PROJECT UPDATE

JULY 3RD, 2020

IML LABELS
COLOMBIA
Granular base installation around the
loading dock, Preparing for concrete.
Getting the
Machine
Foundations
ready for concrete
Lighting above the machine
foundation it has been
completed
Sub-station raised floor and wiring ditches

Studs for drywall partitions in the admin area are


being put up, so the electricians can start wiring
Construction of rebar
drainage in the truck
parking area to collect
Rainwater as well as any
oil residue from loading
dock area
Organizing grounds for
sidewalks and road access
in west façade
SUMMARY

• Now that we have started with the sprinkler work, we also going to start with all
paperwork and site work ready for the prefabricated tank order. (The drawings you requested
this week; the designer is already making adjustments)

• To install the egress doors and other access is necessary to cut the steel tubes holding the
panel to the structure and form and size the frame and lintels of the doors. Is that
material coming from Germany or are we solving it with local material??