Subject : (400) Gals Overhead Tank (8' x 4' x 16')

Sr.No Particulars Unit Qty Amount Remark

I Cost of Material item 1 1,525,885

II Cost of Labour item 1 837,275

Total 2,363,160

Say Kyats 2,363,160


Subject : (400) Gals Overhead Tank (8' x 4' x 16')

Bill Of Quantity
Amount
Item Particulars Quantity Unit Rate Per
Kyats
I Materials

1 Cement 7.21 Bag 4,500 Bag 32,436.00

2 Sand 0.18 Sud 10,000 Sud 1,794.00

3 Hill Gravel 0.36 Sud 40,000 Sud 14,352.00

4 Timber Scantling 0.12 Ton 500,000 Ton 60,500.00

5 5 Plywood ( 8' x 4' ) 1.09 Sht: 9,000 Sht: 9,784.00


6 Wire Nail 0.76 Viss 2,500 Viss 1,891.00

7 16mm M.S Rod 0.11 Ton 650,000 Ton 73,091.00

8 6.5mm M.S Rod 0.01 Ton 650,000 Ton 8,701.00

9 Binding Wire 0.70 Viss 2,500 Viss 1,748.00

10 Fuel 0.78 Gal 3,000 Gal 2,340.00

11 2" Dia P.V.C Pipe (20'L) 2.63 No 20,000 Nos. 52,632.00

12 3"x3"x3/8"Angle Iron 201.60 RF 1,000 RF 201,600.00

13 1-½"x 1-½"x3/16" Angle Iron 63.00 RF 1,000 RF 63,000.00

14 1/2"Thk; Gusset Plate 18.00 SF 7,000 SF 126,000.00

15 2"x2"x3/8"Angle Iron 239.40 RF 1,200 RF 287,280.00

16 20mmAnchor 16.00 Nos 1,000 Nos 16,000.00

17 Ready Mixed Oil Paint 2.11 Gals 3,500 Gal 7,384.00

19 Paint Brush 0.70 Nos 500 No 352.00

20 (400) Gal Fiber Tank 1.00 Nos 465,000 No 465,000.00

C-Channel Roof Truss &


21 40.00 SF 2,500 SF 100,000.00
4-Angle Sheet Roofing Work

Total Material Cost 1,525,885.00

II Labour

1 Mason 0.78 Nos. 8,000 Nos. 6,240.00

2 Carpenter 5.45 Nos. 8,000 Nos. 43,560.00

3 Plumber 1.00 Nos. 8,000 Nos. 8,000.00

4 Painter 2.81 Nos. 8,000 Nos. 22,504.00

5 Steel Fixer 50.01 Nos. 8,000 Nos. 400,076.00

6 Worker 59.48 Nos. 6,000 Nos. 356,895.00

Total Labour Cost 837,275.00

Total Material + Labour Cost ( For 1 Nos. ) 2,363,160.00

Say 2,363,160.00
31,500
11 1" dia; vent pipe 10.00 Set 4,000 Set 40,000.00

12 1" dia;Elbow 90 10.00 Set 300 Set 3,000.00

13 1" dia; equal tee 10.00 Set 500 Set 5,000.00

14 1" dia; vent cowl 10.00 Set 500 Set 5,000.00

15 1" dia; valve socket 10.00 Set 250 Set 2,500.00

16 1" dia; socket 20.00 Set 200 Set 4,000.00

17 1" dia; pipe saddle 30.00 Set 125 Set 3,750.00

18 1.5 Hp pump 1.00 Set 150,000 Set 150,000.00


7.21

0.18

0.36

0.12

1.09
0.76

0.112

0.70

0.78

26,000.00

###

0.78

5.45 12177667

1618111

50.01 543636

14.17 14339414

837,274

2,363,159 1 ###
Subject : (400) Gals Overhead Tank (8' x 4' x 16')

ABSTRACT OF COST

Item Particular Unit Quantity Rate Per Amount

1 C-Channel Roof Truss & 4-Angle Sheet Roofing Wo SF 40.00 2500 SF 100,000.00

2 Earth Work Excavation in Medium Soil CF 89.00 90 CF 8,010.00

3 1:2:4 R.C.C Work


(a) 1:2:4 Cement Concrete CF 39.00 2005.69 CF 78,222.00

( b ) Formwork with Jungle SF 90.75 1395.3168 SF 126,625.00


Wood Scantling & 5 Plywood

( c ) Steel Reinforcement Cut, Bend & Fix Ton 171.000 873.22807 Ton 149,322.00

4 Frame Work Ton 1.133 1172552.7 Ton 1,328,230.00

5 Enamel Painting Work SF 281.304 167.49851 SF 47,118.00

6 2" Dia P.V.C Pipe Fixing Work For Concrete Work FT 2.63 23040.2 FT 60,632.00

7 For Over Head Tank Set 1.000 465000 Set 465,000.00


Grand Total 2,363,159
Say 2,363,159
2,363,160
1910.8
Subject : (400) Gals Overhead Tank (8' x 4' x 16')

Builder 's Estimate

Item Particular Unit Quantity Rate Per Amount

1 C-Channel Roof Truss & 4-Angle Sheet Roofing Work

C-Channel Roof Truss &


SF 40.00 2,500 SF 100,000
4-Angle Sheet Roofing Work
100,000

2 Earth Work Excavation in Medium Soil


CF 89.00
Labours
Worker Nos. 1.34 6,000 Nos. 8,010
8,010

3 1:2:4 R.C.C Work


(a) 1:2:4 Cement Concrete CF 39.00
Materials
Cement Bag 7.21 4,500 Bag 32,436
Sand Sud 0.18 10,000 Sud 1,794
Hill Gravel Sud 0.36 40,000 Sud 14,352
Fuel Gals 0.78 3,000 Gals 2,340
50,922
Labours
Mason Nos 0.78 8,000 Nos 6,240
Worker Nos 3.51 6,000 Nos 21,060
27,300

( b ) Formwork with Jungle SF 90.75


Wood Scantling & 5 Plywood
Materials
Timber Scantling Ton 0.12 500,000 Ton 60,500
5 Plywood ( 8' x 4' ) Sht 1.09 9,000 Sht 9,784
Wire Nail Viss 0.76 2,500 Viss 1,891
72,175
Labours
Carpenter Nos 5.45 8,000 Nos 43,560
Worker Nos 1.82 6,000 Nos 10,890
54,450
( c ) Steel Reinforcement Cut, Bend & Fix
16mm Rft 230.00
Builder 's Estimate

Item Particular Unit Quantity Rate Per Amount

6.5mm Rft 171.00


Material
16mm M.S Rod Ton 0.11 650,000 Ton 73,091
6.5mm M.S Rod Ton 0.01 650,000 Ton 8,701
Binding Wire Viss 0.70 2,500 Viss 1,748
83,540
Labours
Steel Fixer Nos 4.70 8,000 Nos 37,590
Worker Nos 4.70 6,000 Nos 28,192
65,782

4 Frame Work Ton 1.13


3"x3"x3/8"Angle Iron RF 201.60 1,000 RF 201,600
1-½"x 1-½"x3/16" Angle Iron RF 63.00 1,000 RF 63,000
1/2"Thk; Gusset Plate SF 18.00 7,000 SF 126,000
2"x2"x3/8"Angle Iron RF 239.40 1,200 RF 287,280
20mmAnchor Nos 16.00 1,000 Nos 16,000
693,880
Labour
Steel Fixer Nos 45.31 8,000 Nos 362,486
Worker Nos 45.31 6,000 Nos 271,864
634,350
5 Enamel Painting Work SF 281.30
Materials
Ready Mixed Oil Paint Gals 2.11 3,500 Gal 7,384
Paint Brush Nos 0.70 500 No 352
7,736
Labours
Painter Nos 2.81 8,000 No 22,504
Worker Nos 2.81 6,000 No 16,878
39,382

6 2" Dia P.V.C Pipe Fixing Work For Concrete Work


Materials
2" Dia P.V.C Pipe (20'L) Nos 2.63 20,000 No 52,632
Labours
Plumber Nos 1.00 8,000 Nos 8,000
60,632
Builder 's Estimate

Item Particular Unit Quantity Rate Per Amount

7 For Over Head Tank


Materials
(400) Gal Fiber Tank Nos 1.00 465,000 No 465,000

Material Charges 1,525,885


Labour Charges 837,274
Grand Total 2,363,159
Say 2,363,159
Page 12

Subject : (400) Gals Overhead Tank (8' x 4' x 16')

Detail of Measurement
Item Measurement
Particular Qty Deduction Content Total
No. L B H
1 C-Channel Roof Truss & 4-Angle Sheet Roofing Work
1 10 4 40.0 40.0
Sft

2 Earth Work Excavation in Medium Soil


Column Footing 4 2.5 2.5 3 75.00
R/W 2 5.5 1 1 11.00
2 1.5 1 1 3.00
89.0 89.0
Cft

3 Column Footing Work


( a ) 1:2:4 Cement Concrete
Column Footing 4 2.5 2.5 0.75 18.75
Short Column 4 0.75 0.75 3.75 8.44
Beam 2 7.25 0.75 0.75 8.16
2 3.25 0.75 0.75 3.66
39.00 39.00
Cft

( b ) Formwork with Jungle Wood Scantling & 5 Plywood


Column Footing 4x4 2.5 0.75 30.00
C1 4x4 3.75 0.75 45.00
Beam 2 7.25 0.75 10.88
2 3.25 0.75 4.88
90.75 90.75
Sft

( c ) Steel Reinforcement Cut, Bend & Fix


16mm Dia
Column Footing 4x5 2.5 16mm 50.00
Short Column 4x4 5.25 16mm 84.00
Beam 2x4 8 16mm 64.00
2x4 4 16mm 32.00
6.5mm Dia
Short Column
Ties 6.5mm @ 6" c/c 4x7 2.25 6.5mm 63.00
Beam
Ties 6.5mm @ 6" c/c 2x16 2.25 6.5mm 72.00
2x8 2.25 6.5mm 36.00
16mm 230.000 Rft
Page 13

Detail of Measurement
Item Measurement
Particular Qty Deduction Content Total
No. L B H
6.5mm 171.00 Rft

4 Frame Work
3"x3"x3/8"Angle Iron 1x4 16 64.00
2x2 8 32.00
2x2 4 16.00
2 4 8.00
Stair Column 2 17.5 35.00
Stair Step 18.5 2 37.00
192.00 Rft
7.17 lb/ft
0.61 Ton

"
1-½ x 1-½"x3/16" Angle Iron
Angle Iron
1x12 2 24.00
1x2 18 36.00
60.00 Rft
1.79 lb/ft
0.05 Ton

2"x2"x3/8"Angle Iron
Angle Iron 12 9 108.00
12 6 72.00
2x2 8 32.00
2x2 4 16.00
228.00 Rft
4.62 lb/ft
0.47 Ton

1/2"Thk; Gusset Plate


4x4 0.75 0.75 9.00
4x4 0.75 0.75 9.00
18.00 Sft

20mmAnchor
Bolt & Nut (1'-6" Long) 4x4 16.00 Nos
16.00 Nos
Total 1.13 Ton
5 Enamel Painting Work
3"x3" Angle Iron 1x4 0.25 192 96.00
"
1-½ x 1-½"x3/8" 1x4 0.125 60.00 15.00
Angle Iron
1/2"Thk; Gusset Plate 1 18 18.00
Page 14

Detail of Measurement
Item Measurement
Particular Qty Deduction Content Total
No. L B H
2"x2"x3/8"Angle Iron 4 0.167 228 152.30
281.30 SF

6 2" Dia P.V.C Pipe Fixing Work For Concrete Work


1 50.0 50.00 Ft

7 Providing & Fixing Of Over Tank


400 Gals Fiber Tank 1.00 Nos.