STEEL WORKS

FOOTING
Total Length of GI WIRE
MARK SIZE (m) REINFORCEMENT (16 mm) bars in meters (KG)
LENGTH WIDTH LONG. CUT BARS TRANS. CUT BARS
F1 1.55 1.55 8 8 24.8 0.36
F1 1.55 1.55 8 8 24.8 0.36
F1 1.55 1.55 8 8 24.8 0.36
F1 1.55 1.55 8 8 24.8 0.36
F2 1.9 1.9 10 10 38 0.57
F2 1.9 1.9 10 10 38 0.57
F2 1.9 1.9 10 10 38 0.57
F2 1.9 1.9 10 10 38 0.57
F2 1.9 1.9 10 10 38 0.57
F2 1.9 1.9 10 10 38 0.57
F3 2 2 12 12 48 0.82
F3 2 2 12 12 48 0.82
TOTAL 232 424
6.5
TOTAL NO. OF 16MM BARS 71

LENGTH OF 16 MM BAR = 6M ; TIE LENGTH = 0.3M ; 1KG WIRE = 53M


TOTAL LENGTH = Σ[(LENGTH x LONG. CUT BARS) + (WIDTH x TRANS. CUT BARS)]
TOTAL NO. OF BARS = ΣTOTAL LENGTH / LENGTH OF BAR
GI WIRE = Σ(LONG. CUT BARS x TRANS. CUTBARS x TIE LENGTH) / 53
FOOTINGS
F1TOTAL LENGTH = (Length x Long. Cut Bars) + (Width x Trans. Cut Bars) ΣTOTAL LENGTH = 4F1 + 6F2 + 2F3
F1TOTAL LENGTH = (1.55 x 8) + (1.55 x 8) = 24.8 m = 99.2 + 228 + 96
4 F1TOTAL LENGTH = 4 (24.8 m) = 99.2 m ΣTOTAL LENGTH = 423.2 = 424 m

F2TOTAL LENGTH = (Length x Long. Cut Bars) + (Width x Trans. Cut Bars) TOTAL NO. OF BARS = ΣTOTAL
F2TOTAL LENGTH = (1.9 x 10) + (1.9 x 10) = 38 m LENGTH / LENGTH OF BAR
6 F2TOTAL LENGTH = 6 (38m) = 228 m
TOTAL NO. OF BARS = 424 / 6
F3TOTAL LENGTH = (Length x Long. Cut Bars) + (Width x Trans. Cut Bars) TOTAL NO. OF BARS = 70.67 = 71 PCS
F3TOTAL LENGTH = (2 x 12) + (2 x 12) = 48 m
2 F3TOTAL LENGTH = 2 (48 m) = 96 m

GI WIRE = Σ(Long. cut bars x Trans. cutbars x Tie length) / 53

F1 = (8 x 8 x 0.3)/53 =0.36 kg GI WIRE = 4F1 + 6F2 + 2F3


F2 = (10 x 10 x 0.3)/53 = 0.57 kg GI WIRE = 4(0.36) + 6(0.57) + 2(0.82)
F3 = (12 x 12 x 0.3)/53 = 0.82 kg GI WIRE = 1.44 + 3.42 + 1.64 = 6.5 kg
COLUMN
MAIN BARS STIRRUPS GI WIRE (KG)
MARK
LENGTH (m) 16MM BARS LENGTH (m) 10MM BARS
C1 7.7 9 1.2 57 2.9
C1 7.7 9 1.2 57 2.9
C1 8.225 9 1.2 60 3.06
C1 8.225 9 1.2 60 3.06
C1 8.75 9 1.2 64 3.26
C1 8.75 9 1.2 64 3.26
C1 4.7 9 1.2 37 1.88
C1 4.7 9 1.2 37 1.88
C2 7.7 9 1.3 57 2.9
C2 7.7 9 1.3 57 2.9
C2 8.75 9 1.3 64 3.26
C2 8.75 9 1.3 64 3.26
C3 3.525 9 1.2 29 1.48
C3 3.525 9 1.2 29 1.48
TOTAL LENGTH 889 TOTAL LENGTH 908
37.48
TOTAL 16MM BARS 149 TOTAL 10MM BARS 152

LENGTH OF 16MM AND 10MM BAR = 6M ; TIE LENGTH = 0.3M ; 1KG WIRE = 53M
TOTAL LENGTH OF MAIN BAR = Σ(LENGTH x 16MM BARS)
TOTAL LENGTH OF 10MM BAR = Σ(LENGTH x 10MM BARS)
TOTAL NO. OF BARS = ΣTOTAL LENGTH / LENGTH OF BAR
GI WIRE = Σ(16MM BARS x 10MM BARS x TIE LENGTH) / 53

COMPUTATION FOR MAIN BARS


C1TOTAL LENGTH = Length x 16 mm bars C2TOTAL LENGTH = Length x 16 mm bars
C1TOTAL LENGTH = 7.7 x 9 = 69.3 m C1TOTAL LENGTH = 8.75 x 9 = 78.75 m
2 C1TOTAL LENGTH = 2 (69.3) = 138.6 2 C2TOTAL LENGTH = 2 (78.75) = 157.5 m

C1TOTAL LENGTH = Length x 16 mm bars C3TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 8.225 x 9 = 74.025 m C1TOTAL LENGTH = 3.525 x 9 = 31.725 m
2 C1TOTAL LENGTH = 2 (74.025) = 148.05 m 2 C3TOTAL LENGTH = 2 (31.725) = 63.45 m

C1TOTAL LENGTH = Length x 16 mm bars ΣTOTAL LENGTH OF MAIN BAR


C1TOTAL LENGTH = 8.75 x 9 = 78.75 m = 2C1 + 2C1 + 2C1 +2C1 + 2C2 + 2C2 + 2C3
2 C1TOTAL LENGTH = 2 (78.75) = 157.5 m = 138.6 + 148.05 +157.5 + 84.6 + 138.6 + 157.5 + 63.45
= 888.3 = 889 m
C1TOTAL LENGTH = Length x 16 mm bars
C1TOTAL LENGTH = 4.7 x 9 = 42.3 m TOTAL NO. OF MAIN BAR = ΣTOTAL LENGTH OF MAIN BAR
2 C1TOTAL LENGTH = 2 (42.3) = 84.6 m LENGTH OF BAR
TOTAL NO. OF MAIN BAR = 889 / 6
C2TOTAL LENGTH = Length x 16 mm bars TOTAL NO. OF MAIN BAR = 148.17 = 149 PCS
C1TOTAL LENGTH = 7.7 x 9 = 69.3 m
2 C2TOTAL LENGTH = 2 (69.3) = 138.6 m
COMPUTATION FOR STIRRUPS
C1TOTAL LENGTH = Length x 10 mm bars C2TOTAL LENGTH = Length x 16 mm bars
C1TOTAL LENGTH = 1.2 x 57 = 68.4 m C1TOTAL LENGTH = 1.3 x 64 = 83.2 m
2 C1TOTAL LENGTH = 2 (68.4) = 136.8 2 C2TOTAL LENGTH = 2 (83.2) = 166.4 m

C1TOTAL LENGTH = Length x 10 mm bars C3TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 1.2 x 60 = 72 m C1TOTAL LENGTH = 1.2 x 29 = 34.8 m
2 C1TOTAL LENGTH = 2 (72) = 144 m 2 C3TOTAL LENGTH = 2 (34.8) = 69.6 m

C1TOTAL LENGTH = Length x 10 mm bars ΣTOTAL LENGTH OF MAIN BAR


C1TOTAL LENGTH = 1.2 x 64 = 76.8 m = 2C1 + 2C1 + 2C1 +2C1 + 2C2 + 2C2 + 2C3
2 C1TOTAL LENGTH = 2 (76.8) = 153.6 m = 136.8+ 144 +153.6 + 88.8 + 148.2 + 166.4 + 69.6
= 907.4 = 908 m
C1TOTAL LENGTH = Length x 10 mm bars
C1TOTAL LENGTH = 1.2 x 37 = 44.4 m TOTAL NO. OF MAIN BAR = ΣTOTAL LENGTH OF MAIN BAR
2 C1TOTAL LENGTH = 2 (44.4) = 88.8 m LENGTH OF BAR
TOTAL NO. OF MAIN BAR = 908 / 6
C2TOTAL LENGTH = Length x 10 mm bars TOTAL NO. OF MAIN BAR = 151.33 = 152 PCS
C1TOTAL LENGTH = 1.3 x 57 = 74.1 m
2 C2TOTAL LENGTH = 2 (74.1) = 148.2 m

GI WIRE = GI WIRE = Σ(16MM BARS x 10MM BARS x TIE LENGTH) / 53


C1 = (16mm bars x 10mm bars x 0.3)/53 C2 = (16mm bars x 10mm bars x 0.3)/53
C1 = (9 x 57 x 0.3)/53 = 2.9 kg C1 = (9 x 64 x 0.3)/53 = 3.26 kg
2C1 = 2 (2.9) = 5.8 kg 2C2 = 2 (3.26) = 6.52 kg

C1 = (16mm bars x 10mm bars x 0.3)/53 C3 = (16mm bars x 10mm bars x 0.3)/53
C1 = (9 x 60 x 0.3)/53 = 3.06 kg C1 = (9 x 29 x 0.3)/53 = 1.48 kg
2C1 = 2 (3.06) = 6.12 kg 2C3 = 2 (1.48) = 2.96 kg

C1 = (16mm bars x 10mm bars x 0.3)/53 GI WIRE = 2C1 + 2C1 + 2C1 +2C1 + 2C2 + 2C2 + 2C3
C1 = (9 x 64 x 0.3)/53 = 3.26 kg = 5.8 + 6.12 + 6.52 + 3.76 + 5.8 + 6.52 + 2.96
2C1 = 2 (3.26) = 6.52 kg = 37.48 kg

C1 = (16mm bars x 10mm bars x 0.3)/53


C1 = (9 x 37 x 0.3)/53 = 1.88 kg
2C1 = 2 (1.88) = 3.76 kg

C2 = (16mm bars x 10mm bars x 0.3)/53


C1 = (9 x 57 x 0.3)/53 = 2.9 kg
2C2 = 2 (2.9) = 5.8 kg
BEAM
MAIN BARS STIRRUPS GI WIRE (KG)
MARK
LENGTH (m) 16MM BARS LENGTH (m) 10MM BARS
TB1 2.55 7 1.4 25 0.99
TB1 2.55 7 1.4 25 0.99
TB1 2.55 7 1.4 25 0.99
TB1 2.55 7 1.4 25 0.99
TB2 2.5 6 1.4 25 0.85
TB2 2.5 6 1.4 25 0.85
TB2 2.5 6 1.4 25 0.85
TB2 2.5 6 1.4 25 0.85
TB2 2.1 6 1.4 22 0.75
TB2 2.1 6 1.4 22 0.75
B1 2.55 9 1.4 25 1.27
B1 2.55 9 1.4 25 1.27
B1 2.55 9 1.4 25 1.27
B1 2.55 9 1.4 25 1.27
B2 2.55 9 1.4 25 1.27
B2 2.55 9 1.4 25 1.27
B3 2.3 6 1.5 23 0.78
B3 2.3 6 1.5 23 0.78
B4 2.5 9 1.4 25 1.27
B4 2.1 9 1.4 22 1.12
B5 2.5 6 1.3 25 0.85
B6 2.5 9 1.4 25 1.27
B6 2.5 9 1.4 25 1.27
B6 2.1 9 1.4 22 1.12
RB1 2.55 4 1.3 25 0.57
RB1 2.55 4 1.3 25 0.57
RB1 2.55 4 1.3 25 0.57
RB1 2.55 4 1.3 25 0.57
RB1 2.55 4 1.3 25 0.57
RB1 2.55 4 1.3 25 0.57
RB1 2.5 4 1.3 25 0.57
RB1 2.5 4 1.3 25 0.57
RB1 2.5 4 1.3 25 0.57
RB1 2.5 4 1.3 25 0.57
RB1 2.3 4 1.3 23 0.52
RB1 2.3 4 1.3 23 0.52
RB1 3.1 4 1.3 28 0.63
RB1 3.1 4 1.3 28 0.63
RB1 2.2 4 1.3 23 0.52
RB1 2.1 4 1.3 22 0.5
RB1 2.1 4 1.3 22 0.5
TOTAL LENGTH 613 TOTAL LENGTH 1365
34.46
TOTAL 16MM BARS 103 TOTAL 10MM BARS 228
LENGTH OF 16MM AND 10MM BAR = 6M ; TIE LENGTH = 0.3M ; 1KG WIRE = 53M
TOTAL LENGTH OF MAIN BAR = Σ(LENGTH x 16MM BARS)
TOTAL LENGTH OF 10MM BAR = Σ(LENGTH x 10MM BARS)
TOTAL NO. OF BARS = ΣTOTAL LENGTH / LENGTH OF BAR
GI WIRE = Σ(16MM BARS x 10MM BARS x TIE LENGTH) / 53

COMPUTATION FOR MAIN BARS


TB1TOTAL LENGTH = Length x 16 mm bars RB1TOTAL LENGTH = Length x 16 mm bars
C1TOTAL LENGTH = 2.55 x 7 = 17.85 m C1TOTAL LENGTH = 2.55 x 4 = 10.2 m
4 TB1TOTAL LENGTH = 4 (17.85) = 71.4 m 6 TB1TOTAL LENGTH = 6 (10.2) = 61.2 m

TB2TOTAL LENGTH = Length x 16 mm bars RB1TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.5 x 6 = 15 m C1TOTAL LENGTH = 2.5 x 4 = 10 m
4 TB2TOTAL LENGTH = 4 (15) = 60 m 4 TB1TOTAL LENGTH = 4 (10) = 40 m

TB2TOTAL LENGTH = Length x 16 mm bars RB1TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.1 x 6 = 12.6 m C1TOTAL LENGTH = 2.3 x 4 = 9.2 m
2 TB2TOTAL LENGTH = 2 (12.6) = 25.2 m 2 TB1TOTAL LENGTH = 2 (9.2) = 18.4 m

B1TOTAL LENGTH = Length x 16 mm bars RB1TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.55 x 9 = 22.95 m C1TOTAL LENGTH = 3.1 x 4 = 12.4 m
4 B1TOTAL LENGTH = 4 (22.95) = 91.8 m 2 TB1TOTAL LENGTH = 2 (12.4) = 24.8 m

B2TOTAL LENGTH = Length x 16 mm bars RB1TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.55 x 9 = 22.95 m C1TOTAL LENGTH = 2.2 x 4 = 8.8 m
2 B2TOTAL LENGTH = 2 (22.95) = 45.9 m
RB1TOTAL LENGTH = Length x 16 mm bars
C1TOTAL LENGTH = 2.1 x 4 = 8.4 m
B3TOTAL LENGTH = Length x 16 mm bars 2 TB1TOTAL LENGTH = 2 (8.4) = 16.8 m
C1TOTAL LENGTH = 2.3 x 6 = 13.8m
2 B3TOTAL LENGTH = 2 (13.8) = 27.6 m ΣTOTAL LENGTH OF MAIN BAR
= 71.4 + 60 + 25.2 + 91.8 + 45.9 + 27.6 + 22.5 + 18.9 + 15 + 45 + 18.9 +
B4TOTAL LENGTH = Length x 16 mm bars 61.2 + 40 + 18.4 + 24.8 + 24.8 + 8.8 + 16.8
C1TOTAL LENGTH = 2.5 x 9 = 22.5 m = 612.2 = 613 m

B4TOTAL LENGTH = Length x 16 mm bars TOTAL NO. OF MAIN BAR = ΣTOTAL LENGTH OF MAIN BAR
C1TOTAL LENGTH = 2.1 x 9 = 18.9 m LENGTH OF BAR
TOTAL NO. OF MAIN BAR = 613 / 6
B5TOTAL LENGTH = Length x 16 mm bars TOTAL NO. OF MAIN BAR = 102.17= 103 PCS
C1TOTAL LENGTH = 2.5 x 6 = 15 m

B6TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.5 x 9 = 22.5 m
2 B6TOTAL LENGTH = 2 (22.5) = 45 m

B6TOTAL LENGTH = Length x 16 mm bars


C1TOTAL LENGTH = 2.1 x 9 = 18.9 m

COMPUTATION FOR STIRRUP


RB1TOTAL LENGTH = Length x 10 mm bars
C1TOTAL LENGTH = 1.3 x 23 = 29.9 m
TB1TOTAL LENGTH = Length x 10 mm bars
C1TOTAL LENGTH = 1.4 x 25 = 35 m
4 TB1TOTAL LENGTH = 4 (35) = 140 m

TB2TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 25 = 35 m
4 TB2TOTAL LENGTH = 4 (35) = 140 m

TB2TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 22 = 30.8 m
2 TB2TOTAL LENGTH = 2 (30.8) = 61.6 m

B1TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 25 = 35 m
4 B1TOTAL LENGTH = 4 (35) = 140 m

B2TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 25 = 35 m
2 B2TOTAL LENGTH = 2 (35) = 70 m

B3TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.5 x 23 = 34.5 m
2 B3TOTAL LENGTH = 2 (34.5) = 69 m

B4TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 25 = 35 m

B4TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 22 = 30.8 m

B5TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.3 x 25 = 32.5 m

B6TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 25 = 35 m
2 B6TOTAL LENGTH = 2 (35) = 70 m

B6TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.4 x 22 = 30.8 m

RB1TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.3 x 25 = 32.5 m
10 RB1TOTAL LENGTH = 10 (32.5) = 325 m

RB1TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.3 x 23 = 29.9 m
2 TB1TOTAL LENGTH = 2 (29.9) = 59.8 m

RB1TOTAL LENGTH = Length x 10 mm bars


C1TOTAL LENGTH = 1.3 x 28 = 36.4 m
2 TB1TOTAL LENGTH = 2 (36.4) = 72.8 m
CHB REINFORCEMENT FRONT ELEV. (10MM BARS)

LENGTH OF VERT. LENGTH OF HOR. TOTAL GI WIRE


AREA (SQ.M)
REINF. REINF. LENGTH (KG)

25.99 55.3587 55.8785 112 0.83


TOTAL NO. OF 10MM BARS 19 0.83

LENGTH OF BAR = 6M ; GI WIRE = AREA x 0.032


LENGTH OF VERT. REIF. = AREA x 2.13
LENGTH OF HOR. REINF. = AREA x 2.15
TOTAL LENGTH = LENGTH OF VERT. REINF. + LENGTH OF HOR. REINF.

COMPUTATION FOR AREA

Walls Roof Total Area

Length = 6 m Length = 6 m Area Total = (Area walls + Area roof ) – (Ad1 + Ad2 +
Aw1 + Aw2 + Aw3 + C1 + B1 + RB1)
Height = 6.05 m Height = 1.35 m
Area Total = (36.3 + 4.05) – (1.8357 + 3.4 +2.34 +
Area walls = L * H Area roof = ½ (L * H) 0.78 +1.14 + 0.27 + 2.295 +2.295)
= 6 * 6.05 = ½ (6 * 1.35) Area Total = 25.9943 m2
Area walls = 36.3 m2 Area roof = 4.05 m2

Window 1 Door 1 Beam 1

Length = 1.2 m Length = 0.87 m Length = 5.1 m

Height = 1.95 m Height = 2.11 m Height = 0.45 m

Aw1 = L * H Ad1 = L * H N=1

=1.2 * 1.95 = 0.87 * 2.11 AB1 = L * H * N

Aw1 = 2.34 m2 Ad1 = 1.8357 m2 = 5.1 * 0.45 * 1


AB1 = 2.295 m2

Window 2 Door 2 RBeam 1

Length = 0.6 m Length = 1.7 m Length = 5.1 m


Window 3 Column 1

Length = 0.6 m Length = 0.3 m

Height = 1.9 m Height = 0.3 m

Aw3 = L * H N=3

=0.6 * 1.9 AC1 = L * H * N

Aw3 = 1.14 m2 = 0.3 * 0.3 * 3


AC1 = 0.27 m2

GI WIRE = AREA x 0.032


AREA = 25.99 m2 x 0.032 kg/m2
GI WIRE = 0.83 kg
CHB REINFORCEMENT REAR ELEV. (10MM BARS)

LENGTH OF VERT. LENGTH OF HOR. TOTAL GI WIRE


AREA (SQ.M)
REINF. REINF. LENGTH (KG)

32.517 69.26121 69.91155 140 1.04


TOTAL NO. OF 10MM BARS 24 1.04

LENGTH OF BAR = 6M ; GI WIRE = AREA x 0.032


LENGTH OF VERT. REIF. = AREA x 2.13
LENGTH OF HOR. REINF. = AREA x 2.15
TOTAL LENGTH = LENGTH OF VERT. REINF. + LENGTH OF HOR. REINF.

COMPUTATION FOR AREA

Walls Total Area GI WIRE = AREA x 0.032


Length = 6 m Area Total = (Area walls + Area roof ) – (Ad1 + Aw1 + AREA = 32.517 m2 x 0.032 kg/m2
Aw2 + Aw3 + C1 + RB1)
Height = 6.05 m GI WIRE = 1.04 kg
Area Total = (36.3 + 4.05) – (1.688 + 1.68 +1.54 +
Area walls = L * H
0.36 + 0.27 + 2.295)
= 6 * 6.05
Area Total = 32.517 m2
2
Area walls = 36.3 m

Window 1 Door 1 Window 2

Length = 1.4 m Length = 0.8 m Length = 1.4 m

Height = 1.2 m Height = 2.11 m Height = 1.1 m

Aw1 = L * H Ad1 = L * H Aw2 = L * H

=1.4 * 1.2 = 0.8 * 2.11 =1.4 * 1.1

Aw1 = 1.68 m2 Ad1 = 1.688 m2 Aw2 = 1.54 m2


Window 3 Column 1 RBeam 1

Length = 0.6 m Length = 0.3 m Length = 5.1 m

Height = 0.6 m Height = 0.3 m Height = 0.45 m

Aw3 = L * H N=3 N=1

=0.6 * 0.6 AC1 = L * H * N AB1 = L * H * N

Aw3 = 0.36 m2 = 0.3 * 0.3 * 3 = 5.1 * 0.45 * 1


AC1
CHB = 0.27 m2
REINFORCEMENT RIGHT ELEV.A B1 = 2.295
(10MM m2
BARS)
AREA (SQ.M) LENGTH OF VERT. LENGTH OF HOR. TOTAL GI WIRE
REINF. REINF. LENGTH (KG)
64.67 137.7471 139.0405 277 2.07
TOTAL NO. OF 10MM BARS 47 2.07

LENGTH OF BAR = 6M ; GI WIRE = AREA x 0.032


LENGTH OF VERT. REIF. = AREA x 2.13
LENGTH OF HOR. REINF. = AREA x 2.15
TOTAL LENGTH = LENGTH OF VERT. REINF. + LENGTH OF HOR. REINF.

COMPUTATION FOR ARE

Wall 1 Wall 2 Total Area


Length = 9.52 m Length = 9.5 m Area Total = (Area wall1 + Area wall2 + Area wall3 ) – (
Height = 1.05 m C1 + C2 + RB1 + B6)
Height = 6.05 m
Area wall1 = L * H Area Total = (9.996+ 57.475 + 3.965) – (0.18+ 0.2
Area wall2 = L * H
+3.195 + 3.195)
= 9.52 * 1.05 = 9.5 * 6.05
Area Total = 64.666 m2
2
Area wall1 = 9.996 m Area wall2 = 57.475 m2

Wall 3 RBeam 1
Column 1
Length = 1.3 m Length = 7.1 m
Length = 0.3 m
Height = 3.05 m Height = 0.45 m
Height = 0.3 m
Aw1 = L * H N=1
N=2
=1.3 * 3.05 AB1 = L * H * N
AC1 = L * H * N
2
Aw1 = 3.965m = 7.1 * 0.45 * 1
= 0.3 * 0.3 * 2
2
AB1 = 3.195 m
AC1 = 0.18 m2

Column 2 Beam 6 GI WIRE = AREA x 0.032


Length = 0.4 m Length = 7.1 m AREA = 64.67 m2 x 0.032 kg/m2
Height = 0.25 m Height = 0.45 m GI WIRE = 2.07 kg
N=3 N=1
CHB REINFORCEMENT LEFT ELEV. (10MM BARS)

LENGTH OF VERT. LENGTH OF HOR. TOTAL GI WIRE


AREA (SQ.M)
REINF. REINF. LENGTH (KG)

36.41 77.5533 78.2815 156 1.17


TOTAL NO. OF 10MM BARS 26 1.17

LENGTH OF BAR = 6M ; GI WIRE = AREA x 0.032


LENGTH OF VERT. REIF. = AREA x 2.13
LENGTH OF HOR. REINF. = AREA x 2.15
TOTAL LENGTH = LENGTH OF VERT. REINF. + LENGTH OF HOR. REINF.

COMPUTATION FOR AREA

CHB and Mortar (Front Elevation)


Computation for CHB

Wall 1 Wall 2 Total Area

Length = 6.05 m Length = 1.3 m Area Total = (Area wall1 + Area wall2 ) – (Aw1 + Aw2 +
Aw3 + Aw4 + Aw5 + C1 + C2 + B4 + B5 + RB1)
Height = 8.5 m Height = 3.05 m
Area Total = (51.425 + 3.965) – (2.34 + 1.68
Area walls = L * H Area roof = L * H +1.68 + 1.54 +1.54 + 0.18 + 0.2 +2.07 + 1 +
= 6 .05* 8.5 = 1.3 * 3.05 6.75)

Area wall1 = 51.425 m2 Area Wall2 = 3.965 m2 Area Total = 36.41m2

Window 1 Window 5 Beam 4

Length = 1.2 m Length = 1.4 m Length = 4.6 m

Height = 1.95 m Height = 1.1 m Height = 0.45 m

Aw1 = L * H Aw5 = L * H N=1

=1.2 * 1.95 = 1.4 * 1.1 AB4 = L * H * N

Aw1 = 2.34 m2 Aw5 = 1.54 m2 = 4.6 * 0.45 * 1


AB4 = 2.07 m2

RBeam Column 2
Window 4
Length = 7.5 m Length = 0.4 m
Length = 1.4 m
CHB REINFORCEMENT INTERIOR (10MM BARS)

LENGTH OF VERT. LENGTH OF HOR. TOTAL GI WIRE


AREA (SQ.M)
REINF. REINF. LENGTH (KG)

48.03 102.3039 103.2645 206 1.54


TOTAL NO. OF 10MM BARS 35 1.54

LENGTH OF BAR = 6M ; GI WIRE = AREA x 0.032


LENGTH OF VERT. REIF. = AREA x 2.13
LENGTH OF HOR. REINF. = AREA x 2.15
TOTAL LENGTH = LENGTH OF VERT. REINF. + LENGTH OF HOR. REINF.

COMPUTATION FOR AREA

First Floor

Wall 1 Wall 2
Length = 4.23 m Length = 4.2 m
Height = 3.05 m Height = 3.05 m
Area wall1 = L * H Area wall2 = L * H
= 4.23 * 3.05 = 4.2 * 3.05
Second Floor
Area wall1 = 12.9015 m2 Area wall2 = 12.81 m2

Wall 3 Wall 4 Wall 5


Length = 2.54 m Length = 2.37 m Length = 1.8 m
Height = 3 m Height = 3 m Height = 3 m
Awall3 = L * H Area wall4 = L * H Area wall5 = L * H
= 2.54* 3 = 2.37 * 3 = 1.8 * 3
Awall3 = 7.62 m2 Area wall4 = 7.11 m2 Area wall5 = 5.4 m2

Wall 6 Wall 7 Wall 8


Length = 0.4 m Length = 1.8 m Length = 2.3 m
Height = 3 m Height = 3 m Height = 3 m
Area wall6 = L * H Area wall7 = L * H Area wall8 = L * H
= 0.4 * 3 = 1.8 * 3 = 2.3 * 3
Area wall6 = 1.2 m2 Area wall7 = 5.4 m2 Area wall8 = 6.9 m2
SLAB REINFORCEMENT (10MM BARS)
LENGTH WIDTH LONG. CUT BARS TRANS. CUT BARS TOTAL GI WIRE
MARK
(m) (m) TOP BOT TOP BOT LENGTH (KG)
SOG 7.9 5.4 0 27 0 40 430 6.11
S1-2 2.55 2.55 9 10 9 10 97 1.02
S1-2 2.55 2.55 9 10 9 10 97 1.02
S1-2 2.55 2.2 8 9 9 10 86 0.92
S1-2 2.55 2.2 8 9 9 10 86 0.92
S1-2 2.55 2.55 9 10 9 10 97 1.02
S2-2 2.55 0.7 2 3 7 8 24 0.22
S2-2 0.8 0.7 2 3 2 3 8 0.07
TOTAL NO. OF 10MM BARS 155 11.3

LENGTH OF 16 MM BAR = 6M ; TIE LENGTH = 0.3M ; 1KG WIRE = 53M


TOTAL LENGTH = Σ[(LENGTH x LONG. CUT BARS) + (WIDTH x TRANS. CUT BARS)]
TOTAL NO. OF BARS = ΣTOTAL LENGTH / LENGTH OF BAR
GI WIRE = Σ(LONG. CUT BARS x TRANS. CUTBARS x TIE LENGTH) / 53

COMPUTATION FOR TOTAL LENGTH OF BAR


TOTAL LENGTH = Σ[(Length x (top + bot)LONG + Width x (top + bot)TRANS)]

SOG = 7.9 (0+27) + 5.4(0 + 40) = 430 m

S1-2 = 2.55 (9 + 10) + 2.55 (9 + 10) = 97 m

S1-2 = 2.55 (9 + 10) + 2.55 (9 + 10) = 97 m

S1-2 = 2.55 (8 + 9) + 2.2 (9 + 10) = 86 m

S1-2 = 2.55 (8 + 9) + 2.2 (9 + 10) = 86 m

S1-2 = 2.55 (9 + 10) + 2.55 (9 + 10) = 97 m

S2-2 = 2.55 (2 + 3) + 0.7 (7 + 8) = 24 m

S2-2 = 0.8 (2 + 3) + 0.7 (2 + 3) = 8 m

ΣTOTAL LENGTH = SOG + S1-2 + S1-2 + S1-2 + S1-2 + S1-2 + S2-2 + S2-2
= 430 + 97 + 97 + 86 + 86 + 97 + 24 + 8ΣTOTAL LENGTH
= 925 m

TOTAL NO. OF BARS = ΣTOTAL LENGTH / LENGTH OF BAR

TOTAL NO. OF BARS = 925 / 6


TOTAL NO. OF BARS = 154.17 = 155 PCS
GI WIRE = Σ(LONG. CUT BARS x TRANS. CUT BARS x 0.3)/53
SOG = [(0+27) (0+40) (0.3)]/53 = 6.11 kg

S1-2 = [(9+10) (9+10) (0.3)]/53 = 1.02 kg

S1-2 = [(9+10) (9+10) (0.3)]/53 = 1.02 kg

S1-2 = [(8+9) (9+10) (0.3)]/53 = 0.92 kg

S1-2 = [(8+9) (9+10) (0.3)]/53 = 0.92 kg

S1-2 = [(9+10) (9+10) (0.3)]/53 = 1.02 kg

S2-2 = [(2+3) (7+8) (0.3)]/53 = 0.22 kg

S2-2 = [(2+3) (2+3) (0.3)]/53 = 0.07 kg

GI WIRE = SOG + S1-2 + S1-2 + S1-2 + S1-2 + S1-2 + S2-2 + S2-2


= 6.11 + 1.02 + 1.02 + 0.92 + 0.92 + 1.02 + 0.22 + 0.07
= 11.3 kg
COST ESTIMATES FOR STEEL WORKS

SIZE TOTAL NO. OF BARS PRICE (PHP)

10MM 717 117588

12MM 11 2607

16MM 323 135660

TOTAL PRICE (PHP) 255855

GI WIRE

SIZE TOTAL WEIGHT PRICE PER 35 KG (PHP)

16 111.1 2100

TOTAL PRICE (PHP) 6300

TRUSS QTY PRICE

1.5"x1.5"x3/16" ANGLE BAR 24 275

1"x1"x1/8" ANGLE BAR 14 225

WELDING ROD 15 105

TOTAL PRICE (PHP) 11325

C-PURLINS LENGTH (m) QTY

2" x 4" x 1.8mm 9.52 9

TOTAL C-PURLINS (6m) 15

TOTAL PRICE (PHP) 13650


OVERALL COST

TOTAL PROJECT COST 287130 PESOS

OVERHEAD AND
CONTINGENCY 28713 PESOS

TOTAL SINGIL 315843 PESOS