39 million) 
and disruption to road users ($18 million). 
(d) The figure in the table includes agglomeration benefits ($420 million), increased labour 
supply ($82 million), and imperfectly competitive markets ($52 million). 
VAGO from information provided by LXRA. 

 
   

94  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Appendix F  
Contract models 
Figure F1 shows the break-up of initial and additional works, for each package.  

Figure F1  
Contract structure 

Initial or additional 
Package  works  Level crossing sites 
North Eastern  Initial  Grange Road, Alphington 
Lower Plenty Road, Rosanna 
  Additional  Bell Street, Preston 
High Street, Reservoir 
North Western  Initial  Camp Road, Campbellfield 
Skye Road, Frankston 
  Additional  Bell Street, Coburg 
Buckley Street, Essendon 
Glenroy Road, Glenroy 
Moreland Road, Brunswick 
Western  Initial  Kororoit Creek Road, Williamstown  
  Additional  Abbotts Road, Dandenong South 
Aviation Road, Laverton 
Cherry Street, Werribee 
Ferguson Street, Williamstown 
Werribee Street, Werribee 
Southern  Initial  Seaford Road, Seaford 
Eel Race Road, Carrum 
Station Street, Carrum 
Mascot Avenue, Bonbeach 
  Additional  Balcombe Road, Mentone 
Charman Road, Cheltenham 
Edithvale Road, Edithvale 
Park Road, Cheltenham 
Station Street/Bondi Road, 
Bonbeach 
Additional site packages not yet awarded. 
VAGO, based on information provided by LXRA. 
   

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  95 


Appendix G  
Benefits framework 
Figure G1 shows the measures and targets for each of the LRXP’s benefits.  

Figure G1  
Benefits framework 

Measure (KPI)  Target 
Improved productivity from more reliable and efficient transport networks 
Travel time in minutes from  100% of sites will have an improvement in 
specified origin to  travel time following removal of level 
destination during a  crossings.  
specified time period 
 
through the level crossing 
Increased vehicle,  100% of sites will have increased throughput 
pedestrian and cyclist  of vehicles, cyclists or pedestrians following 
throughput per hour in a  removal of level crossings. 
defined area around the 
level crossing 
Standard deviation of travel  100% of sites with boom gate closures of 
time from specified origin  more than 25% of the AM peak will have an 
to destination during a  improvement to the reliability of travel time 
specified time period  following removal of level crossings 
through the level crossing 
Average variability in train  100% of sites will have an elimination of 
punctuality directly  passenger weighted minutes as a result of 
attributable to the level  signal faults at the level crossing following 
crossing  removal of level crossings. 
Percentage of line grade  Dandenong: 100%, Belgrave: 44%, Lilydale: 
separated as a result of the  44%, Hurstbridge: 13%, Pakenham: 55%, 
LXRP  Cranbourne: 73%, South Morang: 11%, 
Upfield: 13%, Craigieburn: 29%, Glen 
Waverley: 33%, Sunbury: 38%, Altona Loop: 
17%, Williamstown: 25%, Werribee: 27%. 
Road based public transport  100% of sites with road based public transport 
service punctuality in a  will have improved punctuality of road based 
defined area around the  public transport (i.e. an increase in the 
level crossing  number of services that are on time) following 
removal of level crossings. 
Access to labour markets  100% of National Employment Clusters will 
for National Employment  have improved access to labour markets 
Clusters that are  following the removal of level crossings. 
constrained by the level 
crossing 

Victorian Auditor-General’s Report Managing the Level Crossing Removal Program  97 


Figure G1 
Benefits framework—continued 

Measure (KPI)  Target 
Better connected, liveable and thriving communities 
Percentage of community  At least 60% of survey respondents at 
satisfied with local amenity as a  each site are satisfied with the changes 
result of the level crossing  as a result of the level crossing removal. 
removal 
IDOs as a result of the level  All sites identified with IDOs at the 
crossing removal  Project Proposal stage will achieve an 
increase in residential units and/or 
lettable retail/business floor space. 
Average time to access  100% of sites will improve access to jobs, 
employment from different  education, and services.  
locations as a result of the level 
 
crossing removal 
Access to local activity centres  100% of sites will have improved access 
and major services within a  to local activity centres and major 
specified number of minutes as a  services.  
result of the level crossing 
 
removal 
Distance and travel time between  100% of sites have reduced distance 
collection and drop off points in a  and/or travel time between collection 
defined area around the level  and drop off points. 
crossing 
Safer communities 
Number of near miss incidents,  100% of sites have zero crashes and near 
fatal and serious injury crashes in  miss incidents involving trains as a result 
a defined area around the level  of the level crossing removal.  
crossing 
No negative safety outcomes as a result 
of the level crossing removal works. 
Improved ALCAM risk score at the  100% of sites have an ALCAM risk score 
level crossing  of zero. 
VAGO, based on information provided by LXRA. 

 
 

98  Managing the Level Crossing Removal Program  Victorian Auditor-General’s Report 


Auditor-General’s reports 
tabled during 2017–18 
 

Report title  Date tabled 
V/Line Passenger Services (2017–18:1)   August 2017 
Internal Audit Performance (2017–18:2)  August 2017 
Effectively Planning for Population Growth (2017–18:3)  August 2017 
Victorian Public Hospital Operating Theatre Efficiency (2017–18:4)  October 2017 
Auditor-General’s Report on the Annual Financial Report of the State  November 2017 
of Victoria, 2016–17 (2017–18:5) 
Results of 2016–17 Audits: Water Entities (2017–18:6)  November 2017 
Results of 2016–17 Audits: Public Hospitals (2017–18:7)  November 2017 
Results of 2016–17 Audits: Local Government (2017–18:8)  November 2017 
ICT Disaster Recovery Planning (2017–18:9)  November 2017 
 
 
All reports are available for download in PDF and HTML format on our website www.audit.vic.gov.au 
 
Victorian Auditor-General’s Office 
Level 31, 35 Collins Street 
Melbourne Vic 3000 
AUSTRALIA 
Phone  +61 3 8601 7000 
Email  enquiries@audit.vic.gov.au 
 

You might also like