Summary of Approved Budget For The Contract: Department of Public Works and Highways
Summary of Approved Budget For The Contract: Department of Public Works and Highways
Summary of Approved Budget For The Contract: Department of Public Works and Highways
1. Earthmoving Equipment
1.1 Bulldozer PhP 3,379.00
1.2 Payloader PhP 1,733.00
1.3 Motorized Road Grader PhP 2,173.00
2. Compaction Equipment
2.1 Plate Compactor PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane PhP 1,522.00
3.2 Crawler Crane PhP 1,902.00
3.3 Crawler Crane PhP 2,151.00
3.4 Truck Mounted Crane PhP 1,631.00
3.5 Truck Mounted Crane PhP 1,861.00
3.6 Truck Mounted Crane PhP 2,606.00
3.7 Truck Mounted, Scissor Lift, Terrain PhP 1,386.00
4. Excavating Equipment
4.1 Backhoe PhP 1,537.00
4.2 Backhoe w/ Breaker PhP 1,998.10
4.3 Backhoe, Wheel Mounted PhP 922.00
4.4 Portable Breaker PhP 129.38
5. Foundation Equipment
5.1 Diesel Hammer PhP 1,286.00
5.2 Vibro Hammer PhP 2,123.00
5.3 Vibro Hammer w/ Hydraulic Power Pack PhP 4,118.00
5.4 Vibro Hammer PhP 3,069.00
6 Concreting Equipment
6.1 Concrete Screeder PhP 545.00
6.2 Concrete Paver PhP 6,765.00
6.3 One Bagger Mixer PhP 172.00
6.4 Transit Mixer PhP 1,318.00
7 Hauling Equipment
7.1 Dump Truck PhP 1,420.00
278
7.2 Cargo/Service Truck PhP 783.00
7.3 Boom Truck PhP 1,017.90
7.4 Cargo/Service Truck PhP 1,212.00
7.5 Water Truck/Pump PhP 2,450.00
8 Air Equipment
8.1 Air Compressor PhP 965.00
8.2 Air Compressor PhP 502.00
8.3 Air Compressor, Portable PhP 450.00
8.4 Air Compressor PhP 205.00
8.5 Diamond Drill PhP 201.25
8.6 Jackhammer PhP 150.00
8.7 Pneumatic Drilling Machine PhP 170.00
9 Pumping Equipment
9.1 Water Pump, 100 mm suction Ø PhP 266.25
9.2 Water Pump, 100 mm suction Ø PhP 123.38
9.3 Pumpcrete PhP 2,076.00
DESCRIPTION RENTAL RATE
10 Power Generating Equipment
10.1 Generator Set PhP 872.87
10.2 Generator Set PhP 2,147.27
11 Shop Equipment
11.1 Welding Machine PhP 391.00
11.2 Welding Machine PhP 371.00
279
Pile Integrity Testing & accessories
14.5 (includes professional fee of Strcutural Engineer PhP 37,000.00
and reports)
280
Revised BP Form 202 (2020 Budget Tier 2)
2. Implementing Department/Agency
DPWH-Abra District Engineering Office
7. Description:
Rehabilitation and Improvement of National Roads
8. Purpose:
for smooth and safer travel to the riding public
9. Beneficiaries: Local Communities, Local Government Units, Tourists (Local and Foreign)
Local Communities
10. Implementation Period: ORIGINAL
REVISED
NEDA Board √
NEDA Board-ICC √
DPWH Certification √
DPWH MOA √
DPWH Costing √
DENR Clearance √
RDC Consultation √
CSO Consultation √
List of Locations √
List of Beneficiaries √
PS
MOOE
FINEX
CO 99,450,000.00
GRAND TOTAL 99,450,000.00
GRAND TOTAL
K0422+676-429+000
Station Limits : (c) Others
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART A FACILITIES FOR THE ENGINEER (PLS. SEE FORM POW-2015-01C-00) 0.00% PhP - 0.00% PhP -
PART B OTHER GENERAL REQUIREMENTS 3.10% PhP 86,297.04 3.10% PhP 86,297.04
PART C EARTH WORKS 0.00% PhP - 0.00% PhP -
PART D SUBBASE AND BASE COURSE 0.00% PhP - 0.00% PhP -
PART E SURFACE COURSE 93.57% PhP 2,603,565.59 93.57% PhP 2,603,565.59
PART H MISCELLANEOUS STRUCTURES 3.33% PhP 92,616.55 3.33% PhP 92,616.55
Total 100.00% PhP 2,782,479.18 100.00% PhP 2,782,479.18
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:
FORM POW-2015-01A-0
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST % DIRECT
QTY
TOTAL UNIT COST (DIRECT+INDIRECT) COST
ITEM NO. DESCRIPTION UNIT
AS AS AS
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
SUBMITTED EVALUATED EVALUATED
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of
No. Equipment Description Capacity
Equipment
1 Asphalt Distributor, 10ft. Wide (5.00 tons) 1.00
2 Asphalt Paver (80 Hp) 1.00
3 Backhoe w/ Pavement Breaker(.80 cu. M) 1.00
4 Bulldozer (D6H SERIES II PSDS/DD) 1.00
5 Cargo Truck(9 -10mt) 1.00
6 Dump Truck 1.00
7 Payloader (1.5 cu.m.) 1.00
8 Water Truck 1.00
9 Motorized Road Grader, G710A 1.00
10 Transit Mixer ( 5 cu.m.) 1.00
TOTAL 10.00
REPAIR/REHABILITATION/IMPROVEMENT OF ABRA CERVANTES ROAD ASPHALT OVERLAY
K0422+676-429+000
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2.00 PhP 9,280.00 PhP 2,068.53 PhP - PhP 11,348.53 25.00% PhP 2,837.13 PhP 709.28 PhP 14,894.94
B.5 Project Billboard/ Signboard each
AS EVALUATED 2.00 PhP 9,280.00 PhP 2,068.53 PhP - PhP 11,348.53 25.00% PhP 2,837.13 PhP 709.28 PhP 14,894.94
AS SUBMITTED 1.00 PhP 2,395.11 PhP 12,057.86 PhP - PhP 14,452.97 8.00% PhP 1,156.24 PhP 780.46 PhP 16,389.67
B.7 (2) Occupational Safety and Health Program lump sum
AS EVALUATED 1.00 PhP 2,395.11 PhP 12,057.86 PhP - PhP 14,452.97 8.00% PhP 1,156.24 PhP 780.46 PhP 16,389.67
AS SUBMITTED 1.00 PhP 1,919.34 PhP 39,283.20 PhP - PhP 41,202.54 8.00% PhP 3,296.20 PhP 2,224.94 PhP 46,723.68
B.8 (2) Traffic Management lump sum
AS EVALUATED 1.00 PhP 1,919.34 PhP 39,283.20 PhP - PhP 41,202.54 8.00% PhP 3,296.20 PhP 2,224.94 PhP 46,723.68
AS SUBMITTED 1.00 PhP - PhP - PhP 19,293.00 PhP 19,293.00 0.00% PhP - PhP 964.65 PhP 20,257.65
B.9 Mobilization/ Demobilization lump sum
AS EVALUATED 1.00 PhP - PhP - PhP 19,293.00 PhP 19,293.00 0.00% PhP - PhP 964.65 PhP 20,257.65
AS SUBMITTED PhP 13,594.45 PhP 53,409.59 PhP 19,293.00 PhP 86,297.04 PhP 7,289.57 PhP 4,679.33 PhP 98,265.94
TOTAL OF PART B
AS EVALUATED PhP 13,594.45 PhP 53,409.59 PhP 19,293.00 PhP 86,297.04 PhP 7,289.57 PhP 4,679.33 PhP 98,265.94
PART E SURFACE COURSE
AS SUBMITTED 3,585.00 PhP 2,326,844.25 PhP 12,041.97 PhP 109,961.37 PhP 2,448,847.59 20.00% PhP 489,769.52 PhP 146,930.86 PhP 3,085,547.97
310(a.2) Bituminous Concrete Surface Course (50mm thk.) sq.m.
AS EVALUATED 3,585.00 PhP 2,326,844.25 PhP 12,041.97 PhP 109,961.37 PhP 2,448,847.59 20.00% PhP 489,769.52 PhP 146,930.86 PhP 3,085,547.97
AS SUBMITTED 3.00 PhP 141,750.00 PhP 2,302.60 PhP 10,665.40 PhP 154,718.00 20.00% PhP 30,943.60 PhP 9,283.08 PhP 194,944.68
302(2) Bituminous Tack Coat (Emulsified Asphalt) m.tons
AS EVALUATED 3.00 PhP 141,750.00 PhP 2,302.60 PhP 10,665.40 PhP 154,718.00 20.00% PhP 30,943.60 PhP 9,283.08 PhP 194,944.68
AS SUBMITTED PhP 2,468,594.25 PhP 14,344.57 PhP 120,626.77 PhP 2,603,565.59 PhP 520,713.12 PhP 156,213.94 PhP 3,280,492.65
TOTAL OF PART E
AS EVALUATED PhP 2,468,594.25 PhP 14,344.57 PhP 120,626.77 PhP 2,603,565.59 PhP 520,713.12 PhP 156,213.94 PhP 3,280,492.65
PART H MISCELLANEOUS STRUCTURES
AS SUBMITTED 121.55 PhP 79,147.28 PhP 2,424.97 PhP 5,295.64 PhP 86,867.89 20.00% PhP 17,373.58 PhP 5,212.07 PhP 109,453.54
612(1) Reflectorized Thermoplastic Pavement Markings White sq.m.
AS EVALUATED 121.55 PhP 79,147.28 PhP 2,424.97 PhP 5,295.64 PhP 86,867.89 20.00% PhP 17,373.58 PhP 5,212.07 PhP 109,453.54
AS SUBMITTED 7.20 PhP 5,284.15 PhP 143.64 PhP 320.87 PhP 5,748.66 20.00% PhP 1,149.73 PhP 344.92 PhP 7,243.31
612(2) Reflectorized Thermoplastic Pavement Markings Yellow each
AS EVALUATED 7.20 PhP 5,284.15 PhP 143.64 PhP 320.87 PhP 5,748.66 20.00% PhP 1,149.73 PhP 344.92 PhP 7,243.31
AS SUBMITTED PhP 84,431.43 PhP 2,568.61 PhP 5,616.51 PhP 92,616.55 PhP 18,523.31 PhP 5,556.99 PhP 116,696.85
TOTAL OF PART H
AS EVALUATED PhP 84,431.43 PhP 2,568.61 PhP 5,616.51 PhP 92,616.55 PhP 18,523.31 PhP 5,556.99 PhP 116,696.85
AS SUBMITTED PhP 2,566,620.13 PhP 70,322.77 PhP 145,536.28 PhP 2,782,479.18 PhP 546,526.00 PhP 166,450.26 PhP 3,495,455.44
GRAND TOTAL
AS EVALUATED PhP 2,566,620.13 PhP 70,322.77 PhP 145,536.28 PhP 2,782,479.18 PhP 546,526.00 PhP 166,450.26 PhP 3,495,455.44
REPAIR/REHABILITATION/IMPROVEMENT OF ABRA CERVANTES ROAD ASPHALT OVERLAY
K0474+000-K474+474
B.1
B.2
A.1 a. Safety Practitioner/Officer (Part Time) 1 112.29 PhP 62.50 PhP 7,017.86
b. Health Personnel (Full Time) 1 144.00 PhP 35.00 PhP 5,040.00
491.00 7.30 0.70 200 12.55 2.51 2,509.01 Left & Right Lane
ITEM 310(a.3)
BITUMINOUS CONCRETE SURFACE COURSE (50mm thk.)
TABULATION AND COMPUTATION OF QUANTITIES FOR BITUMINOUS CONCRETE SURFACE COURSE
0+000 0+000 491.00 7.30 0.05 3,584.30 Left & Right Lane
GRAND TOTAL:
ITEM 612(1) = 121.55 Sq.m.
ITEM 612(2) = 7.20 Sq.m.
UNIT COST DERIVATION OF BITUMINOUS CONCRETE SURFACE COURSE
Volume = 351.33 MT
351.33 MT
Utilizing 6 Dumptruck
= 2.00 DT
w/ 10 cu.m. cap.
Volume Hauled/Day = 2.00 DT x 24.60 MT/DT = 49.20 MT
351.33
No of Days Required = = 22.00 days
49.20 x 0.33
Equipment Cost
Dumptrucks = 2.00 DT 11,360.00 /day x 22.00 days = P 499,840.00
P 499,840.00
LENGTH
419+000 152
409+000 142
ITEM 101(3)a.2
REMOVAL OF EXISTING PCCP
MAIN ROAD
STATION PCCP WIDTH
LENGTH (m) (m) DESCRIPTION ITEM 101(3)a.2
Length x PCCP
WIDTH
44.00 7.30 321.20
LENGTH= 44.00 SUBTOTAL 01 ITEM 101(3)a.2 = 321.20 sqm
ITEM 311
PORTLAND CEMENT CONCRETE PAVEMENT
547 3.20 0.7 2.5 1.00 1.0 1.25 0.6 478.63 681.75 1743.56
ITEM 600
CONCRETE CURB AND GUTTER
Fine Aggregates
Volume = 2.11 cu.m.
Considering 15% Swell Factor, Total Vol. Req'd.= 2.43 cu.m.
Source to Start of Project 22.68
Project Centroid 3.16
TOTAL = 25.84 Kms.
Source : BAGALAY SAND & GRAVEL PIT
K0417+000; 1 KM AWAY FROM ABRA-KALINGA ROAD
2.11
No of Days Required = = 0.01 days
40.00 x 3.82
Equipment Cost
Payloader = 1.00 13,864.00 /day x 0.01 days = P 95.90
Dumptrucks = 4.00 DT 11,360.00 /day x 0.01 days = P 628.67
P 724.57
A. GRAVEL
Unit Cost of Hauling = P 342.75 /cu. m.
Production Cost = P 400.00 /cu. m.From CCIS
Aggregate Tax = P 50.00
Unit Cost of Fine Aggregates = P 792.75 /cu. m.
SAY = P 793.00 /cu. m.
SAY = P 793.00 /cu. m.
B. SAND
Unit Cost of Hauling = P 342.75 /cu. m.
Production Cost = P 350.00 /cu. m.From CCIS
Aggregate Tax = P 50.00
Unit Cost of Fine Aggregates = P 742.75 /cu. m.
SAY = P 743.00 /cu. m.
UNIT COST DERIVATION OF CEMENT
Cement
Quantity Required = 9.45 bags
9.45 bags
No of Days Required = =
480.00 mins./day CT x 250.00 0.01 days
x 1
173.52 mins./trip trip
Equipment Cost
1 Cargo Trucks = 1.00 CT 9,696.00 /day x 0.01 days = P 96.96
Labor Cost
6 Laborers = 6.00 x 321.20 /day x 0.00 days = P 4.82
P 101.78
A. CEMENT
Cost/bag at Source 241.00 /bag
P 101.78
Unit Cost of Hauling = 10.77 /bag
9.45
Total Cost of Cement = 251.77 /bag
SAY = 252.00 /bag
UNIT COST DERIVATION OF CEMENT
A Loading
Quantity: 10,000.00 bags
Source: K0 318+000 Lagawe, Ifugao
Cap. of 1 Dump Truck = 10,000 kgs.
10,000 kg.
No. of bags/Dumptruck = = 250.00 bags
40 kg. /bag
Loading Time :(Employing 6 Laborers) 42.00 mins
10,000 kgs. X 1 min
= = 42.00 min.
40 kgs./man-min x 6.00 laborers
B Handling
Ave. Hauling Dist. = 17.50 km.
Paved Road 4.00 kms. SOURCE to Junction/ Ibulao Bridge (Chainage 0, Mountainous)
4 kms x 60 min/hr
Loaded Trip = = 12.00 mins
20 kms/hr
4 kms x 60 min/hr
Unloaded Trip = = 8.00 mins.
30 kms/hr
Paved Road 13.50 kms. Chainage 0- Project Centroid (Mountainous)
1 Equipment Cost:
10,000.00 bags
# of days req'd. = = 15.50
480 min./day DT x 250.00 bags
X 1
186.25 min./trip trip say 15.50
2 Labor Cost
6 Laborers = 6 Lab. x P343.28 /day x 2.38 days = P1,225.51
4.00 P24,301.99
P24,301.99
Unit Cost of Hauling = P2.43 ,/kg.
10,000.00
Pick-up Prize = 38.00 ,/kg Grade 40
Total Cost/kg = P 38.00 + P2.43 Add 5% contingency 40.43 = P42.45 ,/kg.
SOURCE: Ibulao River (100m, Upstream of Ibulao Bridge, KO314+925 along N.Viscaya-Mt. Prov. Bdry Road.
A.) QUARRYING
Quarrying & Washing (Assume quarry to contain 40% Materials)
Volume of unprocess materials = 1,000.00 /40% = 2,500.00
Assume capacity of Bulldozer = 400.00 cu.m. Note: 40% of Materials will be considered as suitable
Production Cost Materials for course and Fine Aggregates because
# of days required = 2,500.00 = 6.25 days the quarry site consists of Boulders, grasses etc
400.00
B Handling
Ave. Hauling Dist. = 13.60 km.
Ibulao Gravel Pit/ Chainage 0 to Project Centroid
Paved Road 13.50 kms.
13.5 kms x 60 min/hr
Loaded Trip = = 27.00 mins
30 kms/hr
13.5 kms x 60 min/hr
Unloaded Trip = = 20.25 mins.
40 kms/hr
Unpaved Road 0.10 kms.
0.1 kms x 60 min/hr
Loaded Trip = = 0.24 mins
25 kms/hr
0.1 kms x 60 min/hr
Unloaded Trip = = 0.17 mins.
35 kms/hr
SOURCE: Ibulao River (100m, Upstream of Ibulao Bridge, KO314+925 along N.Viscaya-Mt. Prov. Bdry Road.
1.b Labor Cost
Breaking,Picking and Stockpiling
Labor Capacity = 1 cu.m./man-day due to multiple handling, Chipping/breaking, picking & Stock Pilling
No. of Laborers = 50
Total Output/day = 50 cu.m.
No. of days = 1,000.00 cu.m./ 50 = 20.00 say 20.00 days
Labor = 50 Lab. X 20.00 days x 343.28 /day = P343,280.00
P343,280.00
B.2 Handling
Ave. Hauling Dist. = 13.60 km.
Ibulao Gravel Pit/ Chainage 0 to Project Centroid
Paved Road 13.50 kms.
13.5 kms x 60 min/hr
Loaded Trip = = 27.00 mins
30 kms/hr
13.5 kms x 60 min/hr
Unloaded Trip = = 20.25 mins.
40 kms/hr
Unpaved Road 0.10 kms.
0.1 kms x 60 min/hr
Loaded Trip = = 0.24 mins
25 kms/hr
0.1 kms x 60 min/hr
Unloaded Trip = = 0.17 mins.
35 kms/hr
8 hrs x 60 min/hr =
No. of Trips/day = 7.01 trip
68.43 mins
Utilizing 2.00 Dumptrucks ( 10.00 cu.m. capacity )
No. of Days Required = 1000.00 = 7.13 say 7.13 days
20.00 7.01
Equipment Cost
Dumptrucks = 2.00 DT P11,360 /day x 7.13 days = P161,993.60
Loader @ project site = 1 Loader x P13,864 /day x 3.57 days = P49,425.16
P211,418.76
Cost of Aggregate Tax = 1,000.00 x P50 /cu.m. = 50,000.00
P604,699
Unit Cost = = 604.70 /cu.m.
1,000.00
Unit Cost of BOULDERS DELIVERED AT PROJECT SITE = 604.70 /cu.m.
UNIT COST DERIVATION OF AGGREGATES SUB BASE COURSE
VOLUME = 1,000.00 cu.m.
SOURCE: Ibulao River (100m, Upstream of Ibulao Bridge, KO314+925 along N.Viscaya-Mt. Prov. Bdry Road.
A.) QUARRYING
Quarrying & Washing (Assume quarry to contain 70% Materials)
Volume of unprocess materials = 1,000.00 /70% = 1,428.57
Assume capacity of Bulldozer = 400.00 cu.m. Note: 70% of Materials will be considered as suitable
Production Cost Materials for course and Fine Aggregates because
# of days required = 1,428.57 = 4.00 days the quarry site consists of Boulders, grasses etc
400.00
4 kms x 60 min/hr
Loaded Trip = = 12.00 mins
20 kms/hr
4 kms x 60 min/hr
Unloaded Trip = = 8.00 mins.
30 kms/hr
Paved Road 13.50 kms. Chainage 0- Project Centroid (Mountainous)
2 Labor Cost
6 Laborers = 6 Lab. x P343.28 /day x 0.39 days = P401.64
2.00 P4,183.08
MANUAL HAULING
1. HAULING = 20.00 mtrs (Average)
Dirt Road
0.02 kms. x 60 min./hr.
Loaded Trip = = 0.48 mins.
2.5 kms./hr.
0.02 kms. x 60 min./hr.
Unloaded Trip = = 0.34 mins.
3.5 kms./hr.
Slack Time, Allowance for Delay (loading & Unloading) = 1.00 min.
1.82 min.
Total Cycle Time
8 hrs. x 60 min./hr.
# of Trip per Day = = 263.00 trip
1.82 mins.
SOURCE= MANILA
MANILA TO DAMALIN BRIDGE= 453.70 Km. flat train
Note.: The 50-70 ton truck mounted crane which will be used in the launching of the PSCG is assumed to come from manila as there are no availaible
equipment locally.
35 kms x 60 min/hr
Loaded Trip = = 70.00 mins
30 kms/hr
35 kms x 60 min/hr
Unloaded Trip = = 52.50 mins.
40 kms/hr
Paved Road 8.00 kms. River 1 to River 2, rolling
8 kms x 60 min/hr
Loaded Trip = = 16.00 mins
30 kms/hr
8 kms x 60 min/hr
Unloaded Trip = = 12.00 mins.
40 kms/hr
Paved Road 1.50 kms. River 2 to project site, rolling