ED 1104 Re-Submission of Reinforcement Calculation For Columns of Erection Bay Superstructure (Rev.04)

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 1

GUANGXI HYDROELECTRIC CONSTRUCTION BUREAU

Middle Bhotekoshi Hydroelectric Project Management Office


Address: Dhapasi Marg, Rishi Aasram,Bansbari, Kathmandu, Nepal

E-mail: ghcbmbkpmd@163.com

Ref. No.: GHCB/MBKHEP/ED-1104 Date: 5th December, 2019


Attention: Mr. Mukesh Kumar Sharma (Acting Team Leader)
MBKHEP - Tractebel Engineering GmbH, Kathmandu, Nepal
Kathmandu Office, Maharajgunj: Tel: (+977) 1 4721242
Site Office: Tel: (977) 11 489334
E-mail: info.consult@mbjcl.com.np

Subject: Re-submission of Reinforcement Calculation for Columns of

Erection Bay Superstructure (Rev.04)


Lot 1 Civil and Hydro-mechanical Works
Contract Identification No.: MBJCL/MBKHEP/068/69/EPC-1
Reference:
1. Our letter GHCB\MBKHEP\ED 410, dated 30th Dec. 2017
2 Our letter GHCB\MBKHEP\ED 925, dated 5th June 2019
3 Your letter LI/GHCB/3195, dated 17th June 2019
4 Our letter GHCB\MBKHEP\ED 1013, dated 27th Aug. 2019
5 Our letter GHCB\MBKHEP\ED 1018, dated 29th Aug. 2019
6 Your letter LI/GHCB/3402, dated 11th Sept. 2019

Dear Sir,
With reference to the subject above, we hereby resubmit to you “Reinforcement Calculation for
Columns of Erection Bay Superstructure”, Doc. No: 45308-4C/C1-41-CL-05 (Rev.04), for your
review and approval.
Thank you.
Best wishes

Li Zhonghua (Project Manager)


For and on behalf of
China Energy Engineering Group Guangxi Hydroelectric Construction Bureau Co. Ltd.
Middle Bhotekoshi Hydroelectric Project Management Office
Enclosure: As stated above.
cc. MBJCL Chief Executive Officer, Mr. Mani Kumar Kafle.