Professional Documents
Culture Documents
Boq Sector A-4
Boq Sector A-4
SECTOR A-4
BILL OF QUANTITIES
VOLUME-III
DHA QUETTA (SECTOR A-4)
GRAND SUMMARY
1 ROAD WORK
2 STORM WATER DRAINAGE SYSTEM
3 SEWERAGE SYSTEM
4 WATER SUPPLY
5 UTILITY CROSSING DUCTS
6 ELECTRIFICATION
TOTAL AMOUNT =
DHA QUETTA (SECTOR A-4)
SUMMARY (ROAD WORK)
CEMENT PLASTERING
13mm thick cement plaster 1:3
MES: 13-3 SM 1,262.19
finished as specified.
1 SEWERAGE NETWORK
2 DWTS
RCC PIPE
Supply and fix reinforced cement concrete
MES 21-05 pipes230mm bore, laid and jointed with spigot Meter 15,603.00
socket or collars, as specified.
Supply and fix reinforced cement concrete pipes
300mm bore, laid and jointed with spigot socket
MES 21-07 Meter 2,175.00
or tongue and groove joint incl rubber ring, as
specified.
Supply and fix reinforced cement concrete pipes
375mm bore, laid and jointed with spigot socket
MES 21-08 Meter 959.00
or tongue and groove joint incl rubber ring, as
specified.
Supply and fix reinforced cement concrete pipes
450mm bore, laid and jointed with spigot socket
MES 21-09 Meter 419.00
or tongue and groove joint incl rubber ring, as
specified.
Supply and fix reinforced cement concrete pipes
525mm bore, laid and jointed with spigot socket
MES 21-10 Meter 297.00
or tongue and groove joint incl rubber ring, as
specified.
Supply and fix reinforced cement concrete pipes
600mm bore, laid and jointed with spigot socket
MES 21-11 Meter 479.00
or tongue and groove joint incl rubber ring, as
specified.
CONCRETE MANHOLE
Manhole complete rectangular or circular as
MES: 21-31 described, exceeding 600mm but not exceeding
Prorata 1800mm deep with iron steps (in angles 380mm Cum 1,366.41
(200mm wall) centers),230 mm thick poured concerte walls.
DHA QUETTA (SECTOR-A)
ABSTRACT OF QUANTITIES
SEWERAGE SYSTEM
RATE AMOUNT
PAY ITEM DESCRIPTION UNIT QUANTITY
(PKR) (PKR)
MANHOLE COVER
Providing and laying RCC type B manhole cover
(precast complete with angle iron frame
MES: 21-35 Each 832.00
embedded in concrete all as per information
sheet No. Svcs-341 dated 10-11-99.
HOUSE CHAMBER
Manholes complete rectangular or circular as
described n.exceeding 600mm deep form
MES: 21-28 Each 199.00
inverted to surface of cover, including main
channel set in CM 1:1, 150 mm thick RCC walls.
Total Amount Carried to Summary (Sewerage System) (PKR) =
ENGINEER ESTIMATE FOR DHA QUETTA
DIRTY WATER TREATMENT SYSTEM
MAIN SUMMARY
S. NO. DESCRIPTION AMOUNT (PKR)
1 ANAEROBIC BAFFLED REACTOR
2 ANAEROBIC FILTERS
3 EFFLUENT TANK
4 SETTLER TANK
5 CHAMBER
TOTAL AMOUNTCARRIED TO SUMMARY (SEWERAGE
SYSTEM) =
ENGINEER ESTIMATE FOR DHA QUETTA
EFFLUENT TANK
CIVIL WORKS
Sr.
Description Unit Quantity Rate Amount
No.
1 Clearing and Grubbing
Clearing of site including cutting of Tree Shrubs
1.1 and obstruction according to satisfaction of
engineer. Sqm 260.22
2 EXCAVATION
Excavation as in Ordinary Soil upto 1.5m depth,
in foundation and pipe trenches upto 1.5 m wide
in shafts, wells and independent holes upto 30
Sqm each and throw earth clear of edges of
2.1
excavation within 10 m. Timbering to be paid
extra (Trench over 1.5 m width will be treated as
areas).
Cum 891.49
2.2 Back Fill
Earth filling as in Ordinary or hard soil ,filling in
foundation , pipe trenches, shafs, wells,
independent holes, under floors or around plinth
etc, 1.5 M below or above Ground Level (GL),
with spoil obtained from excavation in
trenches/over areas within 10m including
watering and compaction in 150mm layer and
dressing to required profile and shape.
Cum 304.53
Compaction of Natural ground upto 95%
2.3
modified ASHTO density all as spd. Sqm 158.98
3 CONCRETE -
Providing, mixing, depositing, curing and
compacting cement concrete using ordinary
cement 1:4:8 in foundation etc, as shown on the
drawing with clean local sand and using crush
3.1
stone graded as spd including formwork where
required etc, complete in all respect and as
directed by Engineer lncharge.
Cum 15.98
ENGINEER ESTIMATE FOR DHA QUETTA
EFFLUENT TANK
CIVIL WORKS
Sr.
Description Unit Quantity Rate Amount
No.
Providing, mixing, depositing, vibrating and
curing, reinforced cement concrete using
crushed stone and clean sand, conform to
ASTM with minimum cylindrical strength of
3000 psi at 28 days with RCC Type- '8' as under
including water tight shuttering fixing and
removing etc, but excluding the cost of
3.2
reinforcing steel including the cost of extra
labour for fixing of pipes, opening and making of
drip course mould etc, complete in all respects
at any floor and any height, as per
specifications, drawings and all to the approval
of the Engineer lncharge.
-
a. Footings and raft foundation using ordinary
cement as in RCC Type 'B' concrete not
leaner than 3000 PSI. Cum 59.61
b. Beams, lintels, Slab & stair etc using ord
3.3 cement as in RCC Type 'B' concrete not leaner
than 3000 PSI and ratio (1·2:4):- -
I. up to 12 Mtr height from G.L. upto 3rd Floor
Cum 21.25
3.4 a. Walls & Column :- -
I. up to 12 Mtr above from G.L (including GL
to footing). Cum 58.89
STEEL REINFORCEMENT -
a. Supplying, cutting, bending, binding and
fixing in position Deformed bar steel
conforming to ASTM A-615 and made of
best quality billets and having minimum yield
strength of 60,000 PSI including cost of binding
wire of 14SWG including wastage, spd/
3.5 unspd laps, steel chairs rolling margin etc, at
any floor and any height complete in all
respects as per drawings and all to the
approval of the Engineer lncharge any floor
and any height over laps and chairs not to be
paid (incl steelchairs).
Kg 15,600.00
ENGINEER ESTIMATE FOR DHA QUETTA
EFFLUENT TANK
CIVIL WORKS
Sr.
Description Unit Quantity Rate Amount
No.
4 PLASTER WORK
Providing and applying cement sand plaster 13
mm thick internal and external surfaces of walls
ceiling at any floor and any height to all surfaces
and planes both normal and oblique inclusive of
corners, splays in jamb, curves, recesses,
grooves, moulding, scaffoldings, labour, curing,
cleaning, bomding, etc,complete in all respects
as per drawings, specifications, and as directed
by the Engineer Incharge.
-
a. 13mm thick cement plaster (1:6) internal
4.1
walls etc. and add Pudlo Plaster. Sqm 297.40
b. 13mm thick cement plaster (1:4) on ceilings
4.2 surfaces and external walls.etc where
mention Sqm 257.55
5 Grill / Ladder -
Supply and fix hold fast, guard bars, Straps for
wooden trusses, holding down bolts with
washers, ladders, railings, brackets, pipe
supports, tie rods and balusters, chimny bars,
5.1 chains, rings shackles, hinges and type, grating
or gullies, etc. including forging, letting in to
stone or brick work etc: complete, by welding in
lieu of riveting/bolting etc.
Kg 40.00
6 MISCELLANEOUS
---do--- but 50mm dia UPVC for sleeves of GF
6.1 as per drawings.
Mtr 4.00
Supply and fixing cast iron manhole cover for
overhead water tank 600mm with frame
6.2 exceeding 7.5Kg but not exceeding 10 Kg/Each
set in Cm and handing in concrete as spd.
Each 4.00
Providing and fixing of PVC water stopper 190
6.3 Mtr 65.83
mm wide
TOTAL AMOUNT CARRIED TO SUMMARY DWTS (PKR) =
ENGINEER ESTIMATE FOR DHA QUETTA
ANAEROBIC BAFFLED REACTOR
CIVIL WORKS
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
Excavation
01-6 Excavation in over area as in Ordinary soil
upto 1.5 m depth, in foundation / to obtain
earth for filling under floors/areas etc,or for
Cum 832.00
shafts,wells,exc 30 Sqm each clear of edges
of excavation within 10 M
01-6+
1.5 M to 3.0 M. Cum 832.00
01 - 13
01-6+
3.0 M to 4.5 M. Cum 238.40
2 (01 - 13)
Termite
11-1 Termite Proofing of new buildings incl wood
work therein with approved chemicals. Sqm 974.20
R.C.C
03-36 Providing and laying RCC 28 Mpa (4000 psi)
cylinder strength ,as in piers ,foundations
etc,incl lead up to 5 km without the use of
Cum 348.00
shuttring .Reinforcement to be measured and
Paid Separately .
Cum 156.00
DHA QUETTA (SECTOR A-4)
ABSTRACT OF QUANTITIES
OVERHEAD TANKS (2 Nos, 100,000 Each)
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
03-34
ii) Lift 40' - 50' Cum 34.00
+03-71
03-34
iii) Lift 50' - 60' Cum 34.00
+ 2 * (03-
03-34+
iv) Lift 60' - 70' Cum 70.80
3 * (03-71)
03-34
v) Lift 70' - 80' Cum 149.20
+ 4 * (03-
71)
03-34
+ 5 * (03- vi) Lift 80' - 90' Cum 76.20
71)
03-35 Providing and laying RCC 28 Mpa (4000 psi)
cylinder strength ,as in columns
,beams,stairs,posts ,struts ,piers ,lintels
and the like,incl lead up to 5 km as specified
,requiring shuttring .Reinforcement to be
measured and Paid Separately.
i) Lift 00' - 40'
Cum 11.62
03-35 ii) Lift 40' - 50'
Cum 3.40
+ 03-71
03-35 + iii) Lift 50' - 60'
Cum 2.20
2*(03-71)
10-102 One coat of water proofing compound using
bitumen 10-20 applied hot at 14.68 Kg per 10
Sqm 455.00
Sqm.
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
Sand Cushion
02 91 Providing Sand Cushion in layers as specified
, under concrete roads ,hard standings and
Cum 8.80
landing grounds etc.
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
Manhole Cover
21-35 Providing and laying, R.C.C Type 'B' manhole
cover (precast) complete with angle iron
frame, embedded in concrete, all as per Each 2.00
information sheet # Svcs-341
Water Stopper
3-32 Providing and fixing of PVC water stopper 190
M 199.00
mm wide.
M.S Pipe
18-429 MS pipe,water quality(Medium),100 mm
dia,with all fittings i.e.
sockets,bends,tees,elbows etc where
required,laid complete in trenches, as M 20.00
specified (excl cost of excavation),supply and
fixing.
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
Supply and fix,holds fast, guard Bars, straps
tor wooden trusses, holding down bolts with
washers, ladders, railing, brackets pipe
supports, tie rods and balusters, chimney
bars, chains, rings shackels, Hinges any type,
09-16 gratings or gullies, etc, incl, froging, letting Kg 1,600.00
into stone or brick work etc. complete by
welding in lieu of riveting bolting etc.
GAUGE
N.S Providing and fixing guage for masurment of
water level in the tank, guage made of 12"
wide M.S sheet 12 guage with painting in
white masurment marks in red along with
masurment arrangment, complete in all Nos. 4.00
respect including pullies, M.S wire, and fixing
arrangements as per instruction of Engineer
Incharge)
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
Excavation
01-6 Excavation in over area as in Ordinary soil
upto 1.5 m depth, in foundation / to obtain
earth for filling under floors/areas etc,or for
Cum 1,159
shafts,wells,exc 30 Sqm each clear of edges of
excavation within 10 M
01-6+
1.5 M to 3.0 M. Cum 1,159
01 - 13
01-6+
3.0 M to 4.5 M. Cum 980
2 (01 - 13)
Termite
11-1 Termite Proofing of new buildings incl wood
work therein with approved chemicals. Sqm 1,450
R.C.C
03-36 Providing and laying RCC 28 Mpa (4000 psi)
cylinder strength ,as in piers ,foundations
etc,incl lead up to 5 km without the use of
Cum 180
shuttring .Reinforcement to be measured and
Paid Separately .
AMOUNT
Pay Item DESCRIPTION UNIT QUANTITY RATE
(PKR)
10-102 One coat of water proofing compound using
bitumen 10-20 applied hot at 14.68 Kg per 10 Sqm 671
Sqm.
13-03 13mm thick cement plaster 1:3 finished as
Sqm 1,222
specified.
13-11 19mm thick cement plaster 1:4 finished as
Sqm 1,227
specified.
Manhole Cover
21-35 Providing and laying, R.C.C Type 'B' manhole
cover (precast) complete with angle iron frame,
embedded in concrete, all as per information Each 4
sheet # Svcs-341
Water Stopper
3-32 Providing and fixing of PVC water stopper 190
M 880
mm wide.
Vent Pipe
Supply and fix 100mm dia bore cast iron soil
20-02 waste and vent (SWV) Pipes as specified. M 8
GAUGE
Providing and fixing guage for masurment of
water level in the tank, guage made of 12" wide
M.S sheet 12 guage with painting in white
masurment marks in red along with masurment
SP arrangment, complete in all respect including Nos. 4
pullies, M.S wire, and fixing arrangements as
per instruction of Engineer Incharge)
SP BUILDING AREA
Complete area of Building Sft 2,716
Total Amount Carried to Summary (UGT) (PKR) =
DHA QUETTA (SECTOR A-4)
SUMMARY (TUBE WELL)
SR .
DESCRIPTION AMOUNT (PKR)
NO
1 CIVIL WORKS
2 MECHANICAL & PLUMBING WORKS
3 ELECTRIFICATION WORKS
ABSTRACT OF QUANTITIES
CIVIL WORKS
EXCAVATION FOR FOUNDATION
Excavation in foundation of building , bridge and other
structure including dagbelling, dressing and refilling
around structure with excavated earth water and
ramming as directed, lead beyond 8 kilometer and lift
3/ 21 (c) upto 5 feet (1.52 m).
Dressing and levelling of earhtwork to designed section,
etc.
In Ordinary soil
%0 Cft 16,121
GRANULAR FILL
Bottoming/ sub base of any thickness as specified using
Granular Sub Base Material laid and compacted to 100%
Mes/ 02- modified AASHTO density by appropriate compacting
Cft 5,862
15 equipment and roller.
P.C.C
Cement concrete plain including compacting, finishing and
curing placing,complete (including screening and washing
6/ 5(i) of stone aggregate):
ABSTRACT OF QUANTITIES
ABSTRACT OF QUANTITIES
Sft 1,394
DHA QUETTA (SECTOR - A)
ABSTRACT OF QUANTITIES
ABSTRACT OF QUANTITIES
CHAKWAL STONE
Providing and laying 3/4" thick (minimum) natural sand
stone fixng with bond around the building , complete in P.Sft 1,285
all respect.
ABSTRACT OF QUANTITIES
ELECTRIFICATION WORKS
ABSTRACT OF QUANTITIES
ZE-04 Fans
Supply, installation, testing, and commissioning complete
with all hardware, wall brackets, cords and other
1 accessories etc. of:
i. Exhaust Fan 12" dia Nos. 64
ZE-05 Earthing and Bonding
Supply, Installation and connecting of 01 Nos. Earth point
comprising of earth rod (copper claded MS rod) 20 mm
dia. 10 ft. length (for double earthing of DB's body) driven
in ground by means of 8 SWG Hard Drawn Bare Copper
1 Job 32
Conductor. The earthing rod shall be complete with fixing
clamps, necessary hardwares etc as per the satisfaction
of The Engineer.
DHA QUETTA (SECTOR - A)
ABSTRACT OF QUANTITIES
MES:'02-15
Bottoming/ sub base of any thickness as
specified using Granular Sub Base Material
laid and compacted to 100% modified CM 470.00
AASHTO density by appropriate compacting
equipment and roller.
1 11KV RMU
Supply, installation, testing and commissioning
of following MV Pad Mounted switches
including Construction of Foundations as per
technical specification, drawings and as per
directed by the Engineer.
i 4 - way RMU Each 39.00
ii 3 - way RMU Each 58.00
ZE-04 HT & LT Cable and Cable Accessories