Professional Documents
Culture Documents
HCMP 143/2020 (2020) Hkcfi 2669
HCMP 143/2020 (2020) Hkcfi 2669
HCMP 143/2020 A
[2020] HKCFI 2669
B B
C C
D D
E E
F F
G G
H H
I I
J J
K K
L L
M M
N N
O O
P P
Q Q
R R
S S
T T
U U
V V
- 2 -
A A
L
BETWEEN L
and
N N
P ________________ P
_______________________
T T
J U D G M E N T
U _______________________ U
V V
- 3 -
A A
B B
1. This is the substantive hearing of the Originating Summons
C C
("OS") dated 24 January 2020 concerning the application by the plaintiff
D (“Milestone”) for an injunction order restraining the defendant (“YK”), D
for alteration and addition works at 22 Wang Yip Street, Yuen Long,
K K
Y.L.T.L. No 374 (the “Site”).
L L
concern four interim payments (“NSC IP-18, IP-19, IP-20 and IP-21”)
S S
plus interests owed by Milestone to YK pursuant to the NSC. There is no
T dispute that Milestone has not made all or any part of these payments. T
V V
- 4 -
A A
[sub-clause (7)].
M M
(3) The payment is required to be made to each of the
N N
nominated sub-contractors within 14 days of Milestone
receiving payment from the Employer [sub-clause (7)].
O O
(4) If Milestone withholds an amount due to YK and fails to
P P
satisfy the Architect that he has good cause for so doing, the
Architect is required under clause 29.8 of the Main Contract
Q Q
to issue a certificate to that effect and the Employer will be
R entitled, but not obliged, to pay that amount to YK direct R
[sub-clause (8)].
S S
T T
U 1
B2/219-220 U
V V
- 5 -
A A
“Milestone’s Defaults”):
D D
R
of HK$11,121,000 was owed from YK. In particular, it was alleged that R
YK was “provisional liable” for 224 days of delay (between
S S
11 August 2018 – 23 March 2019) and hence liquidated damages in the
T T
2
B2/381
3
B2/383
U 4
See YK’s letter 18/3/2019 at B2/385-387 U
V V
- 6 -
A A
sum of HK$15,680,000 (the “Alleged YK LD”)5. This was the first time
B B
since the Notice of Determination some 5 months earlier, that Milestone
C claimed that YK had caused delay and was in default. It is relevant to C
were that:
N N
V V
- 7 -
A A
C 11. On the issue of whether the Employer had paid Milestone for C
F F
Main Amount paid NSC IP nos. Remarks
Contract by Employer to included
G G
IP nos. Milestone thereunder
K
MC IP-22 Nil NSC IP-20 of Milestone had not yet K
HK$1,201,000 submitted invoice.
HK$11,200,000 had been
L L
cumulatively deducted as
LD
M M
12. Upon YK’s inquiry and YK’s request for direct payment by
Q Q
9
the Employer, the Architect wrote to Milestone stating that:-
R R
(1) YK’s request for payment was under NSC IP 18-21 which
S were under MC IP 20-23. The Architect had issued S
T T
8
B2/452
U 9
B2/493-504 U
V V
- 8 -
A A
D
Defaults; and D
Plaintiff’s case
J J
14. Milestone argues that there are bona fide disputes between
K K
them and YK for the following reasons:-
L L
(1) Firstly, the LD deducted by the Employer under MC IP-21 in
M
the sum of HK$9,730,000 far exceeded the total amount of M
“work done by all nominated sub-contractors” which was
N assessed by the QS as HK$1,410,00010. Therefore, N
T T
U 10
See B2/297 U
V V
- 9 -
A A
O O
(1) Milestone had in fact received payment from the Employer.
T
engineer is required to act independently, honestly, impartially and fairly T
11
B2/302-376
12
B2/317-320
U 13
B2/493 U
V V
- 10 -
A A
as between the employer and the contractor, forming and acting on his
B B
own opinion, and applying his professional skill: Keating on
C Construction Contracts (10th ed, 2016), §§5-062 – 5-063. C
D
(c) Based on Milestone’s own evidence, it had received D
payments for MC IP-21 to IP-23. The Employer released payment of
E HK$1,083,000 under MC IP-2114. This was a net payment after deducting E
HK$1,083,000, the total amount paid by the Employer would have been
J J
HK$156,446,20017. By simple arithmetic, Milestone must have received
a further net payment of HK$5,578,000 from the Employer sometime
K K
between January and October 2019. In fact, if one adds up Milestone’s
L entitlements under MC IP-22 (HK$274,000)18 and MC IP-23 L
S S
14
Tang 1st, §10-12 at A/12; see also
15
B2/298
T 16
B2/299 T
17
B2/295
18
B2/324
U 19
B2/327 U
V V
- 11 -
A A
D
18 days’ delay. The relevant items included “hoisting proposal for D
radiator” and “installation of gondola system”. However, the Architect
E has never certified this delay to be YK’s fault. These items were also not E
time, there were not even particulars of the number of days delayed or
H H
expenses allegedly incurred by Milestone as a result.
I (g) Milestone’s letters dated 15 March 201921 and 25 March 201922 are I
M
determined by the Employer upon Milestone’s Defaults. This M
24
automatically led to the NSC being determined under NSC Clause 38.1 .
N The NSC was not determined by Milestone because of YK’s default. N
V V
- 12 -
A A
D
wholly unparticularized. There is no evidential basis to arrive at the D
alleged 224 days’ delay which was in any event alleged as “YK is
E provisionally liable to…”. Ridiculously, this calculation was apparently E
clearly does not know how much delay YK may be liable for (if at all).
M M
None of the previous bare allegations against YK can thus be taken as
N being prima facie accurate. N
O
Applicable legal principles O
R
HKCFI 1516, §14: R
27
B2/317 especially at 319
U 28
Tang 2nd, §§24-25, 36 [A/6/44, 46] ; Milestone’s Skeleton §§2(2), 13-16, 23. U
V V
- 13 -
A A
V V
- 14 -
A A
K K
Discussion
L L
17. Applying the above principles which are not in dispute
M between the parties, it is my judgment that Milestone has failed to M
N
discharge its burden of demonstrating a bona fide dispute on the Alleged N
Debts for reasons set out hereunder.
O O
R R
“The Contractor [Milestone] is required to pay the Sub-
S
Contractor [YK] the amount included for him in each interim S
Certificate, less any amount properly deductible within 14 days,
or such other time as may be stated in the Sub-Contract, of the
T Contractor receiving payment from the Employer.” [emphasis T
added]
U U
V V
- 15 -
A A
that case, the relevant clause was clause 11(b) of that subcontract which
F F
read:-
G G
J The matter before Hunter J was an Order 14 application taken out by the J
argued that it was not obliged to pay the sub-contractor because the
M M
building owner set up against those two certificates an alleged set off
N arising from a claim for liquidated damages clause under the main N
arising under the certificate, and that discharge can arise from the
Q Q
exercise of a set off. In reply, the main contractor further argued that
R there could only be a discharge or payment if that set off is valid which R
they challenged. Thus in order to show that payment is due to the sub-
S S
contractor under this clause, the sub-contractor has to satisfy the court
T that the set off is not only claimed, but validly claimed. Hunter J held T
V V
- 16 -
A A
said:-
F F
M
20. In my judgment, although the Teakwood case is relevant and M
helpful, it is not determinative nor can it be of direct application. First of
N N
all, Hunter J did not make a final construction of clause 11(b) in that case
O at all. His Lordship was aware that for a final construction, more in- O
V V
- 17 -
A A
pay [YK] the amount included for him in each interim certificate…within
B B
14 days…of [Milestone] receiving payment from the Employer”. In my
C judgment, words “receiving payment from the Employer” must refer back C
contractor. Thus, in Teakwood case, the fact that the employer imposed
H H
liquidated damages on the main contractor under terms of the main
I I
contract could not be taken to mean that the employer had made payment
J
to the main contract against the architect certificate certifying the work J
done by the sub-contractor. In the present case, in relation to NSC Clause
K K
33.1(7), I am of the view that the words “receiving payment” refer to
U U
V V
- 18 -
A A
H
(1) In relation to MC IP-20, payment had been made by the H
Employer as per Employer’s Email at B2/452.
I HK$2,303,000 was paid and received by Milestone at least I
M
20 having been received. At least, there could be no bona M
fide dispute in respect of the debt due under NSC IP-18. The
N amount is already more than $10,000 which is sufficient to N
V V
- 19 -
A A
Q
coincidence but must be the clearest proof (based on Q
Milestone’s own documents) of Milestone having received
R actual payment from the Employer for MC IP-22 and R
MC IP-23.
S S
(4) In respect of MC IP-23, apart from the above deduction, one
T can again refer to Milestone’s Invoice dated T
30
B2/299
U 31
B2/295 U
V V
- 20 -
A A
H
argument. Pursuant to NSC Clause 33.1(7), the amounts due under NSC H
IP-18 to NSC IP-21 had become due and payable by Milestone to YK
I I
unless Milestone rightfully exercised any right of deduction within
J
14 days of payment of each of MC IP-20 to MC IP-23. Milestone clearly J
had not exercised that right of deduction within each respective 14 days
K K
period. The first time Milestone purportedly justified its non-payment as
L “rightful deduction” was on 22 August 201932. L
M M
23. In respect of Milestone’s second argument that it was
U 32
B2/317 U
V V
- 21 -
A A
and if so for how many days. The same is reflected in the stance shown
B B
in Milestone’s affidavit evidence. It has consciously chosen not to carry
C out a detailed programme analysis to examine how the net delay may be C
F F
24. Furthermore, it is also relevant to look at NSC Clause
G 31.1(10) which reads:- G
H H
“If the Employer has exercised a right under the Main Contract
to deduct from monies due to the Contractor, to the extent that
I the deduction is due to a breach of contract or other default of the I
Sub-Contractor or any person for whom the Sub- Contractor is
J responsible the monies deducted may be recovered by the J
Contractor from any monies due or to become due to the Sub-
Contractor or as a debt.” [emphasis added]
K K
L
In my view, the interplay of NSC Clauses 33.1(7) and (10) is as follows:- L
V V
- 22 -
A A
D
Milestone has to pay YK under the NSC IP. Subsequently D
however, if Milestone is able to identify that a certain extent
E of the deduction made by the Employer was due to a breach E
H 25. In the present case, Milestone had not exercised any right to H
or default.
M M
U U
V V
- 23 -
A A
(2) the contract under which the debt is alleged to arise contains
B B
an arbitration clause that covers any dispute relating to the
C debt; and C
D
(3) the company takes the steps required under the arbitration D
clause to commence the contractually mandated dispute
E resolution process (which might include preliminary stages E
arbitration clause.
P P
5 HKLRD 646 [DA#6]. It should now be clear that the Court retains a
S S
discretion under the insolvency legislation which should not be exercised
T T
only in one way by reason of the factor of arbitration although
U
considerable weight should be given to this factor in the exercise of the U
V V
- 24 -
A A
J
intention to resort to arbitration, and that some action is required of the J
recipient: Re Asia Master Logistics Ltd [2020] 2 HKLRD 423, §45 (per
K K
DHCJ W Wong SC). In Re Asia Master Logistics, the debtor company’s
see Sit Kwong Lam, §39 (per Kwan VP). The excuse proffered by
U U
V V
- 25 -
A A
Milestone that it was awaiting the results of its dispute resolution with the
B B
Employer, is plainly unacceptable. Although the SD was served almost 9
C months ago (on 14 January 2020), Milestone has not taken any steps to C
I I
J J
rd
30. Mr Li effectively accepted that the 3 requirement set out by
K Harris J in Lasmos case has not been satisfied. He submitted that the K
its position pending the resolution of its EOT claim under the arbitration
R R
between itself and the Employer. I accept the submission of Mr Lui that
S S
Milestone’s attitude is not materially different from the mere existence of
T
an arbitration agreement between Milestone and YK and I would exercise T
my discretion accordingly.
U U
V V
- 26 -
A A
Milestone.
F F
G G
H H
I I
L L
O O
R R
S S
T T
U U
V V