Terms Related To Events

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

  Module : Network Based Project Management(Event)                                                                              Print this page

<< Previous |  First |  Last |  Next >>      

  If    is the expected occurrences time of an activity between event i and j and and is the earliest
occurrence time of the occurrence of this event then earliest occurrence time of occurrence of the event j is related to
that of event i as
= +

  If there are many activities leading to the event j then earliest expected time of j is

=max( + ) for all i

<< Previous |  First |  Last |  Next >>      