Professional Documents
Culture Documents
Solution of Electromagnetic Compatibility Problem in Electrical Power Network Using The Finite Element Method
Solution of Electromagnetic Compatibility Problem in Electrical Power Network Using The Finite Element Method
net/publication/224224461
CITATIONS READS
0 429
3 authors:
Rino Lucic
University of Split
19 PUBLICATIONS 75 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Numerical modeling of electromagnetic phenomena in the electric power system View project
Power System fault types classification with deep learning method View project
All content following this page was uploaded by Ivica Jurić‐Grgić on 11 May 2020.
(1*,1((5,1*
$3077&URDWLD-RLQW&KDSWHU $1'&20387,1*
&RQIHUHQFH3URFHHGLQJV
WK
,QWHUQDWLRQDO&RQIHUHQFHRQ
$SSOLHG(OHFWURPDJQHWLFVDQG
&RPPXQLFDWLRQV
±6HSWHPEHU
'XEURYQLN&URDWLD
A CIP catalogue record for this publication is available from the National and
University Library in Zagreb under No. 742932.
ISBN 978-953-6037-58-2
Organized by:
University of Zagreb, Faculty of Electrical Engineering and Computing
KoREMA – Croatian Society for Communications, Computing, Electronics,
Measurement and Control, Zagreb, Croatia; member of IMEKO and IFAC
IEEE Croatia Section
IEEE AP/MTT Joint Chapter
Co-sponsored by:
IEEE Region 8
European Association on Antennas and Propagation (EurAAP)
University of Zagreb, Faculty of Electrical Engineering and Computing
University of Dubrovnik
KoREMA
Region 8
ICECom 2010 Conference proceedings
&RQIHUHQFH&KDLU
Juraj Bartoli, University of Zagreb, FER, Croatia
7HFKQLFDO3URJUDP&RPPLWWHH73&
5HYLHZ%RDUG
Abstract
In overall expansion of power distribution and sub-transmission (10 kV - 110 kV) networks, conditioned
with growing consumption of electrical power, there is an increasing of possibility for crossing underground
power cables with home electrical installation cables, telecommunication equipment cables and other
equipment. Furthermore, surge arresters on middle-voltage levels usually are not applied along overhead lines.
Above mentioned can affect on equipment or even human life safety. It is known that interference of the different
electrical installations and equipment is the main theme of researching in Electromagnetic Compatibility
(EMC). In this article, a possibility of using the Finite Element Method (FEM) for EMC calculations in practice,
is explored and presented. For that purpose, a real problem from distribution power network will be used for an
illustrative example. It is worth of mentioning that FEM technique is quite a new tool in power networks
calculations area.
t - time interval
Fig. 1. Multi-conductor transmission line finite
element
. - integration parameter
The corresponding local system of equations, The variables’ vectors in (2) marked by “+” denote
developed in [11], is: vectors at the end of the time interval, while
variables’ vectors without mark denote vectors at the
beginning of the time interval.
i u
1
A
1
B 3. TEST EXAMPLE
i2 u2 (2)
3.1 Description
i u
E 1 F 1
i2 u2
As an example, for illustration of using a
FEM technique in EMC analysis, a real problem
from power distribution network exploitation is
where: taken. Transient surges in one of the overhead
conductors, due to direct lightning strike, causes
( L R t ) ( L R t ) interference in other adjacent conductors. It's a
A 2 2
common phenomenon observed in power lines,
I t I t communication lines etc., even in pipeline systems.
Considered configuration is illustrated on Figure 2. It
is consist from 50 m of 35 kV overhead lines with its
junction to 35 kV busbars in the main area of
I t I t distribution substation. From 35 kV substation
B busbars, a power underground cable with sheath goes
( C G t) ( C G t) as an outgoing feeder toward some consumer load.
2 2 Along first 75 meters beneath power cable, an
installation 0.4 kV power cable is lied. Further,
outgoing feeder goes normally in 100 m length to the
symmetrical three-phase consumer load.
( L R (1 ) t) ( L R (1 ) t)
E 2 2
I (1 ) t I (1 ) t LightningstrokeinphaseL1
Substationbusbars 35 kV
L1 L2 L3
35 kV Overhead line,150mm2
50m
I (1 ) t I (1 ) t
F
35 kV underground cable,150mm2 35 kV underground cable,150mm 2
75m 100 m
( C G (1 ) t) ( C G (1 ) t)
2 2 R 0.001
Sheath phase A
R 0.001
R 0.001
Sheath phaseC
R 0.001
LOAD
equipment. IOHLA IA IA
The magnitudes of those induced voltages in
R 10
installation 0.4 kV cable are considerable in a case of R 0.001 I SHEATH A I SHEATH A
substation, which can cause a serious damage and I SHEATH B I SHEATH B R 10
even jeopardizes a human life. In observed case, a
R 0.001
R 0.001
In purpose of the obtaining network Table 1 Connection matrix between local and
elements parameter, the state-of-art electromagnetic global nodes
transient simulation software is used [12]. The
obtained impedance and admittance matrices are
used as input parameters in FEM program (Figure 3)
Voltage (V)
450
underground power cables etc.) have been modeled
400
as MTL finite elements. With proposed approach,
350 relatively complex part of observed power
300 distribution network can be analyzed as a set of
250 discrete finite elements which are connected via
200 connection matrix. After discretisation and
150 assembling procedures, a system of linear equations
100 is solved in MATLAB program. In that way it is
50 shown that use of FEM in EMC problems is an
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
efficient tool.
-4
Time (s) x 10
180
Compatibility in Power Systems" , (Elsevier
160 Science 2006)
140 [2] Clayton R. Paul, "Introduction to
120
Electromagnetic Compatibility", 2nd ed., (Wiley-
Interscience, 2006.)
100
[3] L.M. Wedepohl, "Applications of matrix
80
methods to the solution of traveling-wave
60 phenomena in polyphase systems", PROC. IEE,
40 Vol. 110 , No. 12, December 1963, pp. 2200-
20
2212
[4] C.R. Paul, "Analysis of Multiconductor
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
-4
Transmission Lines", (John Willey & Sons,
Time (s) x 10
1994).
[5] J.B. Faria, "Multiconductor Transmission-Line
Fig. 6. Induced voltage in a phase B of the 0.4 kV
Structures", (John Willey & Sons, 1993).
installation cable [6] H.W. Dommel, Electromagnetic Transients
Program Reference Manual (EMTP Theory
200 Book).( BPA, 1986).
Voltage (V)
100
1982).
80 [9] J. Fish, T. Belytschko: "A First Course in Finite
60 Elements", (John Willey & Sons , 1982).
40 [10] G. Rizzoni, "Principles and Applications of
20
Electrical Engineering", (McGraw Hill, 2003).
[11] Lucić, R.; Jurić-Grgić, I.; Kurtović, M.: "Time
domain finite element method analysis of multi-
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
-4
Time (s) x 10
conductor transmission lines", ETEP: European
Fig. 7. Induced voltage in a phase C of the 0.4 kV Transactions on Electrical Power, published
installation cable online, DOI: 10.1002/etep.366, 2009. (ISSN:
1430-144X).
In the Figures 5, 6 and 7 induced voltages in phases [12] EMTDC Application's Guide, Transient Analysis
A, B and C of the 0.4 kV installation cable have been for PSCAD Power System Simulation, Manitoba,
shown. Induced voltages are the result of lightning 2008.
stroke in a 35 kV underground power cable.
4. CONCLUSION