Professional Documents
Culture Documents
Piney Estimation of Quantities
Piney Estimation of Quantities
Piney Estimation of Quantities
GROUND WORKS
A. SITE CLEARANCE
B. EXCAVATIONS
3, Rock excavation
As above, but +1200% 1 Lab
C. DISPOSALS
BRICKWORK
Common brickwork:
In foundations,
Half brick thick 375/day
One brick thick 400/day
One and half brick thick 425/day
In superstructure up to 2 storeys,
Half brick thick 350/day
One brick thick 380/day
One and half brick thick 400/day
ESTIMATING DATA
In superstructure up to 2 storeys,
Half brick thick 300/day
One brick thick 325/day
In superstructure up to 2 storeys,
One brick thick 330/day 520.00
Mortar
Mixing by hand 8hrs/m3
BLOCKWORK
115mm blockwork:
In foundations 180/day
In superstructure 150/day
230mm blockwork:
In foundations 150/day
In superstructure 120/day
SUNDRIES
Beam filling 3m/hr/skin
Rough cutting 2.5hrs/m2
Cutting pipe chases 1.5hrs/m
Copings 0.75hrs/m
Fair cuttings 1hr/m
Cut small holes 1hr/skin
Cut large holes 2hrs/skin
Fix door and window frames 0.8hrs/m2
Unload and stack 3 lab hrs/1000
Painting around frames 3hrs/m
BRICKWORK
CEMENT MORTAR
CONCRETING
Labour
FORMWORK
PLASTERWORK
GRANO
Rhinosand 8m2/sack(25kg)
Rhinoset 20m2/sack
Rhino bond 6m2/sack
Cemwash 12m2/sack/coat
1m3 cment = 30bags
PAINTING
Paint to ceiling 50m2/day
Paint to walls 60m2/day
Paint to frames 50m2/day
Paint to timber 45m2/day
Paint to small pipes 25m/hr/coat
Paint to large pipes 10m/hr/coat
NB. Add 10% to labour figures for turps,brushes etc.
PVA to plaster
PVA to blockwork:
1st coat 40m2 6m2
2nd coat 35m2 7m2
3rd coat 45m2 9m2
PAINTING
To timber:
1st coat 35m2 7m2
2nd coat 40m2 8m2
Subsequent 50m2 10m2
REINFORCEMENT
1.BASES 90kg/m3
2.COLUMNS 170kg/m3
3.WALLS 100kg/m3
4.SLABS 120kg/m3
5.BEAMS 150kg/m3
FABRIC REINFORCEMENT
Block Volumes
Practical Equivalents
Cement 1 sack 1 sack 1 sack 1 sack 5.44
Aggregate 3.5barrws 4.5barrws 6 barrows 7 barrows 1.06
Dry Volume 0.234 0.291 0.376 0.433
Waste 5% 0.012 0.015 0.019 0.022
0.222 0.276 0.357 0.411
Plant
Concrete Mixer 4.33 0.5 200.00 433.00
Subtotal
Maintanance 5%
Total Cost all in for production of 2870 blocks
CARPENTRY
Fix purlins 1+2 20m/hr
Fix rafters 1+2 14m/hr
Fix trusses ( 8m ) 1+4 4No/day
Fix sprockets 1+2 3m/hr
Fix joists 1+2 15m/hr
Fix hangers 1+2 3m/hr
ESTIMATING DATA
CARPENTRY
JOINERY
Fix brandering one way 1+2 3m2/hr
Fix ceilings 1+3 2m2/hr
Fix cover strip 1+2 20m/hr
Fix cornice 1+2 15m/hr
Fix skirting 1+2 10m/hr
Fix framing 1+1 6m/hr
Cut and fix blocked shelving 1+1 2hrs/sheet
Fix pre-cut shelving 1+1 6m/hr
Hang doors 1+2 1No /hr
Plugging 1+1 8plugs/hr
Screwing 1+1 20/hr
Wheelbarrow 0.057m3
Sack cement 0.034m3
Grout
WET TRADES
SUBSTRUCTURE
Concrete
Grade 10-20 m3 7 x
7;;] sand 5.51
cement 31.24
stone 5.95
Grade 25-20 m3 7
sand 5.00
cement 41.90
stone 6.17
Grade 30-20 m3 1
sand 0.70
cement 8.87
stone 0.90
Grade 30-40 m3 85
sand 60.69
cement 553.35
stone 76.76
Grade 40-20 m3 1
sand 0.62
cement 7.56
stone 0.91
Polythene sheeting
m2 85
m 56.67
Hardcore
m3 1 1.00
Sand blinding
m3 1 1.00
Termite treatment
m2 1
litres 0.11
Half brick wall
m2 102
commons 5552.82
pit sand 2.52
cement 13.89
One brick wall
m2 25
commons 2756.25
pit sand 1.57
cement 8.70
Piers
m3 0.11
commons 52.90
pit sand 0.04
cement 0.20
Face Brick Wall
m2 1
facings 55.65
pit sand 0.02
cement 0.14
Brick-on-edge
m2 1
bricks 38.38
pit sand 0.02
cement 0.02
Thioflex sealant.
m 2
tubes 0.33
Woodfloat plaster
m2 106.9
pit sand 2.47
cement 23.71
undercoat 8.13
EPVA 24.40
SUPERSTRUCTURE cement-0.33m3
Concrete
Grade 10-20 m3 14
sand 11.03
cement 77.18
stone 11.91
Grade 20-20 m3 85
sand 66.05
cement 624.75
stone 68.72
Grade 25-20 m3 1
sand 0.71
cement 5.99
stone 0.88
Grade 30-20 m3 1
sand 0.72
cement 6.77
stone 0.90
Grade 30-40 m3 1
sand 0.71
cement 6.51
stone 0.90
Grade 40-20 m3 0
sand 0.00
cement 0.00
stone 0.00
Screeds
m2 1
river sand 0.05
cement 0.44
Piers
m3 1
commons 411.60
pit sand 0.32
cement 1.78
Brick-on-edge
m2 1
bricks 38.38
pit sand 0.02
cement 0.02
Woodfloat plaster
m2 872
pit sand 20.14
cement 193.37
undercoat 114.45
EPVA 199.04
ROOF COVERINGS
Concrete roof tiles
m2 123
no. 1808.10
Battens m2 1
m 3.20
Skirting
m 2
varnish L 0.35
Pelmets
m 1
varnish L 0.18
Wall plate
m 1
galvanised hoop iron ties 1
carbolineum 0
Painting to metal
m2 30
undercoat 2.63
metal primer 2.63
high gloss 5.27
Painting to wood
m2 50
undercoat 4
wood primer 4
high gloss 9
ONE BRICK WALL note - brickforce is every 3 courses and includes 10% waste
bricks do not include waste
CONCRETE WORKS
ratio
1:3:6 1 4.3 0.55 0.88
1:6 0 0 0.00
1:6 0 0 0
1:6 0 0 0
3.7 5.2
5.6
Girth Collection
PROJECT ………………………………
31,419.19
Variations -
31,419.19
Sub-Contractor
Checked By …………………………………
Projects Manager Accounts
Authorised by …………………………………
General Manager Project QS
WINDOW & DOOR SCHEDULE FOR THE PROPOSED
DOORS
44mm External quality semi solid core flush panel doors
suitable for painting and hung to pressed steel frames
DOORS
44mm External quality semi solid core
flush panel doors
1 Door size 813x2032mm high No 1 54.00 54.00
IRONMONGERY
The following ironmongery to be fixed to timber
doors and pressed steel frames
"Union" or similar approved lockset
3 Three lever Union lockset No 1 15.00 15.00
4 Two lever Union lockset No 1 12.50 12.50
5 Rubber door stop No. 2 1.00 2.00
112.00
Additions to cottage
Total
SUPERSTRUCTURE
230mm common brickwall for the delivery yard area m2 118 20.00
ROOFING
770.00
200.00
245.00
0.00
195.00
0.00
700.00
0.00
210.00
0.00
6,875.00
172.50
69.00
675.00
69.00
10,180.50
AMOUNT
2,320.00
0.00
2,960.00
2,360.00
590.00
135.00
234.00
640.00
46.80
300.00
3,784.20
0.00
0.00
3,116.40
327.60
0.00
663.00
204.00
144.50
17,825.50
0.00
#VALUE!
0.00
0.00
0.00
9,291,036.43
0.00
3,614,006.59
0.00
502,580.62
0.00
5,831,127.79
0.00
1,851,151.68
0.00
6,027,499.14
0.00
4,457,912.56
0.00
7,715,072.24
0.00
2,584,566.60
0.00
0.00
18,214,872.69
0.00
0.00
10,647,289.83
0.00
163,876.48
0.00
280,931.13
0.00
6,840,238.10
0.00
488,588.60
0.00
2,442,941.76
0.00
1,221,471.09
0.00
87,247.97
0.00
0.00
0.00
334,450.36
0.00
0.00
#VALUE!
0.00
5,831,127.79
0.00
6,840,238.10
0.00
488,588.60
0.00
2,804,541.60
0.00
1,221,471.09
0.00
87,247.97
0.00
0.00
0.00
334,450.36
0.00
0.00
#VALUE!
0.00
5,831,127.79
0.00
6,840,238.10
0.00
488,588.60
0.00
2,804,541.60
0.00
1,221,471.09
0.00
87,247.97
0.00
0.00
0.00
334,450.36
0.00
0.00
#VALUE!
0.00
7,715,072.24
0.00
2,584,566.60
0.00
#VALUE!
22,418,304.17
0.00
0.00
8,650,923.25
0.00
163,876.48
0.00
280,931.13
0.00
6,840,238.10
0.00
488,588.60
0.00
2,442,941.76
0.00
1,221,471.09
0.00
87,247.97
0.00
0.00
0.00
334,450.36
0.00
0.00
#VALUE!
0.00
2,804,541.60
0.00
1,221,471.09
0.00
87,247.97
0.00
0.00
0.00
334,450.36
0.00
0.00
0.00
0.00