Dayshift Activities (04-Apr.2018)
Dayshift Activities (04-Apr.2018)
TK-1507 (mm) TK-1506 (mm) TK-1505 (mm) TK-1504 (mm) TK-1503 (mm) TK-1502 (mm) TK-1501 (mm)
Evaporation pond:
1. Reclaiming oil from retention pond by reclaim oil pump P-1602.
2. Reclaiming oil from evaporation pond NO#1 by vacuum truck.
Dayshift Personnel
Name Company Position
Mosab Balla P.E AGR Operator
Wala omer P.E AGR Operator
Nightshift Personnel
- - -
Ahmed Ali P.E AGR Operator
Activities of AGR
1. Patrol check for engines, vessels and compressors have been done, monitor & record
its parameter.
2. Stopped unit C at 7:00 for 47k routine maintenance and back to normal at 15:00.
3. Fed lube oil to unit C and soft water for unit B.
4. Start unit B at 7:00 and stopped it due changeover to unit C at 15:00.
5. Unit B is standby.
6. Units A & C are running normally.
AGR Units Running (hr) Outlet Pressure (Mpa) Flow Rate (m3/hr.)
1409-A 15 8.35 3974
1409-B 7 8.33 2496
1409-C 7 8.38 3789
Natural Gas treatment Package Outlet Pressure (Mpa) Total Flow Rate
1420-A Not lined up - -
1420-B Stopped - -
FNE 4.02 -
Total Outlet Gas Volume (m3)
103,598
1.4Fula Field
1.4.1 Site Personnel:
Fula Field:-
Moga FPF:
Site Personnel:
FPF
1. Patrol check for all production facilities has been done, monitor & record the parameter.
2. Flushed light crude trunk line by hot water and pump truck from 08:35 to 09:05.
Field:
Field personnel:
1. Routine check for all production wells and OGMs has been done.
2. Tested M18-4.
3. Started M7-5 (PCM) at 10:00 by 5Hz under rig test.
AGR Activities:
Name Company Position
Dayshift Personnel
Omer Mohiad P.E AGR Operator
Night shift
Salih Awad P.E AGR Operator
1. Patrol check for engines, vessels and compressors has been done, monitor & record its
parameters.
2. Unit (PK-2409-A) stopped on Feb.03, 2015 due to compressor 2nd stage piston damage.
Unit (PK-2409-B) Running normally.
1.3.3 AGR daily running and performance report:
Engine No. Running (hrs.) Outlet Pressure (Mpa) Average Flow Rate(m3/h)
A
B 15 7.27 2340
FNE FPF
1Site Personnel:
Nightshift Personnel
Medyan Ali P.E FPF Foreman
Neyazy Abdelmuniem P.E FPF Operator
Nazar Mohammed P.E FPF Operator
Tanks Level:
Dayshift Personnel
Nightshift Personnel
2.2Field Activities:
1. Routine check for all production wells and OGMs has been done.
2. FNE-07 shut-in from 08:00 to 14:00 due to low Pump submergence.
3. FNE-42 shut-in from 08:00 to 20:00 due to low Pump submergence.
4. Cooperated with electrician staff to repair OGM-4 transfer pump.
5. Cooperated with contractor & corrosion engineer to check CP of all wells.
6. Updated well head parameters.
7. Tightened stuffing box for some wells.
Jake FPF
Site Personnel:-
2. Field:-
2.1 Site personnel:-
Nightshift Personnel
Emad Ibrahim P.E Field Operator
Field Activities:-
3. JAKE AGR:-
3.1 Site Personnel:-
5. Vehicles utilized:-
Truck Contractor Work description Remark
KEYI FPF :-
Site Personnel:
1. Field:
2.1. Site Personnel:
Day Activities:
1. Routine check for all wells & OGMs has been done.
2. Checked status of ESDV’s for Gas lifting wells & OGMs.
3. Released casing pressure of K-N-9 & K-N-7.
4. Tested one well
1. AGR:
3.1 Site Personnel:
Name Company Position
Day shift Personnel
Omer Mohammed Omer P.E AGR Operator
Abdalaziz Elnazir P.E AGR Operator
Night shift Personnel
3.2 Day
Mustafa Ahmed P.E AGR Operator
Activities:
1. Patrol check for engines, vessels and compressors has been done, monitor& record parameter.
2. Unit B is running normally.
Engine No. Running Status Outlet Pressure (Mpa) AV-Flow rate (m3/hr.)
A Stopped - -
B Running 8.2 5425
C Under maintenance - -
Total Flow rate (m3/hr.) 5425
Remark
HADIDA FPF :-
Site Personnel:-
Dayshift Personnel
Musa Abu Makeen P.E Operation Supervisor
Abusofyan Ali P.E FPF Foreman
Abubaker Hassan P.E CR Operator
Hosam Eldin Musa P.E FPF Operator
Abdalla Omer P.E FPF Operator
Abdelrahman Hamad P.E Field Operator
Nightshift Personnel
Ammar Mohamed P.E FPF Foreman
Basil Ahmed P.E CR Operator
Awad Ali P.E FPF Operator
Bilal Ali Altahir P.E FPF Operator
Field:
1. Patrol check has been done, monitor & record the parameter.
2. Received 3000 Lt of diesel.
3. Mud pumps- A running for 13 hrs & B standby.
Sufyan FPF
Site Personnel:-
1. Patrol check for all production facilities have been done, monitor & record the
parameters.
2. Fuel gas scrubber’s condensate, was drained several times.
3. One load of hot water was loaded from FPF to well site for flushing job.
4. Performed housekeeping inside EPF has been done.
1.4 Parameters:-
2.0 Field:
2.1 Field personnel:
1. Routine check for all production wells and OGMs has been done.
2. Sufyan-4 flow line flushed by hot water.
3. Restarted OGM-2 transfer pump at 09:00.
4. Sufyan-E1 increased the frequency from 5Hz to 7Hz at 80:30 and then to 9Hz
at 15:10.
5. Sufyan-W6 increased the frequency from 53Hz to 55Hz at 12:30.
6. Sufyan-W8 tested.
7. Sufyan-S2 stopped from 08:45 to 09:45 due to repair the stuffing box leak.
8. Commissionied of OGM-2 test separator (under evaluation).